FDOT contract T7579 bid tabulation

SR 600 (US 92 / HILLSBOROUGH AVE) FROM W OF N 39TH ST TO... Let by Florida DOT on January 28, 2026, Hillsborough, District 7. 6 bids received; low bid $1,641,667 by Preferred Materials Inc..

Owner
Florida DOT
Letting
28 JAN 2026
Pay items
103
Data through
28 OCT 2026

Bidders

RankBidderTotal bidAgainst the low bid
1Preferred Materials Inc.$1,641,667Low
2Blacktip Services Incorporated$1,774,727+8.0%
3Hubbard Construction Company$1,846,440+12%
4Burgess Civil, LLC$1,938,768+18%
5C.W. Roberts Contracting, Inc.$2,052,302+25%
6Ajax Paving Industries of Florida LLC$2,855,816+74%
FDOT contract T7579: bids by rank

Bid tabulation

LinePay itemUnitQuantity1. Preferred Materials Inc.2. Blacktip Services Incorporated3. Hubbard Construction Company4. Burgess Civil, LLC5. C.W. Roberts Contracting, Inc.6. Ajax Paving Industries of Florida LLC
0005Mobilization (0101-1)LS1$181,700$145,680$131,914$185,000$216,295$324,395
0010Maintenance of traffic (0102-1)DA1$95,600$29,000$172,470$170,000$188,840$454,848
0015Traffic control officer (0102-14)HR320$91.11$85.00$110.77$50.00$94.44$116.00
0020Work zone sign (0102-60)ED5,445$0.24$0.25$0.25$0.26$0.29$0.23
0025Channelizing device- types I, II, VP, drum, or LCD (0102-74-1)ED23,100$0.11$0.15$0.12$0.12$0.13$0.11
0030Channelizing device- pedestrian LCD (longitudinal channelizing device) (0102-74-8)FD1,750$0.03$0.20$0.04$0.18$0.20$0.03
0035Arrow board / advance warning arrow panel (0102-76)ED330$4.56$7.00$4.73$7.07$7.86$4.42
0040Portable changeable message sign, temporary (0102-99)ED344$11.39$12.00$11.84$12.96$14.40$11.05
0045Temporary signalization and maintenance, intersection (0102-104)ED165$34.17$33.00$21.20$23.12$69.12$19.89
0050Temporary traffic detection and maintenance, intersection (0102-107-1)ED165$28.47$28.88$47.11$23.12$1.23$44.19
0055Existing ITS maintenance (0102-112)DA165$125.28$246.13$295.62$26.88$473.93$277.29
0060Artificial coverings /rolled erosion control products (0104-1)SY8$41.32$75.00$42.95$10.00$83.33$43.44
0065Sediment barrier (0104-10-3)LF428$4.01$5.00$4.17$1.86$5.67$11.11
0070Inlet protection system (0104-18)EACH14$217.85$50.00$226.43$126.65$226.72$149.87
0075Chemical treatment- powdered, for erosion control (0104-19)SY8$46.95$75.00$48.79$6.25$83.33$57.92
0080Litter removal (0107-1)ACRE11.36$300.00$50.00$750.25$50.08$427.61$729.58
0085Mowing (0107-2)ACRE1.91$300.00$50.00$4,462.24$297.84$2,543.25$4,338.38
0090Clearing & grubbing (0110-1-1)ACRE1$9,117.52$65,000$6,571.07$65,000$9,840.00$87,537
0095Clearing & grubbing (0110-1-1)ACRE1$8,755.23$65,000$9,099.85$35,000$25,300$99,328
0100Removal of existing concrete (0110-4-10)SY1,092$49.47$50.00$51.42$25.00$48.78$165.40
0105Regular excavation (0120-1)CY27.20$49.27$50.00$51.21$82.49$163.64$494.90
0110Embankment (0120-6)CY200.20$85.50$18.00$88.86$47.60$153.12$158.58
0115Optional base, base group 09 (0285-709)SY444$169.61$68.00$101.24$56.81$101.16$246.80
0120Milling existing asphalt pavement, 3" avg depth (0327-70-4)SY12,811$3.37$7.54$5.89$6.35$7.29$8.47
0125Milling existing asphalt pavement, 1 1/2" avg depth (0327-70-6)SY164$28.71$19.00$20.40$2.00$58.74$33.01
0130Milling existing asphalt pavement, 2 1/2" avg depth (0327-70-8)SY1,922$5.23$8.00$3.39$4.00$6.73$12.25
0135Milling existing asphalt pavement, 7 3/4" avg depth (0327-70-33)SY259$19.19$30.00$46.76$1.98$5.71$52.36
0140Superpave asphaltic conc, traffic C (0334-1-13)TN1,281.70$185.72$216.00$220.18$257.75$200.88$254.72
0145Asphalt concrete friction course,traffic C, FC-12.5, PG (0337-7-83)TN1,262.10$174.77$252.00$225.92$295.69$221.72$222.45
0150Miscellaneous asphalt (0339-1)TN0.70$2,458.74$1,000.00$712.12$291.84$3,661.53$3,342.67
0155Cleaning & sealing joints- concrete pavement (0350-5)LF951$24.71$8.80$21.57$30.00$24.06$20.44
0160Grinding concrete pavement (0352-70)SY35$260.35$251.43$133.26$286.00$142.86$285.02
0165Concrete pavement slab replacement (0353-70)CY7.70$1,684.45$1,000.00$2,331.96$3,500.00$4,399.13$3,987.81
0170Manhole, adjust (0425-5)EACH7$1,428.32$2,200.00$1,484.55$951.71$1,325.25$2,706.10
0175Manhole cover- replace (0425-7)EACH5$2,296.56$975.00$2,386.95$951.70$419.34$1,020.23
0180Concrete curb & gutter, type F (0520-1-10)LF599$45.76$31.00$47.56$55.00$89.54$88.04
0185Concrete sidewalk and driveways, 4" thick (0522-1)SY41$102.96$47.00$107.01$124.40$221.11$184.90
0190Concrete sidewalk and driveways, 6" thick (0522-2)SY544$115.64$70.00$120.20$165.00$114.26$155.17
0195Bus shelter pad- concrete (0522-4)SY14$191.43$90.00$198.96$157.41$546.95$587.65
0200Detectable warnings (0527-2)SF104$34.84$32.00$36.21$25.00$38.89$24.30
0205Performance turf, sod (0570-1-2)SY735$5.69$5.00$9.49$11.57$15.32$8.39
0210Conduit, furnish & install, open trench (0630-2-11)LF41$21.92$13.31$29.44$56.77$32.09$27.62
0215Conduit, furnish & install, directional bore (0630-2-12)LF117$51.25$30.25$44.75$56.77$45.05$41.98
0220Pull & splice box, F&I, 13" X 24" cover size (0635-2-11)EACH2$2,044.34$2,003.72$1,342.65$1,184.49$1,579.77$1,259.41
0225Traffic monitoring site vehicle sensor-non-weight, furnish & install (0695-1-1)EACH6$3,162.00$3,987.50$3,003.28$2,882.64$3,139.80$2,817.09
0230Traffic monitoring site inductive loop assembly, & install, 2 loops (0695-6-12)EACH6$2,505.59$3,850.00$2,384.96$2,610.17$2,557.25$2,237.10
0235Traffic monitoring site cabinet, F&I, type 3, 2 pane back, pedestal mount (0695-7162)EACH1$7,121.21$9,128.28$8,126.52$8,479.96$9,835.31$7,622.72
0240Raised pavement marker, type B (0706-1-3)EACH267$5.13$5.50$6.01$4.50$8.30$6.91
0245Painted pavement markings, standard, white, solid, 6" (0710-11101)GM1.09$2,236.92$1,650.00$1,793.09$1,964.09$3,656.38$3,033.76
0250Painted pavement markings, standard, white, solid for crosswalk and roundabout, 12" (0710-11123)LF980$2.05$2.20$2.40$1.80$3.32$2.76
0255Painted pavement markings, standard, white, solid for stop line or crosswalk, 24" (0710-11125)LF1,136$2.28$2.75$3.01$2.00$3.69$3.07
0260Painted pavement markings, standard, white, skip, 10-30 or skip, 6" wide (0710-11131)GM0.81$624.08$770.00$838.33$547.97$1,010.75$844.84
0265Painted pavement markings, standard, white, 2-4 dotted guideline/ 6-10 dotted 6" (0710-11141)GM0.15$842.89$770.00$830.39$740.13$1,365.20$1,152.06
0270Painted pavement markings, standard, white, message or symbol (0710-11160)EACH2$51.25$66.00$72.13$45.00$83.01$69.12
0275Painted pavement markings, standard, white, arrows (0710-11170)EACH29$39.86$38.50$42.07$35.00$64.56$53.76
0280Painted pavement markings, standard, yellow, solid, 6" (0710-11201)GM0.44$2,203.21$2,200.00$2,354.81$1,934.51$3,651.28$3,033.76
0285Painted pavement markings, standard, yellow, 2-4 dotted guideline/6-10 dotted extension, 6" (0710-11241)GM0.09$785.40$1,100.00$1,105.17$689.66$1,431.15$1,152.06
0290Initial contingency amount, DO not bid (0999-25)LS1$30,000$30,000$30,000$30,000$30,000$30,000
0295Initial contingency amount, DO not bid (0999-25)LS1$20,000$20,000$20,000$20,000$20,000$20,000
0300Single column ground sign assembly, F&I ground mount, than 12 SF (0700-1111)EACH8$643.48$605.00$572.81$565.00$548.12$624.18
0305Single column ground sign assembly, F&I ground mount, 20.0 SF (0700-1112)EACH3$1,708.36$2,640.00$2,969.69$1,500.00$2,841.71$1,657.11
0310Single column ground sign assembly, relocate (0700-1500)EACH2$227.79$220.00$289.34$200.00$276.87$220.95
0315Single column ground sign assembly, remove (0700-1600)EACH7$74.03$44.00$98.24$65.00$94.00$71.81
0320Sign panel, furnish & install ground mount, UP to 12 SF (0700-3101)EACH29$398.62$412.50$232.02$350.00$222.02$386.66
0325Sign panel, remove, UP to 12 SF (0700-3601)EACH26$51.25$27.50$120.48$45.00$115.29$49.71
0330Retroreflective sign strip- furnish and install, 5' (0700-13-15)EACH6$170.84$137.50$81.49$150.00$77.98$165.71
0335Tubular marker, 36" white post (0704-1-3)EACH1$261.94$220.00$202.51$230.00$193.78$353.30
0340Tubular marker, 36" yellow (0704-1-4)EACH5$261.95$220.00$233.83$230.00$223.76$353.30
0345Raised pavement marker, type B (0706-1-3)EACH268$5.13$5.50$6.01$4.50$8.30$6.91
0350Painted pavement markings, standard, yellow, island nose (0710-11290)SF11$11.39$5.50$6.01$10.00$18.45$15.36
0355Painted pavement markings, surface (0710-90)LS1$10,357$11,000$12,020$9,094.00$16,774$13,969
0360Thermoplastic, standard, solid, 12" for crosswalk and roundabout (0711-11123)LF980$3.51$6.60$7.21$3.08$5.68$4.73
0365Thermoplastic, standard, solid, 24" for stop line and crosswalk (0711-11125)LF260$7.02$11.00$12.02$6.16$11.36$9.46
0370Thermoplastic, standard, 2-4 dotted guideline/ 6-10 gap extension, 6" (0711-11141)GM0.15$2,809.80$4,400.00$4,744.93$2,467.11$4,550.66$3,840.20
0375Thermoplastic, standard, arrow (0711-11170)EACH25$59.22$88.00$96.16$52.00$95.92$79.88
0380Thermoplastic, standard, yellow, 2-4 dotted guide line dotted extension line, 6" (0711-11241)GM0.09$2,618.16$4,400.00$4,421.38$2,298.85$4,770.34$3,840.20
0385Thermoplastic, preformed, white, solid, 24" for crosswalk (0711-14125)LF876$18.27$17.60$19.23$16.04$29.59$24.64
0390Thermoplastic, preformed, white, message (0711-14160)EACH2$235.76$330.00$360.62$207.00$381.82$317.97
0395Thermoplastic, preformed, white, arrow (0711-14170)EACH4$102.50$220.00$240.41$90.00$166.01$138.25
0400Thermoplastic, standard-other surfaces, white, solid, 6" (0711-16101)GM1.09$5,644.94$7,700.00$8,367.78$4,956.46$9,227.06$7,655.82
0405Thermoplastic, standard-other surfaces, white, skip, 6",10-30 or 3-9 lane drop (0711-16131)GM0.81$1,413.85$2,420.00$2,634.72$1,241.40$2,289.82$1,913.95
0410Thermoplastic, standard-other surfaces, yellow, solid, 6" (0711-16201)GM0.44$5,559.93$7,700.00$8,241.78$4,881.82$9,214.15$7,655.82
0415Permanent tape, white, 10-30 6" wide, for concrete surfaces (0713-103181)GM0.00$12,500$22,000$120,205$62,500$115,285$19,201
0420Permanent tape, yellow, solid, for concrete bridges (0713-103201)GM0.00$50,000$44,000$240,410$250,000$461,135$76,804
0425Permanent tape, black, 10-30 6" wide, for concrete surfaces (0713-103381)GM0.00$12,500$22,000$240,410$125,000$230,570$19,201
0430Itsfm subsurface documentation- project length (0611-1-1)MI0.30$4,555.63$4,812.50$5,182.13$5,032.93$5,331.73$4,860.87
0435Itsfm location documentation- intersection (0611-2-1)EACH1$2,642.26$3,141.88$3,386.05$3,286.18$2,131.46$3,176.13
0440Conduit, furnish & install, open trench (0630-2-11)LF143$21.92$13.31$29.44$34.84$24.68$27.62
0445Conduit, furnish & install, directional bore (0630-2-12)LF483$39.86$37.13$44.75$34.84$46.28$41.98
0450Signal cable- new or reconstructed intersection, furnish & install (0632-7-1)PI1$11,816$28,278$10,600$17,076$15,366$9,942.68
0455Signal cable, remove- intersection (0632-7-6)PI1$1,708.36$4,773.66$2,355.50$922.03$1,950.03$2,209.48
0460Fiber optic cable locator (0633-6)DA165$313.20$206.25$317.99$26.88$371.49$298.28
0465Span wire assembly, F&I, two point, box or drop box (0634-4153)PI1$11,617$12,321$8,862.61$6,676.87$8,667.76$8,313.19
0470Span wire assembly, remove- poles remain (0634-4600)PI1$1,708.36$4,773.66$1,501.64$922.35$1,951.27$1,408.55
0475Fiberglass insulator, furnish & install (0634-5-1)LF80$142.36$308.75$200.22$262.25$75.59$187.81
0480Pull & splice box, F&I, 17" X 30" cover size (0635-2-14)EACH8$2,248.25$3,118.30$1,737.19$1,529.11$2,299.31$1,629.50
0485Aluminum signals pole, (0646-1-11)EACH8$3,325.74$3,244.40$3,533.27$2,612.96$3,332.33$3,314.23
0490Aluminum signals pole, remove (0646-1-60)EACH8$797.23$1,591.22$1,030.54$230.10$390.01$966.65
0495Vehicular traffic signal, relocate- includes removal reinstallation (0650-1-70)AS18$1,846.58$1,450.11$1,707.75$1,562.88$993.53$1,601.88
0500Pedestrian signal, furnish & install LED countdown, 1 way (0653-1-11)AS8$1,229.73$891.43$1,101.20$883.10$1,140.40$1,032.93
0505Pedestrian detector, furnish & install, accessible (0665-1-12)EACH8$2,150.36$314.40$2,231.85$2,764.90$2,098.13$2,093.49
0510Traffic controller, modify (0671-2-40)EACH1$5,352.86$4,773.66$1,177.76$7,982.01$8,515.96$1,104.74
0515Traffic signal controller cabinet, adjust/modify (0676-1500)EACH1$5,352.86$7,956.09$3,533.27$9,518.43$2,544.91$3,314.23
FDOT contract T7579: unit prices by line

The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.

Source

Read from FDOT's tabulation for this contract. FDOT Tabulation of Bids PDFs from its central office lettings, January 2018 to October 2026, all pay items. On A+B contracts the cost part is kept (the total the pay items add up to). Bidders listed without a rank or total are left out.

Every contract let that day: FDOT letting of January 28, 2026. Compiled by Mirage Metrics.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy