ODOT contract 260232 bid tabulation
CUY-Memorial Bridges Loop Trail (BIKEWAYS). Let by Ohio DOT on May 7, 2026, CUY. 3 bids received; low bid $1,924,944 by Perk Company Inc, +3.3% against the engineer's estimate of $1,864,000.
- Owner
- Ohio DOT
- Letting
- 07 MAY 2026
- Pay items
- 179
- Data through
- 12 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | Perk Company Inc | $1,924,944 | Low | +3.0% |
| 2 | Great Lakes Construction Co | $2,008,550 | +4.0% | +8.0% |
| 3 | Catts Construction Inc | $2,492,851 | +30% | +34% |
Engineer's estimate: $1,864,000.
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Perk Company Inc | 2. Great Lakes Construction Co | 3. Catts Construction Inc |
|---|---|---|---|---|---|---|
| 1 | Clearing and grubbing (201E11000) | LS | 1 | $9,000.00 | $23,000 | $15,000 |
| 2 | Pavement removed (202E23000) | SY | 1,842 | $30.00 | $30.00 | $50.00 |
| 3 | Walk removed (202E30000) | SF | 10,388 | $2.50 | $4.00 | $3.00 |
| 4 | Traffic island removed (202E30800) | SY | 138 | $50.00 | $50.00 | $20.00 |
| 5 | Curb removed (202E32000) | FT | 1,211 | $16.00 | $8.00 | $10.00 |
| 6 | Pipe removed, 24" and under (202E35100) | FT | 43 | $26.75 | $82.00 | $61.00 |
| 7 | Catch basin removed (202E58100) | EACH | 4 | $860.00 | $1,850.00 | $765.00 |
| 8 | Fence removed, as per plan (202E75001) | FT | 660 | $7.50 | $3.50 | $15.00 |
| 9 | Removal misc.: railroad ties (202E98200) | FT | 350 | $17.85 | $12.00 | $9.00 |
| 10 | Subgrade compaction (204E10000) | SY | 894 | $3.00 | $2.00 | $2.00 |
| 11 | Excavation of subgrade (204E13000) | CY | 125 | $10.00 | $54.00 | $45.00 |
| 12 | Granular material, type B (204E30010) | CY | 125 | $20.00 | $76.00 | $80.00 |
| 13 | Geotextile fabric (204E50000) | SY | 250 | $1.00 | $3.00 | $2.00 |
| 14 | Geogrid (204E51000) | SY | 250 | $2.00 | $3.25 | $2.25 |
| 15 | Linear grading (209E60200) | STA | 9.67 | $10.00 | $1,300.00 | $2,000.00 |
| 16 | Fence, misc.:6' fence, type CL (607E98000) | FT | 650 | $49.80 | $49.80 | $60.00 |
| 17 | 6" concrete walk, as per plan (608E13001) | SF | 17,580 | $15.00 | $12.50 | $15.00 |
| 18 | Curb ramp, as per plan (608E52001) | SF | 2,187 | $40.00 | $27.50 | $25.00 |
| 19 | Detectable warning, as per plan (608E53021) | SF | 40 | $200.00 | $110.00 | $265.00 |
| 20 | Walkway, misc.:decorative concrete (608E98000) | SF | 1,366 | $27.00 | $21.00 | $15.00 |
| 21 | Special - potholing (690E98000) | EACH | 8 | $100.00 | $1,550.00 | $1,000.00 |
| 22 | Special - pre-construction video (690E98400) | LS | 1 | $1,500.00 | $1,200.00 | $1,050.00 |
| 23 | Topsoil furnished and placed (653E10000) | CY | 41 | $175.00 | $83.00 | $78.00 |
| 24 | Seeding and mulching, class 1 (659E00500) | SY | 338 | $5.00 | $2.88 | $4.00 |
| 25 | Erosion control (832E30000) | EACH | 12,000 | $1.00 | $1.00 | $1.00 |
| 26 | 6" unclassified pipe underdrains, as per plan (605E13301) | FT | 1,275 | $28.05 | $28.00 | $18.00 |
| 27 | 6" conduit, type F for underdrain outlets (611E00510) | FT | 90 | $28.05 | $51.00 | $20.00 |
