TDOT contract CNZ316 bid tabulation

The resurfacing on i-840 from near u.s. 31 (s.r. 6) (l.m. 21.68) to east of arno road (l.m. 31.68), including bridge deck repairs. Let by Tennessee DOT on December 5, 2025, Williamson County. 5 bids received; low bid $9,547,557 by Volunteer Paving, LLC.

Owner
Tennessee DOT
Letting
05 DEC 2025
Pay items
51
Data through
02 OCT 2026

Bidders

RankBidderTotal bidAgainst the low bid
1Volunteer Paving, LLC$9,547,557Low
2Vulcan Construction Materials, LLC$10,555,761+11%
3Rogers Group, Inc.$11,377,840+19%
4Wiregrass Construction Company, Inc$11,840,923+24%
5Jones Bros. Contractors, LLC$13,051,156+37%
TDOT contract CNZ316: bids by rank

Bid tabulation

LinePay itemUnitQuantity1. Volunteer Paving, LLC2. Vulcan Construction Materials, LLC3. Rogers Group, Inc.4. Wiregrass Construction Company, Inc5. Jones Bros. Contractors, LLC
1Brooming & degrassing shoulders (208-01.05)LM40$1,083.81$2,250.00$1,825.00$1,600.00$1,800.00
2Mineral aggregate, type A base, grading D (303-01)TON5,294$31.68$43.00$49.00$50.00$55.00
3Asphalt concrete mix (PG76-22) grading CM (307-03.12)TON28,606$88.45$95.00$98.00$110.00$115.00
4Bituminous material for tack coat (TC) (403-01)TON222$924.75$925.00$880.00$900.00$785.00
5Longitudinal joint sealant (411-01.21)LM12.60$2,828.00$2,950.00$2,400.00$5,907.86$2,450.00
6Acs mix(PG76-22) grading D (411-03.10)TON10,726$119.74$126.00$152.00$158.00$174.00
7Acs mix (PG76-22) ogfc (411-03.23)TON19,357$127.16$149.00$151.00$172.00$174.00
8Scoring shoulders (continuous) (16IN width) (411-12.01)LM32.90$555.50$550.00$820.00$550.73$1,150.00
9Cold planing bituminous pavement (415-01.01)TON38,635$18.20$26.00$26.50$24.45$44.35
10Traffic control (712-01)LS1$233,815$210,000$305,700$165,000$300,000
11Flexible drums (channelizing) (712-04.01)EACH753$30.30$50.00$31.50$30.04$30.00
12Warning lights (type A) (712-05.01)EACH8$15.15$5.00$16.00$15.02$15.00
13Warning lights (type C) (712-05.03)EACH93$15.15$5.00$16.00$15.02$15.00
14Signs (construction) (712-06)SF2,292$7.07$7.00$7.45$7.01$7.00
15Signs (construction)(reduced speed warning) (712-06.16)EACH4$353.50$350.00$370.00$350.47$350.00
16Temporary barricades (type III) (712-07.03)LF48$23.23$50.00$24.25$23.03$23.00
17Speed feedback sign assembly (712-08.08)EACH4$4,242.00$3,500.00$4,400.00$4,205.60$4,200.00
18Digital speed limit sign assembly (712-08.09)EACH30$4,242.00$3,500.00$4,400.00$4,205.59$4,200.00
19Queue protection truck (712-08.12)DAY150$1,161.50$1,200.00$1,390.00$1,151.53$1,150.00
20Changeable message sign unit (713-16.01)EACH4$5,353.00$4,500.00$1,050.00$5,307.06$5,300.00
21Snowplowable raised pavement markers (BI-dir)(2 color) (716-01.23)EACH2,849$40.00$50.00$42.00$40.05$40.00
22Removal of snowplowable reflective marker (716-01.30)EACH2,849$10.00$10.00$16.00$15.02$15.00
23Plastic pavement marking (turn lane arrow) (716-02.06)EACH6$250.00$275.00$212.00$200.27$200.00
24Plastic pavement marking (24" barrier line) (716-02.07)LF11,053$8.00$8.00$10.50$10.01$10.00
25Plastic pavement marking (straight-turn arrow) (716-04.01)EACH5$400.00$400.00$318.00$300.40$300.00
26Plastic pavement marking (straight arrow) (716-04.05)EACH1$225.00$250.00$210.00$200.27$200.00
27Plastic pavement marking (lane reduction arrow) (716-04.14)EACH4$550.00$550.00$530.00$500.67$500.00
28Painted pavement marking (8" barrier line) (716-05.02)LF18,340$0.75$0.75$0.48$0.45$0.45
29Painted pavement marking (6" line) (716-05.20)LM74.90$900.00$1,100.00$1,910.00$1,802.40$1,800.00
30Removal of pavement marking (8" barrier line) (716-08.02)LF3,963$1.50$1.50$2.10$2.00$2.00
31Removal of pavement marking (dotted line) (716-08.09)LF1,824$1.00$1.00$1.05$1.00$1.00
32Removal of pavement marking (line) (716-08.20)LM3$4,000.00$4,000.00$4,250.00$4,005.33$4,000.00
33Removal of pavement marking (24IN barrier line) (716-08.21)LF2,423$5.00$5.00$6.35$6.01$6.00
34Contrast pavement marking 6" (716-09.86)LM2.30$30,000$35,000$21,000$20,027$20,000
35Contrast pavement marking 8" (716-09.88)LM0.70$35,000$40,000$48,000$45,060$45,000
36Contrast pavement marking 12" (716-09.89)LF908$13.00$13.00$12.75$12.02$12.00
37Contrast pavement marking 6" dotted (716-09.90)LF1,372$7.50$7.50$4.00$3.79$3.78
38Contrast pavement shadow marking 6" (716-09.97)LF3,120$7.00$7.00$4.00$3.79$3.78
39Enhanced flatline thermo PVMT MRKNG (6IN line) (716-12.02)LM42.80$6,850.00$7,200.00$8,300.00$7,810.39$7,800.00
40Enhanced flatline thermo PVMT MRKNG (8IN barrier line) (716-12.03)LF18,340$2.50$2.50$2.10$2.00$2.00
41Enhanced flatline thermo PVMT MRKNG (6IN dotted line) (716-12.05)LF12,891$2.00$2.00$1.60$1.50$1.50
42Enhanced flat line thermo (12IN line) (716-12.09)LF5,279$4.00$4.00$5.15$5.01$5.00
43Enhanced flat line thermo (12IN dotted) (716-12.10)LF4,058$4.00$4.00$5.15$5.01$5.00
44Mobilization (717-01)LS1$166,112$55,000$309,840$140,000$125,000
45Install pull box (type A) (730-03.20)EACH4$1,111.00$1,100.00$1,150.00$751.00$750.00
46Conduit 2" diameter (PVC schedule 40) (730-12.02)LF80$24.24$24.00$25.00$18.27$18.25
47Saw slot (730-14.02)LF1,200$5.05$5.00$5.30$6.01$6.00
48Loop wire (730-14.03)LF2,000$1.11$1.10$1.15$1.00$1.00
49Expansion joint repairs (604-10.44)LF372$333.46$330.16$400.00$375.50$375.00
50Trackless tack coat (403-02.01)TON302$950.79$925.00$900.00$850.00
51Hot applied tack coat (403-02.02)TON227$770.00
TDOT contract CNZ316: unit prices by line

The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.

Source

Read from TDOT's tabulation for this contract. TDOT Summary of Bids PDFs: every letting posted for February 2024 to October 2026, and nine lettings of 2018 to 2023 recovered from archived copies of the tn.gov files. Cost-plus-time bids, and bids that did not match their published total, are left out.

Every contract let that day: TDOT letting of December 5, 2025. Compiled by Mirage Metrics.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy