TxDOT contract A00180852 bid tabulation

Bridge Replacement, COUNTY ROAD 203 (0.1 Mi S of Leon River to 0.1 Mi N of Leon River). Let by Texas DOT on June 4, 2025, Hamilton, Waco District. 11 bids received; low bid $4,196,407 by Coppell Construction Co., Inc., +2.1% against the engineer's estimate of $4,110,675.

Owner
Texas DOT
Letting
04 JUN 2025
Pay items
47
Data through
19 NOV 2026

Bidders

RankBidderTotal bidAgainst the low bidAgainst the estimate
1Coppell Construction Co., Inc.$4,196,407Low+2.0%
2STX Civil$4,206,5930.0%+2.0%
3Hodges and Son Construction Company, Inc.$4,324,387+3.0%+5.0%
4Talbert Companies LLC$4,400,553+5.0%+7.0%
5C. E. Barker, LTD.$4,492,801+7.0%+9.0%
6Urban Infraconstruction LLC$4,604,000+10%+12%
7Skyline Bridge LLC$4,918,259+17%+20%
8James Construction Group, LLC$5,142,429+23%+25%
9Earth Builders, L.P.$5,189,447+24%+26%
10Knife River Corporation - South$5,644,389+35%+37%
11Orion Construction, LLC$6,087,877+45%+48%
TxDOT contract A00180852: bids by rank

Engineer's estimate: $4,110,675.

Bid tabulation

LinePay itemUnitQuantityEstimate1. Coppell Construction Co., Inc.2. STX Civil3. Hodges and Son Construction Company, Inc.4. Talbert Companies LLC5. C. E. Barker, LTD.6. Urban Infraconstruction LLC
1Preparing row (100-7002)STA13.60$2,900.00$12,000$4,500.00$7,200.00$6,540.00$33,500$30,000
2Remove (0"-9") TRT/untrt base & asphalt pavement (105-7049)SY1,026$6.00$10.00$10.00$20.00$8.70$20.16$10.00
3Excavation (roadway) (110-7001)CY273$16.60$41.00$20.00$20.00$23.11$55.44$60.00
4Excavation (channel) (110-7002)CY865$30.00$36.50$20.00$20.00$38.15$55.44$50.00
5Embankment (final)(DC)(type B) (132-7004)CY177$19.20$88.00$25.00$40.00$32.70$55.44$85.00
6Furn & place topsoil (4") (160-7002)SY3,519$3.00$4.00$4.00$4.00$8.09$7.31$8.00
7Broadcast seed (permanent_rural_sand) (164-7001)SY3,519$3.00$1.00$1.00$1.50$1.09$0.30$3.00
8Broadcast seed (temporary_warm) (164-7005)SY1,760$1.95$1.00$1.00$1.00$1.09$0.87$4.00
9Broadcast seed (temporary_cool) (164-7006)SY1,760$1.50$1.00$1.00$1.00$1.09$0.87$4.00
10Vegetative watering (168-7001)TGL58$37.00$25.00$50.00$1.00$62.27$105.84$58.00
11Soil ret BLKT(SL_steep_sand_long_spry) (169-7024)SY3,519$4.20$1.10$2.00$4.00$1.18$1.11$3.50
12FL BS (compacted in place)(type D GR 3)(final pos) (247-7189)CY160$100.50$147.00$160.00$120.00$212.55$207.30$160.00
13Emuls asphalt (BS or subgr TRT)(CSS-1H) (314-7004)GAL1,148$3.82$8.25$5.00$15.00$7.63$12.10$7.00
14Fog seal (CSS-1H) (315-7004)GAL96$5.81$45.00$5.00$15.00$6.54$20.16$7.00
15Asphalt (AC-20-5TR) (316-7007)GAL335$7.81$35.00$16.00$30.00$17.33$20.16$40.00
16Asphalt (CRS-2P) (316-7012)GAL574$5.49$18.50$10.00$20.00$10.57$20.16$21.50
17Aggregate (type-PD or PL, GR-4) (316-7258)CY8$945.00$2,200.00$1,525.00$1,400.00$1,662.25$302.40$2,555.00
18Aggregate (type-D or L,GR-3) (316-7278)CY11$925.00$1,575.00$1,100.00$1,000.00$1,199.00$302.40$1,830.00
19Cem stabil BKFL (400-7010)CY133$245.00$250.00$220.00$280.00$245.25$257.04$300.00
20Drilled shaft (18 in) (416-7002)LF88$250.00$140.00$200.00$180.00$222.36$122.40$305.00
21Drilled shaft (36 in) (416-7006)LF1,047$375.00$275.00$350.00$260.00$310.65$325.00$265.00
22Drilled shaft (42 in) (416-7007)LF219$470.66$425.00$380.00$370.00$340.08$450.00$500.00
23Class C concrete (abutment) (420-7012)CY47.40$1,200.00$990.00$1,000.00$1,400.00$1,308.00$1,544.64$2,000.00
24Class C concrete (cap) (420-7022)CY118.40$1,781.63$950.00$1,200.00$1,800.00$1,417.00$1,540.23$2,000.00
25Class C concrete (column) (420-7038)CY82$1,836.67$1,200.00$1,500.00$2,000.00$1,417.00$1,574.01$1,000.00
26Reinforced concrete slab (422-7001)SF28,797$28.85$27.00$15.00$25.00$27.25$23.81$22.95
27Prestressed concrete girder (TX40) (425-7003)LF1,340$200.00$205.00$223.00$270.00$232.98$241.62$249.00
28Prestressed concrete girder (TX54) (425-7005)LF2,290$220.00$220.00$216.00$270.00$227.18$250.75$249.00
29Prestressed concrete girder (TX62) (425-7006)LF737.50$226.49$265.00$309.00$340.00$389.94$393.78$249.00
30Riprap (stone protection)(18 in) (432-7043)CY678$205.00$250.00$200.00$175.00$152.60$143.64$185.00
31Rail (type T66) (450-7022)LF2,180$185.00$165.00$180.00$150.00$201.65$108.36$180.00
32Sealed expansion joint (4 in) (SEJ - M) (454-7004)LF130$250.00$200.00$215.00$250.00$327.00$219.24$300.00
33Removing structure (bridge 1000 FT or greater) (496-7012)EACH1$130,000$280,000$750,000$325,000$228,339$177,660$160,000
34Mobilization (500-7001)LS1$374,016$361,000$330,000$390,000$479,300$412,000$433,755
35Barricades, signs and traffic handling (502-7001)MO13$5,000.00$12,000$4,000.00$2,000.00$6,540.95$4,617.90$7,600.00
36Rock filter dams (install) (type 1) (506-7001)LF200$40.00$43.00$40.00$1.00$43.60$42.49$70.00
37Rock filter dams (remove) (506-7011)LF200$10.00$35.00$10.00$1.00$10.90$34.32$50.00
38Temporary sediment control fence (install) (506-7039)LF1,094$5.14$3.10$4.00$1.00$3.38$4.54$9.00
39Temporary sediment control fence (remove) (506-7041)LF1,094$1.50$1.00$2.00$1.00$1.09$1.01$5.00
40Metal W-beam guard fence (steel post) (540-7002)LF162.50$34.00$28.50$60.00$30.00$32.70$46.22$35.00
41Metal beam guard fence trans (thrie-beam) (540-7005)EACH4$2,724.97$2,100.00$2,800.00$2,400.00$2,834.00$2,605.68$3,000.00
42Downstream anchor terminal section (540-7015)EACH2$1,396.26$1,450.00$2,000.00$1,500.00$1,417.00$1,802.30$1,500.00
43Guardrail end treatment (install) (544-7001)EACH2$3,374.77$3,050.00$4,200.00$3,100.00$3,270.00$3,899.95$3,485.00
44Wire fence (type C) (552-7003)LF410$29.92$25.00$20.00$20.00$16.90$50.40$18.00
45Wire fence (remove) (552-7011)LF410$7.88$5.00$1.00$5.00$2.73$10.08$3.00
46Install delineator assembly (D-SW)SZ 1(BRF)CTB (BI) (658-7013)EACH30$40.00$20.00$18.00$30.00$21.80$16.13$23.00
47Install delineator assembly (D-SW)SZ 1(BRF)GF2(BI) (658-7019)EACH12$40.00$45.00$29.00$30.00$49.05$26.21$52.00
TxDOT contract A00180852: unit prices by line, the 6 lowest bidders (all in the CSV)

The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.

Source

Read from TxDOT's tabulation for this contract. TxDOT Bid Tabulations open-data export (data.texas.gov) from September 2024, read 21 November 2026, and TxDOT's legacy Tabulation of Bids pages for January 2020 to August 2024. The legacy pages are a large sample, not every contract: their file names were reused from year to year. Their district is the one TxDOT gives the county. Bids that did not match their published total are left out.

Every contract let that day: TxDOT letting of June 4, 2025. Compiled by Mirage Metrics.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy