FDOT contract T7579 bid tabulation
SR 600 (US 92 / HILLSBOROUGH AVE) FROM W OF N 39TH ST TO... Let by Florida DOT on January 28, 2026, Hillsborough, District 7. 6 bids received; low bid $1,641,667 by Preferred Materials Inc..
- Owner
- Florida DOT
- Letting
- 28 JAN 2026
- Pay items
- 103
- Data through
- 28 OCT 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | Preferred Materials Inc. | $1,641,667 | Low |
| 2 | Blacktip Services Incorporated | $1,774,727 | +8.0% |
| 3 | Hubbard Construction Company | $1,846,440 | +12% |
| 4 | Burgess Civil, LLC | $1,938,768 | +18% |
| 5 | C.W. Roberts Contracting, Inc. | $2,052,302 | +25% |
| 6 | Ajax Paving Industries of Florida LLC | $2,855,816 | +74% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Preferred Materials Inc. | 2. Blacktip Services Incorporated | 3. Hubbard Construction Company | 4. Burgess Civil, LLC | 5. C.W. Roberts Contracting, Inc. | 6. Ajax Paving Industries of Florida LLC |
|---|---|---|---|---|---|---|---|---|---|
| 0005 | Mobilization (0101-1) | LS | 1 | $181,700 | $145,680 | $131,914 | $185,000 | $216,295 | $324,395 |
| 0010 | Maintenance of traffic (0102-1) | DA | 1 | $95,600 | $29,000 | $172,470 | $170,000 | $188,840 | $454,848 |
| 0015 | Traffic control officer (0102-14) | HR | 320 | $91.11 | $85.00 | $110.77 | $50.00 | $94.44 | $116.00 |
| 0020 | Work zone sign (0102-60) | ED | 5,445 | $0.24 | $0.25 | $0.25 | $0.26 | $0.29 | $0.23 |
| 0025 | Channelizing device- types I, II, VP, drum, or LCD (0102-74-1) | ED | 23,100 | $0.11 | $0.15 | $0.12 | $0.12 | $0.13 | $0.11 |
| 0030 | Channelizing device- pedestrian LCD (longitudinal channelizing device) (0102-74-8) | FD | 1,750 | $0.03 | $0.20 | $0.04 | $0.18 | $0.20 | $0.03 |
| 0035 | Arrow board / advance warning arrow panel (0102-76) | ED | 330 | $4.56 | $7.00 | $4.73 | $7.07 | $7.86 | $4.42 |
| 0040 | Portable changeable message sign, temporary (0102-99) | ED | 344 | $11.39 | $12.00 | $11.84 | $12.96 | $14.40 | $11.05 |
| 0045 | Temporary signalization and maintenance, intersection (0102-104) | ED | 165 | $34.17 | $33.00 | $21.20 | $23.12 | $69.12 | $19.89 |
| 0050 | Temporary traffic detection and maintenance, intersection (0102-107-1) | ED | 165 | $28.47 | $28.88 | $47.11 | $23.12 | $1.23 | $44.19 |
| 0055 | Existing ITS maintenance (0102-112) | DA | 165 | $125.28 | $246.13 | $295.62 | $26.88 | $473.93 | $277.29 |
| 0060 | Artificial coverings /rolled erosion control products (0104-1) | SY | 8 | $41.32 | $75.00 | $42.95 | $10.00 | $83.33 | $43.44 |
| 0065 | Sediment barrier (0104-10-3) | LF | 428 | $4.01 | $5.00 | $4.17 | $1.86 | $5.67 | $11.11 |
| 0070 | Inlet protection system (0104-18) | EACH | 14 | $217.85 | $50.00 | $226.43 | $126.65 | $226.72 | $149.87 |
| 0075 | Chemical treatment- powdered, for erosion control (0104-19) | SY | 8 | $46.95 | $75.00 | $48.79 | $6.25 | $83.33 | $57.92 |
| 0080 | Litter removal (0107-1) | ACRE | 11.36 | $300.00 | $50.00 | $750.25 | $50.08 | $427.61 | $729.58 |
| 0085 | Mowing (0107-2) | ACRE | 1.91 | $300.00 | $50.00 | $4,462.24 | $297.84 | $2,543.25 | $4,338.38 |
| 0090 | Clearing & grubbing (0110-1-1) | ACRE | 1 | $9,117.52 | $65,000 | $6,571.07 | $65,000 | $9,840.00 | $87,537 |
| 0095 | Clearing & grubbing (0110-1-1) | ACRE | 1 | $8,755.23 | $65,000 | $9,099.85 | $35,000 | $25,300 | $99,328 |
| 0100 | Removal of existing concrete (0110-4-10) | SY | 1,092 | $49.47 | $50.00 | $51.42 | $25.00 | $48.78 | $165.40 |
| 0105 | Regular excavation (0120-1) | CY | 27.20 | $49.27 | $50.00 | $51.21 | $82.49 | $163.64 | $494.90 |
| 0110 | Embankment (0120-6) | CY | 200.20 | $85.50 | $18.00 | $88.86 | $47.60 | $153.12 | $158.58 |
| 0115 | Optional base, base group 09 (0285-709) | SY | 444 | $169.61 | $68.00 | $101.24 | $56.81 | $101.16 | $246.80 |
| 0120 | Milling existing asphalt pavement, 3" avg depth (0327-70-4) | SY | 12,811 | $3.37 | $7.54 | $5.89 | $6.35 | $7.29 | $8.47 |
| 0125 | Milling existing asphalt pavement, 1 1/2" avg depth (0327-70-6) | SY | 164 | $28.71 | $19.00 | $20.40 | $2.00 | $58.74 | $33.01 |
| 0130 | Milling existing asphalt pavement, 2 1/2" avg depth (0327-70-8) | SY | 1,922 | $5.23 | $8.00 | $3.39 | $4.00 | $6.73 | $12.25 |
| 0135 | Milling existing asphalt pavement, 7 3/4" avg depth (0327-70-33) | SY | 259 | $19.19 | $30.00 | $46.76 | $1.98 | $5.71 | $52.36 |
| 0140 | Superpave asphaltic conc, traffic C (0334-1-13) | TN | 1,281.70 | $185.72 | $216.00 | $220.18 | $257.75 | $200.88 | $254.72 |
| 0145 | Asphalt concrete friction course,traffic C, FC-12.5, PG (0337-7-83) | TN | 1,262.10 | $174.77 | $252.00 | $225.92 | $295.69 | $221.72 | $222.45 |
| 0150 | Miscellaneous asphalt (0339-1) | TN | 0.70 | $2,458.74 | $1,000.00 | $712.12 | $291.84 | $3,661.53 | $3,342.67 |
| 0155 | Cleaning & sealing joints- concrete pavement (0350-5) | LF | 951 | $24.71 | $8.80 | $21.57 | $30.00 | $24.06 | $20.44 |
| 0160 | Grinding concrete pavement (0352-70) | SY | 35 | $260.35 | $251.43 | $133.26 | $286.00 | $142.86 | $285.02 |
| 0165 | Concrete pavement slab replacement (0353-70) | CY | 7.70 | $1,684.45 | $1,000.00 | $2,331.96 | $3,500.00 | $4,399.13 | $3,987.81 |
| 0170 | Manhole, adjust (0425-5) | EACH | 7 | $1,428.32 | $2,200.00 | $1,484.55 | $951.71 | $1,325.25 | $2,706.10 |
| 0175 | Manhole cover- replace (0425-7) | EACH | 5 | $2,296.56 | $975.00 | $2,386.95 | $951.70 | $419.34 | $1,020.23 |
| 0180 | Concrete curb & gutter, type F (0520-1-10) | LF | 599 | $45.76 | $31.00 | $47.56 | $55.00 | $89.54 | $88.04 |
| 0185 | Concrete sidewalk and driveways, 4" thick (0522-1) | SY | 41 | $102.96 | $47.00 | $107.01 | $124.40 | $221.11 | $184.90 |
| 0190 | Concrete sidewalk and driveways, 6" thick (0522-2) | SY | 544 | $115.64 | $70.00 | $120.20 | $165.00 | $114.26 | $155.17 |
| 0195 | Bus shelter pad- concrete (0522-4) | SY | 14 | $191.43 | $90.00 | $198.96 | $157.41 | $546.95 | $587.65 |
| 0200 | Detectable warnings (0527-2) | SF | 104 | $34.84 | $32.00 | $36.21 | $25.00 | $38.89 | $24.30 |
| 0205 | Performance turf, sod (0570-1-2) | SY | 735 | $5.69 | $5.00 | $9.49 | $11.57 | $15.32 | $8.39 |
| 0210 | Conduit, furnish & install, open trench (0630-2-11) | LF | 41 | $21.92 | $13.31 | $29.44 | $56.77 | $32.09 | $27.62 |
| 0215 | Conduit, furnish & install, directional bore (0630-2-12) | LF | 117 | $51.25 | $30.25 | $44.75 | $56.77 | $45.05 | $41.98 |
| 0220 | Pull & splice box, F&I, 13" X 24" cover size (0635-2-11) | EACH | 2 | $2,044.34 | $2,003.72 | $1,342.65 | $1,184.49 | $1,579.77 | $1,259.41 |
| 0225 | Traffic monitoring site vehicle sensor-non-weight, furnish & install (0695-1-1) | EACH | 6 | $3,162.00 | $3,987.50 | $3,003.28 | $2,882.64 | $3,139.80 | $2,817.09 |
| 0230 | Traffic monitoring site inductive loop assembly, & install, 2 loops (0695-6-12) | EACH | 6 | $2,505.59 | $3,850.00 | $2,384.96 | $2,610.17 | $2,557.25 | $2,237.10 |
| 0235 | Traffic monitoring site cabinet, F&I, type 3, 2 pane back, pedestal mount (0695-7162) | EACH | 1 | $7,121.21 | $9,128.28 | $8,126.52 | $8,479.96 | $9,835.31 | $7,622.72 |
| 0240 | Raised pavement marker, type B (0706-1-3) | EACH | 267 | $5.13 | $5.50 | $6.01 | $4.50 | $8.30 | $6.91 |
| 0245 | Painted pavement markings, standard, white, solid, 6" (0710-11101) | GM | 1.09 | $2,236.92 | $1,650.00 | $1,793.09 | $1,964.09 | $3,656.38 | $3,033.76 |
| 0250 | Painted pavement markings, standard, white, solid for crosswalk and roundabout, 12" (0710-11123) | LF | 980 | $2.05 | $2.20 | $2.40 | $1.80 | $3.32 | $2.76 |
| 0255 | Painted pavement markings, standard, white, solid for stop line or crosswalk, 24" (0710-11125) | LF | 1,136 | $2.28 | $2.75 | $3.01 | $2.00 | $3.69 | $3.07 |
| 0260 | Painted pavement markings, standard, white, skip, 10-30 or skip, 6" wide (0710-11131) | GM | 0.81 | $624.08 | $770.00 | $838.33 | $547.97 | $1,010.75 | $844.84 |
| 0265 | Painted pavement markings, standard, white, 2-4 dotted guideline/ 6-10 dotted 6" (0710-11141) | GM | 0.15 | $842.89 | $770.00 | $830.39 | $740.13 | $1,365.20 | $1,152.06 |
| 0270 | Painted pavement markings, standard, white, message or symbol (0710-11160) | EACH | 2 | $51.25 | $66.00 | $72.13 | $45.00 | $83.01 | $69.12 |
| 0275 | Painted pavement markings, standard, white, arrows (0710-11170) | EACH | 29 | $39.86 | $38.50 | $42.07 | $35.00 | $64.56 | $53.76 |
| 0280 | Painted pavement markings, standard, yellow, solid, 6" (0710-11201) | GM | 0.44 | $2,203.21 | $2,200.00 | $2,354.81 | $1,934.51 | $3,651.28 | $3,033.76 |
| 0285 | Painted pavement markings, standard, yellow, 2-4 dotted guideline/6-10 dotted extension, 6" (0710-11241) | GM | 0.09 | $785.40 | $1,100.00 | $1,105.17 | $689.66 | $1,431.15 | $1,152.06 |
| 0290 | Initial contingency amount, DO not bid (0999-25) | LS | 1 | $30,000 | $30,000 | $30,000 | $30,000 | $30,000 | $30,000 |
| 0295 | Initial contingency amount, DO not bid (0999-25) | LS | 1 | $20,000 | $20,000 | $20,000 | $20,000 | $20,000 | $20,000 |
| 0300 | Single column ground sign assembly, F&I ground mount, than 12 SF (0700-1111) | EACH | 8 | $643.48 | $605.00 | $572.81 | $565.00 | $548.12 | $624.18 |
| 0305 | Single column ground sign assembly, F&I ground mount, 20.0 SF (0700-1112) | EACH | 3 | $1,708.36 | $2,640.00 | $2,969.69 | $1,500.00 | $2,841.71 | $1,657.11 |
| 0310 | Single column ground sign assembly, relocate (0700-1500) | EACH | 2 | $227.79 | $220.00 | $289.34 | $200.00 | $276.87 | $220.95 |
| 0315 | Single column ground sign assembly, remove (0700-1600) | EACH | 7 | $74.03 | $44.00 | $98.24 | $65.00 | $94.00 | $71.81 |
| 0320 | Sign panel, furnish & install ground mount, UP to 12 SF (0700-3101) | EACH | 29 | $398.62 | $412.50 | $232.02 | $350.00 | $222.02 | $386.66 |
| 0325 | Sign panel, remove, UP to 12 SF (0700-3601) | EACH | 26 | $51.25 | $27.50 | $120.48 | $45.00 | $115.29 | $49.71 |
| 0330 | Retroreflective sign strip- furnish and install, 5' (0700-13-15) | EACH | 6 | $170.84 | $137.50 | $81.49 | $150.00 | $77.98 | $165.71 |
| 0335 | Tubular marker, 36" white post (0704-1-3) | EACH | 1 | $261.94 | $220.00 | $202.51 | $230.00 | $193.78 | $353.30 |
| 0340 | Tubular marker, 36" yellow (0704-1-4) | EACH | 5 | $261.95 | $220.00 | $233.83 | $230.00 | $223.76 | $353.30 |
| 0345 | Raised pavement marker, type B (0706-1-3) | EACH | 268 | $5.13 | $5.50 | $6.01 | $4.50 | $8.30 | $6.91 |
| 0350 | Painted pavement markings, standard, yellow, island nose (0710-11290) | SF | 11 | $11.39 | $5.50 | $6.01 | $10.00 | $18.45 | $15.36 |
| 0355 | Painted pavement markings, surface (0710-90) | LS | 1 | $10,357 | $11,000 | $12,020 | $9,094.00 | $16,774 | $13,969 |
| 0360 | Thermoplastic, standard, solid, 12" for crosswalk and roundabout (0711-11123) | LF | 980 | $3.51 | $6.60 | $7.21 | $3.08 | $5.68 | $4.73 |
| 0365 | Thermoplastic, standard, solid, 24" for stop line and crosswalk (0711-11125) | LF | 260 | $7.02 | $11.00 | $12.02 | $6.16 | $11.36 | $9.46 |
| 0370 | Thermoplastic, standard, 2-4 dotted guideline/ 6-10 gap extension, 6" (0711-11141) | GM | 0.15 | $2,809.80 | $4,400.00 | $4,744.93 | $2,467.11 | $4,550.66 | $3,840.20 |
| 0375 | Thermoplastic, standard, arrow (0711-11170) | EACH | 25 | $59.22 | $88.00 | $96.16 | $52.00 | $95.92 | $79.88 |
| 0380 | Thermoplastic, standard, yellow, 2-4 dotted guide line dotted extension line, 6" (0711-11241) | GM | 0.09 | $2,618.16 | $4,400.00 | $4,421.38 | $2,298.85 | $4,770.34 | $3,840.20 |
| 0385 | Thermoplastic, preformed, white, solid, 24" for crosswalk (0711-14125) | LF | 876 | $18.27 | $17.60 | $19.23 | $16.04 | $29.59 | $24.64 |
| 0390 | Thermoplastic, preformed, white, message (0711-14160) | EACH | 2 | $235.76 | $330.00 | $360.62 | $207.00 | $381.82 | $317.97 |
| 0395 | Thermoplastic, preformed, white, arrow (0711-14170) | EACH | 4 | $102.50 | $220.00 | $240.41 | $90.00 | $166.01 | $138.25 |
| 0400 | Thermoplastic, standard-other surfaces, white, solid, 6" (0711-16101) | GM | 1.09 | $5,644.94 | $7,700.00 | $8,367.78 | $4,956.46 | $9,227.06 | $7,655.82 |
| 0405 | Thermoplastic, standard-other surfaces, white, skip, 6",10-30 or 3-9 lane drop (0711-16131) | GM | 0.81 | $1,413.85 | $2,420.00 | $2,634.72 | $1,241.40 | $2,289.82 | $1,913.95 |
| 0410 | Thermoplastic, standard-other surfaces, yellow, solid, 6" (0711-16201) | GM | 0.44 | $5,559.93 | $7,700.00 | $8,241.78 | $4,881.82 | $9,214.15 | $7,655.82 |
| 0415 | Permanent tape, white, 10-30 6" wide, for concrete surfaces (0713-103181) | GM | 0.00 | $12,500 | $22,000 | $120,205 | $62,500 | $115,285 | $19,201 |
| 0420 | Permanent tape, yellow, solid, for concrete bridges (0713-103201) | GM | 0.00 | $50,000 | $44,000 | $240,410 | $250,000 | $461,135 | $76,804 |
| 0425 | Permanent tape, black, 10-30 6" wide, for concrete surfaces (0713-103381) | GM | 0.00 | $12,500 | $22,000 | $240,410 | $125,000 | $230,570 | $19,201 |
| 0430 | Itsfm subsurface documentation- project length (0611-1-1) | MI | 0.30 | $4,555.63 | $4,812.50 | $5,182.13 | $5,032.93 | $5,331.73 | $4,860.87 |
| 0435 | Itsfm location documentation- intersection (0611-2-1) | EACH | 1 | $2,642.26 | $3,141.88 | $3,386.05 | $3,286.18 | $2,131.46 | $3,176.13 |
| 0440 | Conduit, furnish & install, open trench (0630-2-11) | LF | 143 | $21.92 | $13.31 | $29.44 | $34.84 | $24.68 | $27.62 |
| 0445 | Conduit, furnish & install, directional bore (0630-2-12) | LF | 483 | $39.86 | $37.13 | $44.75 | $34.84 | $46.28 | $41.98 |
| 0450 | Signal cable- new or reconstructed intersection, furnish & install (0632-7-1) | PI | 1 | $11,816 | $28,278 | $10,600 | $17,076 | $15,366 | $9,942.68 |
| 0455 | Signal cable, remove- intersection (0632-7-6) | PI | 1 | $1,708.36 | $4,773.66 | $2,355.50 | $922.03 | $1,950.03 | $2,209.48 |
| 0460 | Fiber optic cable locator (0633-6) | DA | 165 | $313.20 | $206.25 | $317.99 | $26.88 | $371.49 | $298.28 |
| 0465 | Span wire assembly, F&I, two point, box or drop box (0634-4153) | PI | 1 | $11,617 | $12,321 | $8,862.61 | $6,676.87 | $8,667.76 | $8,313.19 |
| 0470 | Span wire assembly, remove- poles remain (0634-4600) | PI | 1 | $1,708.36 | $4,773.66 | $1,501.64 | $922.35 | $1,951.27 | $1,408.55 |
| 0475 | Fiberglass insulator, furnish & install (0634-5-1) | LF | 80 | $142.36 | $308.75 | $200.22 | $262.25 | $75.59 | $187.81 |
| 0480 | Pull & splice box, F&I, 17" X 30" cover size (0635-2-14) | EACH | 8 | $2,248.25 | $3,118.30 | $1,737.19 | $1,529.11 | $2,299.31 | $1,629.50 |
| 0485 | Aluminum signals pole, (0646-1-11) | EACH | 8 | $3,325.74 | $3,244.40 | $3,533.27 | $2,612.96 | $3,332.33 | $3,314.23 |
| 0490 | Aluminum signals pole, remove (0646-1-60) | EACH | 8 | $797.23 | $1,591.22 | $1,030.54 | $230.10 | $390.01 | $966.65 |
| 0495 | Vehicular traffic signal, relocate- includes removal reinstallation (0650-1-70) | AS | 18 | $1,846.58 | $1,450.11 | $1,707.75 | $1,562.88 | $993.53 | $1,601.88 |
| 0500 | Pedestrian signal, furnish & install LED countdown, 1 way (0653-1-11) | AS | 8 | $1,229.73 | $891.43 | $1,101.20 | $883.10 | $1,140.40 | $1,032.93 |
| 0505 | Pedestrian detector, furnish & install, accessible (0665-1-12) | EACH | 8 | $2,150.36 | $314.40 | $2,231.85 | $2,764.90 | $2,098.13 | $2,093.49 |
| 0510 | Traffic controller, modify (0671-2-40) | EACH | 1 | $5,352.86 | $4,773.66 | $1,177.76 | $7,982.01 | $8,515.96 | $1,104.74 |
| 0515 | Traffic signal controller cabinet, adjust/modify (0676-1500) | EACH | 1 | $5,352.86 | $7,956.09 | $3,533.27 | $9,518.43 | $2,544.91 | $3,314.23 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from FDOT's tabulation for this contract. FDOT Tabulation of Bids PDFs from its central office lettings, January 2018 to October 2026, all pay items. On A+B contracts the cost part is kept (the total the pay items add up to). Bidders listed without a rank or total are left out.
Every contract let that day: FDOT letting of January 28, 2026. Compiled by Mirage Metrics.