FDOT contract T4739 bid tabulation

SR 9 (I-95) FROM N OF GLADES TO N OF SR 91 (FLORIDA TPK). Let by Florida DOT on February 25, 2026, St Lucie, District 4. 5 bids received; low bid $5,138,833 by Ranger Construction Industries, Inc..

Owner
Florida DOT
Letting
25 FEB 2026
Pay items
112
Data through
28 OCT 2026

Bidders

RankBidderTotal bidAgainst the low bid
1Ranger Construction Industries, Inc.$5,138,833Low
2C.W. Roberts Contracting, Inc.$6,026,007+17%
3Timothy Rose Contracting, Inc.$6,257,205+22%
4Ohla USA Inc$6,426,860+25%
5Halley Engineering Contractors, Inc.$6,599,135+28%
FDOT contract T4739: bids by rank

Bid tabulation

LinePay itemUnitQuantity1. Ranger Construction Industries, Inc.2. C.W. Roberts Contracting, Inc.3. Timothy Rose Contracting, Inc.4. Ohla USA Inc5. Halley Engineering Contractors, Inc.
0005Mobilization (0101-1)LS1$284,815$322,000$276,075$642,000$660,000
0010Maintenance of traffic (0102-1)DA1$189,970$183,000$229,660$551,662$660,000
0015Traffic control officer (0102-14)HR3,020$0.01$1.00$84.55$0.01$0.01
0020Work zone sign (0102-60)ED36,482$0.20$0.20$0.01$0.18$0.18
0025Temporary barrier, F&I, anchored (0102-71-15)LF1,100$0.01$45.25$43.46$0.01$40.00
0030Channelizing device- types I, II, VP, drum, or LCD (0102-74-1)ED183,843$0.10$0.10$0.01$0.09$0.01
0035Arrow board / advance warning arrow panel (0102-76)ED1,002$5.65$6.00$0.01$4.00$5.00
0040Temporary crash cushion, redirective option (0102-89-1)LO1$10.00$1,000.00$1,111.33$0.01$1,600.00
0045Portable changeable message sign, temporary (0102-99)ED1,504$9.95$10.50$9.86$9.00$9.00
0050Temporary signalization and maintenance, intersection (0102-104)ED336$24.15$20.00$19.45$17.26$35.00
0055Temporary traffic detection and maintenance, intersection (0102-107-1)ED336$24.15$20.00$19.45$17.26$35.00
0060Existing ITS maintenance (0102-112)DA168$169.30$560.00$546.90$485.28$250.00
0065Type III barricade (0102-115)ED3,060$0.25$0.30$0.01$0.23$0.23
0070Portable regulatory, sign (0102-150-1)ED1,086$4.55$4.75$4.51$4.00$4.00
0075Radar speed display unit (0102-150-2)ED1,086$4.55$5.30$4.51$4.50$4.50
0080Sediment barrier (0104-10-3)LF46,374$0.01$0.50$2.04$1.50$0.01
0085Floating turbidity barrier (0104-11)LF403$20.40$20.00$16.73$20.00$25.00
0090Inlet protection system (0104-18)EACH12$118.15$278.00$198.53$250.00$200.00
0095Litter removal (0107-1)ACRE420.52$59.10$44.00$58.89$50.00$50.00
0100Mowing (0107-2)ACRE367.65$109.10$110.00$147.21$90.00$150.00
0105Clearing & grubbing (0110-1-1)ACRE1$10,500$32,000$80,218$125,000$15,000
0110Milling existing asphalt pavement, 3" avg depth (0327-70-4)SY143$18.70$70.00$7.83$45.00$10.00
0115Milling existing asphalt pavement, 1 1/2" avg depth (0327-70-6)SY57,383$2.30$4.00$2.94$4.00$3.20
0120Milling existing asphalt pavement, 4" avg depth (0327-70-7)SY2,200$5.20$6.00$9.92$7.50$11.00
0125Milling existing asphalt pavement, 2 1/4" avg depth (0327-70-11)SY84,450$2.20$2.35$2.81$4.00$3.85
0130Milling existing asphalt pavement, 1 3/4" avg depth (0327-70-13)SY340$3.80$8.00$7.38$20.00$10.00
0135Superpave asphaltic conc, traffic E (0334-1-15)TN160.80$182.65$165.00$212.18$170.00$198.00
0140Superpave asphaltic concrete, traffic E, PG76-22 (0334-1-55)TN10,559.90$130.65$156.25$158.98$150.50$160.00
0145Asphalt concrete friction course, inc bit, FC-5, PG 76-22 (0337-7-25)TN3,481.50$172.05$235.00$216.42$181.50$221.00
0150Asphalt concrete friction course,traffic E, FC-12.5, PG (0337-7-88)TN1,552.50$158.45$199.00$182.27$146.25$215.00
0155Miscellaneous asphalt (0339-1)TN40.50$277.40$360.00$361.09$350.00$300.00
0160Guardrail -roadway, general (0536-1-1)LF1,096$25.55$26.25$26.34$23.12$23.00
0165Guardrail transition to rigid barrier, F&I- index 536- 002, approach TL-3 (0536-8122)EACH1$4,660.00$3,400.00$3,337.59$3,005.92$2,961.00
0170Guardrail removal (0536-73)LF1,082$2.45$1.00$0.96$0.86$0.85
0175Guardrail end treatment- parallel approach terminal (0536-85-24)EACH1$3,410.00$3,475.00$3,390.63$3,053.70$3,008.00
0180Performance turf, sod (0570-1-2)SY14,617$4.05$4.75$3.08$11.50$5.50
0185Plastic erosion mat, turf reinforced mat, type 1 (0571-1-11)SY1,000$7.25$9.00$9.09$13.00$6.00
0190Pull & splice box, F&I, 13" X 24" cover size (0635-2-11)EACH1$2,480.00$2,000.00$2,559.63$1,795.94$3,400.00
0195Traffic monitoring site vehicle sensor-non-weight, furnish & install (0695-1-1)EACH3$2,750.00$5,800.00$5,717.34$5,073.10$3,500.00
0200Traffic monitoring site inductive loop assembly, & install, 2 loops (0695-6-12)EACH3$2,310.00$5,000.00$4,831.76$4,287.31$2,500.00
0205Raised pavement marker, type B (0706-1-3)EACH1,764$5.10$7.50$5.08$6.47$4.00
0210Painted pavement markings, standard, white, solid, 6" (0710-11101)GM7.81$1,560.00$1,700.00$1,546.59$1,515.31$1,100.00
0215Painted pavement markings, standard, white, skip, 10-30 or skip, 6" wide (0710-11131)GM15.20$403.40$900.00$400.17$812.79$750.00
0220Painted pavement markings, standard, yellow, solid, 6" (0710-11201)GM7.81$1,560.00$1,700.00$1,546.59$1,515.31$1,100.00
0225Work zone collision detection and avoidance system for operations (0924-102)LS1$28,570$13,500$82,945$40,000$25,000
0230Partnering, DO not bid (0999-16)LS1$6,000.00$6,000.00$6,000.00$6,000.00$6,000.00
0235Initial contingency amount, DO not bid (0999-25)LS1$80,981$80,981$80,981$80,981$80,981
0240Ground-in rumble strips, 16" (0546-72-1)GM7.11$2,170.00$2,100.00$2,322.36$1,300.15$2,400.00
0245Single column ground sign assembly, F&I ground mount, than 12 SF (0700-1111)EACH16$596.60$610.00$591.80$541.24$675.00
0250Single column ground sign assembly, F&I ground mount, 20.0 SF (0700-1112)EACH10$2,390.00$2,000.00$2,367.22$1,462.44$1,588.00
0255Single column ground sign assembly, F&I ground mount, 30.0 SF (0700-1113)EACH2$2,660.00$2,900.00$2,637.76$2,237.02$2,321.00
0260Single column ground sign assembly, F&I ground mount, SF sheeting area for back to back signs (0700-1114)EACH2$2,390.00$3,000.00$2,367.22$2,910.21$2,976.00
0265Single column ground sign assembly, remove (0700-1600)EACH29$22.75$54.00$22.54$51.55$150.00
0270Multi-column ground sign assembly, F&I ground mount, 50.0 SF (0700-2114)EACH3$3,860.00$8,400.00$3,832.64$6,865.57$6,810.00
0275Multi-column ground sign assembly, F&I ground mount, 100.0 SF (0700-2115)EACH3$6,820.00$13,000$6,763.48$9,943.09$9,795.00
0280Multi-column ground sign assembly, F&I ground mount, 1-200.0 SF (0700-2116)EACH6$21,600$22,300$21,418$17,125$16,815
0285Multi-column ground sign assembly, F&I ground mount, 1-300.0 SF (0700-2117)EACH3$28,400$25,500$28,181$24,965$24,420
0290Multi-column ground sign assembly, remove (0700-2600)EACH14$1,250.00$1,400.00$1,239.98$1,546.39$1,700.00
0295Sign panel, furnish & install overhead mount, 21-30 SF (0700-3203)EACH2$3,150.00$2,300.00$3,156.29$2,030.46$3,500.00
0300Sign panel, furnish & install overhead mount, 101-200 SF (0700-3206)EACH2$10,200$8,900.00$8,664.68$7,688.33$8,500.00
0305Sign panel, install, 31-50 SF (0700-3404)EACH1$340.90$4,600.00$338.18$1,005.15$1,126.00
0310Sign panel, remove, 31-50 SF (0700-3604)EACH1$170.45$540.00$169.08$309.28$450.00
0315Overhead static sign furnish & install, cantilever, 50 FT (0700-4114)EACH2$168,864$161,500$157,567$139,812$105,000
0320Object marker, type 2 (0705-10-2)EACH4$238.65$262.00$236.73$255.36$350.00
0325Object marker, type 3 (0705-10-3)EACH4$238.65$262.00$236.73$370.01$460.00
0330Delineator, flexible tubular (0705-11-1)EACH166$85.25$143.00$84.55$106.00$130.00
0335Raised pavement marker, type B (0706-1-3)EACH1,653$5.10$7.50$5.08$6.42$4.00
0340Painted pavement markings, surface (0710-90)LS1$20,200$38,000$20,020$33,133$53,000
0345Thermoplastic, standard, solid, 18" for diagonals and chevrons (0711-11124)LF933$4.55$4.00$4.51$3.31$3.33
0350Thermoplastic, standard, message or symbol (0711-11160)EACH2$142.05$238.00$140.90$207.08$200.00
0355Thermoplastic, preformed, white with black contrast on concrete pavement, message symbol (0711-14560)EACH2$369.30$536.00$366.35$465.93$1,750.00
0360Thermoplastic, standard-open graded asphalt surfaces solid, 6" (0711-15101)GM3.58$7,260.00$6,900.00$7,214.38$5,981.42$4,550.00
0365Thermoplastic, standard-open graded asphalt surfaces, solid, 8" (0711-15102)GM0.29$7,200.00$8,800.00$7,214.38$7,634.74$5,200.00
0370Thermoplastic, standard-open graded asphalt surfaces, skip, 6",10-30 skip or 3-9 lane (0711-15131)GM7.72$2,500.00$2,700.00$2,479.94$2,343.05$2,150.00
0375Thermoplastic, standard-open graded asphalt surfaces, yellow, solid, 6" (0711-15201)GM3.76$7,270.00$6,900.00$7,214.38$5,989.79$4,550.00
0380Thermoplastic, standard-other surfaces, white, solid, 6" (0711-16101)GM1.60$7,040.00$6,500.00$6,988.93$5,630.72$5,100.00
0385Thermoplastic, standard-other surfaces, white, solid, 8" (0711-16102)GM0.34$6,940.00$8,800.00$6,988.93$7,598.60$5,700.00
0390Thermoplastic, standard-other surfaces, white, skip, 6",10-30 or 3-9 lane drop (0711-16131)GM0.12$2,500.00$2,300.00$2,479.94$2,019.00$1,550.00
0395Thermoplastic, standard-other surfaces, yellow, solid, 6" (0711-16201)GM1.24$7,030.00$6,500.00$6,988.93$5,628.68$5,100.00
0400Permanent tape, white, solid, 6" for concrete bridges (0713-103101)GM0.05$21,400$39,000$24,403$33,763$84,750
0405Permanent tape, white, 10-30 6" wide, for concrete surfaces (0713-103181)GM0.09$6,270.00$15,000$6,763.48$11,782$25,000
0410Permanent tape, yellow, solid, for concrete bridges (0713-103201)GM0.05$21,400$38,000$24,403$33,763$84,750
0415Itsfm subsurface documentation- project length (0611-1-1)MI2.76$3,330.00$4,600.00$4,450.76$3,940.64$3,500.00
0420Itsfm location documentation- ITS site (0611-2-2)EACH3$2,100.00$3,000.00$2,880.98$2,556.35$1,800.00
0425Conduit, furnish & install, open trench (0630-2-11)LF4,690$20.15$18.75$18.31$16.24$22.00
0430Conduit, furnish & install, directional bore (0630-2-12)LF1,220$50.85$47.00$45.76$40.61$45.00
0435Conduit, furnish & install, aboveground (0630-2-14)LF45$61.35$59.00$57.21$50.76$46.00
0440Fiber optic cable, F&I, underground,2-12 fibers (0633-1121)LF13,200$3.75$5.15$5.04$4.47$4.90
0445Fiber optic connection, install, splice (0633-2-31)EACH48$51.15$71.50$69.80$61.93$63.00
0450Fiber optic connection hardware, F&I, splice tray (0633-3-12)EACH3$56.80$80.00$77.81$69.04$65.00
0455Fiber optic connection hardware, F&I, preterminated connector assembly (0633-3-13)EACH36$51.15$71.50$69.80$61.93$65.00
0460Fiber optic connection hardware, F&I, patch panel- terminated (0633-3-16)EACH3$1,350.00$1,900.00$1,851.25$1,642.64$1,950.00
0465Fiber optic connection hardware, F&I, connector panel (0633-3-17)EACH3$113.65$160.00$156.75$139.09$160.00
0470Fiber optic connection hardware, adjust/modify splice enclosure (0633-3-51)EACH1$909.10$1,200.00$1,241.41$1,101.52$925.00
0475Fiber optic connection hardware, adjust/modify splice tray (0633-3-52)EACH1$28.40$40.00$38.90$34.52$65.00
0480Fiber optic cable locator (0633-6)DA168$118.20$300.00$289.47$0.01$200.00
0485Pull & splice box, F&I, 13" X 24" cover size (0635-2-11)EACH13$2,220.00$2,100.00$2,559.63$1,795.94$1,850.00
0490Pull & splice box, F&I, 24" X 36" cover size (0635-2-12)EACH15$3,730.00$3,500.00$3,921.17$3,004.06$3,300.00
0495Electrical power service, adjust/modify (0639-1500)AS2$3,520.00$1,400.00$1,451.94$1,288.33$3,850.00
0500Electrical service wire, & install (0639-2-1)LF2,395$13.05$14.00$13.73$12.18$12.00
0505Electrical service disconnect, F&I, pole mount (0639-3-11)EACH5$2,340.00$3,500.00$3,457.63$3,068.02$3,050.00
0510Electrical service disconnect, remove- pole or cabinet to remain (0639-3-60)EACH2$338.65$1,400.00$1,451.94$1,288.33$550.00
0515Electrical power service- transformer, F&I, <5 kva, single phase, copper windings (0639-6111)EACH2$1,920.00$2,300.00$2,323.78$2,061.93$2,750.00
0520Prestressed concrete pole, type P-II service pole (0641-2-12)EACH2$2,590.00$2,500.00$2,457.65$2,180.71$3,000.00
0525Concrete CCTV pole, furnish & install with lowering device, (0641-3169)EACH1$77,000$46,000$45,359$40,248$36,150
0530Concrete CCTV pole, furnish & install with lowering device, (0641-3175)EACH2$77,000$51,000$49,921$44,295$39,250
0535ITS cabinet, furnish & install, pole mount with sunshield, 24" W X 46" H X 22" D (0676-2122)EACH3$11,800$13,000$12,375$10,981$9,500.00
0540ITS CCTV camera, non- pressurized, IP, high definition (0682-1173)EACH3$7,070.00$7,000.00$6,726.49$5,968.53$6,900.00
0545Managed field ethernet switch, furnish & install (0684-1-1)EACH3$13,300$11,000$11,101$9,849.75$9,800.00
0550Managed hub ethernet switch, adjust/modify (0684-7-5)EACH2$3,410.00$4,300.00$4,224.22$3,748.23$3,500.00
0555Uninterruptible power supply, furnish and install, line interactive (0685-1-11)EACH3$7,730.00$4,900.00$4,703.62$4,173.60$8,500.00
0560Remote power management rpmu, furnish and install (0685-2-1)EACH3$1,950.00$820.00$799.76$709.64$1,150.00
FDOT contract T4739: unit prices by line

The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.

Source

Read from FDOT's tabulation for this contract. FDOT Tabulation of Bids PDFs from its central office lettings, January 2018 to October 2026, all pay items. On A+B contracts the cost part is kept (the total the pay items add up to). Bidders listed without a rank or total are left out.

Every contract let that day: FDOT letting of February 25, 2026. Compiled by Mirage Metrics.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy