TDOT contract CNZ163 bid tabulation

The resurfacing on u.s. 641 (s.r. 69) from near mccorkle lane (l.m. 31.50) to the benton county line (l.m. 42.56), including bridge expansion joint repairs and thin epoxy overlay. Let by Tennessee DOT on May 9, 2025, Decatur County. 3 bids received; low bid $2,823,986 by Delta Contracting Company, LLC.

Owner
Tennessee DOT
Letting
09 MAY 2025
Pay items
38
Data through
02 OCT 2026

Bidders

RankBidderTotal bidAgainst the low bid
1Delta Contracting Company, LLC$2,823,986Low
2Volunteer Paving, LLC$3,395,712+20%
3Jones Bros. Contractors, LLC$3,575,692+27%
TDOT contract CNZ163: bids by rank

Bid tabulation

LinePay itemUnitQuantity1. Delta Contracting Company, LLC2. Volunteer Paving, LLC3. Jones Bros. Contractors, LLC
1Removal of asphalt pavement (202-03.01)SY1,632$17.00$34.05$28.90
2Water (203-06)MG30$0.01$9.45$6.00
3Brooming & degrassing shoulders (208-01.05)LM22.12$800.00$1,217.60$2,531.00
4Mineral aggregate, type B base, grading (C or D) (303-02)TON4,031$7.00$48.60$18.00
5Asphalt concrete mix (PG64-22) (BPMB-HM) grading A (307-01.01)TON563$105.00$171.24$142.00
6Asphalt concrete mix (PG64-22) (BPMB-HM) grading B-M2 (307-01.08)TON184$105.00$379.65$174.00
7Trackless tack coat (403-02.01)TON90$250.00$990.79$928.00
8Acs mix(PG64-22) thin lift E shoulder (411-03.34)TON6,334$101.00$97.44$122.00
9Acs mix (PG64-22) thin lift D asphalt limestone (411-03.43)TON7,347$137.50$112.91$130.00
10Scoring for rumble stripe (non-continuous) (8IN width) (411-12.03)LM16.50$875.00$692.30$1,495.00
11Asphalt emulsion (scrub seal) (414-04.03)TON216$1,400.89$1,470.93$1,400.89
12Mineral aggregate (scrub seal) (414-04.04)TON1,787$53.10$55.76$53.10
13Cold planing bituminous pavement (415-01.01)TON457$25.00$56.84$82.50
14Guardrail transition 27IN to 31IN (705-02.10)EACH3$175.00$183.75$175.00
15Earth pad for type 38 GR end treatment (705-04.09)EACH2$1,000.00$1,050.00$1,000.00
16GR terminal (in-inline) MASH TL-3 (705-06.11)EACH1$1,075.00$1,128.75$1,075.00
17Tangent energy absorbing term MASH TL-3 (705-06.20)EACH2$3,900.00$4,095.00$3,900.00
18Guardrail removed (706-01)LF150$6.00$6.30$6.00
19Traffic control (712-01)LS1$28,000$112,613$95,000
20Flexible drums (channelizing) (712-04.01)EACH120$15.00$21.00$15.00
21Signs (construction) (712-06)SF4,040$7.00$8.03$7.00
22Temporary barricades (type III) (712-07.03)LF80$12.00$13.65$12.00
23Arrow board (type C) (712-08.03)EACH2$950.00$525.00$950.00
24Snowplowable raised pavement markers (BI-dir) (1 color) (716-01.21)EACH1,248$33.00$45.00$33.00
25Snowplowable raised pavment markers (mono-dir)(1 color) (716-01.22)EACH40$33.00$45.00$33.00
26Removal of snowplowable reflective marker (716-01.30)EACH115$7.47$10.00$10.00
27Plastic pavement marking(channelization striping) (716-02.04)SY223$33.00$35.00$33.00
28Plastic pavement marking (turn lane arrow) (716-02.06)EACH13$190.00$225.00$190.00
29Plastic pavement marking (8IN line) (716-02.12)LM0.20$15,000$10,000$15,000
30Painted pavement marking (6" line) (716-05.20)LM39$1,100.00$1,200.00$1,100.00
31Removal of pavement marking (channelization striping) (716-08.04)SY223$30.00$25.00$30.00
32Removal of pavement marking (turn lane arrow) (716-08.06)EACH13$150.00$75.00$150.00
33Removal of pavement marking (line) (716-08.20)LM39$780.92$5,300.00$1,095.00
34Enhanced flatline thermo PVMT MRKNG (6IN line) (716-12.02)LM39$6,750.00$7,000.00$6,750.00
35Mobilization (717-01)LS1$39,000$77,454$296,000
36Expansion joint repairs (604-10.44)LF133$300.00$735.00$428.37
37Concrete repairs (604-10.53)SY5$725.00$1,575.00$4,192.00
38Type 1 thin epoxy overlay (epoxy-urethane) (617-04.01)SY210$90.00$45.15$421.24
TDOT contract CNZ163: unit prices by line

The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.

Source

Read from TDOT's tabulation for this contract. TDOT Summary of Bids PDFs: every letting posted for February 2024 to October 2026, and nine lettings of 2018 to 2023 recovered from archived copies of the tn.gov files. Cost-plus-time bids, and bids that did not match their published total, are left out.

Every contract let that day: TDOT letting of May 9, 2025. Compiled by Mirage Metrics.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy