FDOT contract T4739 bid tabulation
SR 9 (I-95) FROM N OF GLADES TO N OF SR 91 (FLORIDA TPK). Let by Florida DOT on February 25, 2026, St Lucie, District 4. 5 bids received; low bid $5,138,833 by Ranger Construction Industries, Inc..
- Owner
- Florida DOT
- Letting
- 25 FEB 2026
- Pay items
- 112
- Data through
- 28 OCT 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | Ranger Construction Industries, Inc. | $5,138,833 | Low |
| 2 | C.W. Roberts Contracting, Inc. | $6,026,007 | +17% |
| 3 | Timothy Rose Contracting, Inc. | $6,257,205 | +22% |
| 4 | Ohla USA Inc | $6,426,860 | +25% |
| 5 | Halley Engineering Contractors, Inc. | $6,599,135 | +28% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Ranger Construction Industries, Inc. | 2. C.W. Roberts Contracting, Inc. | 3. Timothy Rose Contracting, Inc. | 4. Ohla USA Inc | 5. Halley Engineering Contractors, Inc. |
|---|---|---|---|---|---|---|---|---|
| 0005 | Mobilization (0101-1) | LS | 1 | $284,815 | $322,000 | $276,075 | $642,000 | $660,000 |
| 0010 | Maintenance of traffic (0102-1) | DA | 1 | $189,970 | $183,000 | $229,660 | $551,662 | $660,000 |
| 0015 | Traffic control officer (0102-14) | HR | 3,020 | $0.01 | $1.00 | $84.55 | $0.01 | $0.01 |
| 0020 | Work zone sign (0102-60) | ED | 36,482 | $0.20 | $0.20 | $0.01 | $0.18 | $0.18 |
| 0025 | Temporary barrier, F&I, anchored (0102-71-15) | LF | 1,100 | $0.01 | $45.25 | $43.46 | $0.01 | $40.00 |
| 0030 | Channelizing device- types I, II, VP, drum, or LCD (0102-74-1) | ED | 183,843 | $0.10 | $0.10 | $0.01 | $0.09 | $0.01 |
| 0035 | Arrow board / advance warning arrow panel (0102-76) | ED | 1,002 | $5.65 | $6.00 | $0.01 | $4.00 | $5.00 |
| 0040 | Temporary crash cushion, redirective option (0102-89-1) | LO | 1 | $10.00 | $1,000.00 | $1,111.33 | $0.01 | $1,600.00 |
| 0045 | Portable changeable message sign, temporary (0102-99) | ED | 1,504 | $9.95 | $10.50 | $9.86 | $9.00 | $9.00 |
| 0050 | Temporary signalization and maintenance, intersection (0102-104) | ED | 336 | $24.15 | $20.00 | $19.45 | $17.26 | $35.00 |
| 0055 | Temporary traffic detection and maintenance, intersection (0102-107-1) | ED | 336 | $24.15 | $20.00 | $19.45 | $17.26 | $35.00 |
| 0060 | Existing ITS maintenance (0102-112) | DA | 168 | $169.30 | $560.00 | $546.90 | $485.28 | $250.00 |
| 0065 | Type III barricade (0102-115) | ED | 3,060 | $0.25 | $0.30 | $0.01 | $0.23 | $0.23 |
| 0070 | Portable regulatory, sign (0102-150-1) | ED | 1,086 | $4.55 | $4.75 | $4.51 | $4.00 | $4.00 |
| 0075 | Radar speed display unit (0102-150-2) | ED | 1,086 | $4.55 | $5.30 | $4.51 | $4.50 | $4.50 |
| 0080 | Sediment barrier (0104-10-3) | LF | 46,374 | $0.01 | $0.50 | $2.04 | $1.50 | $0.01 |
| 0085 | Floating turbidity barrier (0104-11) | LF | 403 | $20.40 | $20.00 | $16.73 | $20.00 | $25.00 |
| 0090 | Inlet protection system (0104-18) | EACH | 12 | $118.15 | $278.00 | $198.53 | $250.00 | $200.00 |
| 0095 | Litter removal (0107-1) | ACRE | 420.52 | $59.10 | $44.00 | $58.89 | $50.00 | $50.00 |
| 0100 | Mowing (0107-2) | ACRE | 367.65 | $109.10 | $110.00 | $147.21 | $90.00 | $150.00 |
| 0105 | Clearing & grubbing (0110-1-1) | ACRE | 1 | $10,500 | $32,000 | $80,218 | $125,000 | $15,000 |
| 0110 | Milling existing asphalt pavement, 3" avg depth (0327-70-4) | SY | 143 | $18.70 | $70.00 | $7.83 | $45.00 | $10.00 |
| 0115 | Milling existing asphalt pavement, 1 1/2" avg depth (0327-70-6) | SY | 57,383 | $2.30 | $4.00 | $2.94 | $4.00 | $3.20 |
| 0120 | Milling existing asphalt pavement, 4" avg depth (0327-70-7) | SY | 2,200 | $5.20 | $6.00 | $9.92 | $7.50 | $11.00 |
| 0125 | Milling existing asphalt pavement, 2 1/4" avg depth (0327-70-11) | SY | 84,450 | $2.20 | $2.35 | $2.81 | $4.00 | $3.85 |
| 0130 | Milling existing asphalt pavement, 1 3/4" avg depth (0327-70-13) | SY | 340 | $3.80 | $8.00 | $7.38 | $20.00 | $10.00 |
| 0135 | Superpave asphaltic conc, traffic E (0334-1-15) | TN | 160.80 | $182.65 | $165.00 | $212.18 | $170.00 | $198.00 |
| 0140 | Superpave asphaltic concrete, traffic E, PG76-22 (0334-1-55) | TN | 10,559.90 | $130.65 | $156.25 | $158.98 | $150.50 | $160.00 |
| 0145 | Asphalt concrete friction course, inc bit, FC-5, PG 76-22 (0337-7-25) | TN | 3,481.50 | $172.05 | $235.00 | $216.42 | $181.50 | $221.00 |
| 0150 | Asphalt concrete friction course,traffic E, FC-12.5, PG (0337-7-88) | TN | 1,552.50 | $158.45 | $199.00 | $182.27 | $146.25 | $215.00 |
| 0155 | Miscellaneous asphalt (0339-1) | TN | 40.50 | $277.40 | $360.00 | $361.09 | $350.00 | $300.00 |
| 0160 | Guardrail -roadway, general (0536-1-1) | LF | 1,096 | $25.55 | $26.25 | $26.34 | $23.12 | $23.00 |
| 0165 | Guardrail transition to rigid barrier, F&I- index 536- 002, approach TL-3 (0536-8122) | EACH | 1 | $4,660.00 | $3,400.00 | $3,337.59 | $3,005.92 | $2,961.00 |
| 0170 | Guardrail removal (0536-73) | LF | 1,082 | $2.45 | $1.00 | $0.96 | $0.86 | $0.85 |
| 0175 | Guardrail end treatment- parallel approach terminal (0536-85-24) | EACH | 1 | $3,410.00 | $3,475.00 | $3,390.63 | $3,053.70 | $3,008.00 |
| 0180 | Performance turf, sod (0570-1-2) | SY | 14,617 | $4.05 | $4.75 | $3.08 | $11.50 | $5.50 |
| 0185 | Plastic erosion mat, turf reinforced mat, type 1 (0571-1-11) | SY | 1,000 | $7.25 | $9.00 | $9.09 | $13.00 | $6.00 |
| 0190 | Pull & splice box, F&I, 13" X 24" cover size (0635-2-11) | EACH | 1 | $2,480.00 | $2,000.00 | $2,559.63 | $1,795.94 | $3,400.00 |
| 0195 | Traffic monitoring site vehicle sensor-non-weight, furnish & install (0695-1-1) | EACH | 3 | $2,750.00 | $5,800.00 | $5,717.34 | $5,073.10 | $3,500.00 |
| 0200 | Traffic monitoring site inductive loop assembly, & install, 2 loops (0695-6-12) | EACH | 3 | $2,310.00 | $5,000.00 | $4,831.76 | $4,287.31 | $2,500.00 |
| 0205 | Raised pavement marker, type B (0706-1-3) | EACH | 1,764 | $5.10 | $7.50 | $5.08 | $6.47 | $4.00 |
| 0210 | Painted pavement markings, standard, white, solid, 6" (0710-11101) | GM | 7.81 | $1,560.00 | $1,700.00 | $1,546.59 | $1,515.31 | $1,100.00 |
| 0215 | Painted pavement markings, standard, white, skip, 10-30 or skip, 6" wide (0710-11131) | GM | 15.20 | $403.40 | $900.00 | $400.17 | $812.79 | $750.00 |
| 0220 | Painted pavement markings, standard, yellow, solid, 6" (0710-11201) | GM | 7.81 | $1,560.00 | $1,700.00 | $1,546.59 | $1,515.31 | $1,100.00 |
| 0225 | Work zone collision detection and avoidance system for operations (0924-102) | LS | 1 | $28,570 | $13,500 | $82,945 | $40,000 | $25,000 |
| 0230 | Partnering, DO not bid (0999-16) | LS | 1 | $6,000.00 | $6,000.00 | $6,000.00 | $6,000.00 | $6,000.00 |
| 0235 | Initial contingency amount, DO not bid (0999-25) | LS | 1 | $80,981 | $80,981 | $80,981 | $80,981 | $80,981 |
| 0240 | Ground-in rumble strips, 16" (0546-72-1) | GM | 7.11 | $2,170.00 | $2,100.00 | $2,322.36 | $1,300.15 | $2,400.00 |
| 0245 | Single column ground sign assembly, F&I ground mount, than 12 SF (0700-1111) | EACH | 16 | $596.60 | $610.00 | $591.80 | $541.24 | $675.00 |
| 0250 | Single column ground sign assembly, F&I ground mount, 20.0 SF (0700-1112) | EACH | 10 | $2,390.00 | $2,000.00 | $2,367.22 | $1,462.44 | $1,588.00 |
| 0255 | Single column ground sign assembly, F&I ground mount, 30.0 SF (0700-1113) | EACH | 2 | $2,660.00 | $2,900.00 | $2,637.76 | $2,237.02 | $2,321.00 |
| 0260 | Single column ground sign assembly, F&I ground mount, SF sheeting area for back to back signs (0700-1114) | EACH | 2 | $2,390.00 | $3,000.00 | $2,367.22 | $2,910.21 | $2,976.00 |
| 0265 | Single column ground sign assembly, remove (0700-1600) | EACH | 29 | $22.75 | $54.00 | $22.54 | $51.55 | $150.00 |
| 0270 | Multi-column ground sign assembly, F&I ground mount, 50.0 SF (0700-2114) | EACH | 3 | $3,860.00 | $8,400.00 | $3,832.64 | $6,865.57 | $6,810.00 |
| 0275 | Multi-column ground sign assembly, F&I ground mount, 100.0 SF (0700-2115) | EACH | 3 | $6,820.00 | $13,000 | $6,763.48 | $9,943.09 | $9,795.00 |
| 0280 | Multi-column ground sign assembly, F&I ground mount, 1-200.0 SF (0700-2116) | EACH | 6 | $21,600 | $22,300 | $21,418 | $17,125 | $16,815 |
| 0285 | Multi-column ground sign assembly, F&I ground mount, 1-300.0 SF (0700-2117) | EACH | 3 | $28,400 | $25,500 | $28,181 | $24,965 | $24,420 |
| 0290 | Multi-column ground sign assembly, remove (0700-2600) | EACH | 14 | $1,250.00 | $1,400.00 | $1,239.98 | $1,546.39 | $1,700.00 |
| 0295 | Sign panel, furnish & install overhead mount, 21-30 SF (0700-3203) | EACH | 2 | $3,150.00 | $2,300.00 | $3,156.29 | $2,030.46 | $3,500.00 |
| 0300 | Sign panel, furnish & install overhead mount, 101-200 SF (0700-3206) | EACH | 2 | $10,200 | $8,900.00 | $8,664.68 | $7,688.33 | $8,500.00 |
| 0305 | Sign panel, install, 31-50 SF (0700-3404) | EACH | 1 | $340.90 | $4,600.00 | $338.18 | $1,005.15 | $1,126.00 |
| 0310 | Sign panel, remove, 31-50 SF (0700-3604) | EACH | 1 | $170.45 | $540.00 | $169.08 | $309.28 | $450.00 |
| 0315 | Overhead static sign furnish & install, cantilever, 50 FT (0700-4114) | EACH | 2 | $168,864 | $161,500 | $157,567 | $139,812 | $105,000 |
| 0320 | Object marker, type 2 (0705-10-2) | EACH | 4 | $238.65 | $262.00 | $236.73 | $255.36 | $350.00 |
| 0325 | Object marker, type 3 (0705-10-3) | EACH | 4 | $238.65 | $262.00 | $236.73 | $370.01 | $460.00 |
| 0330 | Delineator, flexible tubular (0705-11-1) | EACH | 166 | $85.25 | $143.00 | $84.55 | $106.00 | $130.00 |
| 0335 | Raised pavement marker, type B (0706-1-3) | EACH | 1,653 | $5.10 | $7.50 | $5.08 | $6.42 | $4.00 |
| 0340 | Painted pavement markings, surface (0710-90) | LS | 1 | $20,200 | $38,000 | $20,020 | $33,133 | $53,000 |
| 0345 | Thermoplastic, standard, solid, 18" for diagonals and chevrons (0711-11124) | LF | 933 | $4.55 | $4.00 | $4.51 | $3.31 | $3.33 |
| 0350 | Thermoplastic, standard, message or symbol (0711-11160) | EACH | 2 | $142.05 | $238.00 | $140.90 | $207.08 | $200.00 |
| 0355 | Thermoplastic, preformed, white with black contrast on concrete pavement, message symbol (0711-14560) | EACH | 2 | $369.30 | $536.00 | $366.35 | $465.93 | $1,750.00 |
| 0360 | Thermoplastic, standard-open graded asphalt surfaces solid, 6" (0711-15101) | GM | 3.58 | $7,260.00 | $6,900.00 | $7,214.38 | $5,981.42 | $4,550.00 |
| 0365 | Thermoplastic, standard-open graded asphalt surfaces, solid, 8" (0711-15102) | GM | 0.29 | $7,200.00 | $8,800.00 | $7,214.38 | $7,634.74 | $5,200.00 |
| 0370 | Thermoplastic, standard-open graded asphalt surfaces, skip, 6",10-30 skip or 3-9 lane (0711-15131) | GM | 7.72 | $2,500.00 | $2,700.00 | $2,479.94 | $2,343.05 | $2,150.00 |
| 0375 | Thermoplastic, standard-open graded asphalt surfaces, yellow, solid, 6" (0711-15201) | GM | 3.76 | $7,270.00 | $6,900.00 | $7,214.38 | $5,989.79 | $4,550.00 |
| 0380 | Thermoplastic, standard-other surfaces, white, solid, 6" (0711-16101) | GM | 1.60 | $7,040.00 | $6,500.00 | $6,988.93 | $5,630.72 | $5,100.00 |
| 0385 | Thermoplastic, standard-other surfaces, white, solid, 8" (0711-16102) | GM | 0.34 | $6,940.00 | $8,800.00 | $6,988.93 | $7,598.60 | $5,700.00 |
| 0390 | Thermoplastic, standard-other surfaces, white, skip, 6",10-30 or 3-9 lane drop (0711-16131) | GM | 0.12 | $2,500.00 | $2,300.00 | $2,479.94 | $2,019.00 | $1,550.00 |
| 0395 | Thermoplastic, standard-other surfaces, yellow, solid, 6" (0711-16201) | GM | 1.24 | $7,030.00 | $6,500.00 | $6,988.93 | $5,628.68 | $5,100.00 |
| 0400 | Permanent tape, white, solid, 6" for concrete bridges (0713-103101) | GM | 0.05 | $21,400 | $39,000 | $24,403 | $33,763 | $84,750 |
| 0405 | Permanent tape, white, 10-30 6" wide, for concrete surfaces (0713-103181) | GM | 0.09 | $6,270.00 | $15,000 | $6,763.48 | $11,782 | $25,000 |
| 0410 | Permanent tape, yellow, solid, for concrete bridges (0713-103201) | GM | 0.05 | $21,400 | $38,000 | $24,403 | $33,763 | $84,750 |
| 0415 | Itsfm subsurface documentation- project length (0611-1-1) | MI | 2.76 | $3,330.00 | $4,600.00 | $4,450.76 | $3,940.64 | $3,500.00 |
| 0420 | Itsfm location documentation- ITS site (0611-2-2) | EACH | 3 | $2,100.00 | $3,000.00 | $2,880.98 | $2,556.35 | $1,800.00 |
| 0425 | Conduit, furnish & install, open trench (0630-2-11) | LF | 4,690 | $20.15 | $18.75 | $18.31 | $16.24 | $22.00 |
| 0430 | Conduit, furnish & install, directional bore (0630-2-12) | LF | 1,220 | $50.85 | $47.00 | $45.76 | $40.61 | $45.00 |
| 0435 | Conduit, furnish & install, aboveground (0630-2-14) | LF | 45 | $61.35 | $59.00 | $57.21 | $50.76 | $46.00 |
| 0440 | Fiber optic cable, F&I, underground,2-12 fibers (0633-1121) | LF | 13,200 | $3.75 | $5.15 | $5.04 | $4.47 | $4.90 |
| 0445 | Fiber optic connection, install, splice (0633-2-31) | EACH | 48 | $51.15 | $71.50 | $69.80 | $61.93 | $63.00 |
| 0450 | Fiber optic connection hardware, F&I, splice tray (0633-3-12) | EACH | 3 | $56.80 | $80.00 | $77.81 | $69.04 | $65.00 |
| 0455 | Fiber optic connection hardware, F&I, preterminated connector assembly (0633-3-13) | EACH | 36 | $51.15 | $71.50 | $69.80 | $61.93 | $65.00 |
| 0460 | Fiber optic connection hardware, F&I, patch panel- terminated (0633-3-16) | EACH | 3 | $1,350.00 | $1,900.00 | $1,851.25 | $1,642.64 | $1,950.00 |
| 0465 | Fiber optic connection hardware, F&I, connector panel (0633-3-17) | EACH | 3 | $113.65 | $160.00 | $156.75 | $139.09 | $160.00 |
| 0470 | Fiber optic connection hardware, adjust/modify splice enclosure (0633-3-51) | EACH | 1 | $909.10 | $1,200.00 | $1,241.41 | $1,101.52 | $925.00 |
| 0475 | Fiber optic connection hardware, adjust/modify splice tray (0633-3-52) | EACH | 1 | $28.40 | $40.00 | $38.90 | $34.52 | $65.00 |
| 0480 | Fiber optic cable locator (0633-6) | DA | 168 | $118.20 | $300.00 | $289.47 | $0.01 | $200.00 |
| 0485 | Pull & splice box, F&I, 13" X 24" cover size (0635-2-11) | EACH | 13 | $2,220.00 | $2,100.00 | $2,559.63 | $1,795.94 | $1,850.00 |
| 0490 | Pull & splice box, F&I, 24" X 36" cover size (0635-2-12) | EACH | 15 | $3,730.00 | $3,500.00 | $3,921.17 | $3,004.06 | $3,300.00 |
| 0495 | Electrical power service, adjust/modify (0639-1500) | AS | 2 | $3,520.00 | $1,400.00 | $1,451.94 | $1,288.33 | $3,850.00 |
| 0500 | Electrical service wire, & install (0639-2-1) | LF | 2,395 | $13.05 | $14.00 | $13.73 | $12.18 | $12.00 |
| 0505 | Electrical service disconnect, F&I, pole mount (0639-3-11) | EACH | 5 | $2,340.00 | $3,500.00 | $3,457.63 | $3,068.02 | $3,050.00 |
| 0510 | Electrical service disconnect, remove- pole or cabinet to remain (0639-3-60) | EACH | 2 | $338.65 | $1,400.00 | $1,451.94 | $1,288.33 | $550.00 |
| 0515 | Electrical power service- transformer, F&I, <5 kva, single phase, copper windings (0639-6111) | EACH | 2 | $1,920.00 | $2,300.00 | $2,323.78 | $2,061.93 | $2,750.00 |
| 0520 | Prestressed concrete pole, type P-II service pole (0641-2-12) | EACH | 2 | $2,590.00 | $2,500.00 | $2,457.65 | $2,180.71 | $3,000.00 |
| 0525 | Concrete CCTV pole, furnish & install with lowering device, (0641-3169) | EACH | 1 | $77,000 | $46,000 | $45,359 | $40,248 | $36,150 |
| 0530 | Concrete CCTV pole, furnish & install with lowering device, (0641-3175) | EACH | 2 | $77,000 | $51,000 | $49,921 | $44,295 | $39,250 |
| 0535 | ITS cabinet, furnish & install, pole mount with sunshield, 24" W X 46" H X 22" D (0676-2122) | EACH | 3 | $11,800 | $13,000 | $12,375 | $10,981 | $9,500.00 |
| 0540 | ITS CCTV camera, non- pressurized, IP, high definition (0682-1173) | EACH | 3 | $7,070.00 | $7,000.00 | $6,726.49 | $5,968.53 | $6,900.00 |
| 0545 | Managed field ethernet switch, furnish & install (0684-1-1) | EACH | 3 | $13,300 | $11,000 | $11,101 | $9,849.75 | $9,800.00 |
| 0550 | Managed hub ethernet switch, adjust/modify (0684-7-5) | EACH | 2 | $3,410.00 | $4,300.00 | $4,224.22 | $3,748.23 | $3,500.00 |
| 0555 | Uninterruptible power supply, furnish and install, line interactive (0685-1-11) | EACH | 3 | $7,730.00 | $4,900.00 | $4,703.62 | $4,173.60 | $8,500.00 |
| 0560 | Remote power management rpmu, furnish and install (0685-2-1) | EACH | 3 | $1,950.00 | $820.00 | $799.76 | $709.64 | $1,150.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from FDOT's tabulation for this contract. FDOT Tabulation of Bids PDFs from its central office lettings, January 2018 to October 2026, all pay items. On A+B contracts the cost part is kept (the total the pay items add up to). Bidders listed without a rank or total are left out.
Every contract let that day: FDOT letting of February 25, 2026. Compiled by Mirage Metrics.