FDOT contract T1900 bid tabulation
SR 45 (US 41) FROM 63RD AVE TO 53RD AVE. Let by Florida DOT on May 28, 2025, Manatee, District 1. 4 bids received; low bid $4,662,927 by Traffic Management Solutions, LLC.
- Owner
- Florida DOT
- Letting
- 28 MAY 2025
- Pay items
- 99
- Data through
- 28 OCT 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | Traffic Management Solutions, LLC | $4,662,927 | Low |
| 2 | Carr Construction, LLC | $5,050,195 | +8.0% |
| 3 | Traffic Control Devices, Inc. | $5,222,222 | +12% |
| 4 | Ajax Paving Industries of Florida LLC | $5,811,383 | +25% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Traffic Management Solutions, LLC | 2. Carr Construction, LLC | 3. Traffic Control Devices, Inc. | 4. Ajax Paving Industries of Florida LLC |
|---|---|---|---|---|---|---|---|
| 0005 | Mobilization (0101-1) | LS | 1 | $445,793 | $358,471 | $500,000 | $718,949 |
| 0010 | Maintenance of traffic (0102-1) | DA | 1 | $320,590 | $211,148 | $328,950 | $720,510 |
| 0015 | Pedestrian or bicycle special detour (0102-4-1) | SY | 1 | $14,286 | $11,000 | $154,835 | $15,870 |
| 0020 | Work zone sign (0102-60) | ED | 52,978 | $0.28 | $0.20 | $0.25 | $0.29 |
| 0025 | Channelizing device- types I, II, VP, drum, or LCD (0102-74-1) | ED | 102,334 | $0.12 | $0.10 | $0.10 | $0.13 |
| 0030 | Channelizing device- pedestrian LCD (longitudinal channelizing device) (0102-74-8) | FD | 728,085 | $0.06 | $0.10 | $0.13 | $0.06 |
| 0035 | Arrow board / advance warning arrow panel (0102-76) | ED | 2,520 | $6.02 | $5.00 | $6.10 | $6.35 |
| 0040 | Portable changeable message sign, temporary (0102-99) | ED | 478 | $13.25 | $10.00 | $12.20 | $13.97 |
| 0045 | Temporary signalization and maintenance, intersection (0102-104) | ED | 900 | $8.44 | $11.75 | $18.50 | $10.72 |
| 0050 | Existing ITS maintenance (0102-112) | DA | 225 | $101.97 | $150.00 | $395.00 | $129.46 |
| 0055 | Type III barricade (0102-115) | ED | 450 | $0.42 | $0.40 | $0.45 | $0.44 |
| 0060 | Removable tape, white, solid 6" (0102-913-21) | GM | 3.38 | $14,881 | $12,507 | $15,235 | $15,870 |
| 0065 | Inlet protection system (0104-18) | EACH | 11 | $119.05 | $666.00 | $271.00 | $253.92 |
| 0070 | Litter removal (0107-1) | ACRE | 15.76 | $65.48 | $350.00 | $244.00 | $82.52 |
| 0075 | Mowing (0107-2) | ACRE | 5.70 | $95.24 | $438.00 | $244.00 | $82.52 |
| 0080 | Clearing & grubbing (0110-1-1) | ACRE | 1 | $29,762 | $19,125 | $28,670 | $31,740 |
| 0085 | Removal of existing concrete (0110-4-10) | SY | 296 | $314.88 | $82.00 | $322.00 | $63.48 |
| 0090 | Borrow excavation, truck measure (0120-2-2) | CY | 20.20 | $357.14 | $75.00 | $820.00 | $961.26 |
| 0095 | Milling existing asphalt pavement, 1" avg depth (0327-70-1) | SY | 20 | $5.57 | $131.00 | $220.00 | $11.14 |
| 0100 | Milling existing asphalt pavement, 1 1/2" avg depth (0327-70-6) | SY | 9,644 | $5.57 | $8.00 | $19.80 | $4.74 |
| 0105 | Asphalt concrete friction course,traffic B, FC-9.5, PG 76-22 (0337-7-80) | TN | 1.10 | $5,619.02 | $2,100.00 | $2,925.00 | $4,888.08 |
| 0110 | Asphalt concrete friction course,traffic C, FC-12.5, PG (0337-7-83) | TN | 795.60 | $319.81 | $243.00 | $457.00 | $246.59 |
| 0115 | Valve boxes, adjust (0425-6) | EACH | 1 | $5,535.71 | $350.00 | $5,665.00 | $449.26 |
| 0120 | Concrete curb & gutter, type F (0520-1-10) | LF | 166 | $359.23 | $138.00 | $368.00 | $31.74 |
| 0125 | Concrete sidewalk and driveways, 6" thick (0522-2) | SY | 510 | $175.00 | $170.00 | $180.00 | $82.52 |
| 0130 | Detectable warnings (0527-2) | SF | 477 | $76.19 | $30.00 | $78.00 | $47.61 |
| 0135 | Bumper guards, concrete (0542-70) | EACH | 2 | $1,309.52 | $110.00 | $1,350.00 | $126.96 |
| 0140 | Performance turf, sod (0570-1-2) | SY | 370 | $11.90 | $25.75 | $34.70 | $4.30 |
| 0145 | Fencing- pedestrian barrier P4- steel proprietary alternative fence (0914-550-4) | LF | 820 | $142.36 | $150.00 | $183.00 | $190.44 |
| 0150 | Initial contingency amount, DO not bid (0999-25) | LS | 1 | $50,838 | $50,838 | $50,838 | $50,838 |
| 0155 | Single column ground sign assembly, F&I ground mount, than 12 SF (0700-1111) | EACH | 51 | $892.86 | $495.00 | $629.00 | $793.50 |
| 0160 | Single column ground sign assembly, F&I ground mount, SF sheeting area for back to back signs (0700-1114) | EACH | 1 | $4,428.57 | $1,875.00 | $3,050.00 | $3,935.75 |
| 0165 | Single column ground sign assembly, relocate (0700-1500) | EACH | 1 | $642.86 | $215.00 | $309.00 | $571.32 |
| 0170 | Multi-column ground sign assembly, relocate (0700-2500) | EACH | 1 | $9,285.71 | $2,215.00 | $13,000 | $8,252.38 |
| 0175 | Raised pavement marker, type B (0706-1-3) | EACH | 268 | $5.71 | $5.00 | $5.00 | $5.08 |
| 0180 | Painted pavement markings, surface (0710-90) | LS | 1 | $15,439 | $6,000.00 | $13,171 | $13,721 |
| 0185 | Thermoplastic, standard, solid, 12" for crosswalk and roundabout (0711-11123) | LF | 3,231 | $5.00 | $3.00 | $4.25 | $4.44 |
| 0190 | Thermoplastic, standard, solid, 24" for stop line and crosswalk (0711-11125) | LF | 448 | $10.00 | $6.00 | $8.50 | $8.89 |
| 0195 | Thermoplastic, standard, arrow (0711-11170) | EACH | 6 | $178.57 | $95.00 | $152.00 | $158.70 |
| 0200 | Thermoplastic, standard, blue, solid,6" (0711-11421) | LF | 15 | $14.29 | $3.00 | $12.20 | $12.70 |
| 0205 | Thermoplastic, preformed, white, solid, 24" for crosswalk (0711-14125) | LF | 2,977 | $25.71 | $19.00 | $22.00 | $22.85 |
| 0210 | Thermoplastic, standard-other surfaces, white, solid, 6" (0711-16101) | GM | 0.53 | $11,807 | $6,407.00 | $10,075 | $10,493 |
| 0215 | Thermoplastic, standard-other surfaces, white, skip, 6",10-30 or 3-9 lane drop (0711-16131) | GM | 0.32 | $2,952.86 | $2,625.00 | $2,520.00 | $2,624.26 |
| 0220 | Thermoplastic, remove existing thermoplastic pavement markings- surface to remain (0711-17-1) | SF | 8,437 | $2.70 | $2.00 | $2.30 | $2.40 |
| 0225 | Conduit, furnish & install, open trench (0630-2-11) | LF | 59 | $28.76 | $33.50 | $22.80 | $36.51 |
| 0230 | Conduit, furnish & install, directional bore (0630-2-12) | LF | 302 | $32.09 | $33.75 | $27.65 | $40.74 |
| 0235 | Pull & splice box, F&I, 13" X 24" cover size (0635-2-11) | EACH | 15 | $1,277.13 | $2,198.00 | $2,090.00 | $1,621.44 |
| 0240 | Lighting conductors, F&I, insulated, no.8 - 6 (0715-1-12) | LF | 2,379 | $1.96 | $2.70 | $2.70 | $2.49 |
| 0245 | Lighting conductors, remove & stockpile, fdot or maint owns (0715-1-70) | LF | 994 | $0.65 | $0.50 | $1.95 | $0.83 |
| 0250 | Luminaire, F&I- replace existing luminaire on existing pole/arm, roadway, pole top (0715-11213) | EACH | 7 | $2,284.64 | $3,054.00 | $1,675.00 | $2,900.57 |
| 0255 | Light pole complete, F&I, standard pole standard foundation, 45' mounting height, 0' arm length (0715-61400) | EACH | 1 | $11,454 | $12,837 | $11,000 | $14,543 |
| 0260 | Light pole complete, F&I, standard pole special foundation, 35' mounting height, 15' arm length (0715-62252) | EACH | 10 | $7,618.56 | $14,182 | $7,840.00 | $9,672.50 |
| 0265 | Light pole complete, F&I, utility conflict pole standard foundation, 35' mounting height, 16' arm length (0715-65266) | EACH | 1 | $11,628 | $13,069 | $11,700 | $14,558 |
| 0270 | Light pole complete, F&I, utility conflict pole special foundation, 35' mounting height, 16' arm length (0715-66266) | EACH | 1 | $13,292 | $15,678 | $17,750 | $16,876 |
| 0275 | Light pole complete, remove pole and foundation (0715-69000) | EACH | 1 | $921.08 | $1,681.00 | $1,400.00 | $1,169.40 |
| 0280 | Light pole complete, remove pole, foundation remains (0715-69001) | EACH | 9 | $409.37 | $525.00 | $620.00 | $519.73 |
| 0285 | Pole cable distribution system, furnish and install, conventional (0715-500-1) | EACH | 20 | $873.30 | $1,334.00 | $870.00 | $1,108.74 |
| 0290 | Itsfm location documentation- ITS site (0611-2-2) | EACH | 7 | $2,421.43 | $1,700.00 | $2,065.00 | $3,074.24 |
| 0295 | Conduit, furnish & install, open trench (0630-2-11) | LF | 1,030 | $21.54 | $20.75 | $23.00 | $27.35 |
| 0300 | Conduit, furnish & install, directional bore (0630-2-12) | LF | 1,847 | $45.20 | $52.00 | $41.00 | $57.39 |
| 0305 | Conduit, furnish & install, aboveground (0630-2-14) | LF | 56 | $74.28 | $55.00 | $46.00 | $94.31 |
| 0310 | Signal cable- new or reconstructed intersection, furnish & install (0632-7-1) | PI | 7 | $9,543.80 | $14,060 | $10,500 | $12,117 |
| 0315 | Signal cable- repair/replace/other, furnish & install (0632-7-2) | LF | 1,280 | $4.91 | $37.75 | $7.15 | $6.23 |
| 0320 | Pull & splice box, F&I, 17" X 30" cover size (0635-2-14) | EACH | 110 | $1,636.74 | $2,927.00 | $1,865.00 | $2,078.00 |
| 0325 | Electrical power service, F&I, underground, meter by contractor (0639-1122) | AS | 7 | $4,917.37 | $7,173.00 | $5,910.00 | $6,243.08 |
| 0330 | Electrical service wire, & install (0639-2-1) | LF | 1,297 | $17.84 | $12.00 | $7.60 | $22.65 |
| 0335 | Electrical service disconnect, F&I, pole mount (0639-3-11) | EACH | 7 | $2,385.84 | $1,914.00 | $2,390.00 | $3,029.06 |
| 0340 | Electrical power service- contribution in aid of construction (ciac), FPL (DO not bid) (0639-8130) | LS | 1 | $30,130 | $30,130 | $30,130 | $30,130 |
| 0345 | Prestressed concrete pole, type P-II service pole (0641-2-12) | EACH | 7 | $2,837.99 | $2,702.00 | $2,521.00 | $3,603.10 |
| 0350 | Aluminum signals pole, (0646-1-11) | EACH | 28 | $3,907.47 | $3,761.00 | $4,915.00 | $4,960.91 |
| 0355 | Aluminum signals pole, furnish install pedestrian detector post (0646-1-12) | EACH | 1 | $2,071.76 | $1,483.00 | $2,010.00 | $2,630.30 |
| 0360 | Steel mast arm assembly, and install, single arm 78' (0649-21-21) | EACH | 7 | $118,332 | $151,500 | $113,820 | $150,233 |
| 0365 | Pedestrian signal, furnish & install LED countdown, 1 way (0653-1-11) | AS | 28 | $683.37 | $1,328.00 | $870.00 | $867.60 |
| 0370 | Midblock crosswalk: hybrid beacon assembly, & install complete assembly (0654-3-10) | AS | 42 | $2,026.58 | $2,637.00 | $1,785.00 | $2,572.94 |
| 0375 | Pedestrian detector, furnish & install, standard (0665-1-11) | EACH | 28 | $521.83 | $390.00 | $255.00 | $662.51 |
| 0380 | Traffic controller assembly, F&I, NEMA (0670-5110) | AS | 7 | $52,770 | $71,768 | $50,430 | $66,997 |
| 0385 | Traffic controller, modify (0671-2-40) | EACH | 4 | $753.86 | $2,800.00 | $1,885.00 | $957.10 |
| 0390 | Managed field ethernet switch, furnish & install (0684-1-1) | EACH | 7 | $5,739.34 | $6,500.00 | $7,800.00 | $7,286.65 |
| 0395 | Uninterruptible power supply, furnish and install, line interactive (0685-1-11) | EACH | 7 | $10,631 | $16,049 | $10,450 | $13,497 |
| 0400 | Sign panel, furnish & install overhead mount, UP to 12 SF (0700-3201) | EACH | 44 | $829.64 | $1,231.00 | $700.00 | $1,053.31 |
| 0405 | Sign panel, remove, UP to 12 SF (0700-3601) | EACH | 2 | $100.85 | $88.00 | $292.00 | $128.04 |
| 0410 | Internally illuminated sign, relocate (0700-5-50) | EACH | 10 | $2,071.36 | $2,093.00 | $1,450.00 | $2,629.79 |
| 0415 | Enhanced highway sign AC powered, F&I ground mount, blank out sign <12 SF (0700-141160) | EACH | 3 | $8,608.41 | $14,318 | $12,625 | $10,929 |
| 0420 | Enhanced highway sign AC powered, F&I overhead blank out sign <12 SF (0700-141360) | EACH | 8 | $10,611 | $10,079 | $8,525.00 | $13,471 |
| 0425 | Itsfm subsurface documentation- project length (0611-1-1) | MI | 0.46 | $4,000.00 | $16,820 | $3,415.00 | $5,078.39 |
| 0430 | Conduit, furnish & install, open trench (0630-2-11) | LF | 87 | $16.81 | $36.00 | $17.25 | $21.34 |
| 0435 | Conduit, furnish & install, directional bore (0630-2-12) | LF | 2,356 | $41.22 | $47.00 | $34.60 | $42.46 |
| 0440 | Conduit, furnish & install, split duct (0630-2-18) | LF | 20 | $158.74 | $53.00 | $124.00 | $201.54 |
| 0445 | Fiber optic cable, F&I, underground,2-12 fibers (0633-1121) | LF | 4,481 | $5.21 | $3.70 | $4.50 | $6.61 |
| 0450 | Fiber optic connection, install, splice (0633-2-31) | EACH | 26 | $64.29 | $45.00 | $55.00 | $81.62 |
| 0455 | Fiber optic connection, install, termination (0633-2-32) | EACH | 84 | $107.14 | $75.00 | $92.00 | $136.02 |
| 0460 | Fiber optic connection hardware, F&I, splice (0633-3-11) | EACH | 2 | $1,635.71 | $1,145.00 | $1,400.00 | $2,076.69 |
| 0465 | Fiber optic connection hardware, F&I, splice tray (0633-3-12) | EACH | 2 | $71.43 | $50.00 | $61.00 | $90.69 |
| 0470 | Fiber optic connection hardware, F&I, buffer tube fan out kit (0633-3-14) | EACH | 7 | $121.43 | $85.00 | $103.00 | $154.17 |
| 0475 | Fiber optic connection hardware, F&I, patch panel- terminated (0633-3-16) | EACH | 7 | $1,607.14 | $700.00 | $1,370.00 | $2,040.42 |
| 0480 | Fiber optic connection hardware, adjust/modify splice enclosure (0633-3-51) | EACH | 4 | $992.86 | $700.00 | $850.00 | $1,260.53 |
| 0485 | Fiber optic cable locator (0633-6) | DA | 225 | $350.00 | $280.00 | $215.00 | $444.36 |
| 0490 | Pull & splice box, F&I, 24" X 36" cover size (0635-2-12) | EACH | 12 | $2,840.34 | $3,708.00 | $3,160.00 | $3,606.09 |
| 0495 | Pull & splice box, F&I, 30" X 60" rectangular or 36" round size (0635-2-13) | EACH | 3 | $5,473.75 | $6,738.00 | $6,470.00 | $6,949.46 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from FDOT's tabulation for this contract. FDOT Tabulation of Bids PDFs from its central office lettings, January 2018 to October 2026, all pay items. On A+B contracts the cost part is kept (the total the pay items add up to). Bidders listed without a rank or total are left out.
Every contract let that day: FDOT letting of May 28, 2025. Compiled by Mirage Metrics.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.