FDOT contract T5875 bid tabulation
SR 5 (US 1) OVER PELLICER CREEK, BRIDE NOS 730076 AND 730077. Let by Florida DOT on January 28, 2026, Flagler, District 5. 6 bids received; low bid $12,582,375 by C.W. Roberts Contracting, Inc..
- Owner
- Florida DOT
- Letting
- 28 JAN 2026
- Pay items
- 124
- Data through
- 28 OCT 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | C.W. Roberts Contracting, Inc. | $12,582,375 | Low |
| 2 | Superior Construction Company Southeast, LLC | $13,653,497 | +9.0% |
| 3 | Sema Construction, Inc. | $14,295,000 | +14% |
| 4 | Masci General Contractors, Inc | $14,376,122 | +14% |
| 5 | Vecellio & Grogan, Inc. | $15,797,898 | +26% |
| 6 | Southland Construction, Inc. | $15,944,444 | +27% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. C.W. Roberts Contracting, Inc. | 2. Superior Construction Company Southeast, LLC | 3. Sema Construction, Inc. | 4. Masci General Contractors, Inc | 5. Vecellio & Grogan, Inc. | 6. Southland Construction, Inc. |
|---|---|---|---|---|---|---|---|---|---|
| 0005 | Removal of existing structures/bridges (0110-3) | SF | 1 | $265,000 | $242,440 | $600,000 | $550,000 | $520,000 | $1,137,000 |
| 0010 | Removal of existing structures/bridges (0110-3) | SF | 1 | $178,000 | $204,205 | $600,000 | $550,000 | $520,000 | $1,117,000 |
| 0015 | Concrete class II, approach slabs (0400-2-10) | CY | 193.80 | $756.00 | $800.00 | $1,200.00 | $1,100.00 | $790.00 | $746.00 |
| 0020 | Concrete class IV, superstructure (0400-4-4) | CY | 590.80 | $1,506.00 | $1,285.00 | $1,800.00 | $2,300.00 | $1,250.00 | $1,360.00 |
| 0025 | Concrete class IV, bridge substructure (0400-4-5) | CY | 252.70 | $2,075.00 | $2,068.00 | $2,800.00 | $2,450.00 | $2,000.00 | $3,800.00 |
| 0030 | Bridge deck grooving (0400-7-1) | SY | 2,168 | $9.30 | $9.00 | $7.00 | $14.00 | $7.00 | $5.65 |
| 0035 | Bridge deck planing (0400-9-1) | SY | 2,168 | $7.50 | $11.00 | $7.00 | $14.00 | $14.00 | $10.18 |
| 0040 | Composite neoprene pads (0400-147) | CF | 17 | $2,601.00 | $1,335.00 | $2,500.00 | $2,300.00 | $1,825.00 | $2,345.00 |
| 0045 | Reinforcing steel - bridge superstructure (0415-1-4) | LB | 107,496 | $1.40 | $1.20 | $1.20 | $1.85 | $1.45 | $1.35 |
| 0050 | Reinforcing steel- approach slabs (0415-1-9) | LB | 37,792 | $1.40 | $1.20 | $1.20 | $1.85 | $1.45 | $1.55 |
| 0055 | Fiber reinforced polymer bars, #4 bar (0415-10-4) | LF | 11,144 | $1.70 | $1.50 | $1.70 | $2.75 | $2.55 | $2.57 |
| 0060 | Fiber reinforced polymer bars, #5 bar (0415-10-5) | LF | 3,470 | $1.70 | $1.55 | $2.80 | $2.75 | $5.00 | $2.61 |
| 0065 | Fiber reinforced polymer bars, #6 bar (0415-10-6) | LF | 20,938 | $3.00 | $2.65 | $2.60 | $3.00 | $3.90 | $3.88 |
| 0070 | Fiber reinforced polymer bars, #8 bar (0415-10-8) | LF | 12,008 | $3.10 | $2.75 | $2.90 | $4.50 | $4.40 | $4.00 |
| 0075 | Prest beams: florida-I beam 36" (0450-2-36) | LF | 1,914 | $331.00 | $328.00 | $540.00 | $393.00 | $350.00 | $413.50 |
| 0080 | Preformed pile holes, 30" to 34" drill/punch size (0455-15-15) | LF | 1,120 | $78.00 | $113.00 | $65.00 | $185.00 | $45.00 | $97.90 |
| 0085 | Pile inspection, driven pile (0455-20-1) | EACH | 44 | $2,430.00 | $950.00 | $520.00 | $1,100.00 | $700.00 | $537.00 |
| 0090 | Prestressed concrete piling, SQ (0455-34-5) | LF | 2,088 | $200.00 | $181.00 | $180.00 | $312.00 | $200.00 | $171.50 |
| 0095 | Prestressed concrete piling, SQ W/FRP or stainless steel strand and reinforcing (0455-34-25) | LF | 2,614 | $386.00 | $338.00 | $340.00 | $452.00 | $385.00 | $343.35 |
| 0100 | Pile redrive (0455-115) | EACH | 6 | $6,846.00 | $1,460.00 | $3,800.00 | $6,500.00 | $2,900.00 | $8,318.00 |
| 0105 | Load test (dynamic), data collection and analysis (0455-137) | EACH | 44 | $1,969.00 | $1,673.00 | $1,200.00 | $1,100.00 | $2,750.00 | $1,788.00 |
| 0110 | Load test (dynamic), test (0455-137-2) | EACH | 8 | $1,969.00 | $700.00 | $2,300.00 | $3,900.00 | $5,500.00 | $7,321.00 |
| 0115 | Test piles-prestressed concrete,24" SQ (0455-143-5) | LF | 560 | $208.00 | $450.00 | $290.00 | $369.00 | $325.00 | $381.85 |
| 0120 | Test piles-prestressed concrete, 24" SQ W/ FRP or stainless steel strand and reinforcing (0455-143-25) | LF | 560 | $399.00 | $550.00 | $450.00 | $525.00 | $500.00 | $534.50 |
| 0125 | Bridge deck expansion joint, construction, F&I poured joint with backer rod (0458-1-11) | LF | 164 | $121.00 | $63.00 | $120.00 | $129.00 | $55.00 | $103.00 |
| 0130 | Concrete traffic railing- 36" single-slope (0521-5-13) | LF | 1,200 | $140.00 | $101.00 | $98.00 | $155.00 | $160.00 | $130.50 |
| 0135 | Riprap, sand-cement bags (0530-1100) | CY | 54.40 | $1,051.00 | $811.00 | $1,800.00 | $990.00 | $1,300.00 | $1,050.00 |
| 0140 | Riprap- rubble, bank and shore (0530-3-3) | TN | 1,688.40 | $157.00 | $113.00 | $140.00 | $215.00 | $175.00 | $182.00 |
| 0145 | Bedding stone (0530-74) | TN | 601.30 | $164.00 | $195.00 | $190.00 | $175.00 | $225.00 | $281.00 |
| 0150 | Conduit, furnish & install, embedded concrete barriers and traffic railings (0630-2-16) | LF | 3,600 | $16.00 | $8.25 | $19.00 | $15.50 | $29.00 | $16.20 |
| 0155 | Junction box, furnish & install, embedded (0635-3-13) | EACH | 8 | $1,164.00 | $403.00 | $1,100.00 | $900.00 | $1,200.00 | $1,040.00 |
| 0160 | Mobilization (0101-1) | LS | 1 | $1,200,000 | $1,360,000 | $1,400,000 | $1,306,920 | $1,380,000 | $1,590,000 |
| 0165 | Maintenance of traffic (0102-1) | DA | 1 | $325,000 | $198,000 | $100,000 | $503,500 | $175,000 | $700,000 |
| 0170 | Special detour- temporary pavement (0102-2200) | SY | 1 | $180,000 | $86,000 | $150,000 | $105,050 | $430,000 | $150,000 |
| 0175 | Special detour- temporary earthwork/base (0102-2300) | CY | 1 | $180,000 | $62,000 | $160,000 | $149,895 | $150,000 | $170,000 |
| 0180 | Commercial material for temporary driveway maintenance (0102-3) | CY | 349.20 | $37.00 | $25.00 | $320.00 | $56.00 | $135.00 | $85.00 |
| 0185 | Work zone sign (0102-60) | ED | 20,810 | $0.30 | $0.20 | $0.20 | $0.23 | $0.20 | $0.25 |
| 0190 | Temporary barrier, F&I, free standing (0102-71-16) | LF | 1,713 | $34.00 | $22.00 | $23.00 | $25.00 | $45.00 | $36.00 |
| 0195 | Temporary barrier, relocate, free standing (0102-71-26) | LF | 1,613 | $16.00 | $8.00 | $8.00 | $10.00 | $18.00 | $18.00 |
| 0200 | Channelizing device- types I, II, VP, drum, or LCD (0102-74-1) | ED | 83,690 | $0.10 | $0.09 | $0.10 | $0.12 | $0.11 | $0.11 |
| 0205 | Temporary separator, F&I remove (0102-75-1) | LF | 4,098 | $14.50 | $13.75 | $15.00 | $16.00 | $24.00 | $15.80 |
| 0210 | Arrow board / advance warning arrow panel (0102-76) | ED | 1,020 | $6.00 | $5.00 | $5.00 | $5.50 | $5.80 | $6.20 |
| 0215 | Temporary crash cushion, redirective option (0102-89-1) | LO | 5 | $1,065.00 | $1,375.00 | $3,700.00 | $1,300.00 | $1,025.00 | $1,200.00 |
| 0220 | Portable changeable message sign, temporary (0102-99) | ED | 960 | $11.50 | $10.00 | $10.00 | $12.00 | $11.00 | $12.30 |
| 0225 | Type III barricade (0102-115) | ED | 4,800 | $0.30 | $0.25 | $0.25 | $0.30 | $0.30 | $0.31 |
| 0230 | Removable tape, yellow, solid, (0102-913-31) | GM | 0.09 | $15,800 | $13,500 | $16,000 | $17,000 | $17,500 | $16,000 |
| 0235 | Artificial coverings /rolled erosion control products (0104-1) | SY | 136 | $10.00 | $32.75 | $5.00 | $7.50 | $17.50 | $6.00 |
| 0240 | Sediment barrier (0104-10-3) | LF | 4,258 | $1.00 | $2.50 | $1.10 | $2.50 | $13.50 | $0.95 |
| 0245 | Floating turbidity barrier (0104-11) | LF | 1,106 | $15.00 | $16.00 | $11.00 | $29.65 | $37.00 | $12.60 |
| 0250 | Staked turbidity barrier- nylon reinforced PVC (0104-12) | LF | 1,570 | $8.00 | $10.50 | $5.50 | $10.50 | $10.00 | $8.00 |
| 0255 | Soil tracking prevention device (0104-15) | EACH | 4 | $4,500.00 | $6,500.00 | $3,800.00 | $3,500.00 | $8,500.00 | $3,800.00 |
| 0260 | Inlet protection system (0104-18) | EACH | 4 | $160.00 | $375.00 | $250.00 | $250.00 | $350.00 | $300.00 |
| 0265 | Litter removal (0107-1) | ACRE | 305.06 | $64.00 | $1.00 | $61.00 | $185.00 | $135.00 | $68.00 |
| 0270 | Mowing (0107-2) | ACRE | 273.24 | $123.00 | $1.00 | $120.00 | $300.00 | $175.00 | $130.00 |
| 0275 | Monitor existing structures- inspection and settlement monitoring (0108-1) | LS | 1 | $29,000 | $10,900 | $7,200.00 | $22,900 | $8,500.00 | $13,000 |
| 0280 | Monitor existing structures- vibration monitoring (0108-2) | LS | 1 | $29,500 | $13,216 | $10,300 | $27,900 | $75,000 | $4,000.00 |
| 0285 | Clearing & grubbing (0110-1-1) | ACRE | 1 | $319,000 | $2,488,213 | $615,056 | $156,910 | $1,050,000 | $590,132 |
| 0290 | Removal of existing concrete (0110-4-10) | SY | 112 | $21.00 | $95.00 | $22.00 | $15.00 | $55.00 | $15.00 |
| 0295 | Mailbox, F&I single (0110-7-1) | EACH | 1 | $530.00 | $980.00 | $510.00 | $300.00 | $550.00 | $210.00 |
| 0300 | Regular excavation (0120-1) | CY | 1,138.20 | $6.00 | $25.00 | $60.00 | $14.50 | $97.00 | $8.00 |
| 0305 | Embankment (0120-6) | CY | 9,513.40 | $17.00 | $14.50 | $1.00 | $14.50 | $65.00 | $1.00 |
| 0310 | Type B stabilization (0160-4) | SY | 12,788 | $8.50 | $11.00 | $19.00 | $12.50 | $30.00 | $11.00 |
| 0315 | Soil stabilization/improvement column supported embankment (0173-79100) | 1 | $2,192,000 | $1,625,000 | $2,000,000 | $1,420,075 | $1,700,000 | $2,075,000 | |
| 0320 | Optional base, base group 01 (0285-701) | SY | 3,823 | $24.00 | $21.00 | $15.00 | $29.65 | $45.00 | $27.00 |
| 0325 | Optional base, base group 09 (0285-709) | SY | 7,459 | $29.00 | $28.00 | $26.00 | $39.65 | $45.00 | $29.00 |
| 0330 | Milling existing asphalt pavement, 2 1/4" avg depth (0327-70-11) | SY | 646 | $8.00 | $9.50 | $14.00 | $2.75 | $15.00 | $10.60 |
| 0335 | Milling existing asphalt pavement, 3/4" avg depth (0327-70-19) | SY | 12,200 | $3.80 | $5.00 | $5.50 | $2.35 | $5.00 | $4.90 |
| 0340 | Superpave asphaltic conc, traffic C (0334-1-13) | TN | 741.60 | $125.00 | $135.00 | $210.00 | $149.56 | $295.00 | $151.50 |
| 0345 | Superpave asphaltic concrete, traffic C, PG76-22 (0334-1-53) | TN | 988.10 | $154.00 | $165.00 | $240.00 | $167.59 | $325.00 | $186.30 |
| 0350 | Asphalt concrete friction course, inc bit, FC-5, PG 76-22 (0337-7-25) | TN | 948.10 | $250.00 | $265.00 | $320.00 | $205.15 | $375.00 | $299.30 |
| 0355 | Miscellaneous asphalt (0339-1) | TN | 69.80 | $240.00 | $500.00 | $410.00 | $275.45 | $900.00 | $450.00 |
| 0360 | Conc class IV, retaining walls (0400-4-11) | CY | 99.60 | $1,483.00 | $1,775.00 | $1,900.00 | $1,950.00 | $1,350.00 | $1,478.93 |
| 0365 | Reinforcing steel- retaining wall (0415-1-3) | LB | 11,521 | $1.80 | $1.50 | $1.20 | $1.75 | $1.75 | $1.64 |
| 0370 | Inlets, DT bot, type C,<10' (0425-1521) | EACH | 1 | $5,800.00 | $7,145.00 | $6,100.00 | $10,254 | $7,050.00 | $9,200.00 |
| 0375 | Inlets, ditch bottom, type C, partial (0425-1525) | EACH | 2 | $1,905.00 | $3,045.00 | $5,100.00 | $7,345.00 | $7,500.00 | $2,800.00 |
| 0380 | Inlets, gutter, type S, <10' (0425-1701) | EACH | 7 | $8,700.00 | $7,160.00 | $7,900.00 | $12,525 | $6,500.00 | $8,800.00 |
| 0385 | Pipe culvert optional material, round, 18", gutter drain (0430-173118) | LF | 111 | $209.00 | $406.00 | $730.00 | $124.58 | $270.00 | $252.00 |
| 0390 | Pipe culvert, optional material, round, 24"SD (0430-174124) | LF | 51 | $224.00 | $175.00 | $520.00 | $199.65 | $1,400.00 | $352.00 |
| 0395 | Pipe culvert,optional material,round, 18"S/CD (0430-175118) | LF | 69 | $186.00 | $203.00 | $800.00 | $144.29 | $285.00 | $292.00 |
| 0400 | U-endwall with baffles, index 261/430-011, 1:3 slope, 18"pipe (0430-611225) | EACH | 4 | $4,750.00 | $6,235.00 | $3,500.00 | $4,997.00 | $3,500.00 | $6,000.00 |
| 0405 | Mitered end section, optional round, 24" SD (0430-984129) | EACH | 1 | $5,660.00 | $4,198.00 | $4,100.00 | $4,129.00 | $3,750.00 | $4,060.00 |
| 0410 | Shoulder gutter- concrete (0520-6) | LF | 932 | $38.00 | $32.00 | $41.00 | $47.59 | $135.00 | $42.00 |
| 0415 | Concrete barrier, with slab, 36" single slope (0521-8-7) | LF | 135 | $391.00 | $460.00 | $380.00 | $375.00 | $615.00 | $596.00 |
| 0420 | Concrete sidewalk and driveways, 6" thick (0522-2) | SY | 78 | $85.00 | $91.00 | $110.00 | $90.00 | $150.00 | $91.50 |
| 0425 | Concrete ditch pavement, non reinforced, 4" (0524-1-2) | SY | 30 | $174.00 | $123.00 | $110.00 | $150.00 | $520.00 | $109.00 |
