FDOT contract T4727 bid tabulation
SR A1A (NE OCEAN BLVD) FROM NE SHORE VILLAGE TER TO SR 732 (. Let by Florida DOT on October 29, 2025, Martin, District 4. 13 bids received; low bid $4,898,324 by I N C USA Corporation.
- Owner
- Florida DOT
- Letting
- 29 OCT 2025
- Pay items
- 102
- Data through
- 28 OCT 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | I N C USA Corporation | $4,898,324 | Low |
| 2 | Roadway Construction, LLC | $5,752,508 | +17% |
| 3 | Ranger Construction Industries, Inc. | $6,216,489 | +27% |
| 4 | Florida Engineering & Development Corp | $6,233,365 | +27% |
| 5 | Ohla USA Inc | $6,259,626 | +28% |
| 6 | Carr Construction, LLC | $6,323,013 | +29% |
| 7 | The Stout Group LLC | $6,492,838 | +33% |
| 8 | West Construction, Inc. | $6,528,339 | +33% |
| 9 | General Asphalt Company, LLC | $6,566,546 | +34% |
| 10 | C.W. Roberts Contracting, Inc. | $6,590,425 | +35% |
| 11 | Halley Engineering Contractors, Inc. | $6,841,920 | +40% |
| 12 | Posillico Civil, Inc. | $7,044,177 | +44% |
| 13 | Timothy Rose Contracting, Inc. | $8,512,920 | +74% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. I N C USA Corporation | 2. Roadway Construction, LLC | 3. Ranger Construction Industries, Inc. | 4. Florida Engineering & Development Corp | 5. Ohla USA Inc | 6. Carr Construction, LLC |
|---|---|---|---|---|---|---|---|---|---|
| 0005 | Mobilization (0101-1) | LS | 1 | $454,224 | $575,000 | $615,300 | $621,158 | $625,000 | $552,300 |
| 0010 | Maintenance of traffic (0102-1) | DA | 1 | $200,600 | $350,728 | $580,050 | $614,933 | $500,000 | $322,550 |
| 0015 | Pedestrian or bicycle special detour (0102-4-1) | SY | 1 | $15,235 | $16,932 | $53,600 | $52,109 | $100,000 | $66,165 |
| 0020 | Work zone sign (0102-60) | ED | 22,780 | $0.19 | $0.19 | $0.20 | $0.19 | $0.20 | $0.20 |
| 0025 | Temporary barrier, F&I, low profile, concrete (0102-71-13) | LF | 539 | $41.00 | $0.01 | $60.00 | $47.70 | $1.00 | $57.00 |
| 0030 | Temporary barrier, relocate, low profile concrete (0102-71-23) | LF | 3,634 | $18.00 | $0.01 | $20.00 | $24.36 | $1.00 | $18.75 |
| 0035 | Channelizing device- types I, II, VP, drum, or LCD (0102-74-1) | ED | 126,605 | $0.10 | $0.07 | $0.10 | $0.10 | $0.10 | $0.10 |
| 0040 | Channelizing device- pedestrian LCD (longitudinal channelizing device) (0102-74-8) | FD | 62,864 | $0.04 | $0.05 | $0.05 | $0.04 | $0.04 | $0.10 |
| 0045 | Temporary separator, F&I remove (0102-75-1) | LF | 3,948 | $18.00 | $0.01 | $26.15 | $18.27 | $25.00 | $29.25 |
| 0050 | Portable changeable message sign, temporary (0102-99) | ED | 866 | $9.20 | $9.00 | $10.45 | $9.34 | $9.49 | $9.40 |
| 0055 | Type III barricade (0102-115) | ED | 1,006 | $0.30 | $0.20 | $0.25 | $0.36 | $0.36 | $0.20 |
| 0060 | Sediment barrier (0104-10-3) | LF | 17,124 | $2.45 | $3.46 | $2.30 | $2.63 | $4.00 | $2.60 |
| 0065 | Inlet protection system (0104-18) | EACH | 52 | $143.89 | $117.51 | $162.80 | $116.87 | $250.00 | $631.00 |
| 0070 | Litter removal (0107-1) | ACRE | 228.16 | $27.93 | $0.01 | $42.15 | $34.98 | $200.00 | $253.00 |
| 0075 | Mowing (0107-2) | ACRE | 196.59 | $42.32 | $0.01 | $100.90 | $17.65 | $60.00 | $253.00 |
| 0080 | Monitor existing structures- inspection and settlement monitoring (0108-1) | LS | 1 | $12,696 | $0.01 | $11,500 | $0.00 | $104,698 | $10,323 |
| 0085 | Clearing & grubbing (0110-1-1) | ACRE | 1 | $26,552 | $128,000 | $173,475 | $221,000 | $450,000 | $39,293 |
| 0090 | Removal of existing concrete (0110-4-10) | SY | 2,376 | $38.09 | $23.23 | $16.00 | $48.98 | $35.00 | $33.25 |
| 0095 | Mailbox, F&I single (0110-7-1) | EACH | 4 | $423.20 | $742.40 | $261.60 | $541.91 | $531.00 | $1,010.00 |
| 0100 | Regular excavation (0120-1) | CY | 447.10 | $8.46 | $52.64 | $42.35 | $70.28 | $271.00 | $88.00 |
| 0105 | Embankment (0120-6) | CY | 326.60 | $12.70 | $43.34 | $58.00 | $78.11 | $60.05 | $99.00 |
| 0110 | Type B stabilization (0160-4) | SY | 2,883 | $7.62 | $29.72 | $24.70 | $20.86 | $21.75 | $37.50 |
| 0115 | Optional base, base group 04 (0285-704) | SY | 38 | $29.62 | $43.53 | $52.75 | $45.30 | $138.10 | $88.00 |
| 0120 | Optional base, base group 09 (0285-709) | SY | 1,978 | $25.39 | $71.32 | $63.00 | $110.81 | $90.00 | $80.00 |
| 0125 | Milling existing asphalt pavement, 1 1/2" avg depth (0327-70-6) | SY | 60,019 | $6.00 | $3.47 | $3.50 | $4.57 | $3.75 | $4.60 |
| 0130 | Superpave asphaltic conc, traffic B (0334-1-12) | TN | 139.10 | $360.00 | $341.42 | $350.00 | $288.48 | $115.00 | $381.00 |
| 0135 | Asphalt concrete friction course,traffic B, FC-12.5, PG (0337-7-81) | TN | 5,388.90 | $178.80 | $178.70 | $178.00 | $228.38 | $159.00 | $223.00 |
| 0140 | Miscellaneous asphalt (0339-1) | TN | 1 | $500.00 | $1,710.11 | $2,310.00 | $1,130.90 | $2,000.00 | $751.00 |
| 0145 | Inlets, DT bot, type C,<10' (0425-1521) | EACH | 3 | $8,040.80 | $14,141 | $8,070.00 | $8,419.24 | $8,700.00 | $6,360.00 |
| 0150 | Inlets, DT bot, type C,jbot, <10' (0425-1523) | EACH | 2 | $10,580 | $21,054 | $13,700 | $11,768 | $12,500 | $15,640 |
| 0155 | Inlets, DT bot, type C, jbot, >10' (0425-1524) | EACH | 1 | $12,273 | $21,535 | $13,100 | $16,740 | $11,300 | $14,598 |
| 0160 | Inlets, ditch bottom, type D, J bot, <10' (0425-1543) | EACH | 12 | $9,156.80 | $17,793 | $12,200 | $10,184 | $11,000 | $13,034 |
| 0165 | Inlets, ditch bottom, type D, J bot, >10' (0425-1544) | EACH | 2 | $11,850 | $22,849 | $12,700 | $17,059 | $10,500 | $13,555 |
| 0170 | Inlets, closed flume (0425-1910) | EACH | 4 | $9,310.40 | $8,500.65 | $11,200 | $9,501.20 | $8,250.00 | $9,384.00 |
| 0175 | Manholes, P-7, <10' (0425-2-41) | EACH | 1 | $10,580 | $10,865 | $9,750.00 | $9,552.42 | $7,900.00 | $6,882.00 |
| 0180 | Pipe culvert, optional material, round, 12"SD (0430-174112) | LF | 4 | $202.98 | $614.19 | $2,870.00 | $506.41 | $1,500.00 | $980.00 |
| 0185 | Pipe culvert, optional material, round, 18"SD (0430-174118) | LF | 342 | $187.38 | $320.79 | $170.60 | $123.74 | $300.50 | $271.00 |
| 0190 | Pipe culvert, optional material, round, 36"SD (0430-174136) | LF | 44 | $385.11 | $444.60 | $437.00 | $271.37 | $420.00 | $339.00 |
| 0195 | Mitered end section, optional round, 12" SD (0430-984121) | EACH | 1 | $3,385.60 | $6,127.92 | $5,190.00 | $1,706.04 | $5,000.00 | $3,232.00 |
| 0200 | French drain, 24" (0443-70-4) | LF | 299 | $243.07 | $454.56 | $371.00 | $261.45 | $305.00 | $428.00 |
| 0205 | French drain, 30" (0443-70-5) | LF | 416 | $344.64 | $545.42 | $523.00 | $305.29 | $355.00 | $485.00 |
| 0210 | French drain, 36" (0443-70-6) | LF | 1,652 | $395.43 | $600.66 | $547.50 | $366.56 | $405.00 | $573.00 |
| 0215 | Pipe handrail - guiderail, steel (0515-1-1) | LF | 98 | $101.57 | $104.50 | $104.70 | $60.90 | $164.00 | $130.00 |
| 0220 | Concrete curb & gutter, type F (0520-1-10) | LF | 118 | $40.63 | $79.63 | $92.50 | $73.07 | $70.00 | $123.00 |
| 0225 | Concrete curb, type D (0520-2-4) | LF | 259 | $38.09 | $55.63 | $59.00 | $59.40 | $45.00 | $78.00 |
| 0230 | Concrete sidewalk and driveways, 6" thick (0522-2) | SY | 2,367 | $68.18 | $129.67 | $100.00 | $107.05 | $116.00 | $106.00 |
| 0235 | Detectable warnings (0527-2) | SF | 312 | $42.32 | $60.09 | $75.60 | $44.92 | $42.50 | $31.25 |
| 0240 | Performance turf (0570-1-1) | SY | 6,316 | $2.54 | $12.79 | $11.75 | $7.73 | $19.00 | $1.00 |
| 0245 | Performance turf, sod (0570-1-2) | SY | 3,348 | $5.92 | $12.79 | $22.15 | $8.27 | $18.00 | $4.20 |
| 0250 | Conduit, furnish & install, open trench (0630-2-11) | LF | 30 | $40.21 | $49.00 | $36.05 | $48.72 | $13.59 | $42.75 |
| 0255 | Pull & splice box, F&I, 13" X 24" cover size (0635-2-11) | EACH | 2 | $1,929.41 | $1,149.00 | $2,210.00 | $1,157.10 | $878.66 | $2,032.00 |
| 0260 | Traffic monitoring site vehicle sensor-non-weight, furnish & install (0695-1-1) | EACH | 2 | $3,375.79 | $2,449.00 | $2,990.00 | $2,467.47 | $2,028.07 | $3,564.00 |
| 0265 | Traffic monitoring site non- intrusive vehicle sensor- non- weight, furnish & install (0695-2-1) | EACH | 1 | $3,375.79 | $9,047.00 | $3,490.00 | $9,123.83 | $1.02 | $3,000.00 |
| 0270 | Traffic monitoring site speed/classification unit, furnish & install, volume speed and classification (0695-3-11) | AS | 1 | $13,582 | $11,787 | $16,200 | $11,878 | $5,139.13 | $13,960 |
| 0275 | Traffic monitoring site solar power unit, furnish & install (0695-5-1) | EACH | 1 | $3,442.84 | $4,326.00 | $8,310.00 | $4,362.47 | $2,809.67 | $12,000 |
| 0280 | Traffic monitoring site inductive loop assembly, & install, 2 loops (0695-6-12) | EACH | 2 | $2,909.95 | $3,090.00 | $2,210.00 | $3,115.04 | $1,455.92 | $2,000.00 |
| 0285 | Traffic monitoring site cabinet, furnish & install, type 4, polemount (0695-7143) | EACH | 1 | $14,916 | $4,970.00 | $8,830.00 | $5,012.07 | $1,450.81 | $10,412 |
| 0290 | Traffic monitoring site cabinet, remove existing cabinet (0695-7600) | EACH | 1 | $1,524.00 | $534.00 | $982.50 | $538.96 | $883.77 | $759.00 |
| 0295 | Traffic monitoring site communications modem furnish install (0695-8-11) | EACH | 1 | $5,819.46 | $2,487.00 | $7,560.00 | $2,508.06 | $6,605.27 | $12,727 |
| 0300 | Raised pavement marker, type B (0706-1-3) | EACH | 2,836 | $5.00 | $3.85 | $4.65 | $5.08 | $5.10 | $4.20 |
| 0305 | Painted pavement markings, standard, white, solid, 6" (0710-11101) | GM | 1.89 | $1,800.00 | $2,060.14 | $1,590.00 | $1,827.00 | $1,827.98 | $1,431.00 |
| 0310 | Painted pavement markings, standard, white, solid for stop line or crosswalk, 24" (0710-11125) | LF | 290 | $4.00 | $2.00 | $1.75 | $4.06 | $4.08 | $1.60 |
| 0315 | Painted pavement markings, standard, white, 2-4 dotted guideline/ 6-10 dotted 6" (0710-11141) | GM | 0.20 | $1,000.00 | $743.69 | $742.00 | $1,015.00 | $979.19 | $700.00 |
| 0320 | Painted pavement markings, standard, yellow, solid, 6" (0710-11201) | GM | 3.50 | $1,800.00 | $2,069.41 | $1,590.00 | $1,827.00 | $1,836.21 | $1,437.00 |
| 0325 | Painted pavement markings, standard, yellow, 2-4 dotted guideline/6-10 dotted extension, 6" (0710-11241) | GM | 0.24 | $1,000.00 | $771.78 | $770.00 | $1,014.98 | $1,016.18 | $685.00 |
| 0330 | Partnering, DO not bid (0999-16) | LS | 1 | $6,000.00 | $6,000.00 | $6,000.00 | $6,000.00 | $6,000.00 | $6,000.00 |
| 0335 | Initial contingency amount, DO not bid (0999-25) | LS | 1 | $55,958 | $55,958 | $55,958 | $55,958 | $55,958 | $55,958 |
| 0340 | Single column ground sign assembly, F&I ground mount, than 12 SF (0700-1111) | EACH | 105 | $525.00 | $313.00 | $364.00 | $532.87 | $535.71 | $485.00 |
| 0345 | Single column ground sign assembly, F&I ground mount, 20.0 SF (0700-1112) | EACH | 25 | $1,400.00 | $877.00 | $1,020.00 | $1,421.00 | $1,428.57 | $1,773.00 |
| 0350 | Single column ground sign assembly, F&I ground mount, 30.0 SF (0700-1113) | EACH | 5 | $3,200.00 | $1,505.00 | $1,750.00 | $3,248.00 | $3,265.31 | $1,981.00 |
| 0355 | Single column ground sign assembly, remove (0700-1600) | EACH | 100 | $35.00 | $55.00 | $64.00 | $35.53 | $35.71 | $26.00 |
| 0360 | Raised pavement marker, type B (0706-1-3) | EACH | 1,155 | $5.00 | $3.85 | $5.25 | $5.07 | $5.10 | $4.70 |
| 0365 | Painted pavement markings, durable paint, yellow, island nose (0710-12290) | SF | 132 | $10.00 | $4.00 | $8.15 | $10.15 | $10.20 | $7.30 |
| 0370 | Painted pavement markings, surface (0710-90) | LS | 1 | $40,000 | $30,750 | $24,100 | $40,600 | $40,816 | $21,567 |
| 0375 | Thermoplastic, standard, solid, 12" for crosswalk and roundabout (0711-11123) | LF | 2,489 | $4.00 | $2.98 | $2.35 | $4.06 | $4.08 | $2.10 |
| 0380 | Thermoplastic, standard, solid, 24" for stop line and crosswalk (0711-11125) | LF | 411 | $7.00 | $5.96 | $5.80 | $7.10 | $7.14 | $5.20 |
| 0385 | Thermoplastic, standard, 2-4 dotted guideline/ 6-10 gap extension, 6" (0711-11141) | GM | 1.47 | $3,500.00 | $2,496.60 | $2,550.00 | $3,552.50 | $3,566.58 | $2,306.00 |
| 0390 | Thermoplastic, standard, message or symbol (0711-11160) | EACH | 4 | $250.00 | $79.00 | $145.40 | $253.75 | $255.10 | $130.00 |
| 0395 | Thermoplastic, standard, arrow (0711-11170) | EACH | 63 | $90.00 | $50.00 | $104.70 | $91.35 | $91.84 | $94.00 |
| 0400 | Thermoplastic, standard, yellow, solid, 18" for diagonal or chevron (0711-11224) | LF | 1,257 | $6.00 | $4.07 | $3.50 | $6.09 | $6.12 | $3.10 |
| 0405 | Thermoplastic, standard, yellow, 2-4 dotted guide line dotted extension line, 6" (0711-11241) | GM | 0.37 | $3,500.00 | $2,459.02 | $2,520.00 | $3,552.49 | $3,512.87 | $2,319.00 |
| 0410 | Thermoplastic, preformed, white, solid, 24" for crosswalk (0711-14125) | LF | 228 | $20.00 | $15.13 | $20.95 | $20.30 | $20.41 | $18.75 |
| 0415 | Thermoplastic, preformed, white, message (0711-14160) | EACH | 55 | $200.00 | $206.00 | $232.60 | $203.00 | $204.08 | $209.00 |
| 0420 | Thermoplastic, preformed, white, arrow (0711-14170) | EACH | 55 | $100.00 | $100.00 | $232.60 | $101.50 | $102.04 | $209.00 |
| 0425 | Thermoplastic, preformed, color route shield (0711-14660) | EACH | 8 | $4,000.00 | $1,821.00 | $3,370.00 | $4,060.00 | $4,081.63 | $3,024.00 |
| 0430 | Thermoplastic, standard-other surfaces, white, solid, 6" (0711-16101) | GM | 5.23 | $5,200.00 | $4,355.16 | $7,080.00 | $5,278.00 | $5,299.02 | $6,364.00 |
| 0435 | Thermoplastic, standard-other surfaces, yellow, solid, 6" (0711-16201) | GM | 4.32 | $5,200.00 | $4,165.04 | $7,090.00 | $5,278.00 | $5,304.89 | $6,374.00 |
| 0440 | Thermoplastic, standard-other surfaces, yellow, skip, 6" (0711-16231) | GM | 0.67 | $15,000 | $1,038.90 | $2,780.00 | $15,225 | $15,261 | $2,532.00 |
| 0445 | Green-colored pavement markings, bike lane (0714-10) | SF | 9,565 | $10.00 | $7.75 | $9.75 | $10.15 | $10.20 | $8.80 |
| 0450 | Conduit, furnish & install, open trench (0630-2-11) | LF | 21 | $36.80 | $27.00 | $15.10 | $26.39 | $15.27 | $14.50 |
| 0455 | Conduit, furnish & install, directional bore (0630-2-12) | LF | 369 | $62.77 | $26.00 | $32.85 | $26.39 | $21.71 | $28.50 |
| 0460 | Pull & splice box, F&I, 13" X 24" cover size (0635-2-11) | EACH | 13 | $2,245.96 | $1,179.00 | $2,010.00 | $1,189.58 | $878.66 | $2,032.00 |
| 0465 | Electrical power service, F&I, underground, meter by contractor (0639-1122) | AS | 1 | $7,086.66 | $6,683.00 | $6,010.00 | $6,740.61 | $1,644.93 | $7,360.00 |
| 0470 | Electrical service wire, & install (0639-2-1) | LF | 8 | $8.31 | $17.00 | $10.35 | $17.26 | $20.43 | $11.50 |
| 0475 | Prestressed concrete pole, type P-II service pole (0641-2-12) | EACH | 2 | $4,422.14 | $2,015.00 | $2,430.00 | $2,032.03 | $1,363.97 | $2,900.00 |
| 0480 | Lighting conductors, F&I, insulated, no.8 - 6 (0715-1-12) | LF | 1,987 | $4.57 | $2.00 | $2.45 | $2.03 | $2.61 | $3.00 |
| 0485 | Load center, F&I, secondary voltage (0715-7-11) | EACH | 1 | $22,145 | $13,229 | $23,000 | $13,341 | $9,803.18 | $27,976 |
| 0490 | Luminaire, F&I- replace existing luminaire on existing pole/arm, roadway, pendant/teardrop (0715-11216) | EACH | 9 | $4,825.21 | $4,239.00 | $10,200 | $7,808.39 | $7,054.81 | $13,509 |
| 0495 | Light pole complete, remove pole and foundation (0715-69000) | EACH | 2 | $2,162.81 | $2,188.00 | $756.00 | $2,206.61 | $1,144.30 | $650.00 |
| 0500 | Pole cable distribution system, furnish and install, conventional (0715-500-1) | EACH | 16 | $1,076.85 | $613.00 | $1,220.00 | $618.14 | $832.68 | $1,290.00 |
| 0505 | Light pole complete- special design, F&I, single arm shoulder mount, concrete, 20' (0715-511320) | EACH | 7 | $24,408 | $20,732 | $22,100 | $20,907 | $13,808 | $19,500 |
| 0510 | Fiber optic cable locator (0633-6) | DA | 339 | $235.29 | $0.01 | $187.20 | $314.65 | $300.00 | $180.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from FDOT's tabulation for this contract. FDOT Tabulation of Bids PDFs from its central office lettings, January 2018 to October 2026, all pay items. On A+B contracts the cost part is kept (the total the pay items add up to). Bidders listed without a rank or total are left out.
Every contract let that day: FDOT letting of October 29, 2025. Compiled by Mirage Metrics.