TDOT contract CN264001 bid tabulation
The retracing of pavement markings with spray thermoplastic and random on-call pavement marking on various interstate and state routes. Let by Tennessee DOT on February 6, 2026, Counties Benton, Carroll, Chester, Crockett, Decatur, Dyer, Fayette, Gibson, Hardeman, Hardin, Haywood, Henderson, Henry, Lake, Lauderdale, Madison, Mcnairy, Obion, Shelby, Tipton, And Weakley. 1 bid received; low bid $4,993,915 by Traf-Mark Industries, L.L.C..
- Owner
- Tennessee DOT
- Letting
- 06 FEB 2026
- Pay items
- 77
- Data through
- 02 OCT 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | Traf-Mark Industries, L.L.C. | $4,993,915 | Low |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Traf-Mark Industries, L.L.C. |
|---|---|---|---|---|
| 1 | Maintenance of traffic (712-01.50) | EACH | 50 | $2,000.00 |
| 2 | Raised PVMT markers (BI-directional) (1 color lens) (716-01.11) | EACH | 75 | $10.00 |
| 3 | Raised PVMT markers (mono-directional) (1 color lens) (716-01.12) | EACH | 75 | $10.00 |
| 4 | Raised PVMT markers (BI-directional) (2 color lens) (716-01.13) | EACH | 75 | $10.00 |
| 5 | Snowplowable raised pavement markers (BI-dir) (1 color) (716-01.21) | EACH | 75 | $40.00 |
| 6 | Snowplowable raised pavment markers (mono-dir)(1 color) (716-01.22) | EACH | 75 | $40.00 |
| 7 | Snowplowable raised pavement markers (BI-dir)(2 color) (716-01.23) | EACH | 50 | $40.00 |
| 8 | Removal of snowplowable reflective marker (716-01.30) | EACH | 15 | $20.00 |
| 9 | Remove and replace lens on snowplowable reflective marker (716-01.40) | EACH | 140 | $20.00 |
| 10 | Plastic pavement marking (cross-walk) (716-02.03) | LF | 500 | $17.00 |
| 11 | Plastic pavement marking(channelization striping) (716-02.04) | SY | 300 | $32.00 |
| 12 | Plastic pavement marking (stop line) (716-02.05) | LF | 650 | $21.00 |
| 13 | Plastic pavement marking (turn lane arrow) (716-02.06) | EACH | 75 | $225.00 |
| 14 | Plastic pavement marking (24" barrier line) (716-02.07) | LF | 15 | $21.00 |
| 15 | Plastic pavement marking (8" dotted line) (716-02.08) | LF | 150 | $4.00 |
| 16 | Plastic pavement marking (longitudinal cross-walk) (716-02.09) | LF | 120 | $52.00 |
| 17 | Plastic word pavement marking (only) (716-03.01) | EACH | 30 | $235.00 |
| 18 | Plastic word pavement marking (RXR) (716-03.02) | EACH | 1 | $1,500.00 |
| 19 | Plastic word pavement marking (stop ahead) (716-03.03) | EACH | 1 | $1,500.00 |
| 20 | Plastic word pavement marking (school) (716-03.04) | EACH | 1 | $750.00 |
| 21 | Plastic word pavement marking (bike lane) (716-03.05) | EACH | 1 | $1,500.00 |
| 22 | Plastic word pavement marking (signal ahead) (716-03.06) | EACH | 2 | $1,500.00 |
| 23 | Plastic word pavement marking (stop) (716-03.07) | EACH | 1 | $500.00 |
| 24 | Plastic word pavement marking (ped-xing) (716-03.08) | EACH | 1 | $700.00 |
| 25 | Plastic pavement marking (straight-turn arrow) (716-04.01) | EACH | 2 | $450.00 |
| 26 | Plastic pavement marking(double turning arrow) (716-04.02) | EACH | 1 | $450.00 |
| 27 | Plastic pavement marking (transverse shoulder) (716-04.04) | LF | 500 | $11.00 |
| 28 | Plastic pavement marking (straight arrow) (716-04.05) | EACH | 2 | $225.00 |
| 29 | Plastic pavement marking (wrong way arrow) (716-04.06) | EACH | 1 | $450.00 |
| 30 | Plastic pavement marking (exit only arrow) (716-04.07) | EACH | 3 | $450.00 |
| 31 | Plastic pavement marking (option lane arrow) (716-04.08) | EACH | 3 | $450.00 |
| 32 | Plastic pavement marking (H.O.V. diamond) (716-04.09) | EACH | 5 | $250.00 |
| 33 | Plastic pavement marking (handicap symbol) (716-04.10) | EACH | 1 | $300.00 |
| 34 | Plastic pavement marking (yield line) (716-04.12) | SF | 30 | $25.00 |
| 35 | Plastic pavement marking (lane reduction arrow) (716-04.14) | EACH | 2 | $450.00 |
| 36 | Plastic pavement marking-bike symbol/arrow shared (716-04.15) | EACH | 1 | $600.00 |
| 37 | Painted pavement marking (4" line) (716-05.01) | LM | 50 | $500.00 |
| 38 | Painted pavement marking (contrast shadow marking 6") (716-05.14) | LM | 2 | $1,000.00 |
| 39 | Painted pavement marking (6" line) (716-05.20) | LM | 50 | $835.00 |
| 40 | Performance based retracing spray thermo 6IN (716-05.73) | LM | 2,011 | $1,900.00 |
| 41 | Performance based retracing spray thermo 8IN (716-05.74) | LF | 365,250 | $0.50 |
| 42 | Performance based retracing spray thermo 12IN (716-05.79) | LM | 24 | $2,900.00 |
| 43 | Performance based retracing spray thermo 8IN dotted (716-05.80) | LF | 28,900 | $2.00 |
| 44 | Performance based retracing spray thermo 12IN dotted (716-05.81) | LF | 10,600 | $3.00 |
| 45 | Removal of pavement marking (line) (716-08.01) | LF | 2,500 | $0.80 |
| 46 | Removal of pavement marking (8" barrier line) (716-08.02) | LF | 125 | $1.60 |
| 47 | Removal of pavement marking (cross-walk) (716-08.03) | LF | 1 | $50.00 |
| 48 | Removal of pavement marking (channelization striping) (716-08.04) | SY | 50 | $40.00 |
| 49 | Removal of pavement marking (stop line) (716-08.05) | LF | 1 | $50.00 |
| 50 | Removal of pavement marking (turn lane arrow) (716-08.06) | EACH | 1 | $250.00 |
| 51 | Removal of pavement marking (straight-turn arrow) (716-08.07) | EACH | 1 | $300.00 |
| 52 | Removal of pavement marking (double turning arrow) (716-08.08) | EACH | 1 | $300.00 |
| 53 | Removal of pavement marking (dotted line) (716-08.09) | LF | 1 | $50.00 |
| 54 | Removal of pavement marking (transverse shoulder) (716-08.10) | LF | 1 | $50.00 |
| 55 | Removal of word pavement marking (only) (716-08.11) | EACH | 1 | $235.00 |
| 56 | Removal of word pavement marking (stop ahead) (716-08.12) | EACH | 1 | $1,000.00 |
| 57 | Removal of word pavement marking (school) (716-08.13) | EACH | 1 | $700.00 |
| 58 | Contrast pavement shadow marking 6" (716-09.94) | LM | 1 | $7,500.00 |
| 59 | Preformed plastic pavement marking (interstate shield) (716-10.50) | EACH | 10 | $2,200.00 |
| 60 | Enhanced flatline thermo PVMT MRKNG (4IN line) (716-12.01) | LM | 1 | $2,500.00 |
| 61 | Enhanced flatline thermo PVMT MRKNG (6IN line) (716-12.02) | LM | 1 | $6,200.00 |
| 62 | Enhanced flatline thermo PVMT MRKNG (8IN barrier line) (716-12.03) | LF | 250 | $3.00 |
| 63 | Enhanced flatline thermo PVMT MRKNG (4IN dotted line) (716-12.04) | LF | 125 | $1.00 |
| 64 | Enhanced flatline thermo PVMT MRKNG (6IN dotted line) (716-12.05) | LF | 175 | $2.00 |
| 65 | Enhanced flat line thermo (8IN line) (716-12.06) | LF | 100 | $3.00 |
| 66 | Enhanced flat line thermo (8IN broken LN) (716-12.07) | LF | 50 | $3.00 |
| 67 | Enhanced flat line thermo (12IN barrier line) (716-12.08) | LF | 50 | $12.00 |
| 68 | Enhanced flat line thermo (12IN line) (716-12.09) | LF | 200 | $12.00 |
| 69 | Spray thermo PVMT MRKNG (40 mil) (4IN line) (716-13.06) | LM | 50 | $800.00 |
| 70 | Spray thermo PVMT MRKNG (40 mil) (6IN line) (716-13.07) | LM | 100 | $1,750.00 |
| 71 | Spray thermo PVMT MRKNG (40 mil) (8IN barrier line) (716-13.08) | LF | 10,000 | $1.50 |
| 72 | Spray thermo PVMT MRKNG (40 mil) (4IN dotted line) (716-13.09) | LF | 50 | $2.00 |
| 73 | Spray thermo PVMT MRKNG (40 mil) (6IN dotted line) (716-13.10) | LF | 900 | $2.00 |
| 74 | Roadway cleaning for pavement marking (716-50.01) | LM | 8 | $450.00 |
| 75 | Mobilization (717-01) | LS | 1 | $175,000 |
| 76 | Mobilization (per call-out) (717-01.03) | EACH | 16 | $4,500.00 |
| 77 | Mobilization (per level 1 call-out) (717-01.04) | EACH | 5 | $6,000.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from TDOT's tabulation for this contract. TDOT Summary of Bids PDFs: every letting posted for February 2024 to October 2026, and nine lettings of 2018 to 2023 recovered from archived copies of the tn.gov files. Cost-plus-time bids, and bids that did not match their published total, are left out.
Every contract let that day: TDOT letting of February 6, 2026. Compiled by Mirage Metrics.