| 28 | Catch basin adjusted to grade, as per plan (611E98631) | EACH | 1 | $1,700.00 | $1,200.00 | $1,110.00 |
| 29 | Catch basin reconstructed to grade, as per plan (611E98635) | EACH | 1 | $1,800.00 | $1,600.00 | $1,400.00 |
| 30 | Catch basin grate, as per plan (611E98645) | EACH | 8 | $1,360.00 | $675.00 | $650.00 |
| 31 | Catch basin, misc.: cleveland one (611E98690) | EACH | 5 | $8,500.00 | $12,400 | $7,831.00 |
| 32 | Catch basin, misc.: cleveland two (611E98690) | EACH | 1 | $10,300 | $18,000 | $13,000 |
| 33 | Manhole, no. 3 (611E99574) | EACH | 1 | $10,500 | $14,000 | $6,265.00 |
| 34 | Manhole adjusted to grade, as per plan (611E99655) | EACH | 2 | $1,800.00 | $1,250.00 | $1,075.00 |
| 35 | Manhole reconstructed to grade, as per plan (611E99661) | EACH | 1 | $2,400.00 | $1,850.00 | $1,190.00 |
| 36 | Special - miscellaneous metal (611E99820) | LB | 10,800 | $3.50 | $2.00 | $2.50 |
| 37 | Low strength mortar backfill (type 1) (613E41250) | CY | 125 | $70.00 | $115.00 | $98.00 |
| 39 | 12" conduit, type B, as per plan (611E04401) | FT | 97 | $300.00 | $290.00 | $248.00 |
| 40 | Pavement planing, asphalt concrete, as per plan (T (254E01001) | SY | 11 | $200.00 | $200.00 | $275.00 |
| 41 | Full depth pavement sawing (255E20000) | FT | 1,541 | $3.00 | $5.93 | $7.00 |
| 42 | Asphalt concrete base, PG64-22, (449) (301E56000) | CY | 38 | $500.00 | $500.00 | $680.00 |
| 43 | Aggregate base, as per plan (304E20001) | CY | 170 | $85.25 | $225.00 | $130.00 |
| 44 | 8" concrete base, class QC 1P (305E12010) | SY | 535 | $175.00 | $265.00 | $112.00 |
| 45 | Tack coat, 702.13 (407E13900) | GAL | 37 | $30.00 | $30.00 | $41.00 |
| 46 | Non-tracking tack coat (407E20000) | GAL | 54 | $30.00 | $30.00 | $41.00 |
| 47 | Asphalt concrete surface course, type 1, (449), as per plan (441E70101) | CY | 18 | $600.00 | $600.00 | $815.00 |
| 48 | Asphalt concrete intermediate course, type 1, (449), as per plan (441E70201) | CY | 1 | $1,400.00 | $1,400.00 | $1,900.00 |
| 49 | Asphalt concrete intermediate course, type 2, (449), as per plan (441E70301) | CY | 25 | $550.00 | $550.00 | $746.00 |
| 50 | 8" non-reinforced concrete pavement, class QC MS, as per plan (452E12051) | SY | 47 | $210.00 | $210.00 | $96.00 |
| 51 | Combination curb and gutter, type 2, as per plan (609E12001) | FT | 534 | $65.00 | $82.00 | $60.00 |
| 52 | Curb, type 2-B, as per plan (609E16001) | FT | 822 | $21.00 | $22.50 | $6.00 |
| 53 | Curb, type 3-A, as per plan (609E20001) | FT | 136 | $17.35 | $13.50 | $2.40 |
| 54 | Curb, type 6, as per plan (609E26001) | FT | 264 | $65.00 | $58.73 | $55.00 |
| 55 | 6" concrete traffic island (609E54000) | SY | 189 | $105.00 | $160.00 | $60.00 |
| 56 | Curb, misc.: granite removed and relocated (609E98000) | FT | 128 | $45.00 | $135.00 | $132.00 |
| 57 | Longitudinal joint adhesive (875E10000) | LB | 281 | $15.00 | $9.00 | $9.00 |
| 58 | Fire hydrant removed, as per plan (638E10481) | EACH | 4 | $2,500.00 | $8,825.00 | $169.00 |
| 59 | Special - 6" fire hydrant (cleveland) (638E20750) | EACH | 2 | $13,750 | $15,900 | $13,035 |
| 60 | Water work, misc.: meter adjusted to grade (638E98000) | EACH | 1 | $2,650.00 | $1,050.00 | $1,190.00 |
| 61 | Light pole foundation, 24" X 6' deep, as per plan (625E14001) | EACH | 8 | $1,800.00 | $1,800.00 | $3,655.00 |
| 62 | Conduit, 2", 725.051 (625E25408) | FT | 29 | $7.50 | $7.50 | $182.00 |
| 63 | Conduit, misc.: encased lighting conduit bank (4-2 (625E25920) | FT | 1,079 | $28.00 | $28.00 | $231.00 |
| 64 | Trench (625E29000) | FT | 1,108 | $15.00 | $15.00 | $67.00 |
| 65 | Pull box, misc.:pull box, 15?X25? (625E31600) | EACH | 8 | $950.00 | $950.00 | $2,375.00 |
| 66 | Ground rod, as per plan (625E32001) | EACH | 8 | $300.00 | $300.00 | $578.00 |
| 67 | Underground warning marking tape (625E36010) | FT | 1,108 | $3.00 | $3.00 | $5.00 |
| 68 | Light pole removed (625E75400) | EACH | 2 | $300.00 | $300.00 | $1,096.00 |
| 69 | Light pole foundation removed (625E75500) | EACH | 6 | $500.00 | $500.00 | $1,523.00 |
| 70 | Luminaire removed (625E75506) | EACH | 2 | $75.00 | $75.00 | $549.00 |
| 71 | Lighting, misc.: vent stack removal (625E98000) | EACH | 1 | $1,200.00 | $1,200.00 | $1,157.00 |
| 72 | Manhole adjusted to grade, as per plan (611E99655) | EACH | 8 | $1,800.00 | $1,234.04 | $1,066.00 |
| 73 | Manhole reconstructed to grade, as per plan (611E99661) | EACH | 2 | $2,500.00 | $1,858.17 | $1,189.00 |
| 74 | Pull box, misc.: adjusted to grade (625E31600) | EACH | 4 | $300.00 | $1,025.99 | $2,680.00 |
| 75 | Pull box, misc.: reconstructed to grade (625E31600) | EACH | 1 | $500.00 | $1,234.06 | $3,411.00 |
| 76 | Ground mounted support, no. 2 post (630E02100) | FT | 83 | $12.00 | $12.00 | $15.00 |
| 77 | Sign post reflector (630E08600) | EACH | 1 | $45.00 | $45.00 | $54.00 |
| 78 | Sign hanger assembly, mast arm, as per plan (630E79101) | EACH | 3 | $525.00 | $525.00 | $630.00 |
| 79 | Sign support assembly, pole mounted (630E79500) | EACH | 70 | $60.00 | $60.00 | $72.00 |
| 80 | Sign, flat sheet (630E80100) | SF | 100.50 | $20.00 | $20.00 | $24.00 |
| 81 | Sign, flat sheet, as per plan (630E80101) | SF | 216.10 | $25.00 | $25.00 | $30.00 |
| 82 | Removal of ground mounted sign and disposal (630E84900) | EACH | 1 | $35.00 | $35.00 | $42.00 |
| 83 | Removal of ground mounted post support and disposal (630E86002) | EACH | 2 | $35.00 | $35.00 | $42.00 |
| 84 | Removal of overhead mounted sign and disposal (630E87400) | EACH | 3 | $235.00 | $235.00 | $290.00 |
| 85 | Removal of pole mounted sign and disposal (630E87500) | EACH | 31 | $30.00 | $30.00 | $37.00 |
| 86 | Removal of pole mounted sign and storage, as per plan (630E87511) | EACH | 1 | $35.00 | $35.00 | $43.00 |
| 87 | Signing, misc.: reboundable delineator post assemb (630E97700) | EACH | 102 | $80.00 | $80.00 | $96.00 |
| 88 | Signing, misc.: rectangular rapid flashing beacon (630E97700) | EACH | 2 | $9,250.00 | $9,250.00 | $11,110 |
| 89 | Edge line, 4" (644E00100) | MI | 0.22 | $5,000.00 | $5,000.00 | $6,005.00 |
| 90 | Edge line, 6" (644E00104) | MI | 0.01 | $50,000 | $50,000 | $60,058 |
| 91 | Lane line, 4" (644E00200) | MI | 0.40 | $1,650.00 | $1,650.00 | $1,981.00 |
| 92 | Center line (644E00300) | MI | 0.22 | $7,500.00 | $7,500.00 | $9,010.00 |
| 93 | Channelizing line, 8" (644E00400) | FT | 1,242 | $1.50 | $1.50 | $2.00 |
| 94 | Stop line (644E00500) | FT | 172 | $8.00 | $8.00 | $10.00 |
| 95 | Crosswalk line, 12", as per plan (644E00621) | FT | 697 | $5.00 | $5.00 | $6.00 |
| 96 | Crosswalk line, 24", as per plan (644E00631) | FT | 1,030 | $6.75 | $6.75 | $8.00 |
| 97 | Transverse/diagonal line (644E00700) | FT | 213 | $7.50 | $7.50 | $9.00 |
| 98 | Lane arrow (644E01300) | EACH | 37 | $105.00 | $105.00 | $126.00 |
| 99 | Dotted line, 4" (644E01500) | FT | 486 | $1.00 | $1.00 | $2.00 |
| 100 | Dotted line, 8" (644E01514) | FT | 634 | $1.25 | $1.25 | $2.00 |
| 101 | Bike lane symbol marking (644E01630) | EACH | 1 | $315.00 | $315.00 | $379.00 |
| 102 | Shared lane marking (644E19000) | EACH | 6 | $350.00 | $350.00 | $420.00 |
| 103 | Removal of pavement marking (644E30000) | FT | 3,271 | $0.60 | $0.60 | $1.00 |
| 104 | Removal of pavement marking (644E30020) | EACH | 35 | $60.00 | $60.00 | $72.00 |
| 105 | Removal of pavement marking (644E30030) | MI | 0.95 | $1,275.00 | $1,275.00 | $1,531.00 |
| 106 | Pavement marking, misc.:left turn queue box (644E50100) | EACH | 2 | $1,000.00 | $1,000.00 | $1,201.00 |
| 107 | Pavement marking, misc.:center line, shared-use PA (644E50300) | FT | 9 | $8.00 | $8.00 | $10.00 |
| 108 | Pavement marking, misc.:green colored bike crossin (644E50300) | FT | 243 | $12.50 | $12.50 | $15.00 |
| 109 | Edge line, 4" (646E10000) | MI | 1.34 | $2,000.00 | $2,000.00 | $2,402.00 |
| 110 | Edge line, 6" (646E10010) | MI | 0.40 | $4,850.00 | $4,850.00 | $5,825.00 |
| 111 | Lane line, 4" (646E10100) | MI | 0.41 | $1,850.00 | $1,850.00 | $2,222.00 |
| 112 | Center line (646E10200) | MI | 0.40 | $4,950.00 | $4,950.00 | $5,945.00 |
| 113 | Channelizing line, 8" (646E10300) | FT | 1,159 | $1.85 | $1.85 | $3.00 |
| 114 | Stop line (646E10400) | FT | 137 | $12.25 | $12.25 | $15.00 |
| 115 | Crosswalk line, 12", as per plan (646E10511) | FT | 268 | $8.00 | $8.00 | $10.00 |
| 116 | Crosswalk line, 24", as per plan (646E10521) | FT | 429 | $11.50 | $11.50 | $14.00 |
| 117 | Transverse/diagonal line (646E10600) | FT | 1,722 | $9.00 | $9.00 | $11.00 |
| 118 | Lane arrow (646E20300) | EACH | 33 | $165.00 | $165.00 | $200.00 |
| 119 | Dotted line, 4" (646E20502) | FT | 198 | $2.00 | $2.00 | $3.00 |
| 120 | Dotted line, 8" (646E20506) | FT | 646 | $3.50 | $3.50 | $4.00 |
| 121 | Yield line (646E20800) | FT | 53 | $15.00 | $15.00 | $18.00 |
| 122 | Removal of pavement marking (646E50000) | EACH | 27 | $60.00 | $60.00 | $72.00 |
| 123 | Removal of pavement marking (646E50100) | FT | 2,325 | $2.25 | $2.25 | $3.00 |
| 124 | Removal of pavement marking (646E50300) | MI | 1.50 | $1,250.00 | $1,250.00 | $1,501.00 |
| 125 | Green colored pavement for bike lanes (646E60100) | SF | 222 | $9.00 | $9.00 | $11.00 |
| 126 | Pavement marking, misc.:center line, shared-use PA (646E90000) | FT | 2,697 | $2.25 | $2.25 | $3.00 |
| 127 | Conduit, 2", 725.051 (625E25408) | FT | 18 | $8.50 | $8.50 | $37.00 |
| 128 | Conduit, 3", 725.051 (625E25504) | FT | 54 | $11.50 | $11.50 | $46.00 |
| 129 | Conduit cleaned and cables removed, as per plan (625E25911) | FT | 138 | $6.00 | $6.00 | $7.00 |
| 130 | Trench (625E29000) | FT | 67 | $18.00 | $18.00 | $67.00 |
| 131 | Pull box, misc.: pull box, 17" X 30" (625E31600) | EACH | 1 | $975.00 | $975.00 | $2,132.00 |
| 132 | Ground rod, as per plan (625E32001) | EACH | 1 | $300.00 | $300.00 | $579.00 |
| 133 | Underground warning marking tape (625E36010) | FT | 67 | $3.50 | $3.50 | $5.00 |
| 134 | Vehicular signal head, (LED), 3-section, 12" lens, 1-way, polycarbonate (632E05006) | EACH | 1 | $950.00 | $950.00 | $2,254.00 |
| 135 | Vehicular signal head, (LED), 4-section, 12" lens, 1-way, polycarbonate (632E05064) | EACH | 1 | $1,150.00 | $1,150.00 | $2,680.00 |
| 136 | Vehicular signal head, (LED), 5-section, 12" lens, 1-way, polycarbonate (632E05086) | EACH | 1 | $1,500.00 | $1,500.00 | $3,289.00 |
| 137 | Pedestrian signal head (LED), type D2, countdown, as per plan (632E20731) | EACH | 2 | $675.00 | $675.00 | $1,523.00 |
| 138 | Covering of vehicular signal head (632E25000) | EACH | 2 | $150.00 | $150.00 | $61.00 |
| 139 | Covering of pedestrian signal head (632E25010) | EACH | 2 | $50.00 | $50.00 | $49.00 |
| 140 | Pedestrian pushbutton, as per plan (632E26001) | EACH | 1 | $275.00 | $275.00 | $549.00 |
| 141 | Detector loop, as per plan (632E26501) | EACH | 8 | $1,500.00 | $1,500.00 | $7,066.00 |
| 142 | Signal cable, 5 conductor, no. 14 AWG (632E40500) | FT | 835 | $2.55 | $2.55 | $8.00 |
| 143 | Signal cable, 7 conductor, no. 14 AWG (632E40700) | FT | 2,180 | $2.75 | $2.75 | $9.00 |
| 144 | Pedestal foundation (632E64020) | EACH | 1 | $1,800.00 | $1,800.00 | $3,411.00 |
| 145 | Loop detector lead-in cable (632E65200) | FT | 2,769 | $1.60 | $1.60 | $7.00 |
| 146 | Pedestal, misc.: pedestal, 15', transformer base (632E90010) | EACH | 1 | $2,100.00 | $2,100.00 | $4,508.00 |
| 147 | Removal of traffic signal installation, as per plan (632E90101) | EACH | 1 | $3,800.00 | $3,800.00 | $9,747.00 |
| 148 | Reuse of vehicular signal head, as per plan (632E90201) | EACH | 6 | $600.00 | $600.00 | $2,680.00 |
| 149 | Planting, misc.: ornamental grasses (661E99900) | EACH | 260 | $37.10 | $26.25 | $48.00 |
| 150 | Law enforcement officer with patrol car for assistance (614E11110) | HR | 80 | $125.00 | $100.00 | $114.00 |
| 151 | Asphalt concrete for maintaining traffic (614E13000) | CY | 20 | $350.00 | $385.00 | $397.00 |
| 152 | Portable changeable message sign, as per plan (614E18601) | SNMT | 12 | $1,000.00 | $800.00 | $961.00 |
| 153 | Work zone lane line, class I, 4" (614E20000) | MI | 0.56 | $2,500.00 | $2,500.00 | $3,002.00 |
| 154 | Work zone center line, class I (614E21000) | MI | 0.58 | $3,000.00 | $3,000.00 | $3,603.00 |
| 155 | Work zone edge line, class I, 4" (614E22000) | MI | 1.17 | $2,500.00 | $2,500.00 | $3,002.00 |
| 156 | Work zone channelizing line, class I, 8" (614E23000) | FT | 2,026 | $0.45 | $0.45 | $1.00 |
| 157 | Work zone dotted line, class I (614E24000) | FT | 986 | $0.45 | $0.45 | $1.00 |
| 158 | Work zone transverse/diagonal line, class I (614E25000) | FT | 684 | $3.00 | $3.00 | $4.00 |
| 159 | Work zone stop line, class I (614E26000) | FT | 235 | $3.00 | $3.00 | $4.00 |
| 160 | Work zone arrow, class I (614E30000) | EACH | 57 | $40.00 | $40.00 | $48.00 |
| 161 | Water (616E10000) | MGAL | 10 | $100.00 | $36.21 | $316.00 |
| 162 | Removal misc.: bridge sidewalk removed (202E98300) | SY | 120 | $250.00 | $313.16 | $480.00 |
| 163 | Sealing of concrete surfaces (non-epoxy) (512E10050) | SY | 20 | $75.00 | $36.00 | $135.00 |
| 164 | Structural steel expansion joint, as per plan (516E12201) | FT | 13 | $5,000.00 | $3,325.00 | $9,950.00 |
| 165 | Structural joint or joint sealer, misc.: rubberize (516E14600) | FT | 162 | $700.00 | $677.00 | $895.00 |
| 166 | Structure drainage, misc.: bridge scupper and catc (518E62200) | EACH | 8 | $1,525.00 | $1,200.00 | $1,525.00 |
| 167 | Special - structures: concrete curb repair (530E01300) | FT | 108 | $225.00 | $180.00 | $225.00 |
| 168 | Micro silica modified concrete overlay (2 3/4" thi (847E10000) | SY | 116 | $155.00 | $230.00 | $155.00 |
| 169 | Micro silica modified concrete overlay (variable thickness), material only (847E20000) | CY | 1 | $245.00 | $441.00 | $350.00 |
| 170 | Test slab (847E30000) | LS | 1 | $2,060.00 | $2,500.00 | $2,061.00 |
| 171 | Existing concrete overlay removed (2 1/2" thick) (847E30400) | SY | 116 | $65.00 | $190.00 | $116.00 |
| 172 | Hand chipping (847E50000) | SY | 2 | $1,250.00 | $545.00 | $1,250.00 |
| 173 | Premium for contract performance bond and for payment bond (103E05000) | LS | 1 | $20,000 | $17,400 | $50,000 |
| 174 | CPM progress schedule short duration projects (108E30000) | LS | 1 | $10,000 | $500.00 | $3,003.00 |
| 175 | Maintaining traffic, as per plan (614E11001) | LS | 1 | $76,500 | $50,000 | $100,000 |
| 176 | Construction layout stakes and surveying (623E10000) | LS | 1 | $20,000 | $13,000 | $24,700 |
| 177 | Preconstruction survey monument verification and report (623E50000) | LS | 1 | $3,000.00 | $2,000.00 | $3,002.00 |
| 178 | Post construction survey monument verification and report (623E51000) | LS | 1 | $3,000.00 | $2,000.00 | $3,002.00 |
| 179 | Mobilization (624E10000) | LS | 1 | $65,000 | $100,500 | $25,000 |
| 180 | Special - as-built drawings (690E98400) | LS | 1 | $10,000 | $2,500.00 | $1,177.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from ODOT's tabulation for this contract. ODOT Official Bid Tabulation PDFs from its public DigitalPaper bid tab cabinet, January 2020 to November 2026 (the source links open after DigitalPaper starts a guest session). ODOT prints unit prices to two decimals but computes line amounts from the full price, so a few bids miss their total and are left out. Descriptions are cut at about 50 characters, as ODOT prints them.
Every contract let that day: ODOT letting of May 7, 2026. Compiled by Mirage Metrics.