| 0430 | Riprap, rubble, F&I, ditch lining (0530-3-4) | TN | 77 | $177.00 | $147.00 | $150.00 | $215.00 | $350.00 | $238.00 |
| 0435 | Bedding stone (0530-74) | TN | 55.20 | $212.00 | $422.00 | $230.00 | $175.00 | $290.00 | $253.00 |
| 0440 | Guardrail -roadway, general (0536-1-1) | LF | 1,062 | $26.00 | $24.00 | $25.00 | $27.19 | $32.00 | $27.50 |
| 0445 | Guardrail- roadway, double (0536-1-3) | LF | 231 | $35.00 | $33.00 | $34.00 | $42.69 | $47.00 | $37.80 |
| 0450 | Guardrail transition to rigid barrier, F&I- index 536- 001, approach TL-3 (0536-8112) | EACH | 4 | $3,500.00 | $3,250.00 | $3,400.00 | $3,450.00 | $3,500.00 | $3,700.00 |
| 0455 | Guardrail transition to rigid barrier, F&I- index 536- 001, trailing (0536-8113) | EACH | 2 | $2,150.00 | $2,000.00 | $2,100.00 | $1,974.00 | $1,000.00 | $2,290.00 |
| 0460 | Guardrail removal (0536-73) | LF | 1,608 | $2.50 | $2.00 | $2.10 | $2.50 | $1.90 | $2.25 |
| 0465 | Guardrail end treatment- trailing anchorage (0536-85-20) | EACH | 2 | $2,150.00 | $2,000.00 | $2,100.00 | $1,974.00 | $1,700.00 | $2,290.00 |
| 0470 | Guardrail end treatment- parallel approach terminal (0536-85-24) | EACH | 2 | $3,440.00 | $3,200.00 | $3,300.00 | $3,495.00 | $3,500.00 | $3,660.00 |
| 0475 | Crash cushion, TL-3, narrow (0544-3-1) | EACH | 2 | $24,200 | $22,500 | $23,400 | $34,100 | $33,000 | $25,700 |
| 0480 | Performance turf, sod (0570-1-2) | SY | 12,992 | $6.00 | $6.60 | $6.00 | $5.25 | $4.60 | $3.90 |
| 0485 | Performance turf, sod and shoulder treatment index (0570-1-3) | SY | 585 | $8.00 | $11.20 | $15.00 | $10.25 | $7.10 | $3.50 |
| 0490 | Conduit, furnish & install, embedded concrete barriers and traffic railings (0630-2-16) | LF | 405 | $15.50 | $9.50 | $12.00 | $15.50 | $28.00 | $16.20 |
| 0495 | Junction box, furnish & install, embedded (0635-3-13) | EACH | 1 | $1,165.00 | $575.00 | $510.00 | $900.00 | $1,650.00 | $1,040.00 |
| 0500 | Raised pavement marker, type B (0706-1-3) | EACH | 2,181 | $5.30 | $5.00 | $5.50 | $6.00 | $5.75 | $6.00 |
| 0505 | Painted pavement markings, standard, white, solid, 6" (0710-11101) | GM | 2.75 | $1,700.00 | $1,600.00 | $1,300.00 | $2,500.00 | $2,800.00 | $1,900.00 |
| 0510 | Painted pavement markings, standard, yellow, solid, 6" (0710-11201) | GM | 3.47 | $1,698.00 | $1,600.00 | $1,300.00 | $2,500.00 | $2,800.00 | $1,900.00 |
| 0515 | Painted pavement markings, standard, yellow, 2-4 dotted guideline/6-10 dotted extension, 6" (0710-11241) | GM | 0.19 | $1,065.00 | $1,000.00 | $1,600.00 | $1,000.00 | $750.00 | $1,200.00 |
| 0520 | Initial contingency amount, DO not bid (0999-25) | LS | 1 | $117,250 | $117,250 | $117,250 | $117,250 | $117,250 | $117,250 |
| 0525 | Ground-in rumble strips, 8" sinusoidal (0546-72-3) | GM | 2.28 | $9,132.00 | $5,900.00 | $2,000.00 | $7,500.00 | $6,800.00 | $5,000.00 |
| 0530 | Single column ground sign assembly, F&I ground mount, than 12 SF (0700-1111) | EACH | 5 | $585.00 | $537.00 | $530.00 | $936.00 | $1,000.00 | $1,050.00 |
| 0535 | Single column ground sign assembly, F&I ground mount, 30.0 SF (0700-1113) | EACH | 1 | $3,700.00 | $3,264.00 | $2,200.00 | $2,750.00 | $3,500.00 | $3,520.00 |
| 0540 | Single column ground sign assembly, relocate (0700-1500) | EACH | 5 | $106.00 | $165.00 | $210.00 | $990.00 | $350.00 | $575.00 |
| 0545 | Single column ground sign assembly, remove (0700-1600) | EACH | 9 | $53.00 | $40.00 | $51.00 | $225.00 | $120.00 | $285.00 |
| 0550 | Retroreflective sign strip- furnish and install, 5' (0700-13-15) | EACH | 1 | $266.00 | $102.00 | $130.00 | $200.00 | $180.00 | $135.00 |
| 0555 | Tubular marker, 36" yellow (0704-1-4) | EACH | 2 | $160.00 | $223.00 | $130.00 | $285.00 | $350.00 | $170.00 |
| 0560 | Object marker, type 1 (0705-10-1) | EACH | 2 | $266.00 | $117.00 | $290.00 | $285.00 | $400.00 | $235.00 |
| 0565 | Object marker, type 3 (0705-10-3) | EACH | 4 | $372.00 | $337.00 | $290.00 | $285.00 | $400.00 | $235.00 |
| 0570 | Raised pavement marker, type B (0706-1-3) | EACH | 242 | $5.30 | $5.00 | $5.50 | $6.00 | $5.85 | $6.00 |
| 0575 | Painted pavement markings, surface (0710-90) | LS | 1 | $10,640 | $10,000 | $5,000.00 | $15,000 | $13,000 | $11,000 |
| 0580 | Thermoplastic, standard, arrow (0711-11170) | EACH | 4 | $160.00 | $150.00 | $300.00 | $175.00 | $150.00 | $172.00 |
| 0585 | Thermoplastic, standard, yellow, 2-4 dotted guide line dotted extension line, 6" (0711-11241) | GM | 0.16 | $5,058.00 | $4,500.00 | $7,000.00 | $2,700.00 | $6,000.00 | $5,200.00 |
| 0590 | Thermoplastic, standard-open graded asphalt surfaces solid, 6" (0711-15101) | GM | 1.23 | $6,950.00 | $6,500.00 | $6,300.00 | $7,600.00 | $9,000.00 | $7,500.00 |
| 0595 | Thermoplastic, standard-open graded asphalt surfaces, skip, 6",10-30 skip or 3-9 lane (0711-15131) | GM | 1.23 | $4,810.00 | $4,500.00 | $2,100.00 | $1,900.00 | $9,000.00 | $5,200.00 |
| 0600 | Thermoplastic, standard-open graded asphalt surfaces, yellow, solid, 6" (0711-15201) | GM | 1.07 | $6,926.00 | $6,500.00 | $6,300.00 | $7,600.00 | $9,000.00 | $7,400.00 |
| 0605 | Permanent tape, white, solid, 6" for concrete bridges (0713-103101) | GM | 0.09 | $40,500 | $35,000 | $52,000 | $85,000 | $90,000 | $40,000 |
| 0610 | Permanent tape, white, 10-30 6" wide, for concrete surfaces (0713-103181) | GM | 0.09 | $17,350 | $15,000 | $14,000 | $17,000 | $20,000 | $17,000 |
| 0615 | Permanent tape, yellow, solid, for concrete bridges (0713-103201) | GM | 0.09 | $40,500 | $35,000 | $52,000 | $8,500.00 | $90,000 | $40,000 |
| 0620 | Permanent tape, black, 10-30 6" wide, for concrete surfaces (0713-103381) | GM | 0.09 | $17,357 | $15,000 | $12,000 | $17,000 | $20,000 | $17,000 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from FDOT's tabulation for this contract. FDOT Tabulation of Bids PDFs from its central office lettings, January 2018 to October 2026, all pay items. On A+B contracts the cost part is kept (the total the pay items add up to). Bidders listed without a rank or total are left out.
Every contract let that day: FDOT letting of January 28, 2026. Compiled by Mirage Metrics.