FDOT contract T4736 bid tabulation
SR 27 (US 27) AT I-75/US 27 INTERCHANGE. Let by Florida DOT on July 30, 2025, Palm Beach, District 4. 7 bids received; low bid $20,985,425 by Prince Contracting, LLC..
- Owner
- Florida DOT
- Letting
- 30 JUL 2025
- Pay items
- 137
- Data through
- 28 OCT 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | Prince Contracting, LLC. | $20,985,425 | Low |
| 2 | Lead Engineering Contractors, LLC | $22,688,237 | +8.0% |
| 3 | Ranger Construction Industries, Inc. | $25,295,999 | +21% |
| 4 | Cone & Graham, Inc. | $25,835,661 | +23% |
| 5 | Johnson Bros. Corporation, A Southland Company | $28,254,476 | +35% |
| 6 | Strongcore Group, LLC | $28,497,737 | +36% |
| 7 | Asphalt Group, Inc. | $28,681,335 | +37% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Prince Contracting, LLC. | 2. Lead Engineering Contractors, LLC | 3. Ranger Construction Industries, Inc. | 4. Cone & Graham, Inc. | 5. Johnson Bros. Corporation, A Southland Company | 6. Strongcore Group, LLC |
|---|---|---|---|---|---|---|---|---|---|
| 0005 | Conc class II, bridge superstructure (0400-2-4) | CY | 1,312.80 | $1,100.00 | $1,200.00 | $1,320.00 | $1,500.00 | $1,100.00 | $1,320.00 |
| 0010 | Concrete class II, approach slabs (0400-2-10) | CY | 311.30 | $550.00 | $700.00 | $960.00 | $1,000.00 | $600.00 | $516.00 |
| 0015 | Concrete class IV, bridge substructure (0400-4-5) | CY | 136.80 | $2,500.00 | $2,600.00 | $3,030.00 | $2,700.00 | $4,000.00 | $3,375.00 |
| 0020 | Concrete class IV, mass, substructure (0400-4-25) | CY | 384.30 | $1,300.00 | $300.00 | $1,535.00 | $2,500.00 | $1,500.00 | $1,200.00 |
| 0025 | Bridge deck grooving (0400-7-1) | SY | 2,597 | $8.00 | $5.00 | $6.50 | $4.00 | $4.00 | $5.50 |
| 0030 | Bridge deck planing (0400-9-1) | SY | 2,597 | $8.00 | $8.00 | $6.50 | $5.00 | $8.00 | $5.50 |
| 0035 | Composite neoprene pads (0400-147) | CF | 10.10 | $1,500.00 | $1,500.00 | $2,850.00 | $3,000.00 | $2,350.00 | $1,550.00 |
| 0040 | Plain neoprene bearing pads (0400-148) | CF | 28.60 | $600.00 | $800.00 | $1,500.00 | $1,500.00 | $1,100.00 | $770.00 |
| 0045 | Reinforcing steel - bridge superstructure (0415-1-4) | LB | 256,750 | $1.20 | $1.00 | $1.65 | $2.00 | $1.25 | $1.20 |
| 0050 | Reinforcing steel- bridge substructure (0415-1-5) | LB | 59,937 | $1.60 | $1.40 | $2.05 | $2.00 | $1.30 | $1.50 |
| 0055 | Reinforcing steel- approach slabs (0415-1-9) | LB | 64,033 | $1.20 | $1.02 | $1.70 | $2.00 | $1.25 | $1.20 |
| 0060 | Prest beams: florida-I beam 36" (0450-2-36) | LF | 1,800 | $450.00 | $495.00 | $546.00 | $700.00 | $450.00 | $312.00 |
| 0065 | Preformed pile holes, 36" to 43" drill/punch size (0455-15-16) | LF | 2,764 | $200.00 | $65.00 | $150.00 | $200.00 | $225.00 | $245.00 |
| 0070 | Pile inspection, driven pile (0455-20-1) | EACH | 69 | $800.00 | $520.00 | $900.00 | $750.00 | $3,100.00 | $300.00 |
| 0075 | Prestressed concrete piling, SQ (0455-34-5) | LF | 3,955 | $300.00 | $225.00 | $410.00 | $100.00 | $305.00 | $230.00 |
| 0080 | Pile redrive (0455-115) | EACH | 16 | $3,700.00 | $6,500.00 | $2,000.00 | $200.00 | $3,300.00 | $1,970.00 |
| 0085 | Load test (dynamic), data collection and analysis (0455-137) | EACH | 85 | $600.00 | $700.00 | $2,230.00 | $2,500.00 | $1,700.00 | $641.00 |
| 0090 | Load test (dynamic), test (0455-137-2) | EACH | 8 | $2,200.00 | $700.00 | $1,105.00 | $5,000.00 | $2,000.00 | $1,020.00 |
| 0095 | Test piles-prestressed concrete,24" SQ (0455-143-5) | LF | 650 | $450.00 | $260.00 | $600.00 | $800.00 | $400.00 | $547.00 |
| 0100 | Bridge deck expansion joint, construction, F&I poured joint with backer rod (0458-1-11) | LF | 504 | $45.00 | $25.00 | $37.50 | $125.00 | $9.00 | $85.00 |
| 0105 | Concrete traffic railing- 36" single-slope (0521-5-13) | LF | 994 | $130.00 | $96.00 | $150.00 | $200.00 | $225.00 | $665.00 |
| 0110 | Riprap, sand-cement bags (0530-1100) | CY | 76.20 | $850.00 | $1,500.00 | $1,080.00 | $1,100.00 | $1,400.00 | $2,190.00 |
| 0115 | Riprap- rubble, bank and shore (0530-3-3) | TN | 8,704 | $100.00 | $100.00 | $67.00 | $1.00 | $150.00 | $90.00 |
| 0120 | Bedding stone (0530-74) | TN | 5,654 | $90.00 | $90.00 | $54.00 | $1.00 | $165.00 | $51.00 |
| 0125 | Conduit, furnish & install, embedded concrete barriers and traffic railings (0630-2-16) | LF | 2,485 | $55.00 | $51.76 | $39.70 | $70.36 | $85.00 | $64.00 |
| 0130 | Junction box, furnish & install, embedded (0635-3-13) | EACH | 6 | $1,650.00 | $1,552.80 | $1,590.00 | $1,962.95 | $2,300.00 | $1,920.00 |
| 0135 | Mobilization (0101-1) | LS | 1 | $2,100,000 | $2,000,000 | $2,394,500 | $2,583,000 | $2,615,000 | $2,800,000 |
| 0140 | Maintenance of traffic (0102-1) | DA | 1 | $650,000 | $385,000 | $970,000 | $939,288 | $90,000 | $1,000,000 |
| 0145 | Special detour- temporary pavement (0102-2200) | SY | 1 | $750,000 | $890,000 | $915,250 | $1,336,610 | $600,000 | $200,000 |
| 0150 | Special detour- temporary earthwork/base (0102-2300) | CY | 1 | $450,000 | $800,000 | $1,456,300 | $1,307,348 | $953,000 | $200,000 |
| 0155 | Traffic control officer (0102-14) | HR | 360 | $100.00 | $90.00 | $105.90 | $97.28 | $115.00 | $92.00 |
| 0160 | Work zone sign (0102-60) | ED | 46,223 | $0.19 | $0.19 | $0.20 | $0.22 | $0.23 | $0.20 |
| 0165 | Temporary barrier, F&I, anchored (0102-71-15) | LF | 240 | $0.01 | $47.00 | $45.30 | $54.59 | $85.00 | $41.00 |
| 0170 | Temporary barrier, F&I, free standing (0102-71-16) | LF | 6,312 | $0.01 | $43.00 | $27.05 | $49.74 | $85.00 | $25.00 |
| 0175 | Temporary barrier, relocate, free standing (0102-71-26) | LF | 16,296 | $0.01 | $17.00 | $10.45 | $19.41 | $16.00 | $10.00 |
| 0180 | Channelizing device- types I, II, VP, drum, or LCD (0102-74-1) | ED | 91,941 | $0.09 | $0.10 | $0.10 | $0.12 | $0.10 | $0.10 |
| 0185 | Arrow board / advance warning arrow panel (0102-76) | ED | 1,007 | $5.10 | $5.20 | $5.90 | $6.07 | $6.00 | $6.40 |
| 0190 | Temporary crash cushion, redirective option (0102-89-1) | LO | 6 | $1,800.00 | $960.00 | $4,470.00 | $2,069.87 | $1,100.00 | $3,990.00 |
| 0195 | Temporary glare screen, F&I, wall material-concrete (0102-94-1) | LF | 2,300 | $25.51 | $25.00 | $29.40 | $33.97 | $31.00 | $30.50 |
| 0200 | Glare screen, temporary, relocate, wall material- concrete (0102-94-11) | LF | 2,300 | $14.29 | $14.00 | $16.45 | $10.92 | $18.00 | $17.00 |
| 0205 | Portable changeable message sign, temporary (0102-99) | ED | 1,624 | $9.18 | $11.20 | $10.60 | $13.10 | $14.00 | $11.50 |
| 0210 | Type III barricade (0102-115) | ED | 1,596 | $0.23 | $0.50 | $0.25 | $0.55 | $0.45 | $0.30 |
| 0215 | Removable tape, white, solid 6" (0102-913-21) | GM | 0.55 | $9,700.00 | $16,200 | $11,100 | $17,168 | $16,000 | $11,700 |
| 0220 | Removable tape, yellow, solid, (0102-913-31) | GM | 0.09 | $9,500.00 | $20,500 | $10,700 | $17,168 | $17,000 | $11,100 |
| 0225 | Sediment barrier (0104-10-3) | LF | 1,700 | $4.00 | $8.15 | $3.70 | $2.70 | $40.00 | $20.50 |
| 0230 | Floating turbidity barrier (0104-11) | LF | 404 | $16.50 | $35.00 | $18.70 | $14.00 | $75.00 | $81.50 |
| 0235 | Inlet protection system (0104-18) | EACH | 2 | $23.00 | $1,200.00 | $235.30 | $1,912.62 | $1,315.00 | $521.00 |
| 0240 | Litter removal (0107-1) | ACRE | 365.32 | $30.00 | $30.00 | $50.00 | $141.61 | $25.00 | $113.00 |
| 0245 | Mowing (0107-2) | ACRE | 237.04 | $135.00 | $150.00 | $275.00 | $274.63 | $35.00 | $439.00 |
| 0250 | Monitor existing structures- inspection and settlement monitoring (0108-1) | LS | 1 | $5,600.00 | $5,000.00 | $6,350.00 | $1.00 | $30,000 | $5,430.00 |
| 0255 | Monitor existing structures- vibration monitoring (0108-2) | LS | 1 | $10,200 | $5,000.00 | $11,600 | $1.00 | $30,000 | $13,500 |
| 0260 | Clearing & grubbing (0110-1-1) | ACRE | 1 | $421,614 | $450,000 | $825,000 | $1,228,356 | $217,000 | $5,280,000 |
| 0265 | Regular excavation (0120-1) | CY | 6,156 | $3.50 | $19.00 | $5.30 | $6.89 | $15.00 | $12.50 |
| 0270 | Subsoil excavation (0120-4) | CY | 1,400 | $15.00 | $100.00 | $31.75 | $49.00 | $40.00 | $30.00 |
| 0275 | Channel excavation (0120-5) | CY | 36,899 | $30.00 | $27.00 | $11.80 | $29.00 | $30.00 | $30.00 |
| 0280 | Embankment (0120-6) | CY | 23,001 | $10.00 | $26.00 | $2.65 | $6.70 | $15.00 | $15.50 |
| 0285 | Surcharge embankment (0120-74) | CY | 718.70 | $25.00 | $190.00 | $14.40 | $76.46 | $100.00 | $10.00 |
| 0290 | Geosynthetic reinforced foundation over soft soil (0145-2) | SY | 2,065 | $6.25 | $9.00 | $3.20 | $4.85 | $10.00 | $25.00 |
| 0295 | Type B stabilization (0160-4) | SY | 19,126 | $2.00 | $18.00 | $8.65 | $8.83 | $25.00 | $0.01 |
| 0300 | Optional base, base group 01 (0285-701) | SY | 7,295 | $9.50 | $14.00 | $7.55 | $10.37 | $22.00 | $18.00 |
| 0305 | Optional base, base group 09 (0285-709) | SY | 11,371 | $15.00 | $26.00 | $21.90 | $16.33 | $45.00 | $28.00 |
| 0310 | Milling existing asphalt pavement, 1 1/2" avg depth (0327-70-6) | SY | 3,481 | $6.60 | $5.00 | $6.15 | $8.00 | $6.00 | $7.00 |
| 0315 | Milling existing asphalt pavement, 2 1/4" avg depth (0327-70-11) | SY | 21,230 | $4.00 | $5.00 | $3.50 | $6.00 | $8.55 | $6.00 |
| 0320 | Superpave asphaltic conc, traffic E (0334-1-15) | TN | 721.60 | $210.00 | $180.00 | $195.00 | $225.00 | $215.00 | $195.00 |
| 0325 | Superpave asphaltic concrete, traffic E, PG76-22 (0334-1-55) | TN | 4,382.90 | $180.00 | $165.00 | $165.50 | $200.00 | $240.00 | $175.00 |
| 0330 | Asphalt concrete friction course, inc bit, FC-5, PG 76-22 (0337-7-25) | TN | 1,347.60 | $255.00 | $220.00 | $235.00 | $280.00 | $275.00 | $269.00 |
| 0335 | Miscellaneous asphalt (0339-1) | TN | 147 | $290.00 | $220.00 | $287.20 | $250.00 | $430.00 | $221.00 |
| 0340 | Precast bulkhead panels (0400-72) | SF | 6,671 | $85.00 | $140.00 | $151.10 | $117.00 | $110.00 | $133.00 |
| 0345 | Inlets, DT bot, type D, <10' (0425-1541) | EACH | 1 | $9,000.00 | $8,000.00 | $10,000 | $9,728.25 | $15,000 | $10,100 |
| 0350 | Inlets, DT bot, type F, <10' (0425-1561) | EACH | 4 | $6,000.00 | $8,000.00 | $7,290.00 | $7,095.90 | $15,000 | $9,550.00 |
| 0355 | Inlets, gutter, type S, <10' (0425-1701) | EACH | 23 | $6,000.00 | $8,000.00 | $8,350.00 | $8,125.95 | $19,000 | $9,290.00 |
| 0360 | Inlets, adjacent barrier, <=10' (0425-1921) | EACH | 1 | $10,000 | $9,500.00 | $10,400 | $10,072 | $24,000 | $10,600 |
| 0365 | Inlets, adjust (0425-4) | EACH | 1 | $5,000.00 | $2,000.00 | $4,120.00 | $4,005.75 | $4,500.00 | $3,740.00 |
| 0370 | Pipe culvert,optional material,round, 18"S/CD (0430-175118) | LF | 1,168 | $150.00 | $120.00 | $194.10 | $188.84 | $225.00 | $188.00 |
| 0375 | Pipe culvert,optional material,round, 24"S/CD (0430-175124) | LF | 146 | $180.00 | $130.00 | $241.20 | $234.62 | $300.00 | $308.00 |
| 0380 | Pipe culvert, opt material, round, 30"S/CD (0430-175130) | LF | 348 | $250.00 | $240.00 | $270.60 | $263.24 | $345.00 | $307.00 |
| 0385 | Pipe culvert,optional material,other-elip/arch, (0430-175218) | LF | 31 | $205.00 | $260.00 | $223.50 | $217.46 | $335.00 | $335.00 |
| 0390 | Mitered end section, optional round, 18" CD (0430-982125) | EACH | 9 | $3,500.00 | $3,500.00 | $4,000.00 | $3,891.30 | $4,000.00 | $6,490.00 |
| 0395 | Mitered end section, optional round, 24" CD (0430-982129) | EACH | 4 | $4,000.00 | $3,600.00 | $4,240.00 | $4,120.20 | $4,200.00 | $8,030.00 |
| 0400 | Mitered end section , optional round, 30" SD (0430-984133) | EACH | 2 | $12,000 | $16,000 | $21,200 | $20,601 | $8,500.00 | $9,900.00 |
| 0405 | Underdrain, type III (0440-1-30) | LF | 130 | $150.00 | $155.00 | $141.20 | $137.34 | $120.00 | $111.00 |
| 0410 | Underdrain outlet pipe, 6" (0440-73-2) | LF | 8 | $110.00 | $450.00 | $129.40 | $125.90 | $270.00 | $175.00 |
| 0415 | Preformed pile holes, 24" to 29" drill/punch size (0455-15-14) | LF | 1,995 | $225.00 | $180.00 | $149.00 | $129.56 | $375.00 | $293.00 |
| 0420 | Pile inspection, driven pile (0455-20-1) | EACH | 105 | $600.00 | $315.00 | $900.00 | $254.18 | $1,800.00 | $245.00 |
| 0425 | Prestressed concrete piling, SQ (0455-34-3) | LF | 3,442 | $190.00 | $260.00 | $293.00 | $173.42 | $255.00 | $185.00 |
| 0430 | Sheet piling steel, temporary- critical (0455-133-2) | SF | 9,500 | $45.00 | $96.00 | $115.00 | $101.00 | $160.00 | $95.00 |
| 0440 | Shoulder gutter- concrete (0520-6) | LF | 3,379 | $40.00 | $74.00 | $58.00 | $63.23 | $60.00 | $61.50 |
| 0445 | Concrete barrier, with slab, 36" single slope (0521-8-7) | LF | 600 | $525.00 | $550.00 | $716.00 | $789.00 | $900.00 | $677.00 |
| 0450 | Riprap- rubble, bank and shore (0530-3-3) | TN | 1,777 | $125.00 | $112.00 | $67.00 | $1.00 | $175.00 | $90.00 |
| 0455 | Bedding stone (0530-74) | TN | 663 | $140.00 | $160.00 | $54.00 | $1.00 | $230.00 | $51.00 |
| 0460 | Guardrail -roadway, general (0536-1-1) | LF | 4,049 | $30.00 | $24.00 | $27.80 | $28.72 | $40.00 | $29.50 |
| 0465 | Guardrail transition to rigid barrier, F&I- index 536- 001, approach TL-3 (0536-8112) | EACH | 4 | $3,025.00 | $2,800.00 | $3,170.00 | $3,588.09 | $4,760.00 | $3,340.00 |
| 0470 | Guardrail transition to rigid barrier, F&I- index 536- 001, trailing (0536-8113) | EACH | 4 | $1,500.00 | $1,200.00 | $1,460.00 | $1,063.81 | $2,300.00 | $1,540.00 |
| 0475 | Guardrail removal (0536-73) | LF | 1,711 | $4.00 | $2.30 | $2.65 | $0.63 | $5.00 | $2.80 |
| 0480 | Guardrail end treatment- trailing anchorage (0536-85-20) | EACH | 7 | $1,300.00 | $1,300.00 | $1,500.00 | $1,703.66 | $2,350.00 | $1,580.00 |
| 0485 | Guardrail end treatment- parallel approach terminal (0536-85-24) | EACH | 3 | $3,100.00 | $3,000.00 | $3,520.00 | $3,687.06 | $5,300.00 | $3,720.00 |
| 0490 | Fencing, type A, 5.1-6.0, standard (0550-10120) | LF | 2,212 | $15.25 | $15.00 | $17.60 | $30.66 | $23.00 | $18.50 |
| 0495 | Fence gate, type A, single, opening (0550-60112) | EACH | 2 | $2,000.00 | $1,784.00 | $2,060.00 | $3,090.15 | $2,500.00 | $2,170.00 |
| 0500 | Performance turf, sod (0570-1-2) | SY | 16,886 | $7.75 | $3.00 | $5.90 | $4.15 | $6.00 | $5.40 |
| 0505 | Raised pavement marker, type B (0706-1-3) | EACH | 16,454 | $4.00 | $4.33 | $4.35 | $4.29 | $5.00 | $4.50 |
| 0510 | Painted pavement markings, standard, white, solid, 6" (0710-11101) | GM | 5.36 | $1,650.00 | $1,400.00 | $1,850.00 | $1,791.14 | $2,000.00 | $1,930.00 |
| 0515 | Painted pavement markings, standard, white, solid for stop line or crosswalk, 24" (0710-11125) | LF | 98 | $2.25 | $2.00 | $2.35 | $2.29 | $2.45 | $2.50 |
| 0520 | Painted pavement markings, standard, white, 2-4 dotted guideline/ 6-10 dotted 6" (0710-11141) | GM | 0.21 | $700.00 | $901.00 | $757.50 | $795.43 | $850.00 | $788.00 |
| 0525 | Painted pavement markings, standard, white, message or symbol (0710-11160) | EACH | 72 | $36.00 | $108.00 | $41.20 | $74.39 | $80.00 | $43.00 |
| 0530 | Painted pavement markings, standard, yellow, solid, 6" (0710-11201) | GM | 2.62 | $1,700.00 | $1,388.00 | $1,850.00 | $1,814.03 | $1,900.00 | $1,930.00 |
| 0535 | Partnering, DO not bid (0999-16) | LS | 1 | $6,000.00 | $6,000.00 | $6,000.00 | $6,000.00 | $6,000.00 | $6,000.00 |
| 0540 | Disputes review board, meeting- DO not bid (0999-20-1) | DA | 26 | $3,900.00 | $3,900.00 | $3,900.00 | $3,900.00 | $3,900.00 | $3,900.00 |
| 0545 | Disputes review board, hearing- DO not bid (0999-20-2) | EACH | 2 | $4,500.00 | $4,500.00 | $4,500.00 | $4,500.00 | $4,500.00 | $4,500.00 |
| 0550 | Local agency initial amount (DO not bid) (0999-26) | LS | 1 | $1,231,392 | $1,231,392 | $1,231,392 | $1,231,392 | $1,231,392 | $1,231,392 |
| 0555 | Ground-in rumble strips, 8" sinusoidal (0546-72-3) | GM | 1.28 | $13,000 | $1,800.00 | $6,950.00 | $1,974.26 | $15,000 | $15,700 |
| 0560 | Single column ground sign assembly, F&I ground mount, than 12 SF (0700-1111) | EACH | 26 | $575.00 | $554.00 | $642.00 | $549.36 | $600.00 | $667.00 |
| 0565 | Single column ground sign assembly, F&I ground mount, 30.0 SF (0700-1113) | EACH | 7 | $1,850.00 | $1,750.00 | $2,030.00 | $2,689.58 | $3,000.00 | $2,110.00 |
| 0570 | Single column ground sign assembly, remove (0700-1600) | EACH | 38 | $50.00 | $41.00 | $47.05 | $85.84 | $92.00 | $49.00 |
| 0575 | Retroreflective sign strip- furnish and install, 2' (0700-13-12) | EACH | 8 | $100.00 | $134.00 | $111.80 | $143.06 | $185.00 | $116.00 |
| 0580 | Retroreflective sign strip- furnish and install, 5' (0700-13-15) | EACH | 19 | $150.00 | $160.00 | $164.70 | $112.16 | $125.00 | $171.00 |
| 0585 | Object marker, type 1 (0705-10-1) | EACH | 3 | $425.00 | $430.00 | $458.00 | $251.79 | $270.00 | $476.00 |
| 0590 | Raised pavement marker, type B (0706-1-3) | EACH | 823 | $4.00 | $4.00 | $4.35 | $4.29 | $5.00 | $4.50 |
| 0595 | Painted pavement markings, surface (0710-90) | LS | 1 | $22,500 | $38,500 | $25,000 | $16,023 | $17,000 | $26,000 |
| 0600 | Thermoplastic, standard, solid, 18" for diagonals and chevrons (0711-11124) | LF | 26 | $7.00 | $3.00 | $7.20 | $5.72 | $6.00 | $7.50 |
| 0605 | Thermoplastic, standard, message or symbol (0711-11160) | EACH | 4 | $150.00 | $215.00 | $163.50 | $211.73 | $225.00 | $170.00 |
| 0610 | Thermoplastic, standard, arrow (0711-11170) | EACH | 44 | $80.00 | $267.00 | $88.20 | $91.56 | $100.00 | $92.00 |
| 0615 | Thermoplastic, standard, yield line (0711-11180) | LF | 248 | $7.00 | $5.80 | $7.55 | $17.05 | $19.00 | $7.90 |
| 0620 | Thermoplastic, standard, yellow, 2-4 dotted guide line dotted extension line, 6" (0711-11241) | GM | 0.18 | $2,400.00 | $4,500.00 | $2,740.00 | $3,261.83 | $3,500.00 | $2,850.00 |
| 0625 | Thermoplastic, standard-open graded asphalt surfaces solid, 6" (0711-15101) | GM | 1.75 | $7,100.00 | $5,600.00 | $8,090.00 | $6,981.45 | $7,500.00 | $8,410.00 |
| 0630 | Thermoplastic, standard-open graded asphalt surfaces, skip, 6",10-30 skip or 3-9 lane (0711-15131) | GM | 1.87 | $1,800.00 | $3,600.00 | $2,020.00 | $2,289.00 | $2,500.00 | $2,110.00 |
| 0635 | Thermoplastic, standard-open graded asphalt surfaces, skip, 12"- approach to toll plaza or 3-9 lane drop (0711-15133) | GM | 0.08 | $3,200.00 | $7,400.00 | $3,590.00 | $7,610.93 | $7,200.00 | $4,260.00 |
| 0640 | Thermoplastic, standard-open graded asphalt surfaces, 6", 6-10 dotted managed lane marking (0711-15171) | GM | 0.16 | $2,700.00 | $3,500.00 | $2,970.00 | $4,051.53 | $4,300.00 | $3,110.00 |
| 0645 | Thermoplastic, standard-open graded asphalt surfaces, yellow, solid, 6" (0711-15201) | GM | 1.19 | $6,500.00 | $5,600.00 | $7,390.00 | $6,981.45 | $7,500.00 | $7,690.00 |
| 0650 | Permanent tape, white, solid, 6" for concrete bridges (0713-103101) | GM | 0.14 | $38,000 | $5,800.00 | $43,500 | $44,063 | $46,000 | $45,200 |
| 0655 | Permanent tape, white, 10-30 6" wide, for concrete surfaces (0713-103181) | GM | 0.14 | $10,000 | $19,500 | $10,600 | $13,734 | $15,000 | $11,100 |
| 0660 | Permanent tape, yellow, solid, for concrete bridges (0713-103201) | GM | 0.09 | $37,000 | $29,000 | $41,900 | $44,063 | $46,000 | $43,600 |
| 0665 | Permanent tape, black, 10-30 6" wide, for concrete surfaces (0713-103381) | GM | 0.13 | $10,000 | $20,000 | $10,300 | $10,827 | $12,000 | $10,800 |
| 0670 | Conduit, furnish & install, mount (0630-2-15) | LF | 500 | $87.00 | $82.82 | $63.50 | $113.44 | $135.00 | $102.00 |
| 0675 | Conduit, furnish & install, embedded concrete barriers and traffic railings (0630-2-16) | LF | 500 | $54.25 | $51.76 | $39.70 | $67.81 | $80.00 | $64.00 |
| 0680 | Junction box, furnish & install, embedded (0635-3-13) | EACH | 2 | $1,650.00 | $1,552.80 | $1,590.00 | $1,962.95 | $2,300.00 | $2,530.00 |
| 0685 | Local agency initial amount (DO not bid) (0999-26) | LS | 1 | $1,623.98 | $1,623.98 | $1,623.98 | $1,623.98 | $1,623.98 | $1,623.98 |
| 0690 | Local agency initial amount (DO not bid) (0999-26) | LS | 1 | $774.51 | $774.51 | $774.51 | $774.51 | $774.51 | $774.51 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from FDOT's tabulation for this contract. FDOT Tabulation of Bids PDFs from its central office lettings, January 2018 to October 2026, all pay items. On A+B contracts the cost part is kept (the total the pay items add up to). Bidders listed without a rank or total are left out.
Every contract let that day: FDOT letting of July 30, 2025. Compiled by Mirage Metrics.