FDOT contract T7563 bid tabulation
SR 39 (JAMES L REDMAN PKWY) AT TRAPNELL RD. Let by Florida DOT on June 11, 2025, Hillsborough, District 7. 5 bids received; low bid $8,023,564 by Webber, LLC.
- Owner
- Florida DOT
- Letting
- 11 JUN 2025
- Pay items
- 112
- Data through
- 28 OCT 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | Webber, LLC | $8,023,564 | Low |
| 2 | Gosalia Concrete Constructors, Inc. | $8,347,298 | +4.0% |
| 3 | Watson Civil Construction, Inc. | $8,521,721 | +6.0% |
| 4 | Ajax Paving Industries of Florida LLC | $10,380,937 | +29% |
| 5 | Preferred Materials Inc. | $10,392,776 | +30% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Webber, LLC | 2. Gosalia Concrete Constructors, Inc. | 3. Watson Civil Construction, Inc. | 4. Ajax Paving Industries of Florida LLC | 5. Preferred Materials Inc. |
|---|---|---|---|---|---|---|---|---|
| 0005 | Mobilization (0101-1) | LS | 1 | $425,000 | $834,700 | $850,000 | $1,035,000 | $1,350,000 |
| 0010 | Maintenance of traffic (0102-1) | DA | 1 | $800,000 | $329,548 | $860,000 | $1,035,000 | $384,000 |
| 0015 | Special detour- temporary pavement (0102-2200) | SY | 1 | $250,000 | $60,999 | $77,000 | $85,607 | $65,965 |
| 0020 | Special detour- temporary earthwork/base (0102-2300) | CY | 1 | $275,000 | $270,000 | $69,000 | $64,451 | $656,975 |
| 0025 | Commercial material for temporary driveway maintenance (0102-3) | CY | 21.20 | $500.00 | $350.00 | $97.00 | $354.81 | $306.60 |
| 0030 | Pedestrian or bicycle special detour (0102-4-1) | SY | 1 | $51,000 | $1,700.00 | $1,500.00 | $36,670 | $14,981 |
| 0035 | Traffic control officer (0102-14) | HR | 400 | $91.50 | $125.00 | $90.00 | $118.98 | $95.04 |
| 0040 | Work zone sign (0102-60) | ED | 17,221 | $0.25 | $0.22 | $0.30 | $0.24 | $0.25 |
| 0045 | Business sign (0102-61) | EACH | 2 | $22.00 | $48.15 | $46.00 | $33.99 | $35.64 |
| 0050 | Temporary barrier, F&I, low profile, concrete (0102-71-13) | LF | 2,852 | $37.00 | $39.00 | $41.00 | $41.93 | $43.95 |
| 0055 | Temporary barrier, relocate, low profile concrete (0102-71-23) | LF | 8,333 | $10.00 | $12.00 | $12.50 | $11.33 | $11.88 |
| 0060 | Channelizing device- types I, II, VP, drum, or LCD (0102-74-1) | ED | 15,360 | $0.10 | $0.10 | $0.13 | $0.14 | $0.12 |
| 0065 | Channelizing device- pedestrian LCD (longitudinal channelizing device) (0102-74-8) | FD | 12,131 | $0.05 | $0.09 | $0.12 | $0.08 | $0.08 |
| 0070 | Arrow board / advance warning arrow panel (0102-76) | ED | 285 | $4.95 | $25.00 | $7.00 | $5.67 | $5.94 |
| 0075 | Portable changeable message sign, temporary (0102-99) | ED | 1,388 | $10.80 | $10.70 | $14.00 | $13.60 | $11.88 |
| 0080 | Temporary signalization and maintenance, intersection (0102-104) | ED | 285 | $35.00 | $5.30 | $46.00 | $5.86 | $6.14 |
| 0085 | Temporary traffic detection and maintenance, intersection (0102-107-1) | ED | 285 | $30.00 | $5.30 | $31.00 | $5.86 | $6.14 |
| 0090 | Type III barricade (0102-115) | ED | 2,510 | $0.25 | $0.35 | $0.40 | $0.34 | $0.36 |
| 0095 | Sediment barrier (0104-10-3) | LF | 5,390 | $2.20 | $1.20 | $1.25 | $3.97 | $2.60 |
| 0100 | Floating turbidity barrier (0104-11) | LF | 43 | $12.00 | $12.00 | $12.00 | $15.86 | $26.79 |
| 0105 | Soil tracking prevention device (0104-15) | EACH | 2 | $3,920.00 | $1,250.00 | $4,600.00 | $2,266.29 | $6,481.14 |
| 0110 | Inlet protection system (0104-18) | EACH | 9 | $205.00 | $140.00 | $140.00 | $169.97 | $196.18 |
| 0115 | Litter removal (0107-1) | ACRE | 93.75 | $100.00 | $30.00 | $49.00 | $198.30 | $187.70 |
| 0120 | Mowing (0107-2) | ACRE | 85.60 | $150.00 | $25.00 | $90.00 | $179.04 | $207.89 |
| 0125 | Clearing & grubbing (0110-1-1) | ACRE | 1 | $489,000 | $10,300 | $195,000 | $935,000 | $255,480 |
| 0130 | Removal of existing concrete (0110-4-10) | SY | 407 | $110.00 | $65.00 | $27.00 | $71.12 | $82.27 |
| 0135 | Regular excavation (0120-1) | CY | 2,797 | $75.00 | $57.08 | $15.00 | $73.60 | $58.53 |
| 0140 | Embankment (0120-6) | CY | 322.10 | $50.00 | $50.00 | $15.00 | $117.83 | $61.96 |
| 0145 | Type B stabilization (0160-4) | SY | 9,531 | $37.50 | $17.00 | $30.00 | $30.23 | $48.84 |
| 0150 | Turnout base- optional materials (0286-1) | SY | 158 | $380.00 | $118.32 | $79.00 | $86.85 | $110.87 |
| 0155 | Milling existing asphalt pavement, 1 1/2" avg depth (0327-70-6) | SY | 9,810 | $9.50 | $2.80 | $3.15 | $7.24 | $4.62 |
| 0160 | Milling existing asphalt pavement, 9" avg depth (0327-70-39) | SY | 142 | $9.00 | $6.15 | $71.70 | $27.69 | $73.95 |
| 0165 | Milling existing asphalt pavement, 12" avg depth (0327-70-46) | SY | 19,865 | $8.00 | $7.01 | $15.00 | $23.74 | $12.80 |
| 0170 | Superpave asphaltic conc, traffic C (0334-1-13) | TN | 4,141.50 | $142.00 | $182.39 | $155.00 | $174.96 | $177.06 |
| 0175 | Asphalt concrete friction course,traffic C, FC-12.5, PG (0337-7-83) | TN | 822.40 | $211.00 | $172.07 | $195.00 | $239.74 | $235.08 |
| 0180 | Plain cement concrete 9" (0350-3-7) | SY | 24,776 | $95.00 | $151.91 | $137.00 | $139.09 | $153.42 |
| 0185 | Cleaning & sealing joints- concrete pavement (0350-5) | LF | 35,941 | $4.00 | $4.10 | $4.05 | $6.69 | $7.01 |
| 0190 | Grinding concrete pavement (0352-70) | SY | 24,776 | $7.00 | $4.77 | $4.20 | $4.48 | $5.00 |
| 0195 | Inlets, DT bot, type F, <10' (0425-1561) | EACH | 1 | $10,000 | $7,500.00 | $7,100.00 | $4,759.21 | $12,783 |
| 0200 | Manhole, adjust (0425-5) | EACH | 1 | $2,000.00 | $5,169.08 | $2,600.00 | $3,626.07 | $2,184.39 |
| 0205 | Pipe culvert,optional material,round, 18"S/CD (0430-175118) | LF | 5 | $1,000.00 | $1,005.35 | $750.00 | $240.23 | $449.15 |
| 0210 | Edgedrain draincrete, (0446-1-1) | LF | 5,162 | $35.00 | $52.31 | $43.00 | $37.39 | $58.65 |
| 0215 | Edgedrain outlet pipe, 4" (0446-71-1) | LF | 420 | $35.00 | $128.79 | $43.00 | $37.39 | $79.49 |
| 0220 | Concrete curb & gutter, type E (0520-1-7) | LF | 357 | $90.00 | $55.47 | $55.00 | $67.27 | $57.28 |
| 0225 | Curb-concrete pavement joint (0520-4) | LF | 357 | $30.00 | $18.90 | $5.40 | $7.37 | $7.72 |
| 0230 | Concrete sidewalk and driveways, 4" thick (0522-1) | SY | 285 | $145.00 | $75.00 | $104.00 | $99.87 | $114.39 |
| 0235 | Concrete sidewalk and driveways, 6" thick (0522-2) | SY | 199 | $170.00 | $85.00 | $111.00 | $125.60 | $172.31 |
| 0240 | Concrete ditch pavement, non reinforced, 4" (0524-1-2) | SY | 1,060 | $150.00 | $143.92 | $81.00 | $66.47 | $142.44 |
| 0245 | Detectable warnings (0527-2) | SF | 190 | $48.50 | $50.27 | $53.00 | $22.66 | $34.93 |
| 0250 | Performance turf, sod (0570-1-2) | SY | 16,281 | $5.25 | $1.50 | $5.95 | $7.48 | $4.75 |
| 0255 | Raised pavement marker, type B (0706-1-3) | EACH | 3,456 | $4.00 | $4.00 | $4.05 | $4.53 | $4.75 |
| 0260 | Painted pavement markings, standard, white, solid, 6" (0710-11101) | GM | 4.71 | $1,700.00 | $1,671.80 | $1,700.00 | $1,898.02 | $1,986.01 |
| 0265 | Painted pavement markings, standard, white, solid for crosswalk and roundabout, 12" (0710-11123) | LF | 2,007 | $2.00 | $1.60 | $1.65 | $1.81 | $1.90 |
| 0270 | Painted pavement markings, standard, white, solid for stop line or crosswalk, 24" (0710-11125) | LF | 302 | $2.00 | $1.80 | $1.85 | $2.04 | $2.14 |
| 0275 | Painted pavement markings, standard, white, skip, 10-30 or skip, 6" wide (0710-11131) | GM | 0.44 | $500.00 | $493.12 | $499.00 | $566.57 | $585.80 |
| 0280 | Painted pavement markings, standard, white, 2-4 dotted guideline/ 6-10 dotted 6" (0710-11141) | GM | 0.14 | $700.00 | $665.49 | $673.00 | $764.87 | $790.56 |
| 0285 | Painted pavement markings, standard, white, message or symbol (0710-11160) | EACH | 6 | $41.00 | $40.00 | $40.50 | $45.33 | $47.52 |
| 0290 | Painted pavement markings, standard, white, arrows (0710-11170) | EACH | 48 | $35.00 | $35.00 | $35.40 | $39.66 | $41.58 |
| 0295 | Painted pavement markings, standard, yellow, solid, 6" (0710-11201) | GM | 3.69 | $1,700.00 | $1,672.27 | $1,700.00 | $1,898.02 | $1,986.58 |
| 0300 | Painted pavement markings, standard, yellow, 2-4 dotted guideline/6-10 dotted extension, 6" (0710-11241) | GM | 0.04 | $700.00 | $642.86 | $650.00 | $764.87 | $763.57 |
| 0305 | Painted pavement markings, standard,black, skip, 6" (0710-11331) | GM | 0.89 | $500.00 | $494.94 | $500.00 | $566.57 | $587.95 |
| 0310 | Painted pavement markings, standard, black, 2-4 dotted guideline/ 6-10 dotted 6" (0710-11341) | GM | 0.31 | $700.00 | $661.76 | $670.00 | $764.87 | $786.14 |
| 0315 | Initial contingency amount, DO not bid (0999-25) | LS | 1 | $90,500 | $90,500 | $90,500 | $90,500 | $90,500 |
| 0320 | Single column ground sign assembly, F&I ground mount, than 12 SF (0700-1111) | EACH | 8 | $419.00 | $450.00 | $445.00 | $474.79 | $497.75 |
| 0325 | Single column ground sign assembly, F&I ground mount, 20.0 SF (0700-1112) | EACH | 2 | $1,820.00 | $2,800.00 | $1,950.00 | $2,066.86 | $2,166.83 |
| 0330 | Single column ground sign assembly, remove (0700-1600) | EACH | 6 | $50.00 | $35.00 | $53.00 | $56.66 | $59.40 |
| 0335 | Multi-column ground sign assembly, F&I ground mount, 50.0 SF (0700-2114) | EACH | 2 | $6,670.00 | $8,200.00 | $7,100.00 | $7,554.68 | $7,920.07 |
| 0340 | Multi-column ground sign assembly, remove (0700-2600) | EACH | 2 | $800.00 | $1,450.00 | $845.00 | $906.52 | $950.36 |
| 0345 | Object marker, type 1 (0705-10-1) | EACH | 2 | $218.60 | $300.00 | $220.00 | $234.56 | $245.91 |
| 0350 | Delineator, flexible tubular (0705-11-1) | EACH | 6 | $103.00 | $100.00 | $109.00 | $116.71 | $122.36 |
| 0355 | Raised pavement marker, type B (0706-1-3) | EACH | 521 | $4.00 | $4.00 | $4.05 | $4.53 | $4.75 |
| 0360 | Painted pavement markings, durable paint, yellow, island nose (0710-12290) | SF | 135 | $4.00 | $4.00 | $4.05 | $4.53 | $4.75 |
| 0365 | Painted pavement markings, surface (0710-90) | LS | 1 | $32,000 | $31,093 | $28,000 | $35,233 | $36,937 |
| 0370 | Thermoplastic, preformed, white, 2-4 dotted guideline on concrete surfaces (0711-14141) | GM | 0.34 | $9,000.00 | $8,748.45 | $8,900.00 | $10,063 | $10,393 |
| 0375 | Thermoplastic, preformed, yellow, 2-4 dotted guideline on concrete surfaces (0711-14241) | GM | 0.06 | $9,000.00 | $8,458.10 | $8,600.00 | $10,063 | $10,048 |
| 0380 | Thermoplastic, preformed, black, 2-4 dotted guideline on concrete surfaces (0711-14341) | GM | 0.33 | $9,000.00 | $8,881.00 | $9,000.00 | $10,063 | $10,550 |
| 0385 | Thermoplastic, preformed, 24" white with 4" black contrast crosswalk on concrete pavement, 32" (0711-14526) | LF | 738 | $22.00 | $21.64 | $22.00 | $24.52 | $25.71 |
| 0390 | Thermoplastic, preformed, 24" white with 4" black contrast stop line on concrete 32" (0711-14527) | LF | 132 | $22.00 | $21.64 | $22.00 | $24.52 | $25.71 |
| 0395 | Thermoplastic, preformed, 12" white with 4" black contrast crosswalk on concrete pavement, 20" (0711-14528) | LF | 792 | $11.00 | $10.70 | $10.90 | $12.12 | $12.71 |
| 0400 | Thermoplastic, preformed, white with black contrast on concrete pavement, message symbol (0711-14560) | EACH | 2 | $490.00 | $482.00 | $490.00 | $546.18 | $572.60 |
| 0405 | Thermoplastic, preformed, white with black contrast, arrow on concrete surface (0711-14570) | EACH | 20 | $1,065.00 | $1,052.00 | $1,100.00 | $1,192.07 | $1,249.72 |
| 0410 | Thermoplastic, standard-open graded asphalt surfaces solid, 6" (0711-15101) | GM | 0.58 | $8,000.00 | $8,055.56 | $8,000.00 | $9,065.17 | $9,404.62 |
| 0415 | Thermoplastic, standard-open graded asphalt surfaces, skip, 6",10-30 skip or 3-9 lane (0711-15131) | GM | 0.58 | $2,000.00 | $2,013.89 | $2,000.00 | $2,266.29 | $2,351.15 |
| 0420 | Thermoplastic, standard-open graded asphalt surfaces, yellow, solid, 6" (0711-15201) | GM | 0.58 | $8,000.00 | $8,055.56 | $8,000.00 | $9,065.17 | $9,404.62 |
| 0425 | Thermoplastic, standard-other surfaces, white, solid, 6" (0711-16101) | GM | 1.32 | $6,000.00 | $5,953.49 | $6,050.00 | $6,751.28 | $7,072.45 |
| 0430 | Thermoplastic, standard-other surfaces, yellow, solid, 6" (0711-16201) | GM | 0.84 | $5,700.00 | $5,618.25 | $5,700.00 | $6,396.61 | $6,674.19 |
| 0435 | Permanent tape, white, solid W/contrast, 6" primary line width, for concrete surfaces (0713-103121) | GM | 0.45 | $37,000 | $36,663 | $37,100 | $41,914 | $43,554 |
| 0440 | Permanent tape, white, 6-10 skip/dotted, 6" for concrete surfaces (0713-103141) | GM | 0.05 | $9,700.00 | $9,553.19 | $9,700.00 | $12,720 | $11,349 |
| 0445 | Permanent tape, white, 10-30 6" wide, for concrete surfaces (0713-103181) | GM | 0.87 | $9,300.00 | $9,173.33 | $9,300.00 | $10,479 | $10,897 |
| 0450 | Permanent tape, yellow, 6-10 dotted extension, 6" wide, for concrete surfaces (0713-103241) | GM | 0.16 | $10,700 | $10,590 | $10,700 | $12,720 | $12,580 |
| 0455 | Permanent tape, black, 6-10 dotted extension, 6" for concrete surfaces (0713-103341) | GM | 0.04 | $10,800 | $10,690 | $11,000 | $12,720 | $12,700 |
| 0460 | Permanent tape, black, 10-30 6" wide, for concrete surfaces (0713-103381) | GM | 0.87 | $9,400.00 | $9,237.38 | $9,350.00 | $10,479 | $10,974 |
| 0465 | Conduit, furnish & install, open trench (0630-2-11) | LF | 396 | $15.00 | $18.50 | $9.75 | $20.45 | $21.44 |
| 0470 | Conduit, furnish & install, directional bore (0630-2-12) | LF | 145 | $25.00 | $26.23 | $29.50 | $29.00 | $30.40 |
| 0475 | Pull & splice box, F&I, 13" X 24" cover size (0635-2-11) | EACH | 6 | $1,700.00 | $2,338.11 | $1,920.00 | $2,584.80 | $2,709.81 |
| 0480 | Lighting conductors, F&I, insulated, no.8 - 6 (0715-1-12) | LF | 1,905 | $2.00 | $2.38 | $3.20 | $2.63 | $2.76 |
| 0485 | Luminaire, F&I- replace existing luminaire on existing pole/arm, roadway, cobra head (0715-11211) | EACH | 19 | $1,590.00 | $1,248.08 | $1,300.00 | $1,379.76 | $1,446.50 |
| 0490 | Light pole complete, relocate (0715-68000) | EACH | 3 | $3,800.00 | $7,270.92 | $2,500.00 | $8,038.06 | $8,426.82 |
| 0495 | Pole cable distribution system, furnish and install, conventional (0715-500-1) | EACH | 3 | $650.00 | $949.29 | $917.00 | $1,049.45 | $1,100.21 |
| 0500 | Signal cable- new or reconstructed intersection, furnish & install (0632-7-1) | PI | 1 | $6,000.00 | $6,919.44 | $11,400 | $7,649.49 | $8,019.46 |
| 0505 | Vehicular traffic signal, furnish & install aluminum, 5 section cluster, 1 way (0650-1-19) | AS | 2 | $3,500.00 | $3,240.13 | $2,920.00 | $3,581.99 | $3,755.23 |
| 0510 | Vehicular traffic signal, remove- poles to remain (0650-1-60) | AS | 2 | $550.00 | $168.55 | $378.00 | $186.33 | $195.35 |
| 0515 | Vehicular traffic signal, relocate- includes removal reinstallation (0650-1-70) | AS | 4 | $1,600.00 | $505.65 | $1,400.00 | $559.00 | $586.04 |
| 0520 | Vehicular signal auxiliaries, repair/replace/retrofit- & install, backplate- flexible required (0650-2109) | EACH | 8 | $1,100.00 | $615.69 | $751.00 | $680.65 | $713.57 |
| 0525 | Loop detector inductive, remove- cabinet to remain (0660-1600) | EACH | 8 | $70.00 | $21.06 | $108.00 | $23.29 | $24.41 |
| 0530 | Vehicle detection system- furnish & install cabinet equipment (0660-4-11) | EACH | 1 | $28,100 | $30,814 | $35,600 | $34,065 | $35,713 |
| 0535 | Vehicle detection system- furnish & install above ground equipment (0660-4-12) | EACH | 2 | $11,000 | $6,876.28 | $12,400 | $7,601.78 | $7,969.44 |
| 0540 | Pedestrian detector, furnish & install, standard (0665-1-11) | EACH | 2 | $500.00 | $509.42 | $487.00 | $563.16 | $590.40 |
| 0545 | Pedestrian detector, remove- pole/pedestal to remain (0665-1-60) | EACH | 2 | $70.00 | $84.28 | $54.00 | $93.17 | $97.67 |
| 0550 | Traffic controller, modify (0671-2-40) | EACH | 1 | $825.00 | $1,040.75 | $4,900.00 | $1,150.56 | $1,206.21 |
| 0555 | Uninterruptible power supply, install - equipment furnished others (0685-1-30) | EACH | 1 | $3,840.00 | $4,133.57 | $10,700 | $4,569.69 | $4,790.71 |
| 0560 | Uninterruptible power supply, remove- pole/cabinet remains (0685-1-60) | EACH | 1 | $700.00 | $1,011.30 | $593.00 | $1,118.00 | $1,172.07 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from FDOT's tabulation for this contract. FDOT Tabulation of Bids PDFs from its central office lettings, January 2018 to October 2026, all pay items. On A+B contracts the cost part is kept (the total the pay items add up to). Bidders listed without a rank or total are left out.
Every contract let that day: FDOT letting of June 11, 2025. Compiled by Mirage Metrics.