Reference monument, type A, ODOT 623E40500

Low bidders on ODOT contracts carried a median of $450.00 per EACH for this item, from 23 JAN 2020 to 24 AUG 2023, across 59 low bids. Half of all 282 bids fell between $350.00 and $783.75.

Owner
Ohio DOT
Item
623E40500
Unit
EACH
Data through
12 NOV 2026

ODOT prints this item as “REFERENCE MONUMENT”.

$450.00Low bidder's median, per EACH
$500.00Median of all bids, per EACH
60Contracts in the window

By year of letting

Reference monument, type A, ODOT: unit prices by year
YearContractsLow bidsLow-bid medianAll bidsMedian, all bids
20201818$440.0093$500.00
20212019$400.00109$487.00
20221414$500.0048$500.00
202388$600.0032$650.00

Bid prices as published, not adjusted for inflation.

By county

CountyLow bidsLow-bid medianAll bidsMedian, all bids
BRO5$350.0029$450.00
LIC5$450.0023$600.00
SCI3$448.0019$418.00
BUT3$735.0017$509.49
MEG3$500.0015$500.00
CLE4$650.0011$578.55
Reference monument, type A, ODOT: unit prices by county, all lettings

Countys with at least three low bids, over all lettings.

By quantity

Quantity (EACH)Low bidsLow-bid median
1 to 314$475.00
3 to 615$600.00
6 to 815$500.00
9 to 5515$385.00
Reference monument, type A, ODOT: low bidder's median by quantity band

The low bids split into four bands of equal count by the quantity on the contract. Larger quantities usually carry lower unit prices.

Who is lowest on this line

Reference monument, type A, ODOT: bidders most often lowest on this line

The lowest unit price on each line, whoever won the contract, over all lettings in the data, for firms with five lines or more.

Latest contracts with this item

LetContractCountyQuantityLow bidder's priceMedianBidsLow bidderSource
24 AUG 2023230428HAM1$999.20$937.736KT Holden Construction LLCODOT
25 MAY 2023234017GAL8$500.00$548.504Parker CorporationODOT
11 MAY 2023230245FRA2$1,875.00$1,302.502Shelly & Sands IncODOT
11 MAY 2023230291HEN1$600.00$600.003Vernon Nagel IncODOT
27 APR 2023230253DEL50$90.00$600.005Shelly & Sands IncODOT
27 APR 2023230260HIG4$600.00$600.003Axis Civil Construction LLCODOT
13 APR 2023230206ADA6$200.00$625.004Allard Excavation LLCODOT
09 MAR 2023230174LIC4$850.00$850.005Miller Bros Const IncODOT
14 APR 2022220210LOR2$330.00$330.003Digioia-Suburban Excavating LLCODOT
14 APR 2022220243LIC8$450.00$450.002Shelly & Sands IncODOT
14 APR 2022220249PIK6$2,500.00$569.276Allied Construction, LLCODOT
17 MAR 2022220178LIC24$850.00$830.004Buds IncODOT
10 MAR 2022220078UNI2$830.00$500.003Complete General Construction CompanyODOT
10 MAR 2022220082BUT24$975.00$991.754Barrett Paving Materials IncODOT
10 MAR 2022220148MEG8$500.00$500.005Parker CorporationODOT
Latest ODOT contracts carrying Reference monument, type A

Filter this item by your own quantity, county and period, or check your price against it, in the ODOT explorer.

How these prices were read

ODOT Official Bid Tabulation PDFs from its public DigitalPaper bid tab cabinet, January 2020 to November 2026 (the source links open after DigitalPaper starts a guest session). ODOT prints unit prices to two decimals but computes line amounts from the full price, so a few bids miss their total and are left out. Descriptions are cut at about 50 characters, as ODOT prints them.

  • Statistics leave out bids over three times the low bid, zero or negative prices and token prices under 5% of the median.
  • Item codes and units are ODOT's own: this item is compared with ODOT contracts only.
  • Prices are bid prices, not paid prices. Use them as a reference range, never as a quote.
  • The data runs to the ODOT letting of 12 NOV 2026 and was rebuilt on 26 NOV 2026.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy