FDOT contract T6587 bid tabulation

SR 972 (CORAL WAY / SW 3 AVE) FROM W OF SW 12 AVE TO BRICK.. Let by Florida DOT on January 29, 2025, Miami-Dade, District 6. 7 bids received; low bid $11,128,266 by General Asphalt Company, LLC.

Owner
Florida DOT
Letting
29 JAN 2025
Pay items
206
Data through
28 OCT 2026

Bidders

RankBidderTotal bidAgainst the low bid
1General Asphalt Company, LLC$11,128,266Low
2Jva Engineering Contractor, Inc$11,841,505+6.0%
3Bacallao Construction & Engineering Development, LLC D/B/A B$12,312,013+11%
4Ohla USA Inc$12,429,319+12%
5Roadway Construction, LLC$12,536,420+13%
6Aum Construction Inc.$12,974,705+17%
7Florida Engineering & Development Corp$12,993,051+17%
FDOT contract T6587: bids by rank

Bid tabulation

LinePay itemUnitQuantity1. General Asphalt Company, LLC2. Jva Engineering Contractor, Inc3. Bacallao Construction & Engineering Development, LLC D/B/A B4. Ohla USA Inc5. Roadway Construction, LLC6. Aum Construction Inc.
0005Mobilization (0101-1)LS1$300,000$876,500$1,000,000$500,000$1,253,642$500,000
0010Mobilization (0101-1)LS1$75,000$151,000$230,000$500,000$1,253,642$500,000
0015Maintenance of traffic (0102-1)DA1$800,000$297,400$225,000$500,000$277,543$175,000
0020Maintenance of traffic (0102-1)DA1$200,000$44,600$110,863$365,000$37,295$200,000
0025Traffic control officer (0102-14)HR1,068$88.00$70.00$85.00$70.00$70.00$90.00
0030Work zone sign (0102-60)ED81,520$0.22$0.30$0.23$0.20$0.19$0.35
0035Temporary barrier, F&I, low profile, concrete (0102-71-13)LF492$53.90$61.30$0.01$0.01$49.00$80.00
0040Channelizing device- types I, II, VP, drum, or LCD (0102-74-1)ED163,890$0.12$0.19$0.11$0.10$0.09$0.20
0045Channelizing device- pedestrian LCD (longitudinal channelizing device) (0102-74-8)FD238,000$0.03$0.13$0.04$0.03$0.03$0.10
0050Arrow board / advance warning arrow panel (0102-76)ED2,770$5.50$12.50$6.00$5.20$5.00$10.00
0055Portable changeable message sign, temporary (0102-99)ED5,244$9.90$18.70$10.00$9.40$9.00$12.00
0060Temporary signalization and maintenance, intersection (0102-104)ED4,620$17.85$14.00$6.30$6.40$16.93$12.00
0065Temporary traffic detection and maintenance, intersection (0102-107-1)ED4,620$1.28$14.00$6.30$6.40$1.21$12.00
0070Type III barricade (0102-115)ED3,120$0.03$1.25$0.25$0.30$0.23$0.50
0075Removable tape, white, solid 6" (0102-913-21)GM0.09$11,000$5.85$6.00$21,000$13,500$20,000
0080Removable tape, white, 24" stop bar (0102-913-23)LF11$11.00$23.40$20.00$100.00$20.00$50.00
0085Removable tape, yellow, solid, (0102-913-31)GM0.15$11,000$31,500$30,000$20,000$13,776$20,000
0090Removable tape, yellow, 10'-30', 9', 6'-10', or 2'-4' skip (0102-913-32)GM0.02$11,000$8,580.00$8,500.00$30,000$7,222.22$15,000
0095Sediment barrier (0104-10-3)LF14,347$1.10$3.70$0.01$0.01$2.15$3.50
0100Inlet protection system (0104-18)EACH131$132.00$179.00$50.00$230.00$110.00$250.00
0105Litter removal (0107-1)ACRE178.46$0.01$230.00$0.01$55.00$0.01$150.00
0110Mowing (0107-2)ACRE144.97$0.01$250.00$0.01$155.00$0.01$150.00
0115Monitor existing structures- inspection and settlement monitoring (0108-1)LS1$1.10$47,900$10,000$60,000$1,000.00$45,000
0120Monitor existing structures- inspection and settlement monitoring (0108-1)LS1$1.10$4,850.00$10,000$50,000$750.00$45,000
0125Monitor existing structures- vibration monitoring (0108-2)LS1$1.10$8,190.00$8,000.00$5,000.00$7,000.00$15,000
0130Clearing & grubbing (0110-1-1)ACRE1$30,256$93,600$220,000$265,000$228,884$40,000
0135Clearing & grubbing (0110-1-1)ACRE1$20,187$9,360.00$10,000$265,000$228,884$25,000
0140Clearing & grubbing (0110-1-1)ACRE1$24,750$10,530$12,500$265,000$228,884$32,000
0145Removal of existing concrete (0110-4-10)SY6,013$27.50$21.00$30.00$33.00$18.24$35.00
0150Tree protection barrier (0110-21)LF11,302$9.90$4.30$0.01$8.00$6.00$15.00
0155Tree root and branch pruning (0110-22)EACH20$1,320.00$5,265.00$1,000.00$4,275.00$1,000.00$6,000.00
0160Tree removal (0110-23)EACH7$3,300.00$3,510.00$1,500.00$900.00$1,500.00$3,000.00
0165Borrow excavation, truck measure (0120-2-2)CY97.80$27.50$45.00$50.00$68.00$89.83$50.00
0170Regular excavation (3-R projects only) (0120-71)LS1$20,350$29,460$35,000$30,000$22,681$25,000
0175Regular excavation (3-R projects only) (0120-71)LS1$16,500$9,580.00$20,000$10,500$5,668.40$21,000
0180Type B stabilization (0160-4)SY1,358$7.43$28.00$0.01$1.00$28.87$20.00
0185Reworking limerock base, 4" (0210-1-8)SY972$1.10$45.60$15.00$4.25$19.78$50.00
0190Reworking limerock base, 3" (0210-1-9)SY127$1.10$24.90$16.00$33.00$17.29$70.00
0195Optional base, base group 06 (0285-706)SY574$46.20$45.70$60.00$80.00$50.85$70.00
0200Optional base, base group 09 (0285-709)SY784$49.50$55.80$110.00$95.00$40.44$80.00
0205Optional base, base group 11 (0285-711)SY287$52.80$85.70$200.00$90.00$70.30$85.00
0210Turnout base- optional materials (0286-1)SY294$57.20$48.00$34.00$50.00$56.53$75.00
0215Milling existing asphalt pavement, 1 1/2" avg depth (0327-70-6)SY16,493$3.33$5.81$7.00$5.50$3.78$5.00
0220Milling existing asphalt pavement, 2 1/2" avg depth (0327-70-8)SY67,247$4.28$7.00$7.00$5.20$4.87$6.00
0225Milling existing asphalt pavement, 1 1/4" avg depth (0327-70-12)SY2,427$8.54$7.00$7.00$24.20$9.70$5.50
0230Superpave asphaltic conc, traffic C (0334-1-13)TN4,815.70$165.09$196.00$210.00$187.00$180.00$215.00
0235Asphalt concrete friction course,traffic C, FC-9.5, PG 76-22 (0337-7-82)TN6,287.30$194.39$234.00$250.00$200.00$216.00$255.00
0240Inlets, curb, type 9, <10' (0425-1201)EACH2$13,587$8,470.00$8,500.00$12,250$7,946.88$18,500
0245Inlets, curb, type 9, partial (0425-1205)EACH1$7,975.00$7,070.00$4,800.00$6,125.00$5,386.29$11,000
0250Inlets, ditch bottom, type F, J bot, <10' (0425-1563)EACH4$17,859$10,130$10,500$12,250$9,621.56$24,500
0255Inlets, ditch bottom, type F, partial (0425-1565)EACH1$6,358.00$7,190.00$4,000.00$6,125.00$5,908.34$9,000.00
0260Manholes, P-7, <10' (0425-2-41)EACH4$10,780$8,440.00$10,000$12,500$7,631.38$15,000
0265Inlets, adjust (0425-4)EACH28$572.00$2,340.00$750.00$2,050.00$909.60$1,000.00
0270Manhole, adjust (0425-5)EACH62$880.00$1,050.00$750.00$815.00$787.82$1,500.00
0275Pipe culvert,optional material,round, 12"S/CD (0430-175112)LF4$880.00$1,010.00$740.00$300.00$573.48$1,200.00
0280Pipe culvert,optional material,round, 15"S/CD (0430-175115)LF4$880.00$870.00$800.00$300.00$581.87$1,200.00
0285Pipe culvert,optional material,round, 18"S/CD (0430-175118)LF49$550.00$323.00$350.00$300.00$449.90$850.00
0290Pipe culvert,optional material,round, 24"S/CD (0430-175124)LF10$880.00$450.00$225.00$300.00$454.17$1,300.00
0295French drain, 24" (0443-70-4)LF265$412.50$249.00$340.00$400.00$301.82$600.00
0300Concrete curb & gutter, type E (0520-1-7)LF45$63.80$117.00$46.00$54.00$54.46$85.00
0305Concrete curb & gutter, type F (0520-1-10)LF4,547$74.80$53.00$45.00$50.00$39.75$95.00
0310Concrete curb, type D (0520-2-4)LF1,286$42.90$49.00$42.00$38.00$36.19$60.00
0315Concrete sidewalk and driveways, 4" thick (0522-1)SY1,624$90.20$71.00$80.00$82.00$64.61$110.00
0320Concrete sidewalk and driveways, 6" thick (0522-2)SY4,756$121.00$84.50$110.00$94.00$92.92$140.00
0325Pavers, architectural, (0526-1-2)SY8$260.70$340.00$425.00$400.00$350.00$500.00
0330Pavers, architectural, remove existing and reinstall (0526-1101)SY65$99.00$141.00$260.00$300.00$85.00$150.00
0335Detectable warnings (0527-2)SF2,073$35.20$41.00$34.00$38.00$33.59$45.00
0340Guardrail removal (0536-73)LF17$11.00$100.00$6.00$20.00$100.00$100.00
0345Performance turf, sod (0570-1-2)SY3,033$10.78$13.90$3.50$17.00$16.99$20.00
0350Performance turf, sod and shoulder treatment index (0570-1-3)SY4,069$16.87$14.70$8.00$14.00$20.77$30.00
0355Conduit, furnish & install, directional bore (0630-2-12)LF173$47.88$76.00$42.25$36.00$45.42$40.00
0360Pull & splice box, F&I, 13" X 24" cover size (0635-2-11)EACH4$1,882.79$2,340.00$1,650.00$1,710.00$1,785.88$1,800.00
0365Electrical power service- contribution in aid of construction (ciac), FPL (DO not bid) (0639-8130)LS1$14,000$14,000$14,000$14,000$14,000$14,000
0370Electrical power service- contribution in aid of construction (ciac), FPL (DO not bid) (0639-8130)LS1$4,000.00$4,000.00$4,000.00$4,000.00$4,000.00$4,000.00
0375Traffic monitoring site vehicle sensor-non-weight, furnish & install (0695-1-1)EACH9$2,087.39$2,925.00$2,050.00$2,065.00$1,979.85$2,000.00
0380Traffic monitoring site inductive loop assembly, & install, 2 loops (0695-6-12)EACH9$2,322.41$2,340.00$2,750.00$2,650.00$2,202.86$1,800.00
0385Traffic monitoring site cabinet, furnish & install, type 3, pedestal mount (0695-7132)EACH2$9,555.04$7,605.00$11,000$10,225$9,063.21$10,000
0390Painted pavement markings, standard, white, solid, 6" (0710-11101)GM3.87$2,750.00$3,089.00$3,100.00$1,700.00$1,350.35$2,000.00
0395Painted pavement markings, standard, white, solid for interchange and urban island, (0710-11102)GM1.26$2,915.00$3,410.00$3,400.00$2,250.00$1,494.02$2,500.00
0400Painted pavement markings, standard, white, solid for crosswalk and roundabout, 12" (0710-11123)LF7,126$1.10$1.00$0.90$1.50$1.00$1.50
0405Painted pavement markings, standard, white, solid for diagonal or chevron, 18" (0710-11124)LF1,370$1.65$1.40$1.40$1.60$2.00$3.00
0410Painted pavement markings, standard, white, solid for stop line or crosswalk, 24" (0710-11125)LF1,586$2.20$1.90$1.75$1.70$3.00$4.50
0415Painted pavement markings, standard, white, skip, 10-30 or skip, 6" wide (0710-11131)GM3.42$2,750.00$772.00$775.00$500.00$799.77$1,200.00
0420Painted pavement markings, standard, white, 2-4 dotted guideline/ 6-10 dotted 6" (0710-11141)GM1.26$2,750.00$772.00$775.00$675.00$800.00$1,200.00
0425Painted pavement markings, standard, white, message or symbol (0710-11160)EACH95$55.00$70.00$70.00$33.00$85.00$130.00
0430Painted pavement markings, standard, white, arrows (0710-11170)EACH96$33.00$35.00$35.00$33.00$40.00$60.00
0435Painted pavement markings, standard, white, yield line (0710-11180)LF377$1.10$4.70$4.50$5.00$15.00$22.50
0440Painted pavement markings, standard, yellow, solid, 6" (0710-11201)GM2.46$2,750.00$2,570.00$2,500.00$1,700.00$1,345.61$2,000.00
0445Painted pavement markings, standard, yellow, solid for interchange and urban island, (0710-11202)GM1.73$2,915.00$1,280.00$1,550.00$2,250.00$1,500.00$2,500.00
0450Painted pavement markings, standard, yellow, solid for diagonal or chevron, 18" (0710-11224)LF634$1.65$1.40$1.25$1.60$2.00$3.00
0455Painted pavement markings, standard, yellow, 2-4 dotted guideline/6-10 dotted extension, 6" (0710-11241)GM0.29$2,750.00$765.00$800.00$670.00$791.81$4,000.00
0460Painted pavement markings, standard, blue, solid for parking lot- accessible markings, 6" (0710-11421)LF104$2.20$1.00$1.00$3.00$5.00$10.00
0465Initial contingency amount, DO not bid (0999-25)LS1$98,324$98,324$98,324$98,324$98,324$98,324
0470Initial contingency amount, DO not bid (0999-25)LS1$2,852.00$2,852.00$2,852.00$2,852.00$2,852.00$2,852.00
0475Initial contingency amount, DO not bid (0999-25)LS1$16,572$16,572$16,572$16,572$16,572$16,572
0480Conduit, furnish & install, directional bore (0630-2-12)LF30$49.71$117.00$41.00$40.00$47.15$40.00
0485Loop detector inductive, F&I, type 2 (0660-1102)EACH2$545.35$655.00$1,000.00$860.00$517.28$200.00
0490Single column ground sign assembly, F&I ground mount, than 12 SF (0700-1111)EACH215$544.50$579.00$450.00$425.00$500.00$800.00
0495Single column ground sign assembly, F&I ground mount, 20.0 SF (0700-1112)EACH11$1,705.00$2,750.00$350.00$1,375.00$1,800.00$1,500.00
0500Single column ground sign assembly, F&I ground mount, 30.0 SF (0700-1113)EACH33$1,815.00$2,980.00$1,725.00$1,550.00$1,900.00$1,900.00
0505Single column ground sign assembly, F&I ground mount, SF sheeting area for back to back signs (0700-1114)EACH22$2,145.00$2,980.00$2,900.00$1,850.00$1,850.00$2,500.00
0510Single column ground sign assembly, install (0700-1400)EACH3$440.00$1,164.00$450.00$135.00$300.00$950.00
0515Single column ground sign assembly, relocate (0700-1500)EACH4$385.00$497.00$350.00$225.00$300.00$1,500.00
0520Single column ground sign assembly, remove (0700-1600)EACH176$44.00$11.70$20.00$25.00$150.00$150.00
0525Single column ground sign assembly, F&I cantilever mount, less than 12 SF (0700-1911)EACH8$715.00$1,860.00$450.00$500.00$525.00$2,250.00
0530Sign panel, furnish & install ground mount, UP to 12 SF (0700-3101)EACH7$715.00$216.00$275.00$200.00$250.00$600.00
0535Sign panel, furnish & install ground mount, 12-20 SF (0700-3102)EACH2$935.00$240.00$550.00$350.00$350.00$825.00
0540Sign panel, furnish & install overhead mount, 51-100 SF (0700-3205)EACH4$6,297.45$5,675.00$3,500.00$3,000.00$2,905.90$7,700.00
0545Sign panel, furnish & install overhead mount, 101-200 SF (0700-3206)EACH1$8,214.33$11,000$5,000.00$4,150.00$4,105.30$11,000
0550Sign panel, relocate, UP to 12 SF (0700-3501)EACH95$440.00$438.00$650.00$150.00$100.00$400.00
0555Sign panel, relocate, 12-20 SF (0700-3502)EACH1$1,045.00$678.00$850.00$380.00$150.00$1,050.00
0560Sign panel, remove, UP to 12 SF (0700-3601)EACH33$71.50$82.00$150.00$185.00$100.00$150.00
0565Sign panel, remove, 12-20 SF (0700-3602)EACH3$82.50$117.00$150.00$175.00$150.00$400.00
0570Sign panel, remove, 51-100 SF (0700-3605)EACH2$825.00$702.00$900.00$525.00$748.30$900.00
0575Overhead static sign furnish & install, cantilever, 40 FT (0700-4113)EACH1$121,380$162,000$90,000$88,000$86,199$130,000
0580Overhead static sign furnish & install, cantilever, 50 FT (0700-4114)EACH1$135,055$263,250$100,000$100,000$99,294$150,000
0585Overhead static sign shallow foundation removal, span (0700-4621)EACH2$19,229$17,550$7,250.00$6,000.00$5,986.40$25,000
0590Retroreflective sign strip- furnish and install, 5' (0700-13-15)EACH117$115.50$105.00$125.00$95.00$110.00$135.00
0595Object marker, type 3 (0705-10-3)EACH1$247.50$462.00$100.00$225.00$300.00$225.00
0600Object marker, type 4 (0705-10-4)EACH2$247.50$462.00$100.00$250.00$300.00$375.00
0605Delineator, flexible tubular (0705-11-1)EACH40$110.00$105.00$100.00$135.00$100.00$200.00
0610Raised pavement marker, type B (0706-1-3)EACH4,340$3.85$5.80$5.00$3.75$5.00$7.50
0615Painted pavement markings, standard, yellow, island nose (0710-11290)SF145$5.50$2.30$2.25$4.00$5.00$10.00
0620Painted pavement markings, durable paint, yellow, island nose (0710-12290)SF140$5.50$2.30$2.25$4.00$6.00$12.00
0625Painted pavement markings, surface (0710-90)LS1$49,143$34,380$45,000$33,750$30,000$40,000
0630Painted pavement markings, surface (0710-90)LS1$14,179$23,400$10,000$8,425.00$7,000.00$10,000
0635Thermoplastic, standard, solid, 12" for crosswalk and roundabout (0711-11123)LF3,254$2.20$2.80$2.75$3.20$4.00$6.00
0640Thermoplastic, standard, solid, 18" for diagonals and chevrons (0711-11124)LF1,370$3.30$4.20$4.25$4.80$5.00$7.50
0645Thermoplastic, standard, solid, 24" for stop line and crosswalk (0711-11125)LF1,526$4.40$5.60$5.50$6.50$6.00$9.00
0650Thermoplastic, standard, 2-4 dotted guideline/ 6-10 gap extension, 6" (0711-11141)GM1.26$4,647.50$1,850.00$1,750.00$2,500.00$3,500.00$5,000.00
0655Thermoplastic, standard, message or symbol (0711-11160)EACH51$132.00$140.00$140.00$125.00$225.00$3.50
0660Thermoplastic, standard, arrow (0711-11170)EACH96$66.00$93.00$95.00$69.00$85.00$130.00
0665Thermoplastic, standard, yield line (0711-11180)LF377$1.10$23.00$23.00$8.00$15.00$23.00
0670Thermoplastic, standard, yellow, solid, 18" for diagonal or chevron (0711-11224)LF634$3.30$4.20$4.25$4.50$5.00$7.50
0675Thermoplastic, standard, yellow, 2-4 dotted guide line dotted extension line, 6" (0711-11241)GM0.29$4,647.50$7,330.00$7,500.00$2,475.00$3,464.16$5,000.00
0680Thermoplastic, standard, blue, solid,6" (0711-11421)LF104$4.40$0.70$0.70$4.00$10.00$15.00
0685Thermoplastic, preformed, white, solid, 12" for crosswalk (0711-14123)LF3,827$13.20$12.80$13.00$9.00$8.00$15.00
0690Thermoplastic, preformed, white, solid, 24" for crosswalk (0711-14125)LF3,614$22.00$22.20$22.00$18.00$16.00$25.00
0695Thermoplastic, preformed, white, message (0711-14160)EACH86$385.00$304.00$310.00$355.00$285.00$425.00
0700Thermoplastic, preformed, white, arrow (0711-14170)EACH38$220.00$175.00$175.00$115.00$100.00$150.00
0705Thermoplastic, preformed, color route shield (0711-14660)EACH2$3,300.00$3,530.00$3,500.00$3,025.00$2,500.00$4,000.00
0710Thermoplastic, standard-other surfaces, white, solid, 6" (0711-16101)GM3.79$5,808.00$7,410.00$7,500.00$5,225.00$5,500.00$8,500.00
0715Thermoplastic, standard-other surfaces, white, solid, 8" (0711-16102)GM1.34$6,930.00$7,716.24$7,750.00$7,000.00$6,040.27$9,000.00
0720Thermoplastic, standard-other surfaces, white, skip, 6",10-30 or 3-9 lane drop (0711-16131)GM3.36$5,808.00$1,850.00$1,800.00$1,300.00$3,498.96$5,000.00
0725Thermoplastic, standard-other surfaces white, skip, 12"- approach to toll plaza or 3-9 lane drop (0711-16133)GM0.05$5,808.00$3,432.00$4,000.00$2,400.00$6,481.48$20,000
0730Thermoplastic, standard-other surfaces, yellow, solid, 6" (0711-16201)GM2.46$5,808.00$7,420.00$7,500.00$5,225.00$5,504.48$8,000.00
0735Thermoplastic, standard-other surfaces, yellow, solid, 8" (0711-16202)GM1.73$6,930.00$7,720.00$7,900.00$7,000.00$6,000.00$9,000.00
0740Green-colored pavement markings, bike lane (0714-10)SF814$11.00$11.70$10.00$9.00$10.00$15.00
0745Conduit, furnish & install, directional bore (0630-2-12)LF1,875$44.50$41.00$85.00$84.00$42.50$40.00
0750Pull & splice box, F&I, 13" X 24" cover size (0635-2-11)EACH130$1,882.79$1,989.00$1,700.00$1,715.00$1,785.88$1,800.00
0755Electrical power service, F&I, underground, meter by contractor (0639-1122)AS5$5,192.25$7,254.00$7,250.00$7,135.00$4,924.99$7,500.00
0760Electrical power service, remove underground (0639-1620)AS4$1,020.15$995.00$900.00$860.00$967.64$750.00
0765Electrical service wire, & install (0639-2-1)LF440$12.03$17.50$18.00$17.50$11.42$10.00
0770Electrical service wire, (0639-2-6)LF235$0.64$1.20$0.25$0.20$0.06$1.00
0775Electrical service disconnect, F&I, pole mount (0639-3-11)EACH5$4,860.35$4,563.00$4,000.00$4,135.00$4,610.28$1,750.00
0780Electrical service disconnect, remove- pole or cabinet to remain (0639-3-60)EACH1$765.12$655.00$600.00$575.00$725.73$500.00
0785Prestressed concrete pole, type P-II service pole (0641-2-12)EACH5$4,445.74$3,393.00$3,500.00$3,500.00$4,216.90$2,500.00
0790Prestressed concrete pole, complete pole removal- pedestal/service pole (0641-2-60)EACH5$765.12$1,053.00$900.00$860.00$725.73$750.00
0795Lighting conductors, F&I, insulated, no.8 - 6 (0715-1-12)LF7,894$4.02$3.50$4.50$4.20$3.81$3.25
0800Lighting conductors, F&I, insulated, no 4 to no 2 (0715-1-13)LF1,580$6.09$6.60$5.00$5.00$5.78$5.00
0805Lighting conductors, remove & dispose, contractor owns (0715-1-60)LF3,930$0.51$0.53$0.25$0.20$0.48$0.50
0810Load center, F&I, secondary voltage (0715-7-11)EACH5$19,699$26,325$18,000$18,000$18,685$20,000
0815Load center, remove, voltage (0715-7-41)EACH5$1,530.23$1,050.00$1,100.00$1,150.00$1,451.47$750.00
0820Luminaire, F&I- replace existing luminaire on existing pole/arm, roadway, pendant/teardrop (0715-11216)EACH59$3,267.98$2,726.00$3,100.00$3,100.00$3,099.77$2,300.00
0825Pole cable distribution system, furnish and install, conventional (0715-500-1)EACH74$1,458.77$1,040.00$1,250.00$1,200.00$1,383.67$750.00
0830Light pole complete- special design, F&I, single arm shoulder mount, aluminum, 20' (0715-511120)EACH7$21,319$19,830$16,000$15,600$20,221$18,000
0835Light pole complete- special design, remove (0715-550000)EACH6$1,275.20$700.00$900.00$860.00$1,209.56$1,500.00
0840Conduit, furnish & install, directional bore (0630-2-12)LF7,854$44.04$46.80$100.00$96.00$41.77$40.00
0845Signal cable- new or reconstructed intersection, furnish & install (0632-7-1)PI8$10,907$10,530$20,500$17,125$10,346$15,000
0850Signal cable, remove- intersection (0632-7-6)PI1$2,040.31$995.00$1,100.00$1,800.00$1,935.29$750.00
0855Pull & splice box, F&I, 13" X 24" cover size (0635-2-11)EACH247$1,808.14$1,989.00$2,000.00$1,900.00$1,715.07$1,800.00
0860Pull & splice box, F&I, 24" X 36" cover size (0635-2-12)EACH8$3,066.82$3,740.00$3,000.00$2,635.00$2,908.96$3,500.00
0865Pull & splice box, install (0635-2-30)EACH16$1,351.93$1,400.00$900.00$870.00$1,282.35$1,500.00
0870Electrical power service, F&I, underground, meter by contractor (0639-1122)AS16$7,265.90$6,550.00$5,500.00$4,900.00$6,891.89$7,500.00
0875Electrical service wire, & install (0639-2-1)LF3,263$12.03$11.70$15.00$12.70$11.42$10.00
0880Electrical service wire, (0639-2-6)LF160$0.51$0.59$0.25$0.20$0.48$1.00
0885Electrical service disconnect, remove- pole or cabinet to remain (0639-3-60)EACH4$765.12$995.00$900.00$760.00$725.73$500.00
0890Prestressed concrete pole, type P-II service pole (0641-2-12)EACH16$4,445.74$655.00$3,250.00$3,125.00$4,216.90$2,500.00
0895Prestressed concrete pole, complete pole removal- pedestal/service pole (0641-2-60)EACH5$765.12$3,800.00$900.00$760.00$725.73$750.00
0900Aluminum signals pole, (0646-1-11)EACH61$3,006.66$175.00$3,000.00$2,600.00$2,851.90$2,000.00
0905Aluminum signals pole, remove (0646-1-60)EACH22$765.12$175.00$900.00$760.00$725.73$500.00
0910Vehicular signal auxiliaries, repair/replace/retrofit- & install, backplate- flexible required (0650-2109)EACH51$1,113.49$1,111.00$550.00$500.00$1,056.17$600.00
0915Pedestrian signal, furnish & install LED countdown, 1 way (0653-1-11)AS50$1,173.65$1,400.00$900.00$825.00$1,113.23$1,800.00
0920Pedestrian signal, furnish & install LED countdown, 2 ways (0653-1-12)AS11$2,175.20$2,165.00$2,000.00$1,735.00$2,063.23$2,500.00
0925Pedestrian signal, remove ped signal- pole/pedestal to remain (0653-1-60)AS24$255.04$58.50$150.00$125.00$241.91$250.00
0930Midblock crosswalk: rectangular rapid flashing beacon, furnish & install- AC, complete sign assembly- back back (0654-2-12)AS11$16,235$11,670$15,000$13,325$15,400$16,000
0935Midblock crosswalk: rectangular rapid flashing beacon, remove complete sign assembly (0654-2-60)AS10$1,020.15$1,400.00$900.00$760.00$967.64$1,500.00
0940Loop detector inductive, F&I, type 9 (0660-1109)EACH2$456.71$760.00$400.00$360.00$433.20$250.00
0945Loop assembly, F&I, type F (0660-2106)AS6$2,486.92$2,925.00$2,800.00$2,350.00$2,358.91$1,800.00
0950Vehicle detection system- furnish & install cabinet equipment (0660-4-11)EACH6$8,958.96$9,595.00$7,900.00$6,500.00$8,497.82$10,000
0955Vehicle detection system- furnish & install above ground equipment (0660-4-12)EACH8$5,504.47$3,800.00$3,500.00$3,000.00$5,221.14$4,000.00
0960Vehicle detection system- adjust/modify above ground equipment (0660-4-52)EACH4$1,434.88$1,400.00$1,225.00$1,020.00$1,361.03$2,000.00
0965Pedestrian detector, furnish & install, standard (0665-1-11)EACH75$462.41$655.00$300.00$265.00$438.60$450.00
0970Pedestrian detector, furnish & install, accessible (0665-1-12)EACH10$2,264.34$4,500.00$2,500.00$2,115.00$2,147.79$1,500.00
0975Pedestrian detector, remove- pole/pedestal to remain (0665-1-60)EACH16$127.52$53.00$150.00$125.00$120.96$50.00
0980Traffic controller assembly, furnish & install model 2070 (0670-5140)AS7$53,868$54,990$75,000$51,000$51,095$50,000
0985Traffic controller assembly, remove controller with (0670-5600)AS7$2,040.31$936.00$1,200.00$1,000.00$1,935.29$1,500.00
0990Network device, cellular (0684-90102)EACH7$3,187.48$2,925.00$2,000.00$2,000.00$3,023.41$2,500.00
0995Sign panel, furnish & install ground mount, UP to 12 SF (0700-3101)EACH4$1,550.89$216.00$800.00$680.00$1,470.22$950.00
1000Sign panel, furnish & install overhead mount, UP to 12 SF (0700-3201)EACH5$1,887.99$1,123.00$1,325.00$1,135.00$1,790.80$1,500.00
1005Sign panel, remove, UP to 12 SF (0700-3601)EACH5$255.04$122.00$200.00$190.00$241.91$250.00
1010Internally illuminated sign, furnish & install ground UP to 12 SF (0700-5-11)EACH3$5,663.69$4,095.00$4,000.00$3,815.00$5,372.17$4,000.00
1015Internally illuminated sign, remove (0700-5-60)EACH3$1,020.15$526.00$300.00$250.00$967.64$750.00
1020Enhanced highway sign AC powered, F&I ground mount, W/eds, UP to 12 SF of static sign panels (0700-141131)EACH4$18,170$14,040$19,000$16,400$17,235$16,000
1025Enhanced highway sign AC powered, F&I ground mount, W/eds, 12-20 SF of static sign panels (0700-141132)EACH2$18,675$20,475$19,000$16,400$17,714$17,000
1030Enhanced highway sign AC powered, remove - ground mount (0700-141902)EACH2$1,020.15$995.00$900.00$760.00$967.64$1,500.00
FDOT contract T6587: unit prices by line, the 6 lowest bidders (all in the CSV)

The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.

Source

Read from FDOT's tabulation for this contract. FDOT Tabulation of Bids PDFs from its central office lettings, January 2018 to October 2026, all pay items. On A+B contracts the cost part is kept (the total the pay items add up to). Bidders listed without a rank or total are left out.

Every contract let that day: FDOT letting of January 29, 2025. Compiled by Mirage Metrics.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy