TxDOT contract A00180852 bid tabulation
Bridge Replacement, COUNTY ROAD 203 (0.1 Mi S of Leon River to 0.1 Mi N of Leon River). Let by Texas DOT on June 4, 2025, Hamilton, Waco District. 11 bids received; low bid $4,196,407 by Coppell Construction Co., Inc., +2.1% against the engineer's estimate of $4,110,675.
- Owner
- Texas DOT
- Letting
- 04 JUN 2025
- Pay items
- 47
- Data through
- 19 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | Coppell Construction Co., Inc. | $4,196,407 | Low | +2.0% |
| 2 | STX Civil | $4,206,593 | 0.0% | +2.0% |
| 3 | Hodges and Son Construction Company, Inc. | $4,324,387 | +3.0% | +5.0% |
| 4 | Talbert Companies LLC | $4,400,553 | +5.0% | +7.0% |
| 5 | C. E. Barker, LTD. | $4,492,801 | +7.0% | +9.0% |
| 6 | Urban Infraconstruction LLC | $4,604,000 | +10% | +12% |
| 7 | Skyline Bridge LLC | $4,918,259 | +17% | +20% |
| 8 | James Construction Group, LLC | $5,142,429 | +23% | +25% |
| 9 | Earth Builders, L.P. | $5,189,447 | +24% | +26% |
| 10 | Knife River Corporation - South | $5,644,389 | +35% | +37% |
| 11 | Orion Construction, LLC | $6,087,877 | +45% | +48% |
Engineer's estimate: $4,110,675.
Bid tabulation
| Line | Pay item | Unit | Quantity | Estimate | 1. Coppell Construction Co., Inc. | 2. STX Civil | 3. Hodges and Son Construction Company, Inc. | 4. Talbert Companies LLC | 5. C. E. Barker, LTD. | 6. Urban Infraconstruction LLC |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Preparing row (100-7002) | STA | 13.60 | $2,900.00 | $12,000 | $4,500.00 | $7,200.00 | $6,540.00 | $33,500 | $30,000 |
| 2 | Remove (0"-9") TRT/untrt base & asphalt pavement (105-7049) | SY | 1,026 | $6.00 | $10.00 | $10.00 | $20.00 | $8.70 | $20.16 | $10.00 |
| 3 | Excavation (roadway) (110-7001) | CY | 273 | $16.60 | $41.00 | $20.00 | $20.00 | $23.11 | $55.44 | $60.00 |
| 4 | Excavation (channel) (110-7002) | CY | 865 | $30.00 | $36.50 | $20.00 | $20.00 | $38.15 | $55.44 | $50.00 |
| 5 | Embankment (final)(DC)(type B) (132-7004) | CY | 177 | $19.20 | $88.00 | $25.00 | $40.00 | $32.70 | $55.44 | $85.00 |
| 6 | Furn & place topsoil (4") (160-7002) | SY | 3,519 | $3.00 | $4.00 | $4.00 | $4.00 | $8.09 | $7.31 | $8.00 |
| 7 | Broadcast seed (permanent_rural_sand) (164-7001) | SY | 3,519 | $3.00 | $1.00 | $1.00 | $1.50 | $1.09 | $0.30 | $3.00 |
| 8 | Broadcast seed (temporary_warm) (164-7005) | SY | 1,760 | $1.95 | $1.00 | $1.00 | $1.00 | $1.09 | $0.87 | $4.00 |
| 9 | Broadcast seed (temporary_cool) (164-7006) | SY | 1,760 | $1.50 | $1.00 | $1.00 | $1.00 | $1.09 | $0.87 | $4.00 |
| 10 | Vegetative watering (168-7001) | TGL | 58 | $37.00 | $25.00 | $50.00 | $1.00 | $62.27 | $105.84 | $58.00 |
| 11 | Soil ret BLKT(SL_steep_sand_long_spry) (169-7024) | SY | 3,519 | $4.20 | $1.10 | $2.00 | $4.00 | $1.18 | $1.11 | $3.50 |
| 12 | FL BS (compacted in place)(type D GR 3)(final pos) (247-7189) | CY | 160 | $100.50 | $147.00 | $160.00 | $120.00 | $212.55 | $207.30 | $160.00 |
| 13 | Emuls asphalt (BS or subgr TRT)(CSS-1H) (314-7004) | GAL | 1,148 | $3.82 | $8.25 | $5.00 | $15.00 | $7.63 | $12.10 | $7.00 |
| 14 | Fog seal (CSS-1H) (315-7004) | GAL | 96 | $5.81 | $45.00 | $5.00 | $15.00 | $6.54 | $20.16 | $7.00 |
| 15 | Asphalt (AC-20-5TR) (316-7007) | GAL | 335 | $7.81 | $35.00 | $16.00 | $30.00 | $17.33 | $20.16 | $40.00 |
| 16 | Asphalt (CRS-2P) (316-7012) | GAL | 574 | $5.49 | $18.50 | $10.00 | $20.00 | $10.57 | $20.16 | $21.50 |
| 17 | Aggregate (type-PD or PL, GR-4) (316-7258) | CY | 8 | $945.00 | $2,200.00 | $1,525.00 | $1,400.00 | $1,662.25 | $302.40 | $2,555.00 |
| 18 | Aggregate (type-D or L,GR-3) (316-7278) | CY | 11 | $925.00 | $1,575.00 | $1,100.00 | $1,000.00 | $1,199.00 | $302.40 | $1,830.00 |
| 19 | Cem stabil BKFL (400-7010) | CY | 133 | $245.00 | $250.00 | $220.00 | $280.00 | $245.25 | $257.04 | $300.00 |
| 20 | Drilled shaft (18 in) (416-7002) | LF | 88 | $250.00 | $140.00 | $200.00 | $180.00 | $222.36 | $122.40 | $305.00 |
| 21 | Drilled shaft (36 in) (416-7006) | LF | 1,047 | $375.00 | $275.00 | $350.00 | $260.00 | $310.65 | $325.00 | $265.00 |
| 22 | Drilled shaft (42 in) (416-7007) | LF | 219 | $470.66 | $425.00 | $380.00 | $370.00 | $340.08 | $450.00 | $500.00 |
| 23 | Class C concrete (abutment) (420-7012) | CY | 47.40 | $1,200.00 | $990.00 | $1,000.00 | $1,400.00 | $1,308.00 | $1,544.64 | $2,000.00 |
| 24 | Class C concrete (cap) (420-7022) | CY | 118.40 | $1,781.63 | $950.00 | $1,200.00 | $1,800.00 | $1,417.00 | $1,540.23 | $2,000.00 |
| 25 | Class C concrete (column) (420-7038) | CY | 82 | $1,836.67 | $1,200.00 | $1,500.00 | $2,000.00 | $1,417.00 | $1,574.01 | $1,000.00 |
| 26 | Reinforced concrete slab (422-7001) | SF | 28,797 | $28.85 | $27.00 | $15.00 | $25.00 | $27.25 | $23.81 | $22.95 |
| 27 | Prestressed concrete girder (TX40) (425-7003) | LF | 1,340 | $200.00 | $205.00 | $223.00 | $270.00 | $232.98 | $241.62 | $249.00 |
| 28 | Prestressed concrete girder (TX54) (425-7005) | LF | 2,290 | $220.00 | $220.00 | $216.00 | $270.00 | $227.18 | $250.75 | $249.00 |
| 29 | Prestressed concrete girder (TX62) (425-7006) | LF | 737.50 | $226.49 | $265.00 | $309.00 | $340.00 | $389.94 | $393.78 | $249.00 |
| 30 | Riprap (stone protection)(18 in) (432-7043) | CY | 678 | $205.00 | $250.00 | $200.00 | $175.00 | $152.60 | $143.64 | $185.00 |
| 31 | Rail (type T66) (450-7022) | LF | 2,180 | $185.00 | $165.00 | $180.00 | $150.00 | $201.65 | $108.36 | $180.00 |
| 32 | Sealed expansion joint (4 in) (SEJ - M) (454-7004) | LF | 130 | $250.00 | $200.00 | $215.00 | $250.00 | $327.00 | $219.24 | $300.00 |
| 33 | Removing structure (bridge 1000 FT or greater) (496-7012) | EACH | 1 | $130,000 | $280,000 | $750,000 | $325,000 | $228,339 | $177,660 | $160,000 |
| 34 | Mobilization (500-7001) | LS | 1 | $374,016 | $361,000 | $330,000 | $390,000 | $479,300 | $412,000 | $433,755 |
| 35 | Barricades, signs and traffic handling (502-7001) | MO | 13 | $5,000.00 | $12,000 | $4,000.00 | $2,000.00 | $6,540.95 | $4,617.90 | $7,600.00 |
| 36 | Rock filter dams (install) (type 1) (506-7001) | LF | 200 | $40.00 | $43.00 | $40.00 | $1.00 | $43.60 | $42.49 | $70.00 |
| 37 | Rock filter dams (remove) (506-7011) | LF | 200 | $10.00 | $35.00 | $10.00 | $1.00 | $10.90 | $34.32 | $50.00 |
| 38 | Temporary sediment control fence (install) (506-7039) | LF | 1,094 | $5.14 | $3.10 | $4.00 | $1.00 | $3.38 | $4.54 | $9.00 |
| 39 | Temporary sediment control fence (remove) (506-7041) | LF | 1,094 | $1.50 | $1.00 | $2.00 | $1.00 | $1.09 | $1.01 | $5.00 |
| 40 | Metal W-beam guard fence (steel post) (540-7002) | LF | 162.50 | $34.00 | $28.50 | $60.00 | $30.00 | $32.70 | $46.22 | $35.00 |
| 41 | Metal beam guard fence trans (thrie-beam) (540-7005) | EACH | 4 | $2,724.97 | $2,100.00 | $2,800.00 | $2,400.00 | $2,834.00 | $2,605.68 | $3,000.00 |
| 42 | Downstream anchor terminal section (540-7015) | EACH | 2 | $1,396.26 | $1,450.00 | $2,000.00 | $1,500.00 | $1,417.00 | $1,802.30 | $1,500.00 |
| 43 | Guardrail end treatment (install) (544-7001) | EACH | 2 | $3,374.77 | $3,050.00 | $4,200.00 | $3,100.00 | $3,270.00 | $3,899.95 | $3,485.00 |
| 44 | Wire fence (type C) (552-7003) | LF | 410 | $29.92 | $25.00 | $20.00 | $20.00 | $16.90 | $50.40 | $18.00 |
| 45 | Wire fence (remove) (552-7011) | LF | 410 | $7.88 | $5.00 | $1.00 | $5.00 | $2.73 | $10.08 | $3.00 |
| 46 | Install delineator assembly (D-SW)SZ 1(BRF)CTB (BI) (658-7013) | EACH | 30 | $40.00 | $20.00 | $18.00 | $30.00 | $21.80 | $16.13 | $23.00 |
| 47 | Install delineator assembly (D-SW)SZ 1(BRF)GF2(BI) (658-7019) | EACH | 12 | $40.00 | $45.00 | $29.00 | $30.00 | $49.05 | $26.21 | $52.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from TxDOT's tabulation for this contract. TxDOT Bid Tabulations open-data export (data.texas.gov) from September 2024, read 21 November 2026, and TxDOT's legacy Tabulation of Bids pages for January 2020 to August 2024. The legacy pages are a large sample, not every contract: their file names were reused from year to year. Their district is the one TxDOT gives the county. Bids that did not match their published total are left out.
Every contract let that day: TxDOT letting of June 4, 2025. Compiled by Mirage Metrics.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.