ODOT contract 250079 bid tabulation
HEN-US 24-00.43 CR-17D Interchng (INTERCHANGE). Let by Ohio DOT on March 27, 2025, HEN. 3 bids received; low bid $12,310,624 by E S Wagner Company, -23% against the engineer's estimate of $16,048,000.
- Owner
- Ohio DOT
- Letting
- 27 MAR 2025
- Pay items
- 267
- Data through
- 12 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | E S Wagner Company | $12,310,624 | Low | -23% |
| 2 | Vernon Nagel Inc | $12,346,048 | 0.0% | -23% |
| 3 | Miller Bros Const Inc | $12,915,753 | +5.0% | -20% |
Engineer's estimate: $16,048,000.
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. E S Wagner Company | 2. Vernon Nagel Inc | 3. Miller Bros Const Inc |
|---|---|---|---|---|---|---|
| 1 | Clearing and grubbing (201E11000) | LS | 1 | $25,000 | $25,000 | $10,000 |
| 2 | Pavement removed (202E23000) | SY | 19,080 | $8.00 | $7.35 | $4.30 |
| 3 | Pipe removed, 24" and under (202E35100) | FT | 719 | $24.00 | $8.00 | $70.00 |
| 4 | Pipe removed, over 24" diameter (202E35200) | FT | 146 | $52.00 | $28.00 | $80.00 |
| 5 | Manhole removed (202E58000) | EACH | 1 | $710.00 | $500.00 | $625.00 |
| 6 | Catch basin removed (202E58100) | EACH | 3 | $875.00 | $300.00 | $400.00 |
| 7 | Fence removed (202E75000) | FT | 8,453 | $1.80 | $4.00 | $1.80 |
| 8 | Removal misc.:metal post (202E98100) | EACH | 3 | $240.00 | $25.00 | $135.00 |
| 9 | Excavation (203E10000) | CY | 34,358 | $9.50 | $5.00 | $5.40 |
| 10 | Embankment (203E20000) | CY | 165,863 | $6.50 | $9.00 | $7.65 |
| 11 | Granular material, type C (203E35120) | CY | 2,518 | $40.10 | $65.00 | $50.00 |
| 12 | Special - settlement platform (203E65000) | EACH | 4 | $1,400.00 | $1,000.00 | $1,000.00 |
| 13 | Subgrade compaction (204E10000) | SY | 15,041 | $2.00 | $1.00 | $1.00 |
| 14 | Proof rolling (204E45000) | HR | 9 | $350.00 | $250.00 | $100.00 |
| 15 | Cement (206E10500) | TON | 617 | $220.00 | $215.00 | $215.00 |
| 16 | Curing coat (206E11000) | SY | 23,793 | $1.10 | $0.98 | $1.20 |
| 17 | Cement stabilized subgrade, 12 inches deep (206E15010) | SY | 20,214 | $3.86 | $2.82 | $3.24 |
| 18 | Cement stabilized subgrade, 14 inches deep (206E15020) | SY | 3,579 | $3.86 | $2.82 | $3.24 |
| 19 | Mixture design for chemically stabilized soils (206E30000) | LS | 1 | $10,500 | $15,000 | $18,500 |
| 20 | Guardrail, type MGS (606E15050) | FT | 2,213 | $20.00 | $20.00 | $20.00 |
| 21 | Anchor assembly, MGS type B (606E26050) | EACH | 5 | $2,520.00 | $2,520.00 | $2,520.00 |
| 22 | Anchor assembly, MGS type E MASH 2016 (606E26150) | EACH | 6 | $2,480.00 | $2,480.00 | $2,480.00 |
| 23 | Anchor assembly, MGS type T (606E26550) | EACH | 7 | $1,345.00 | $1,345.00 | $1,345.00 |
| 24 | Bridge terminal assembly, type 1 (606E35000) | EACH | 4 | $975.00 | $975.00 | $975.00 |
| 25 | Fence, type 47 (607E15000) | FT | 8,587 | $12.80 | $12.80 | $12.80 |
| 26 | Concrete barrier end section, type D (622E25000) | EACH | 4 | $3,050.00 | $3,050.00 | $3,050.00 |
| 27 | Concrete barrier, end anchorage, reinforced, type D (622E25050) | EACH | 4 | $3,050.00 | $3,250.00 | $3,250.00 |
| 28 | Monument assembly, type D (623E38550) | EACH | 2 | $1,100.00 | $500.00 | $1,000.00 |
| 29 | Special - mailbox removed and reset (690E50350) | EACH | 1 | $300.00 | $195.00 | $195.00 |
| 30 | Tied concrete block mat with type 1 underlayment (601E21050) | SY | 46 | $166.00 | $75.00 | $150.00 |
| 31 | Tied concrete block mat with type 2 underlayment (601E21060) | SY | 250 | $83.00 | $75.00 | $45.00 |
| 32 | Rock channel protection, type C with filter (601E32200) | CY | 159 | $150.00 | $90.00 | $98.50 |
| 33 | Detention basin filter (601E45030) | SY | 984 | $21.00 | $13.00 | $18.00 |
| 34 | Water (616E10000) | MGAL | 600 | $125.00 | $1.00 | $5.00 |
| 35 | Soil analysis test (659E00100) | EACH | 2 | $50.00 | $100.00 | $50.00 |
| 36 | Topsoil (659E00300) | CY | 11,469 | $7.00 | $4.00 | $4.50 |
| 37 | Seeding and mulching (659E10000) | SY | 103,221 | $0.62 | $0.62 | $0.62 |
| 38 | Repair seeding and mulching (659E14000) | SY | 5,166 | $2.78 | $0.30 | $0.30 |
| 39 | Inter-seeding (659E15000) | SY | 5,166 | $0.20 | $0.20 | $0.20 |
| 40 | Commercial fertilizer (659E20000) | TON | 13.95 | $600.00 | $600.00 | $600.00 |
| 41 | Lime (659E31000) | ACRE | 21.35 | $5.00 | $5.00 | $5.00 |
| 42 | Water (659E35000) | MGAL | 558 | $5.00 | $5.00 | $5.00 |
| 43 | Mowing (659E40000) | MSF | 232 | $5.00 | $5.00 | $5.00 |
| 44 | Slope erosion protection (670E00500) | SY | 2,013 | $2.00 | $2.00 | $2.00 |
| 45 | Storm water pollution prevention plan (832E15000) | LS | 1 | $5,000.00 | $2,500.00 | $3,250.00 |
| 46 | Storm water pollution prevention inspections (832E15002) | LS | 1 | $18,000 | $15,000 | $18,360 |
| 47 | Storm water pollution prevention inspection software (832E15010) | LS | 1 | $17,000 | $15,100 | $15,100 |
| 48 | Erosion control (832E30000) | EACH | 303,734 | $1.00 | $1.00 | $1.00 |
| 49 | Concrete masonry (602E20000) | CY | 13.80 | $1,580.00 | $1,200.00 | $1,910.00 |
| 50 | 6" shallow pipe underdrains (605E11100) | FT | 16,570 | $15.00 | $12.00 | $12.00 |
| 51 | 6" unclassified pipe underdrains (605E13300) | FT | 3,652 | $23.00 | $15.00 | $17.00 |
| 52 | 6" unclassified pipe underdrains, as per plan (605E13301) | FT | 283 | $30.00 | $18.00 | $15.50 |
| 53 | 6" base pipe underdrains (605E14000) | FT | 3,470 | $11.00 | $14.00 | $8.50 |
| 54 | 4" conduit, type E (611E00400) | FT | 14 | $60.00 | $10.00 | $100.00 |
| 55 | 4" conduit, type F for underdrain outlet (611E00410) | FT | 11 | $45.00 | $18.00 | $48.00 |
| 56 | 6" conduit, type F for underdrain outlets (611E00510) | FT | 1,392 | $33.00 | $20.00 | $33.00 |
| 57 | 6" conduit, type F (611E01500) | FT | 100 | $25.00 | $15.00 | $27.00 |
| 58 | 8" conduit, type E (611E02500) | FT | 5,900 | $16.50 | $16.00 | $23.50 |
| 59 | 8" conduit, type F (611E02600) | FT | 200 | $30.00 | $20.00 | $40.00 |
| 60 | 12" conduit, type A (611E04200) | FT | 62 | $80.00 | $81.00 | $110.00 |
| 61 | 12" conduit, type B (611E04400) | FT | 144 | $90.00 | $80.00 | $100.00 |
| 62 | 12" conduit, type C (611E04600) | FT | 18 | $135.00 | $43.00 | $57.00 |
| 63 | 12" conduit, type D (611E04900) | FT | 50 | $60.00 | $52.00 | $60.00 |
| 64 | 12" conduit, type F (611E05200) | FT | 163 | $90.00 | $85.00 | $79.00 |
| 65 | 15" conduit, type B (611E05900) | FT | 10 | $230.00 | $90.00 | $195.00 |
| 66 | 15" conduit, type C (611E06100) | FT | 54 | $90.00 | $55.00 | $100.00 |
| 67 | 18" conduit, type B (611E07400) | FT | 263 | $104.00 | $112.00 | $120.00 |
| 68 | 24" conduit, type A (611E10200) | FT | 90 | $125.00 | $130.00 | $160.00 |
| 69 | 36" conduit, type C (611E16600) | FT | 55 | $167.00 | $110.00 | $205.00 |
| 70 | 48" conduit, type A, 706.02 (611E20700) | FT | 112 | $267.00 | $250.00 | $400.00 |
| 71 | 60" conduit, type A, 706.02 (611E23600) | FT | 196 | $389.00 | $375.00 | $500.00 |
| 72 | Catch basin, no. 2-2B (611E98470) | EACH | 2 | $2,600.00 | $2,000.00 | $1,850.00 |
| 73 | Catch basin, no. 2-3 (611E98510) | EACH | 1 | $3,300.00 | $3,000.00 | $2,250.00 |
| 74 | Inlet, no. 3D (611E98820) | EACH | 4 | $12,600 | $12,000 | $11,000 |
| 75 | Manhole, no. 3 (611E99574) | EACH | 1 | $4,300.00 | $4,500.00 | $3,600.00 |
| 76 | Precast reinforced concrete outlet (611E99710) | EACH | 25 | $480.00 | $385.00 | $380.00 |
| 77 | Water quality basin, detention (611E99854) | EACH | 1 | $7,600.00 | $6,000.00 | $4,400.00 |
| 78 | Pavement planing, asphalt concrete, 1.5" (254E01000) | SY | 38,692 | $1.32 | $1.32 | $1.32 |
| 79 | Asphalt concrete base, as per plan (302E66001) | CY | 5,065 | $197.00 | $197.00 | $197.00 |
| 80 | Aggregate base (304E20000) | CY | 6,241 | $60.00 | $55.00 | $57.00 |
| 81 | Non-tracking tack coat (407E20000) | GAL | 6,513 | $2.35 | $2.50 | $2.35 |
| 82 | Stabilized crushed aggregate (411E10000) | CY | 531 | $75.00 | $70.00 | $65.00 |
| 83 | Asphalt concrete surface course, 12.5 MM, type A (446) (442E10000) | CY | 2,489 | $270.00 | $270.00 | $270.00 |
| 84 | Asphalt concrete intermediate course, 19 MM, type A (446) (442E10100) | CY | 1,524 | $235.00 | $240.00 | $235.00 |
| 85 | 9" non-reinforced concrete pavement, class QC 1P (452E13010) | SY | 12,909 | $79.55 | $80.00 | $80.20 |
| 86 | Curb, type 4-C (609E24510) | FT | 77 | $36.89 | $38.00 | $29.00 |
| 87 | Curb, type 4-C, as per plan (609E24511) | FT | 46 | $34.79 | $38.00 | $29.00 |
| 88 | Rumble strips, shoulder (asphalt concrete) (618E40100) | FT | 23,856 | $0.32 | $0.28 | $0.28 |
| 89 | Connection, unfused permanent (625E00480) | EACH | 36 | $110.00 | $110.00 | $110.00 |
| 90 | Light pole, conventional, 40' (625E10490) | EACH | 16 | $3,450.00 | $3,450.00 | $3,450.00 |
| 91 | Light pole foundation, 24" X 8' deep (625E14100) | EACH | 16 | $1,900.00 | $1,900.00 | $1,900.00 |
| 92 | No. 4 AWG 2400 volt distribution cable (625E23200) | FT | 2,763 | $4.00 | $4.00 | $4.00 |
| 93 | 1-1/2" duct cable with three no. 4 AWG 2400 volt cables (625E24320) | FT | 6,359 | $13.00 | $13.00 | $13.00 |
| 94 | Conduit, 1-1/2", 725.04 (625E25300) | FT | 250 | $17.00 | $17.00 | $17.00 |
| 95 | Conduit, 1-1/2", 725.051 (625E25304) | FT | 641 | $7.00 | $7.00 | $7.00 |
| 96 | Luminaire, conventional, solid state (LED), as per plan (625E26253) | EACH | 16 | $400.00 | $400.00 | $400.00 |
| 97 | Trench (625E29000) | FT | 6,365 | $9.00 | $9.00 | $9.00 |
| 98 | Trench in paved area (625E29400) | FT | 300 | $24.00 | $24.00 | $24.00 |
| 99 | Junction box (625E29900) | EACH | 3 | $725.00 | $725.00 | $725.00 |
| 100 | Pull box, 725.06, size 4 (625E30510) | EACH | 26 | $925.00 | $925.00 | $925.00 |
| 101 | Power service, as per plan (625E34001) | EACH | 1 | $7,500.00 | $7,500.00 | $7,500.00 |
| 102 | Light pole removed (625E75400) | EACH | 2 | $110.00 | $110.00 | $110.00 |
| 103 | Light pole foundation removed (625E75500) | EACH | 2 | $250.00 | $250.00 | $250.00 |
| 104 | Power service removed (625E75510) | EACH | 1 | $800.00 | $800.00 | $800.00 |
| 105 | RPM (621E00100) | EACH | 121 | $49.98 | $44.50 | $41.00 |
| 106 | RPM (621E00100) | EACH | 127 | $49.98 | $44.50 | $41.00 |
| 107 | RPM (621E00100) | EACH | 79 | $51.02 | $44.50 | $41.00 |
| 108 | Ground mounted support, no. 3 post, as per plan (630E03101) | FT | 340 | $14.50 | $14.50 | $14.50 |
| 109 | Ground mounted structural beam support, W6X9 (630E06500) | FT | 18 | $38.00 | $38.00 | $38.00 |
| 110 | Ground mounted structural beam support, W10X22 (630E07500) | FT | 400 | $50.00 | $50.00 | $50.00 |
| 111 | Sign post reflector, as per plan (630E08601) | EACH | 8 | $45.00 | $45.00 | $45.00 |
| 112 | Breakaway structural beam connection (630E09000) | EACH | 24 | $875.00 | $875.00 | $875.00 |
| 113 | Overhead sign support, type TC-12.31, design 10 (630E72330) | EACH | 3 | $39,750 | $39,750 | $39,750 |
| 114 | Sign, flat sheet (630E80100) | SF | 437 | $16.00 | $16.00 | $16.00 |
| 115 | Sign, ground mounted extrusheet (630E80200) | SF | 1,103 | $23.00 | $23.00 | $23.00 |
| 116 | Ground mounted structural beam support foundation (630E84500) | EACH | 28 | $875.00 | $875.00 | $875.00 |
| 117 | Rigid overhead sign support foundation (630E84510) | EACH | 3 | $7,850.00 | $7,850.00 | $7,850.00 |
| 118 | Removal of ground mounted sign and disposal (630E84900) | EACH | 65 | $10.00 | $10.00 | $10.00 |
| 119 | Removal of ground mounted major sign and disposal (630E85400) | EACH | 3 | $220.00 | $220.00 | $220.00 |
| 120 | Removal of ground mounted post support and disposal (630E86002) | EACH | 99 | $15.00 | $15.00 | $15.00 |
| 121 | Removal of ground mounted structural beam support (630E86102) | EACH | 10 | $290.00 | $290.00 | $290.00 |
| 122 | Signing, misc.:,solid wood post, 4X6 (630E97700) | EACH | 12 | $445.00 | $445.00 | $445.00 |
| 123 | Signing, misc.:,solid wood post, 6X8 (630E97700) | EACH | 6 | $675.00 | $675.00 | $675.00 |
| 124 | Stop line (644E00500) | FT | 92 | $8.27 | $8.00 | $10.00 |
| 125 | Transverse/diagonal line (644E00700) | FT | 351 | $6.20 | $6.00 | $9.00 |
| 126 | Island marking (644E00900) | SF | 96 | $10.33 | $10.00 | $8.00 |
| 127 | Lane arrow (644E01300) | EACH | 18 | $87.84 | $85.00 | $125.00 |
| 128 | Lane arrow (646E20300) | EACH | 6 | $129.17 | $125.00 | $150.00 |
| 129 | Wrong way arrow (646E20320) | EACH | 4 | $155.01 | $150.00 | $140.00 |
| 130 | Edge line, 6" (646E10010) | MI | 0.98 | $6,200.34 | $6,000.00 | $4,100.00 |
| 131 | Edge line, 6" (646E10010) | MI | 0.81 | $6,200.35 | $6,000.00 | $4,100.00 |
| 132 | Center line (646E10200) | MI | 0.05 | $10,334 | $10,000 | $6,000.00 |
| 133 | Channelizing line, 12" (646E10310) | FT | 197 | $3.10 | $3.00 | $3.00 |
| 134 | Edge line, 6" (644E00104) | MI | 3.49 | $4,650.26 | $4,500.00 | $3,550.00 |
| 135 | Edge line, 6" (644E00104) | MI | 3.07 | $4,650.25 | $4,500.00 | $3,550.00 |
| 136 | Lane line, 6" (644E00204) | MI | 2.69 | $1,550.09 | $1,500.00 | $1,775.00 |
| 137 | Center line (644E00300) | MI | 0.16 | $6,200.31 | $6,000.00 | $5,200.00 |
| 138 | Channelizing line, 12" (644E00404) | FT | 4,785 | $2.07 | $2.00 | $2.00 |
| 139 | Dotted line, 6" (644E01510) | FT | 2,454 | $1.03 | $1.00 | $1.00 |
| 140 | Work zone impact attenuator, 24" wide hazards, (unidirectional) (614E12380) | EACH | 10 | $2,380.00 | $2,380.00 | $1,982.31 |
| 141 | Work zone speed limit sign (614E12470) | EACH | 4 | $400.00 | $200.00 | $283.02 |
| 142 | Replacement sign (614E12500) | EACH | 5 | $400.00 | $192.00 | $150.00 |
| 143 | Replacement drum (614E12600) | EACH | 5 | $100.00 | $56.00 | $55.00 |
| 144 | Barrier reflector, type 1, BI-directional (614E13310) | EACH | 192 | $10.00 | $8.00 | $11.64 |
| 145 | Barrier reflector, type 5, one-way (614E13318) | EACH | 14 | $24.00 | $8.00 | $13.39 |
| 146 | Object marker, one way (614E13350) | EACH | 14 | $26.00 | $16.00 | $20.23 |
| 147 | Object marker, two way (614E13360) | EACH | 192 | $26.00 | $16.00 | $20.23 |
| 148 | Portable changeable message sign, as per plan (614E18601) | SNMT | 18 | $440.00 | $850.00 | $993.36 |
| 149 | Work zone edge line, class I, 6", 807 paint (614E22056) | MI | 2.47 | $2,686.81 | $2,600.00 | $2,400.00 |
| 150 | Work zone edge line, class I, 6", 807 paint (614E22056) | MI | 1.72 | $2,686.81 | $2,600.00 | $2,400.00 |
| 151 | Work zone channelizing line, class I, 12", 807 paint (614E23110) | FT | 930 | $2.07 | $2.00 | $3.00 |
| 152 | Work zone stop line, class I (614E26000) | FT | 50 | $3.10 | $3.00 | $5.00 |
| 153 | Work zone arrow, class I, 642 paint (614E30200) | EACH | 7 | $51.67 | $50.00 | $125.00 |
| 154 | Portable barrier, unanchored (622E41100) | FT | 9,148 | $19.27 | $12.00 | $17.00 |
| 155 | Portable barrier, unanchored (622E41100) | FT | 425 | $19.27 | $14.00 | $12.00 |
| 156 | Digital speed limit (DSL) sign assembly (808E18700) | SNMT | 64 | $100.00 | $750.00 | $627.96 |
| 157 | Embankment (203E20000) | CY | 257 | $13.43 | $11.00 | $26.00 |
| 158 | Granular material, type B (203E35110) | CY | 265 | $60.00 | $55.00 | $60.00 |
| 159 | Sealing of concrete surfaces (epoxy-urethane), as per plan (512E10101) | SY | 209 | $30.46 | $30.00 | $31.00 |
| 160 | Concrete slope protection, as per plan (601E21001) | SY | 21 | $154.00 | $90.00 | $105.00 |
| 161 | Paved gutter, type 2, as per plan (601E38401) | FT | 83 | $48.00 | $30.00 | $45.00 |
| 162 | Mechanically stabilized earth wall (840E20000) | SF | 2,556 | $55.00 | $50.00 | $52.00 |
| 163 | Wall excavation (840E21000) | CY | 775 | $12.00 | $6.00 | $6.00 |
| 164 | Foundation preparation (840E22000) | SY | 360 | $51.00 | $30.00 | $23.00 |
| 165 | Select granular backfill (840E23000) | CY | 1,710 | $65.00 | $65.00 | $66.00 |
| 166 | Natural soil (840E23050) | CY | 92 | $13.00 | $15.00 | $24.00 |
| 167 | 6" drainage pipe, perforated (840E25010) | FT | 320 | $9.00 | $7.00 | $4.00 |
| 168 | 6" drainage pipe, non-perforated (840E25020) | FT | 10 | $31.00 | $25.00 | $33.00 |
| 169 | Concrete coping (840E26000) | FT | 165 | $110.00 | $115.00 | $135.00 |
| 170 | Aesthetic surface treatment (840E26050) | SF | 2,224 | $0.58 | $6.00 | $1.00 |
| 171 | On-site assistance (840E27000) | DAY | 5 | $100.00 | $100.00 | $100.00 |
| 172 | SGB inspection and compaction testing (840E28000) | LS | 1 | $7,220.00 | $4,000.00 | $2,680.00 |
| 173 | Embankment (203E20000) | CY | 333 | $11.00 | $11.00 | $26.00 |
| 174 | Granular material, type B (203E35110) | CY | 274 | $60.00 | $55.00 | $60.00 |
| 175 | Sealing of concrete surfaces (epoxy-urethane), as per plan (512E10101) | SY | 219 | $30.46 | $30.00 | $29.00 |
| 176 | Concrete slope protection, as per plan (601E21001) | SY | 19 | $148.00 | $90.00 | $190.00 |
| 177 | Paved gutter, type 2, as per plan (601E38401) | FT | 96 | $50.00 | $30.00 | $45.00 |
| 178 | Mechanically stabilized earth wall (840E20000) | SF | 2,275 | $53.00 | $50.00 | $59.00 |
| 179 | Wall excavation (840E21000) | CY | 794 | $12.00 | $6.00 | $6.00 |
| 180 | Foundation preparation (840E22000) | SY | 400 | $21.00 | $30.00 | $23.00 |
| 181 | Select granular backfill (840E23000) | CY | 1,740 | $65.00 | $65.00 | $66.00 |
| 182 | Natural soil (840E23050) | CY | 113 | $13.00 | $15.00 | $24.00 |
| 183 | 6" drainage pipe, perforated (840E25010) | FT | 362 | $9.00 | $7.00 | $4.00 |
| 184 | 6" drainage pipe, non-perforated (840E25020) | FT | 15 | $31.00 | $25.00 | $22.00 |
| 185 | Concrete coping (840E26000) | FT | 168 | $110.00 | $115.00 | $135.00 |
| 186 | Aesthetic surface treatment (840E26050) | SF | 1,939 | $0.58 | $6.00 | $1.00 |
| 187 | On-site assistance (840E27000) | DAY | 5 | $100.00 | $100.00 | $100.00 |
| 188 | SGB inspection and compaction testing (840E28000) | LS | 1 | $7,220.00 | $4,000.00 | $2,680.00 |
| 189 | Cofferdams and excavation bracing (503E11100) | LS | 1 | $1.00 | $2,500.00 | $1.00 |
| 190 | Unclassified excavation (503E21300) | LS | 1 | $10,000 | $2,500.00 | $27,500 |
| 191 | Steel sheet piling left in place, as per plan (504E11101) | SF | 1,405 | $22.50 | $60.00 | $62.00 |
| 192 | Pile driving equipment mobilization (505E11100) | LS | 1 | $20,000 | $75,000 | $52,400 |
| 193 | 14" cast-in-place reinforced concrete piles, driven (507E00600) | FT | 2,430 | $12.00 | $22.00 | $36.00 |
| 194 | 14" cast-in-place reinforced concrete piles, furnished (507E00650) | FT | 2,700 | $56.00 | $46.00 | $43.00 |
| 195 | Epoxy coated steel reinforcement (509E10000) | LB | 113,512 | $1.32 | $1.30 | $1.30 |
| 196 | No. 4 deformed GFRP reinforcement (509E30020) | FT | 7,537 | $1.26 | $1.32 | $1.40 |
| 197 | Semi-integral diaphragm guide (511E33500) | EACH | 2 | $3,500.00 | $3,300.00 | $3,100.00 |
| 198 | Class QC2 concrete with QC/QA, bridge deck (511E34446) | CY | 343 | $800.00 | $800.00 | $798.00 |
| 199 | Class QC2 concrete with QC/QA, bridge deck (parapet) (511E34450) | CY | 74 | $825.00 | $750.00 | $1,579.00 |
| 200 | Class QC1 concrete with QC/QA, pier above footings (511E41012) | CY | 46 | $950.00 | $1,000.00 | $1,050.00 |
| 201 | Class QC1 concrete with QC/QA, abutment including footing, as per plan (511E43513) | CY | 172 | $625.00 | $500.00 | $600.00 |
| 202 | Class QC1 concrete with QC/QA, footing (511E46512) | CY | 39 | $480.00 | $550.00 | $600.00 |
| 203 | Sealing of concrete surfaces (epoxy-urethane) (512E10100) | SY | 4 | $253.81 | $250.00 | $290.00 |
| 204 | Sealing of concrete surfaces (epoxy-urethane) (512E10100) | SY | 1,309 | $21.92 | $30.00 | $28.00 |
| 205 | Draped strand prestressed concrete bridge I-beam members, level 3, type WF42-49 (515E15080) | EACH | 10 | $55,000 | $55,000 | $61,000 |
| 206 | Intermediate diaphragms (515E20000) | EACH | 24 | $1,900.00 | $1,703.58 | $1,450.00 |
| 207 | 1" preformed expansion joint filler (516E13600) | SF | 20 | $9.00 | $10.99 | $6.00 |
| 208 | 2" preformed expansion joint filler (516E13900) | SF | 55 | $10.00 | $8.00 | $9.00 |
| 209 | Semi-integral abutment expansion joint seal (516E14020) | FT | 112 | $33.00 | $34.00 | $25.00 |
| 210 | Elastomeric bearing with internal laminates and load plate (516E44100) | EACH | 10 | $2,735.00 | $2,500.00 | $1,400.00 |
| 211 | Elastomeric bearing with internal laminates and load plate, as per plan (516E44101) | EACH | 10 | $1,885.00 | $1,650.00 | $2,200.00 |
| 212 | Porous backfill with geotextile fabric (518E21200) | CY | 60 | $80.00 | $90.00 | $140.00 |
| 213 | 6" perforated corrugated plastic pipe (518E40000) | FT | 157 | $17.00 | $6.00 | $10.00 |
| 214 | 6" non-perforated corrugated plastic pipe, including specials (518E40010) | FT | 132 | $25.00 | $8.00 | $15.00 |
| 215 | Dynamic load testing (523E20000) | EACH | 2 | $4,900.00 | $3,500.00 | $5,300.00 |
| 216 | Reinforced concrete approach slabs with QC/QA (T=1 (526E30010) | SY | 296 | $353.00 | $325.00 | $370.00 |
| 217 | Type A installation (526E90010) | FT | 91 | $94.00 | $120.00 | $170.00 |
| 218 | Special - structures, aesthetic parapet lettering (530E00200) | LS | 1 | $13,600 | $18,000 | $13,500 |
| 219 | Special - form liner (530E13000) | SF | 1,387 | $35.00 | $14.00 | $13.50 |
| 220 | Vandal protection fence, 6' straight, coated fabric, as per plan (607E39901) | FT | 370 | $106.55 | $95.80 | $106.55 |
| 221 | Structure grounding system (625E33000) | EACH | 2 | $4,317.00 | $4,317.00 | $4,317.00 |
| 222 | Polymer modified asphalt expansion joint system (846E00110) | CF | 38 | $582.80 | $582.80 | $582.80 |
| 223 | Cofferdams and excavation bracing (503E11100) | LS | 1 | $12,000 | $8,000.00 | $100,000 |
| 224 | Unclassified excavation (503E21300) | LS | 1 | $1,897.89 | $20,000 | $25,800 |
| 225 | Epoxy coated steel reinforcement (509E10000) | LB | 11,265 | $1.38 | $1.28 | $1.30 |
| 226 | Class QC1 concrete, retaining/wingwall not including footing (511E46010) | CY | 30 | $1,250.01 | $1,000.00 | $1,500.00 |
| 227 | Class QC1 concrete, footing (511E46510) | CY | 71 | $410.00 | $450.00 | $670.00 |
| 228 | Class QC1 concrete, headwall (511E46610) | CY | 1 | $1,557.00 | $850.00 | $1,800.00 |
| 229 | Sealing of concrete surfaces (non-epoxy) (512E10050) | SY | 100 | $14.21 | $26.00 | $11.50 |
| 230 | Type 2 waterproofing (512E33000) | SY | 487 | $33.00 | $20.00 | $24.00 |
| 231 | 1" preformed expansion joint filler (516E13600) | SF | 44 | $3.00 | $10.00 | $6.50 |
| 232 | Porous backfill with geotextile fabric (518E21200) | CY | 30 | $284.00 | $85.00 | $145.00 |
| 233 | Rock channel protection, type B with aggregate filter (601E32110) | CY | 110 | $88.00 | $120.00 | $170.00 |
| 234 | 12' X 8' conduit, type A, 706.05, as per plan (611E96001) | FT | 120 | $1,700.00 | $1,650.00 | $2,500.00 |
| 235 | Cofferdams and excavation bracing (503E11100) | LS | 1 | $12,000 | $8,000.00 | $84,000 |
| 236 | Unclassified excavation (503E21300) | LS | 1 | $2,100.00 | $20,000 | $25,800 |
| 237 | Epoxy coated steel reinforcement (509E10000) | LB | 11,163 | $1.39 | $1.28 | $1.30 |
| 238 | Class QC1 concrete, retaining/wingwall not including footing (511E46010) | CY | 28 | $1,323.00 | $1,000.00 | $1,500.00 |
| 239 | Class QC1 concrete, footing (511E46510) | CY | 73 | $410.00 | $450.00 | $650.00 |
| 240 | Class QC1 concrete, headwall (511E46610) | CY | 1 | $1,557.00 | $850.00 | $1,800.00 |
| 241 | Sealing of concrete surfaces (non-epoxy) (512E10050) | SY | 100 | $14.21 | $26.00 | $11.50 |
| 242 | Type 2 waterproofing (512E33000) | SY | 371 | $33.00 | $20.00 | $25.00 |
| 243 | 1" preformed expansion joint filler (516E13600) | SF | 44 | $3.00 | $10.00 | $6.50 |
| 244 | Porous backfill with geotextile fabric (518E21200) | CY | 23 | $284.00 | $85.00 | $160.00 |
| 245 | Rock channel protection, type A with aggregate filter (601E32010) | CY | 170 | $88.00 | $120.00 | $150.00 |
| 246 | 12' X 8' conduit, type A, 706.05, as per plan (611E96001) | FT | 91 | $1,700.00 | $1,600.00 | $2,400.00 |
| 247 | Premium for contract performance bond and for payment bond (103E05000) | LS | 1 | $55,000 | $75,000 | $70,000 |
| 248 | CPM progress schedule (108E10000) | LS | 1 | $5,000.00 | $15,000 | $1,000.00 |
| 249 | Maintaining traffic (614E11000) | LS | 1 | $91,442 | $100,000 | $124,000 |
| 250 | Field office, type C, as per plan (619E16021) | MNTH | 20 | $6,000.00 | $6,500.00 | $6,200.00 |
| 251 | Construction layout stakes and surveying (623E10000) | LS | 1 | $15,000 | $75,000 | $65,600 |
| 252 | Mobilization (624E10000) | LS | 1 | $615,531 | $615,000 | $645,400 |
| 300 | Special - drilled water well abandoned (202E66000) | EACH | 1 | $1,770.00 | $2,500.00 | $4,500.00 |
| 301 | Special - piezometer (203E07510) | EACH | 1 | $40,000 | $25,000 | $44,000 |
| 302 | Light pole removed (625E75400) | EACH | 2 | $110.00 | $1,000.00 | $110.00 |
| 303 | Transverse/diagonal line (644E00700) | FT | 235 | $6.20 | $6.00 | $4.00 |
| 304 | Work zone increased penalties sign (614E12484) | EACH | 8 | $620.00 | $150.00 | $153.72 |
| 305 | Work zone lane line, class III, 6", 642 paint (614E20560) | MI | 2.69 | $310.02 | $750.00 | $80.00 |
| 306 | Work zone center line, class III, 642 paint (614E21550) | MI | 0.21 | $826.71 | $800.00 | $975.00 |
| 307 | Work zone edge line, class III, 6", 642 paint (614E22360) | MI | 4.47 | $620.03 | $600.00 | $890.00 |
| 308 | Work zone edge line, class III, 6", 642 paint (614E22360) | MI | 3.88 | $620.03 | $600.00 | $890.00 |
| 309 | Work zone channelizing line, class III, 12", 642 paint (614E23690) | FT | 4,982 | $0.52 | $0.50 | $0.50 |
| 310 | Work zone dotted line, class I, 6", 807 paint (614E24102) | FT | 146 | $1.03 | $1.00 | $0.50 |
| 311 | Work zone dotted line, class III, 6", 642 paint (614E24612) | FT | 2,454 | $0.52 | $0.50 | $0.45 |
| 312 | Work zone transverse/diagonal line, class I, 642 paint (614E25200) | FT | 94 | $3.10 | $3.00 | $5.00 |
| 313 | Law enforcement officer with patrol car for assistance (614E11110) | HR | 100 | $75.00 | $85.00 | $80.00 |
| 314 | Ground mounted support, no. 3 post (630E03100) | FT | 240 | $14.50 | $14.50 | $14.50 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from ODOT's tabulation for this contract. ODOT Official Bid Tabulation PDFs from its public DigitalPaper bid tab cabinet, January 2020 to November 2026 (the source links open after DigitalPaper starts a guest session). ODOT prints unit prices to two decimals but computes line amounts from the full price, so a few bids miss their total and are left out. Descriptions are cut at about 50 characters, as ODOT prints them.
Every contract let that day: ODOT letting of March 27, 2025. Compiled by Mirage Metrics.