Strongcore Group, LLC submitted 12 bids on Florida DOT contracts in the data, from 26 JAN 2022 to 30 JUL 2025, and was the low bidder on 2 of them (17%). When it was not low, its total sat a median +20% above the low bid.
- Owner
- Florida DOT
- Low bid volume
- $21,799,180
- Latest bid
- 30 JUL 2025
- Data through
- 28 OCT 2026
By year
| Year | Bids | Low bids | Win rate |
|---|---|---|---|
| 2022 | 5 | 1 | 20% |
| 2023 | 4 | 1 | 25% |
| 2025 | 3 | 0 | 0% |
By district
| District | Bids | Low bids | Win rate |
|---|---|---|---|
| District 4 | 8 | 2 | 25% |
| District 6 | 4 | 0 | 0% |
Pay items where it is most often lowest
| Pay item | Code | Unit | Lines bid | Lowest on the line | Its median price | All bidders' median |
|---|---|---|---|---|---|---|
| Removal of existing concrete | 0110-4-10 | SY | 9 | 5 (56%) | $22.50 | $33.96 |
| Prestressed concrete pole, type P-II service pole | 0641-2-12 | EACH | 16 | 4 (25%) | $2,475.00 | $2,200.00 |
| Traffic control officer | 0102-14 | HR | 11 | 4 (36%) | $67.00 | $80.00 |
| Miscellaneous asphalt | 0339-1 | TN | 9 | 4 (44%) | $250.00 | $375.00 |
| Pull & splice box, F&I, 13" X 24" cover size | 0635-2-11 | EACH | 27 | 3 (11%) | $2,150.62 | $1,150.00 |
| Raised pavement marker, type B | 0706-1-3 | EACH | 20 | 3 (15%) | $3.95 | $5.00 |
| Embankment | 0120-6 | CY | 12 | 3 (25%) | $39.50 | $30.04 |
| Pull & splice box, F&I, 24" X 36" cover size | 0635-2-12 | EACH | 11 | 3 (27%) | $2,800.00 | $2,231.27 |
| Concrete sidewalk and driveways, 6" thick | 0522-2 | SY | 9 | 3 (33%) | $59.50 | $86.00 |
| Tree root and branch pruning | 0110-22 | EACH | 9 | 3 (33%) | $554.00 | $1,334.00 |
| Traffic controller assembly, remove controller with | 0670-5600 | AS | 7 | 3 (43%) | $946.64 | $871.00 |
| Aluminum signals pole, remove | 0646-1-60 | EACH | 6 | 3 (50%) | $183.28 | $332.00 |
A line counts when the firm priced it and at least one other bidder did too; the lowest unit price on the line counts whoever won the contract. Token prices and bids over three times the low bid are left out.
Who it meets most
| Firm | Contracts in common | That firm ranked ahead |
|---|---|---|
| General Asphalt Company, LLC | 8 | 5 of 8 |
| Ohla USA Inc | 7 | 5 of 7 |
| Florida Engineering & Development Corp | 7 | 5 of 7 |
| Ranger Construction Industries, Inc. | 6 | 3 of 6 |
| Weekley Asphalt Paving, Inc. | 5 | 3 of 5 |
| Asphalt Group, Inc. | 4 | 2 of 4 |
| Horizon Contractors, Inc. | 4 | 1 of 4 |
| The Stout Group LLC | 4 | 3 of 4 |
| Zahlene Enterprises Inc. | 3 | 1 of 3 |
| Jva Engineering Contractor, Inc | 2 | 1 of 2 |
Latest bids
| Let | Contract | District | Project | Rank | Its bid | Against the low bid |
|---|---|---|---|---|---|---|
| 30 JUL 2025 | T4736 | District 4 | SR 27 (US 27) AT I-75/US 27 INTERCHANGE | 6 of 7 | $28,497,737 | +36% |
| 28 MAY 2025 | T4724 | District 4 | SR 862 (I-595) FROM SR 9 (I-95) NB OFF-RAMP TO EB I-595 | 4 of 5 | $6,293,400 | +19% |
| 29 JAN 2025 | T6610 | District 6 | SR A1A (COLLINS AVE / INDIAN CREEK DR) AND SR 112 FROM 44... | 2 of 3 | $10,160,694 | +11% |
| 26 JUL 2023 | T4638 | District 4 | SR 9 (I-95) MOBILITY HUB, AT CYPRESS CREEK RD, N ANDREWS... | 1 of 7 | $8,148,235 | Low, 5.0% under the second |
| 29 MAR 2023 | T6572 | District 6 | SR 852 (CO LINE RD) | 4 of 7 | $2,884,500 | +22% |
| 22 FEB 2023 | T6549 | District 6 | SR 994 (QUAIL ROOST DR) | 6 of 6 | $5,841,206 | +41% |
| 25 JAN 2023 | T4637 | District 4 | SR 7 (US 441) | 5 of 5 | $2,535,315 | +18% |
| 25 MAY 2022 | T4606 | District 4 | UNIVERSITY DR | 1 of 6 | $13,650,945 | Low, 0.0% under the second |
| 27 APR 2022 | T4612 | District 4 | PROSPECT RD | 9 of 9 | $8,262,631 | +23% |
| 27 APR 2022 | T6514 | District 6 | SR 112 (I-195) (JULIA TUTTLE CSWY) AND SR 907 (ALTON RD) | 3 of 3 | $14,767,066 | +18% |
| 26 JAN 2022 | T4595 | District 4 | SR 817 (UNIVERSITY DR) | 2 of 9 | $12,511,318 | +11% |
| 26 JAN 2022 | T4596 | District 4 | SR 817 (UNIVERSITY DR) | 5 of 6 | $10,860,848 | +22% |
How this record was read
FDOT Tabulation of Bids PDFs from its central office lettings, January 2018 to October 2026, all pay items. On A+B contracts the cost part is kept (the total the pay items add up to). Bidders listed without a rank or total are left out.
- Every bid counted here matched its published total to within one dollar; FDOT's rank decides who was low.
- The gap to the low bid is the firm's total over the low total, minus one, on contracts it did not win, leaving out bids over three times the low bid.
- A record covers the lettings in the data, not every contract the firm ever bid. Coverage by year is on the state page.
A name split in two, or a figure that does not match the owner's tabulation? Write to mehdi@miragemetrics.com and we correct it.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.