FDOT contract T6615 bid tabulation

SR 5 (US 1 / BISCAYNE BLVD) FROM S OF NE 38TH ST TO NE 61... Let by Florida DOT on December 3, 2025, Miami-Dade, District 6. 8 bids received; low bid $6,267,634 by General Asphalt Company, LLC.

Owner
Florida DOT
Letting
03 DEC 2025
Pay items
145
Data through
28 OCT 2026

Bidders

RankBidderTotal bidAgainst the low bid
1General Asphalt Company, LLC$6,267,634Low
2Weekley Asphalt Paving, Inc.$6,286,7210.0%
3Bacallao Construction & Engineering Development, LLC D/B/A BC&E$6,574,213+5.0%
4Florida Engineering & Development Corp$7,055,440+13%
5Ohla USA Inc$7,304,730+17%
6The Stout Group LLC$7,358,335+17%
7Aum Construction Inc.$7,397,446+18%
8Asphalt Group, Inc.$7,863,373+25%
FDOT contract T6615: bids by rank

Bid tabulation

LinePay itemUnitQuantity1. General Asphalt Company, LLC2. Weekley Asphalt Paving, Inc.3. Bacallao Construction & Engineering Development, LLC D/B/A BC&E4. Florida Engineering & Development Corp5. Ohla USA Inc6. The Stout Group LLC
0005Mobilization (0101-1)LS1$100,000$105,530$350,000$350,000$365,000$350,000
0010Mobilization (0101-1)LS1$100,000$114,400$300,000$350,000$365,000$350,000
0015Maintenance of traffic (0102-1)DA1$275,000$144,000$110,537$200,000$300,000$350,000
0020Maintenance of traffic (0102-1)DA1$275,000$156,000$100,000$194,000$305,902$350,000
0025Traffic control officer (0102-14)HR732$84.00$89.00$75.00$81.20$0.01$95.00
0030Work zone sign (0102-60)ED25,260$0.18$0.20$0.18$0.18$0.18$0.18
0035Channelizing device- types I, II, VP, drum, or LCD (0102-74-1)ED75,650$0.09$0.08$0.10$0.10$0.10$0.10
0040Channelizing device- pedestrian LCD (longitudinal channelizing device) (0102-74-8)FD125,760$0.04$0.04$0.04$0.04$0.03$0.04
0045Arrow board / advance warning arrow panel (0102-76)ED570$4.73$4.25$5.00$5.08$4.88$5.00
0050Portable changeable message sign, temporary (0102-99)ED3,632$8.93$9.00$8.50$9.08$9.21$8.95
0055Temporary signalization and maintenance, intersection (0102-104)ED2,660$5.99$5.00$5.00$5.08$5.08$5.00
0060Temporary traffic detection and maintenance, intersection (0102-107-1)ED2,660$5.99$5.00$5.00$5.08$5.08$5.00
0065Type III barricade (0102-115)ED1,280$0.24$0.25$0.23$0.32$0.25$0.32
0070Inlet protection system (0104-18)EACH238$126.00$16.00$50.00$130.38$268.10$150.00
0075Litter removal (0107-1)ACRE375.97$1.05$15.00$0.01$19.30$119.92$1.00
0080Mowing (0107-2)ACRE295.79$1.05$15.00$0.01$29.33$100.00$1.00
0085Monitor existing structures- inspection and settlement monitoring (0108-1)LS1$1.05$5,000.00$1.00$4,009.25$69,373$30,000
0090Monitor existing structures- inspection and settlement monitoring (0108-1)LS1$1.05$5,000.00$1.00$4,009.25$1.04$30,000
0095Monitor existing structures- vibration monitoring (0108-2)LS1$1.05$1,400.00$1.00$5,227.25$1.00$15,000
0100Monitor existing structures- vibration monitoring (0108-2)LS1$1.05$1,400.00$1.00$5,227.25$1.00$15,000
0105Clearing & grubbing (0110-1-1)ACRE1$6,195.00$114,150$70,000$4,526.90$50,000$75,000
0110Clearing & grubbing (0110-1-1)ACRE1$24,255$114,149$15,000$11,317$50,000$75,000
0115Removal of existing concrete (0110-4-10)SY5,960$34.96$37.33$30.00$29.38$40.00$25.00
0120Tree protection barrier (0110-21)LF2,540$10.50$14.00$0.01$9.66$9.78$15.00
0125Tree root and branch pruning (0110-22)EACH18$1,260.00$1,334.00$1,200.00$3,552.50$3,000.00$1,100.00
0130Borrow excavation, truck measure (0120-2-2)CY89.70$111.09$150.00$50.00$139.17$1.00$100.00
0135Regular excavation (3-R projects only) (0120-71)LS1$21,000$11,834$750.00$4,319.43$100,000$10,000
0140Type B stabilization (0160-4)SY26$57.89$55.00$0.01$40.80$81.40$100.00
0145Optional base, base group 09 (0285-709)SY26$139.09$90.00$55.00$47.62$255.80$300.00
0150Milling existing asphalt pavement, 1 1/2" avg depth (0327-70-6)SY97,419$2.89$3.00$4.25$3.35$4.00$3.25
0155Superpave asphaltic conc, traffic C (0334-1-13)TN624.80$187.62$215.00$200.00$209.44$146.75$215.00
0160Asphalt concrete friction course,traffic C, FC-12.5, PG (0337-7-83)TN8,038.50$181.76$193.75$200.00$210.00$146.75$225.00
0165Miscellaneous asphalt (0339-1)TN6.30$1,049.16$375.00$350.00$244.57$1,590.25$250.00
0170Cleaning & sealing joints- concrete pavement (0350-5)LF529$13.11$9.00$40.00$15.22$20.00$50.00
0175Concrete pavement slab replacement (0353-70)CY39$997.50$2,600.00$650.00$558.25$800.00$1,500.00
0180Manhole, adjust (0425-5)EACH49$945.00$1,200.00$750.00$967.50$1,203.70$950.00
0185Bullet rail, double rail (0515-4-2)LF20$262.50$250.00$125.00$253.75$122.00$85.00
0190Concrete curb & gutter, type F (0520-1-10)LF4,216$25.20$57.90$50.00$45.42$56.15$40.00
0195Concrete curb, type D (0520-2-4)LF34$22.05$79.00$50.00$50.05$180.15$35.00
0200Valley gutter- concrete (0520-3)LF294$33.08$65.00$50.00$52.41$136.29$42.00
0205Traffic separator concrete- type IV, 4' wide (0520-5-41)LF193$50.40$93.82$190.00$142.69$191.60$95.00
0210Traffic separator concrete- type IV, 6' wide (0520-5-42)LF19$50.40$146.50$320.00$177.98$531.32$120.00
0215Concrete sidewalk and driveways, 4" thick (0522-1)SY1,510$51.40$89.31$85.00$69.62$95.77$60.00
0220Concrete sidewalk and driveways, 6" thick (0522-2)SY3,187$62.16$93.00$125.00$88.75$108.42$80.00
0225Patterned pavement (0523-3)SY1,091$498.75$45.00$48.00$482.12$482.23$180.00
0230Detectable warnings (0527-2)SF1,242$32.92$44.00$35.00$34.75$46.94$45.00
0235Guardrail -roadway, general/low speed TL-2 (0536-1-0)LF162$23.10$22.00$25.00$22.33$23.00$20.00
0240Guardrail transition to rigid barrier, F&I- index 536- 002, approach TL-3 (0536-8122)EACH2$4,410.00$4,200.00$4,100.00$4,263.00$3,628.00$4,300.00
0245Guardrail removal (0536-73)LF181$4.20$400.00$1.00$4.06$3.00$3.00
0250Guardrail end treatment- parallel approach terminal (0536-85-24)EACH2$3,570.00$3,400.00$4,100.00$3,451.00$3,579.00$3,000.00
0255Performance turf, sod (0570-1-2)SY404$5.78$18.00$5.00$9.02$14.40$25.00
0260Performance turf, sod and shoulder treatment index (0570-1-3)SY9$15.75$100.00$25.00$10.11$14.40$25.00
0265Electrical power service- contribution in aid of construction (ciac), FPL (DO not bid) (0639-8130)LS1$7,000.00$7,000.00$7,000.00$7,000.00$7,000.00$7,000.00
0270Electrical power service- contribution in aid of construction (ciac), FPL (DO not bid) (0639-8130)LS1$3,000.00$3,000.00$3,000.00$3,000.00$3,000.00$3,000.00
0275Initial contingency amount, DO not bid (0999-25)LS1$33,359$33,359$33,359$33,359$33,359$33,359
0280Initial contingency amount, DO not bid (0999-25)LS1$41,774$41,774$41,774$41,774$41,774$41,774
0285Single column ground sign assembly, F&I ground mount, than 12 SF (0700-1111)EACH82$577.50$550.00$550.00$558.25$609.14$599.00
0290Single column ground sign assembly, F&I ground mount, 20.0 SF (0700-1112)EACH8$2,047.50$1,950.00$1,700.00$1,979.25$2,182.74$1,850.00
0295Single column ground sign assembly, F&I ground mount, 30.0 SF (0700-1113)EACH11$2,677.50$2,550.00$3,000.00$2,588.25$2,690.36$2,650.00
0300Single column ground sign assembly, F&I ground mount, SF sheeting area for back to back signs (0700-1114)EACH13$2,089.50$1,990.00$4,000.00$2,019.85$2,817.26$3,850.00
0305Single column ground sign assembly, relocate (0700-1500)EACH4$446.25$425.00$400.00$431.38$862.95$450.00
0310Single column ground sign assembly, remove (0700-1600)EACH66$10.50$10.00$10.00$10.15$45.69$50.00
0315Sign panel, furnish & install ground mount, 101-200 SF (0700-3106)EACH1$6,142.50$5,850.00$5,500.00$5,937.75$5,203.05$8,500.00
0320Sign panel, install, 21-30 SF (0700-3403)EACH1$315.00$300.00$1,325.00$304.50$1,675.13$1,500.00
0325Sign panel, relocate, UP to 12 SF (0700-3501)EACH68$393.75$375.00$150.00$380.63$142.13$150.00
0330Sign panel, remove, UP to 12 SF (0700-3601)EACH1$73.50$70.00$12.00$71.05$45.69$50.00
0335Sign panel, remove, 21-30 SF (0700-3603)EACH1$126.00$120.00$12.00$152.25$45.69$50.00
0340Sign panel, remove, 101-200 SF (0700-3606)EACH1$567.00$540.00$12.00$548.10$177.67$3,000.00
0345Retroreflective sign strip- furnish and install, 5' (0700-13-15)EACH41$105.00$100.00$12.00$101.50$126.90$150.00
0350Object marker, type 1 (0705-10-1)EACH13$367.50$350.00$450.00$355.25$329.95$400.00
0355Delineator, flexible tubular (0705-11-1)EACH23$84.00$90.00$150.00$91.35$128.15$100.00
0360Raised pavement marker, type B (0706-1-3)EACH4,038$3.68$5.00$4.50$5.08$4.27$4.00
0365Painted pavement markings, durable paint, yellow, island nose (0710-12290)SF236$5.25$2.00$3.50$2.03$5.34$2.00
0370Painted pavement markings, surface (0710-90)LS1$42,000$29,600$35,000$32,480$22,004$37,127
0375Painted pavement markings, surface (0710-90)LS1$42,000$32,100$35,000$30,084$22,720$24,751
0380Thermoplastic, standard, solid, 12" for crosswalk and roundabout (0711-11123)LF6,108$2.10$2.00$2.25$2.03$3.56$3.00
0385Thermoplastic, standard, solid, 18" for diagonals and chevrons (0711-11124)LF542$2.63$3.00$3.50$3.05$5.34$4.00
0390Thermoplastic, standard, solid, 24" for stop line and crosswalk (0711-11125)LF1,280$3.15$4.00$4.50$4.06$7.11$5.00
0395Thermoplastic, standard, 2-4 dotted guideline/ 6-10 gap extension, 6" (0711-11141)GM0.17$210.00$1,320.00$1,725.00$1,339.82$2,388.77$1,950.00
0400Thermoplastic, standard, message or symbol (0711-11160)EACH36$105.00$120.00$175.00$121.80$120.67$100.00
0405Thermoplastic, standard, arrow (0711-11170)EACH195$63.00$80.00$110.00$81.20$66.21$90.00
0410Thermoplastic, standard, yellow, solid, 18" for diagonal or chevron (0711-11224)LF1,498$3.15$3.00$3.50$3.05$4.91$4.00
0415Thermoplastic, standard, yellow, 2-4 dotted guide line dotted extension line, 6" (0711-11241)GM0.23$2,100.00$1,320.00$1,700.00$1,339.78$2,318.51$1,950.00
0420Thermoplastic, preformed, white, solid, 24" for crosswalk (0711-14125)LF2,605$15.75$18.00$20.00$18.27$18.04$18.00
0425Thermoplastic, standard-other surfaces, white, solid, 6" (0711-16101)GM7.11$5,250.00$5,900.00$5,250.00$5,988.50$5,154.73$5,350.00
0430Thermoplastic, standard-other surfaces, white, solid, 8" (0711-16102)GM0.29$5,775.00$6,600.00$8,750.00$6,698.98$6,758.81$7,800.00
0435Thermoplastic, standard-other surfaces, white, skip, 6",10-30 or 3-9 lane drop (0711-16131)GM4.97$1,890.00$1,320.00$1,650.00$1,339.80$1,287.70$1,950.00
0440Thermoplastic, standard-other surfaces white, skip, 12"- approach to toll plaza or 3-9 lane drop (0711-16133)GM0.15$2,625.00$3,168.00$3,250.00$3,215.50$2,424.23$3,500.00
0445Thermoplastic, standard-other surfaces, yellow, solid, 6" (0711-16201)GM6.13$5,250.00$5,900.00$5,250.00$5,988.50$4,736.89$5,350.00
0450Permanent tape, white, solid, 6" for concrete bridges (0713-103101)GM0.07$29,400$52,800$60,000$53,592$48,245$39,000
0455Permanent tape, white, 10-30 6" wide, for concrete surfaces (0713-103181)GM0.07$12,600$6,600.00$30,000$6,698.94$12,244$18,000
0460Permanent tape, yellow, solid, for concrete bridges (0713-103201)GM0.13$29,400$52,800$32,250$53,592$50,115$39,000
0465Permanent tape, black, 10-30 6" wide, for concrete surfaces (0713-103381)GM0.07$12,600$6,800.00$30,000$6,901.97$11,930$18,000
0470Conduit, furnish & install, directional bore (0630-2-12)LF2,090$31.08$35.00$30.00$35.53$25.38$36.00
0475Pull & splice box, F&I, 13" X 24" cover size (0635-2-11)EACH48$1,475.78$1,700.00$1,400.00$1,725.50$1,319.80$1,750.00
0480Pull & splice box, install (0635-2-30)EACH1$1,075.83$1,204.13$1,100.00$1,222.19$1,032.99$1,290.14
0485Electrical power service, F&I, underground, meter by contractor (0639-1122)AS2$7,305.90$5,262.27$6,000.00$5,341.21$5,869.55$5,638.15
0490Electrical power service, remove underground (0639-1620)AS1$707.18$1,184.11$1,100.00$1,201.87$1,072.08$1,268.69
0495Prestressed concrete pole, type P-II service pole (0641-2-12)EACH2$3,198.09$3,050.39$3,500.00$3,096.15$3,082.24$3,268.27
0500Prestressed concrete pole, complete pole removal- pedestal/service pole (0641-2-60)EACH1$707.18$592.05$800.00$600.93$770.56$634.34
0505Lighting conductors, F&I, insulated, no.8 - 6 (0715-1-12)LF10,714$3.36$3.04$3.25$3.09$2.94$3.26
0510Lighting conductors, F&I, insulated, no 4 to no 2 (0715-1-13)LF174$4.73$8.59$5.00$8.72$4.57$9.20
0515Lighting conductors, remove & dispose, contractor owns (0715-1-60)LF8,292$1.26$0.39$0.50$0.40$0.41$0.42
0520Load center, F&I, secondary voltage (0715-7-11)EACH2$19,788$14,250$18,000$14,464$16,843$14,250
0525Load center, remove, voltage (0715-7-41)EACH2$942.90$789.41$650.00$801.25$603.05$845.79
0530Luminaire, F&I- replace existing luminaire on existing pole/arm, roadway, pole top (0715-11213)EACH4$1,622.99$1,815.50$2,200.00$1,842.73$2,137.56$1,945.18
0535Luminaire, F&I- replace existing luminaire on existing pole/arm, roadway, pendant/teardrop (0715-11216)EACH15$2,862.41$3,142.64$3,500.00$3,189.78$3,275.63$3,367.11
0540Light pole complete, F&I, standard pole standard foundation, 40' mounting height, 8' arm length (0715-61311)EACH1$8,205.65$10,500$9,000.00$10,658$8,121.83$11,514
0545Light pole complete, remove pole and foundation (0715-69000)EACH2$707.18$789.41$700.00$801.25$642.13$845.79
0550Pole cable distribution system, furnish and install, conventional (0715-500-1)EACH26$880.11$1,293.28$1,500.00$1,312.68$1,375.63$1,385.66
0555Light pole complete- special design, F&I, single arm shoulder mount, galvanized steel, 40' (0715-511240)EACH2$38,392$41,526$40,000$42,149$39,329$44,492
0560Light pole complete-special design, F&I, pole top mount, aluminum, 15' (0715-516115)EACH2$21,230$16,725$17,500$16,976$16,244$17,920
0565Conduit, furnish & install, directional bore (0630-2-12)LF3,675$33.81$36.00$32.00$36.54$30.46$36.00
0570Signal cable- new or reconstructed intersection, furnish & install (0632-7-1)PI8$12,585$7,500.00$12,000$7,612.50$10,457$8,567.28
0575Signal cable, remove- intersection (0632-7-6)PI7$942.90$1,381.46$2,000.00$1,402.18$1,754.31$1,480.14
0580Pull & splice box, F&I, 13" X 24" cover size (0635-2-11)EACH194$1,475.78$1,700.00$1,400.00$1,725.50$1,319.80$1,750.00
0585Pull & splice box, F&I, 24" X 36" cover size (0635-2-12)EACH8$2,382.13$2,334.63$3,250.00$2,369.65$3,046.19$2,501.38
0590Pull & splice box, install (0635-2-30)EACH8$1,075.83$1,204.13$1,100.00$1,222.19$1,033.00$1,290.14
0595Electrical power service, F&I, underground, meter by contractor (0639-1122)AS8$8,566.84$4,800.00$7,500.00$4,872.00$6,385.79$5,623.34
0600Electrical power service, F&I, underground, meter not required (0639-1123)AS2$8,080.49$5,248.45$4,500.00$5,327.18$4,286.80$5,623.34
0605Electrical power service, remove underground (0639-1620)AS7$707.18$592.05$400.00$600.93$378.68$634.34
0610Electrical service wire, & install (0639-2-1)LF2,690$11.87$9.80$11.00$9.95$10.15$10.50
0615Electrical service wire, (0639-2-6)LF1,872$0.63$0.39$1.00$0.40$1.02$0.42
0620Prestressed concrete pole, type P-II service pole (0641-2-12)EACH8$2,990.30$3,050.39$3,250.00$3,096.15$3,045.69$3,268.27
0625Prestressed concrete pole, complete pole removal- pedestal/service pole (0641-2-60)EACH4$942.90$493.38$1,100.00$500.78$982.74$528.62
0630Aluminum signals pole, (0646-1-11)EACH36$2,554.02$2,000.00$3,400.00$2,030.00$3,041.62$2,000.00
0635Aluminum signals pole, remove (0646-1-60)EACH10$707.18$394.70$300.00$400.62$271.07$422.90
0640Steel mast arm assembly, and install, single arm 78' (0649-21-21)EACH1$92,484$75,000$100,000$76,125$84,436$75,000
0645Vehicular traffic signal, furnish & install aluminum, 3 section, 1 way (0650-1-14)AS5$1,490.58$1,524.70$2,000.00$1,547.57$1,887.31$1,633.61
0650Vehicular traffic signal, remove- poles to remain (0650-1-60)AS1$235.73$98.68$225.00$100.16$201.02$105.73
0655Vehicular signal auxiliaries, repair/replace/retrofit- & install, backplate- flexible required (0650-2109)EACH50$479.54$700.00$650.00$710.50$566.50$700.00
0660Pedestrian signal, furnish & install LED countdown, 1 way (0653-1-11)AS32$762.30$919.98$1,000.00$933.78$959.90$985.70
0665Pedestrian signal, furnish & install LED countdown, 2 ways (0653-1-12)AS4$1,631.60$1,749.41$1,750.00$1,775.65$1,573.10$1,874.37
0670Pedestrian signal, remove ped signal- pole/pedestal to remain (0653-1-60)AS10$117.92$98.68$200.00$100.16$181.73$105.72
0675Midblock crosswalk: rectangular rapid flashing beacon, remove complete sign assembly (0654-2-60)AS4$942.90$789.41$850.00$801.25$670.05$845.79
0680Loop detector inductive, F&I, type 9 (0660-1109)EACH20$359.42$339.58$650.00$344.67$549.24$363.83
0685Loop assembly, F&I, type F (0660-2106)AS20$1,930.95$1,500.00$2,250.00$1,522.50$2,030.46$1,500.00
0690Pedestrian detector, furnish & install, standard (0665-1-11)EACH44$383.99$404.72$650.00$410.79$541.62$433.62
0695Pedestrian detector, remove- pole/pedestal to remain (0665-1-60)EACH8$117.92$98.68$80.00$100.16$67.01$105.72
0700Traffic controller assembly, F&I, caltrans W/standard lock (0670-5180)AS1$47,157$43,068$50,000$43,714$45,016$46,144
0705Cellular modem, furnish and install (0684-8-1)EACH1$2,006.87$2,327.20$4,500.00$2,362.11$3,947.21$2,493.42
0710Sign panel, furnish & install overhead mount, UP to 12 SF (0700-3201)EACH2$883.79$1,085.26$1,000.00$1,101.54$916.25$1,162.78
0715Sign panel, remove, UP to 12 SF (0700-3601)EACH3$235.73$98.68$150.00$71.05$141.62$105.73
0720Lighting conductors, F&I, insulated, no.8 - 6 (0715-1-12)LF235$3.36$3.27$3.00$3.32$2.94$3.50
0725Lighting conductors, remove & dispose, contractor owns (0715-1-60)LF249$1.26$0.40$1.00$0.41$1.02$0.42
FDOT contract T6615: unit prices by line, the 6 lowest bidders (all in the CSV)

The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.

Source

Read from FDOT's tabulation for this contract. FDOT Tabulation of Bids PDFs from its central office lettings, January 2018 to October 2026, all pay items. On A+B contracts the cost part is kept (the total the pay items add up to). Bidders listed without a rank or total are left out.

Every contract let that day: FDOT letting of December 3, 2025. Compiled by Mirage Metrics.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy