ODOT contract 250559 bid tabulation
HOC-SR 664-12.74 (INTERSECTION). Let by Ohio DOT on December 4, 2025, HOC. 5 bids received; low bid $2,047,827 by Complete General Construction Company, -7.5% against the engineer's estimate of $2,215,000.
- Owner
- Ohio DOT
- Letting
- 04 DEC 2025
- Pay items
- 144
- Data through
- 12 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | Complete General Construction Company | $2,047,827 | Low | -8.0% |
| 2 | Shelly & Sands Inc | $2,228,180 | +9.0% | +1.0% |
| 3 | Allard Excavation LLC | $2,298,817 | +12% | +4.0% |
| 4 | Axis Civil Construction LLC | $2,637,555 | +29% | +19% |
| 5 | D G M Inc | $2,776,152 | +36% | +25% |
Engineer's estimate: $2,215,000.
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Complete General Construction Company | 2. Shelly & Sands Inc | 3. Allard Excavation LLC | 4. Axis Civil Construction LLC | 5. D G M Inc |
|---|---|---|---|---|---|---|---|---|
| 1 | Clearing and grubbing (201E11000) | LS | 1 | $16,000 | $30,000 | $21,781 | $30,000 | $35,000 |
| 2 | Pavement removed (202E23000) | SY | 5,562 | $13.00 | $12.00 | $3.00 | $14.00 | $10.00 |
| 3 | Walk removed (202E30000) | SF | 40 | $3.00 | $5.00 | $6.00 | $14.00 | $10.00 |
| 4 | Pipe removed, 24" and under (202E35100) | FT | 300 | $30.00 | $28.00 | $8.00 | $35.00 | $15.00 |
| 5 | Guardrail removed (202E38000) | FT | 100 | $2.40 | $5.00 | $5.00 | $12.00 | $3.00 |
| 6 | Guard post removed (202E38800) | EACH | 5 | $25.00 | $20.00 | $5.00 | $120.00 | $20.00 |
| 7 | Anchor assembly removed, type A (202E42000) | EACH | 1 | $345.00 | $500.00 | $120.00 | $600.00 | $300.00 |
| 8 | Anchor assembly removed, type T (202E42040) | EACH | 1 | $95.00 | $150.00 | $120.00 | $600.00 | $200.00 |
| 9 | Monument assembly removed (202E60010) | EACH | 2 | $200.00 | $100.00 | $32.00 | $150.00 | $200.00 |
| 10 | Fence removed (202E75000) | FT | 951 | $3.00 | $7.50 | $2.43 | $7.50 | $5.00 |
| 11 | Gate removed (202E75250) | EACH | 1 | $95.00 | $500.00 | $94.00 | $500.00 | $200.00 |
| 12 | Removal misc.: billboard removed (202E98100) | EACH | 2 | $6,500.00 | $3,750.00 | $2,981.00 | $6,500.00 | $2,000.00 |
| 13 | Removal misc.: decorative boulder (202E98100) | EACH | 2 | $850.00 | $100.00 | $359.00 | $65.00 | $50.00 |
| 14 | Excavation (203E10000) | CY | 3,969 | $18.00 | $19.00 | $15.00 | $40.00 | $29.00 |
| 15 | Excavation, as per plan (203E10001) | CY | 128 | $30.00 | $35.00 | $31.00 | $40.00 | $40.00 |
| 16 | Embankment (203E20000) | CY | 5,380 | $14.00 | $15.50 | $12.00 | $40.00 | $28.60 |
| 17 | Subgrade compaction (204E10000) | SY | 6,700 | $3.00 | $7.00 | $3.00 | $2.50 | $5.00 |
| 18 | Excavation of subgrade, as per plan (204E13001) | CY | 1,489 | $30.00 | $32.00 | $21.00 | $35.00 | $30.00 |
| 19 | Granular material, type C, as per plan (204E30021) | CY | 1,489 | $68.00 | $72.00 | $88.00 | $95.00 | $110.00 |
| 20 | Proof rolling (204E45000) | HR | 4 | $350.00 | $265.00 | $249.00 | $250.00 | $2,000.00 |
| 21 | Geotextile fabric, as per plan (204E50001) | SY | 4,467 | $3.00 | $2.00 | $1.32 | $1.50 | $1.50 |
| 22 | Guardrail, type MGS (606E15050) | FT | 50 | $64.00 | $35.00 | $35.00 | $35.00 | $40.00 |
| 23 | Anchor assembly, MGS type E, MASH 2016 (606E26150) | EACH | 1 | $3,780.00 | $2,700.00 | $2,700.00 | $2,700.00 | $3,000.00 |
| 24 | Anchor assembly, MGS type T (606E26550) | EACH | 1 | $1,695.00 | $1,250.00 | $1,250.00 | $1,250.00 | $1,300.00 |
| 25 | Gate, type 47 (607E40500) | EACH | 1 | $220.00 | $1,000.00 | $1,000.00 | $1,000.00 | $1,200.00 |
| 26 | Fence, misc.: 4-rail wooden fence (607E98000) | FT | 513 | $44.50 | $22.00 | $22.00 | $22.00 | $23.00 |
| 27 | Monument assembly, type C (623E38500) | EACH | 2 | $1,100.00 | $1,900.00 | $1,189.00 | $3,000.00 | $1,000.00 |
| 28 | Reference monument, type A (623E40500) | EACH | 9 | $1,050.00 | $825.00 | $514.40 | $600.00 | $500.00 |
| 29 | Right-of-way monument, type B (623E40520) | EACH | 11 | $450.00 | $185.00 | $523.00 | $400.00 | $250.00 |
| 30 | Monument, misc.: mag spike (623E40900) | EACH | 9 | $200.00 | $150.00 | $117.00 | $400.00 | $200.00 |
| 31 | Special - mailbox support system, single (690E50100) | EACH | 5 | $1,840.00 | $275.00 | $180.00 | $150.00 | $200.00 |
| 32 | Tied concrete block mat with type 1 underlayment (601E21050) | SY | 31 | $80.00 | $100.00 | $80.00 | $95.00 | $200.00 |
| 33 | Rock channel protection, type C with filter (601E32200) | CY | 5 | $205.00 | $400.00 | $184.00 | $220.00 | $250.00 |
| 34 | Bioretention cell (601E45050) | CY | 128 | $140.00 | $140.00 | $185.00 | $120.00 | $200.00 |
| 35 | Soil analysis test (659E00100) | EACH | 2 | $150.00 | $150.00 | $180.00 | $150.00 | $150.00 |
| 36 | Topsoil (659E00300) | CY | 696 | $35.00 | $23.00 | $23.00 | $48.00 | $17.50 |
| 37 | Seeding and mulching (659E10000) | SY | 6,165 | $0.75 | $0.75 | $0.75 | $0.75 | $2.00 |
| 38 | Repair seeding and mulching (659E14000) | SY | 314 | $0.75 | $0.75 | $0.75 | $0.75 | $0.05 |
| 39 | Inter-seeding (659E15000) | SY | 314 | $0.75 | $0.75 | $0.75 | $0.75 | $0.05 |
| 40 | Commercial fertilizer (659E20000) | TON | 0.12 | $1,250.00 | $1,250.00 | $1,250.00 | $1,250.00 | $1,500.00 |
| 41 | Lime (659E31000) | ACRE | 0.18 | $150.00 | $150.00 | $150.00 | $150.00 | $300.00 |
| 42 | Water (659E35000) | MGAL | 17 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 43 | Mowing (659E40000) | MSF | 1,569 | $2.00 | $2.00 | $2.00 | $2.00 | $2.00 |
| 44 | Slope erosion protection mat, type B (670E00520) | SY | 1,464 | $2.50 | $2.50 | $2.50 | $2.50 | $2.75 |
| 45 | Ditch erosion protection mat, type B (670E00720) | SY | 96 | $2.50 | $2.50 | $2.50 | $2.50 | $2.75 |
| 46 | Erosion control mat (671E14000) | SY | 91 | $2.50 | $2.50 | $2.50 | $2.50 | $2.75 |
| 47 | Storm water pollution prevention plan (832E15000) | LS | 1 | $2,500.00 | $2,500.00 | $3,000.00 | $2,500.00 | $3,000.00 |
| 48 | Storm water pollution prevention inspections (832E15002) | LS | 1 | $7,350.00 | $9,000.00 | $8,500.00 | $9,000.00 | $12,000 |
| 49 | Storm water pollution prevention inspection software (832E15010) | LS | 1 | $10,500 | $10,500 | $12,500 | $10,500 | $10,500 |
| 50 | Erosion control (832E30000) | EACH | 26,004 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 51 | Concrete masonry (602E20000) | CY | 1 | $3,500.00 | $3,500.00 | $5,480.00 | $3,800.00 | $2,500.00 |
| 52 | 4" base pipe underdrains with geotextile fabric, as per plan (605E06021) | FT | 161 | $28.00 | $8.50 | $23.00 | $30.00 | $16.00 |
| 53 | 6" base pipe underdrains with geotextile fabric (605E14020) | FT | 3,194 | $12.00 | $15.00 | $16.00 | $25.00 | $15.00 |
| 54 | Aggregate drains (605E31100) | FT | 43 | $30.00 | $22.00 | $12.00 | $60.00 | $30.00 |
| 55 | 4" conduit, type C (611E00200) | FT | 26 | $40.00 | $25.00 | $17.00 | $38.00 | $30.00 |
| 56 | 6" conduit, type F for underdrain outlets (611E00510) | FT | 418 | $35.00 | $30.00 | $19.00 | $38.00 | $25.00 |
| 57 | 12" conduit, type B (611E04400) | FT | 218 | $100.00 | $87.00 | $106.00 | $84.00 | $95.00 |
| 58 | 12" conduit, type C (611E04600) | FT | 173 | $85.00 | $80.00 | $148.00 | $95.00 | $115.00 |
| 59 | 12" conduit, type D (611E04900) | FT | 48 | $75.00 | $95.00 | $107.00 | $95.00 | $90.00 |
| 60 | 15" conduit, type C (611E06100) | FT | 15 | $105.00 | $115.00 | $102.00 | $160.00 | $125.00 |
| 61 | 15" conduit, type D (611E06400) | FT | 32 | $80.00 | $90.00 | $115.00 | $100.00 | $110.00 |
| 62 | 18" conduit, type B (611E07400) | FT | 492 | $155.00 | $105.00 | $141.00 | $105.00 | $140.00 |
| 63 | 18" conduit, type D (611E07900) | FT | 52 | $75.00 | $95.00 | $130.00 | $105.00 | $110.00 |
| 64 | 21" conduit, type D (611E09400) | FT | 46 | $110.00 | $115.00 | $148.00 | $150.00 | $140.00 |
| 65 | Catch basin, no. 3 (611E98150) | EACH | 3 | $5,300.00 | $4,700.00 | $6,555.00 | $5,500.00 | $5,500.00 |
| 66 | Catch basin, no. 3A (611E98180) | EACH | 1 | $4,600.00 | $4,100.00 | $5,713.00 | $4,500.00 | $4,500.00 |
| 67 | Catch basin, no. 2-3 (611E98510) | EACH | 3 | $4,300.00 | $3,500.00 | $5,137.00 | $4,000.00 | $3,000.00 |
| 68 | Manhole, no. 3 (611E99574) | EACH | 3 | $5,000.00 | $4,600.00 | $5,813.00 | $8,000.00 | $5,100.00 |
| 69 | Precast reinforced concrete outlet (611E99710) | EACH | 5 | $650.00 | $450.00 | $349.00 | $600.00 | $300.00 |
| 70 | Low strength mortar backfill (type 1) (613E41250) | CY | 204 | $205.00 | $128.00 | $174.00 | $200.00 | $170.00 |
| 71 | Pavement planing, asphalt concrete, 1.25" depth (254E01000) | SY | 88 | $85.75 | $9.00 | $85.75 | $45.00 | $30.00 |
| 72 | Asphalt concrete base, PG64-22, (449) (301E56000) | CY | 704 | $213.00 | $210.00 | $213.00 | $213.00 | $240.00 |
| 73 | Aggregate base (304E20000) | CY | 1,428 | $75.00 | $90.00 | $86.00 | $130.00 | $105.00 |
| 74 | Aggregate base (304E20000) | CY | 120 | $100.00 | $115.00 | $144.00 | $130.00 | $150.00 |
| 75 | Aggregate base, as per plan (304E20001) | CY | 75 | $68.00 | $180.00 | $180.00 | $240.00 | $200.00 |
| 76 | Non-tracking tack coat (407E20000) | GAL | 648 | $4.10 | $3.50 | $4.10 | $4.10 | $4.50 |
| 77 | Asphalt concrete surface course, type 1, (448), PG64-22 (441E50000) | CY | 216 | $234.00 | $240.00 | $234.00 | $234.00 | $285.00 |
| 78 | Asphalt concrete intermediate course, type 2, (448) (441E50300) | CY | 253 | $233.00 | $230.00 | $233.00 | $233.00 | $260.00 |
| 79 | 9" non-reinforced concrete pavement, class QC 1P (452E13010) | SY | 338 | $95.00 | $115.00 | $106.00 | $140.00 | $115.00 |
| 80 | Combination curb and gutter, type 2 (609E12000) | FT | 1,677 | $30.00 | $45.00 | $31.00 | $38.00 | $36.00 |
| 81 | Curb, type 6 (609E26000) | FT | 216 | $42.00 | $55.00 | $22.00 | $36.00 | $30.00 |
| 82 | Curb, type 7 (609E28000) | FT | 85 | $50.00 | $69.00 | $23.00 | $45.00 | $30.00 |
| 83 | Combination curb and gutter, type 9 (609E31000) | FT | 296 | $45.00 | $81.00 | $29.00 | $37.00 | $33.00 |
| 84 | Concrete median (609E72000) | SY | 330 | $130.00 | $145.00 | $127.00 | $135.00 | $145.00 |
| 85 | Rumble strips, shoulder (concrete) (618E40200) | FT | 506 | $10.00 | $15.00 | $28.00 | $8.00 | $40.00 |
| 86 | Connection, fused pull apart (625E00450) | EACH | 20 | $150.00 | $150.00 | $150.00 | $150.00 | $160.00 |
| 87 | Connection, unfused permanent (625E00480) | EACH | 15 | $130.00 | $131.00 | $150.00 | $130.00 | $160.00 |
| 88 | Light pole, conventional, AT12B40 (625E10490) | EACH | 10 | $3,400.00 | $3,400.00 | $5,500.00 | $3,400.00 | $5,600.00 |
| 89 | Light pole foundation, 24" X 8' deep (625E14100) | EACH | 10 | $2,200.00 | $2,200.00 | $3,200.00 | $2,200.00 | $3,300.00 |
| 90 | No. 4 AWG 2400 volt distribution cable (625E23200) | FT | 1,125 | $3.30 | $3.30 | $6.00 | $3.30 | $6.00 |
| 91 | No. 10 AWG pole and bracket cable (625E23400) | FT | 1,698 | $1.50 | $1.50 | $3.50 | $1.50 | $4.00 |
| 92 | 1-1/2" duct cable with three no. 4 AWG 2400 volt cables (625E24320) | FT | 1,070 | $15.00 | $15.00 | $13.00 | $15.00 | $13.00 |
| 93 | Conduit, 2", 725.04 (625E25400) | FT | 25 | $35.00 | $35.00 | $26.00 | $35.00 | $30.00 |
| 94 | Conduit, 3", 725.04 (625E25500) | FT | 23 | $45.00 | $45.00 | $37.00 | $45.00 | $40.00 |
| 95 | Conduit, jacked or drilled, 725.04, 3" (625E25902) | FT | 116 | $65.00 | $65.00 | $75.00 | $65.00 | $85.00 |
| 96 | Luminaire, conventional, solid state (LED), as per plan (625E26253) | EACH | 2 | $325.00 | $325.00 | $650.00 | $325.00 | $700.00 |
| 97 | Luminaire, conventional, solid state (LED), as per plan (625E26253) | EACH | 8 | $300.00 | $300.00 | $650.00 | $300.00 | $700.00 |
| 98 | Trench, 24" deep (625E29002) | FT | 1,018 | $12.00 | $12.00 | $24.00 | $12.00 | $27.00 |
| 99 | Pull box, 725.08, 18" (625E30700) | EACH | 2 | $1,200.00 | $1,200.00 | $1,250.00 | $1,200.00 | $1,300.00 |
| 100 | Pull box, 725.08, 24" (625E30706) | EACH | 2 | $1,500.00 | $1,500.00 | $1,500.00 | $1,500.00 | $1,600.00 |
| 101 | Ground rod (625E32000) | EACH | 10 | $400.00 | $400.00 | $265.00 | $400.00 | $300.00 |
| 102 | Power service, as per plan (625E34001) | EACH | 1 | $10,000 | $10,000 | $12,500 | $10,000 | $13,000 |
| 103 | Underground warning marking tape (625E36010) | FT | 1,018 | $1.85 | $1.85 | $3.00 | $1.85 | $3.00 |
| 104 | Arc flash calculations and label, control center (625E76000) | EACH | 3 | $3,500.00 | $3,500.00 | $3,450.00 | $3,500.00 | $3,500.00 |
| 105 | Ground mounted support, no. 3 post (630E03100) | FT | 358 | $16.00 | $15.00 | $15.00 | $15.00 | $16.00 |
| 106 | Ground mounted support, no. 4 post (630E04100) | FT | 103 | $17.00 | $25.00 | $25.00 | $25.00 | $27.00 |
| 107 | Ground mounted structural beam support, S4X7.7 (630E06400) | FT | 32 | $80.00 | $27.50 | $27.50 | $27.50 | $30.00 |
| 108 | Sign post reflector (630E08600) | EACH | 14 | $45.00 | $45.00 | $45.00 | $45.00 | $50.00 |
| 109 | Breakaway structural beam connection (630E09000) | EACH | 2 | $895.00 | $200.00 | $200.00 | $200.00 | $210.00 |
| 110 | Sign attachment assembly (630E75000) | EACH | 4 | $440.00 | $75.00 | $75.00 | $75.00 | $85.00 |
| 111 | Sign, flat sheet (630E80100) | SF | 255 | $23.00 | $25.00 | $25.00 | $25.00 | $30.00 |
| 112 | Ground mounted structural beam support foundation (630E84500) | EACH | 2 | $1,720.00 | $1,350.00 | $28.00 | $1,350.00 | $1,400.00 |
| 113 | Removal of ground mounted sign and disposal (630E84900) | EACH | 23 | $10.00 | $20.00 | $20.00 | $20.00 | $21.00 |
| 114 | Removal of ground mounted sign and reerection (630E85100) | EACH | 5 | $65.00 | $150.00 | $150.00 | $150.00 | $160.00 |
| 115 | Removal of ground mounted post support and disposal (630E86002) | EACH | 17 | $18.00 | $20.00 | $20.00 | $20.00 | $22.00 |
| 116 | Removal of ground mounted post support and reerection (630E86010) | EACH | 3 | $165.00 | $225.00 | $225.00 | $225.00 | $230.00 |
| 117 | Edge line, 6" (644E00104) | MI | 0.84 | $7,000.00 | $7,000.00 | $7,000.00 | $7,000.00 | $8,000.00 |
| 118 | Center line (644E00300) | MI | 0.28 | $9,900.00 | $9,900.00 | $9,900.00 | $9,900.00 | $11,000 |
| 119 | Transverse/diagonal line (644E00700) | FT | 182 | $8.25 | $8.25 | $8.25 | $8.25 | $9.00 |
| 120 | Dotted line, 12" (644E01520) | FT | 112 | $3.45 | $3.45 | $3.45 | $3.45 | $4.00 |
| 121 | Yield line (644E20800) | FT | 50 | $14.25 | $14.25 | $14.25 | $14.25 | $15.00 |
| 122 | Fence, misc.: temporary livestock fence (607E98000) | FT | 529 | $16.50 | $27.00 | $27.00 | $27.00 | $30.00 |
| 123 | Fence, misc.: temporary livestock gate (607E98100) | EACH | 1 | $1,450.00 | $1,000.00 | $1,000.00 | $1,000.00 | $1,000.00 |
| 124 | Law enforcement officer with patrol car for assistance (614E11110) | HR | 40 | $90.00 | $90.00 | $95.00 | $75.00 | $100.00 |
| 125 | Special - work zone traffic signal (614E11300) | EACH | 1 | $5,000.00 | $6,000.00 | $7,200.00 | $7,200.00 | $7,000.00 |
| 126 | Work zone impact attenuator, 24" wide hazards, (bidirectional) (614E12384) | EACH | 8 | $2,580.00 | $2,250.00 | $2,250.00 | $3,000.00 | $2,000.00 |
| 127 | Work zone lighting system (614E12740) | EACH | 8 | $500.00 | $6,000.00 | $2,650.00 | $800.00 | $1,000.00 |
| 128 | Barrier reflector, type 1 (one way) (614E13310) | EACH | 37 | $13.59 | $10.00 | $48.00 | $20.00 | $50.00 |
| 129 | Object marker, one way (614E13350) | EACH | 37 | $22.21 | $15.00 | $48.00 | $30.00 | $50.00 |
| 130 | Portable changeable message sign, as per plan (614E18601) | SNMT | 12 | $1,000.00 | $1,500.00 | $1,500.00 | $1,500.00 | $1,500.00 |
| 131 | Work zone center line, class I (614E21000) | MI | 0.04 | $3,220.00 | $23,154 | $23,154 | $7,955.00 | $25,000 |
| 132 | Work zone edge line, class I, 6" (614E22010) | MI | 1.91 | $1,545.00 | $2,156.00 | $2,156.00 | $5,390.00 | $3,000.00 |
| 133 | Work zone edge line, class I, 6", 740.06, type I (614E22210) | MI | 0.16 | $9,604.00 | $12,500 | $12,500 | $9,542.50 | $13,000 |
| 134 | Work zone stop line, class I (614E26000) | FT | 87 | $3.95 | $14.50 | $14.50 | $5.00 | $15.00 |
| 135 | Roads for maintaining traffic (615E10000) | LS | 1 | $40,000 | $97,000 | $200,000 | $110,000 | $75,000 |
| 136 | Pavement for maintaining traffic, class A (615E20000) | SY | 1,186 | $66.00 | $70.00 | $88.00 | $92.00 | $110.00 |
| 137 | Water (616E10000) | MGAL | 18 | $705.00 | $80.00 | $1.00 | $1.00 | $1.00 |
| 138 | Portable barrier, unanchored (622E41100) | FT | 2,130 | $20.00 | $20.00 | $23.00 | $23.00 | $20.00 |
| 139 | Premium for contract performance bond and for payment bond (103E05000) | LS | 1 | $16,000 | $13,357 | $16,015 | $18,000 | $60,000 |
| 140 | Maintaining traffic (614E11000) | LS | 1 | $35,000 | $65,000 | $83,500 | $108,000 | $275,000 |
| 141 | Construction layout stakes and surveying (623E10000) | LS | 1 | $30,000 | $28,725 | $52,200 | $30,000 | $30,000 |
| 142 | Mobilization (624E10000) | LS | 1 | $100,000 | $100,000 | $73,000 | $70,000 | $100,000 |
| 200 | RPM (621E00100) | EACH | 91 | $70.00 | $55.00 | $55.00 | $55.00 | $55.00 |
| 201 | Raised pavement marker removed (621E54000) | EACH | 30 | $6.00 | $18.00 | $4.00 | $20.00 | $1.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from ODOT's tabulation for this contract. ODOT Official Bid Tabulation PDFs from its public DigitalPaper bid tab cabinet, January 2020 to November 2026 (the source links open after DigitalPaper starts a guest session). ODOT prints unit prices to two decimals but computes line amounts from the full price, so a few bids miss their total and are left out. Descriptions are cut at about 50 characters, as ODOT prints them.
Every contract let that day: ODOT letting of December 4, 2025. Compiled by Mirage Metrics.
Your own bid history, read the same way