TxDOT contract A00195344 bid tabulation

Bridge Replacement, FM 816 (At Loring Creek Relief to .). Let by Texas DOT on March 5, 2026, Hunt, Paris District. 12 bids received; low bid $2,085,509 by Hodges and Son Construction Company, Inc., -23% against the engineer's estimate of $2,724,592.

Owner
Texas DOT
Letting
05 MAR 2026
Pay items
58
Data through
19 NOV 2026

Bidders

RankBidderTotal bidAgainst the low bidAgainst the estimate
1Hodges and Son Construction Company, Inc.$2,085,509Low-23%
2Tucan Contracting, LLC$2,125,564+2.0%-22%
3Skyline Bridge LLC$2,246,938+8.0%-18%
4Texas Steel Industrial Placing, LLC$2,269,867+9.0%-17%
5East Texas Bridge, Inc.$2,414,424+16%-11%
6THK Construction LLC$2,456,073+18%-10%
7Talbert Companies LLC$2,467,312+18%-9.0%
8Highway 19 Construction LLC$2,501,732+20%-8.0%
9R Construction Civil, LLC$2,564,064+23%-6.0%
10Garret Shields Infrastructure$2,588,319+24%-5.0%
11RB Contracting, LLC$2,625,218+26%-4.0%
12Coppell Construction Co., Inc.$3,038,489+46%+12%
TxDOT contract A00195344: bids by rank

Engineer's estimate: $2,724,592.

Bid tabulation

LinePay itemUnitQuantityEstimate1. Hodges and Son Construction Company, Inc.2. Tucan Contracting, LLC3. Skyline Bridge LLC4. Texas Steel Industrial Placing, LLC5. East Texas Bridge, Inc.6. THK Construction LLC
1Preparing row (100-7002)STA16$2,500.00$3,250.00$1,210.00$775.00$500.00$2,500.00$1,400.00
2Removing concrete (mowstrip) (104-7003)SY736$15.00$15.00$7.70$16.05$13.00$20.00$10.00
3Excavation (roadway) (110-7001)CY199$25.00$20.00$49.50$13.72$17.00$15.00$20.00
4Excavation (channel) (110-7002)CY1,031$25.00$15.00$33.00$12.90$17.00$15.00$15.00
5Embankment (final)(OC)(type A) (132-7001)CY166$20.00$20.00$99.00$32.13$25.00$15.00$15.00
6Embankment (final)(DC)(type C) (132-7006)CY4,786$60.00$15.00$22.00$29.25$20.00$15.00$14.00
7Broadcast seed (temporary_warm) (164-7005)SY4,407$0.20$0.25$0.31$0.54$0.25$0.30$0.27
8Broadcast seed (temporary_cool) (164-7006)SY4,407$0.20$0.25$0.33$0.54$0.25$0.30$0.27
9Straw/hay mulch seed(permanent_rural_clay) (164-7026)SY8,814$0.30$0.50$0.53$0.63$0.50$0.55$0.54
10Vegetative watering (168-7001)TGL53$40.00$1.00$110.00$1.00$1.00$30.00$10.00
11Rework BS metal (type C)(8")(ord comp) (251-7051)SY3,706$3.10$4.00$3.30$10.57$8.00$10.00$25.00
12D-GR HMA type-B PG64-22 (exempt) (341-7003)TON1,006$180.00$140.00$155.98$170.84$144.50$145.00$157.11
13D-GR HMA type-C sac-A PG64-22(exempt) (341-7034)TON741$180.00$145.00$177.43$194.33$132.45$148.00$150.88
14Tack coat (341-7082)GAL293$6.40$4.50$11.00$12.24$4.00$7.00$9.25
15Cem stabil BKFL (400-7010)CY140$250.00$190.00$220.00$280.57$200.00$300.00$350.00
16Drilled shaft (36 in) (416-7006)LF800$225.00$195.00$154.00$215.00$203.00$235.00$221.72
17Class C concrete (abutment) (420-7012)CY89.20$1,200.00$900.00$1,210.00$972.14$1,100.00$1,300.00$1,075.00
18Class C concrete (cap) (420-7022)CY31.40$900.00$1,320.00$1,331.21$1,500.00$1,350.00$1,500.00
19Class C concrete (column) (420-7038)CY17.20$1,500.00$1,210.00$1,594.22$1,300.00$1,350.00$1,500.00
20Reinforced concrete slab (422-7001)SF7,560$23.00$26.00$28.60$20.50$23.00$38.00$26.00
21Approach slab (422-7013)CY108$600.00$795.00$990.00$635.10$550.00$775.00$800.00
22Prestressed concrete girder (TX28) (425-7001)LF1,040$300.00$230.00$191.32$274.75$234.53$255.00$259.46
23Riprap (mow strip)(4 in) (432-7013)CY74$750.00$650.00$715.00$671.24$600.00$650.00$800.00
24Riprap (stone protection)(24 in) (432-7045)CY1,641$190.00$175.00$148.50$144.72$165.00$170.00$160.00
25Rail (type T223) (450-7008)LF516$180.00$120.00$187.00$117.89$150.00$115.00$175.00
26Armor joint (sealed) (454-7003)LF204$150.00$120.00$88.00$100.00$135.00$100.00$150.00
27Removing structure (bridge 0 - 99 FT length) (496-7009)EACH2$30,000$15,000$16,500$14,590$30,000$25,000$25,000
28Mobilization (500-7001)LS1$247,690$170,000$100,000$180,000$226,782$200,000$240,000
29Barricades, signs and traffic handling (502-7001)MO8$3,500.00$2,000.00$1,650.00$2,176.17$1,500.00$4,000.00$1,185.60
30Portable changeable message sign (503-7002)EACH4$10,000$10,500$8,800.00$8,433.60$17,000$10,000$20,000
31TMA (stationary) (505-7001)DAY10$500.00$250.00$550.00$180.72$100.00$250.00$300.00
32TMA (mobile operation) (505-7002)HR40$100.00$40.00$165.00$10.00$1.00$30.00$100.00
33Rock filter dams (install) (type 2) (506-7002)LF160$50.00$1.00$44.00$42.86$50.00$55.00$53.75
34Rock filter dams (remove) (506-7011)LF160$20.00$1.00$11.00$5.58$15.00$15.00$16.13
35Construction exits (install) (type 1) (506-7020)SY600$30.00$1.00$22.00$1.00$37.00$40.00$39.78
36Construction exits (remove) (506-7024)SY600$15.00$1.00$5.50$1.00$10.00$11.00$10.75
37Temporary sediment control fence (install) (506-7039)LF2,052$4.50$1.00$3.30$3.58$4.50$5.00$4.84
38Temporary sediment control fence (remove) (506-7041)LF2,052$1.50$1.00$1.10$1.12$1.00$1.10$1.08
39Driveways (base) (530-7015)SY680$28.00$33.00$33.12$65.00$25.00$40.00
40Metal W-beam guard fence (steel post) (540-7002)LF500$35.00$25.00$28.11$29.52$28.00$26.50$27.42
41Metal beam guard fence trans (thrie-beam) (540-7005)EACH8$2,000.00$1,900.00$2,513.50$2,271.05$2,200.00$2,200.00$2,026.38
42Remove metal beam guard fence (542-7001)LF450$2.00$2.00$2.20$3.17$2.50$2.20$2.15
43RM metal beam guard fence trans (thrie-beam) (542-7004)EACH8$100.00$150.00$220.00$278.61$250.00$165.00$161.25
44Guardrail end treatment (install) (544-7001)EACH8$3,000.00$3,075.00$3,375.90$3,614.40$2,950.00$3,300.00$3,225.00
45Guardrail end treatment (remove) (544-7003)EACH8$500.00$300.00$220.00$250.00$250.00$220.00$215.00
46Install small roadside sign support and assembly type 10BWG(1)SA(P) (644-7001)EACH16$720.00$800.00$720.50$1,084.32$655.00$800.00$782.60
47Remove SM RD SN sup&AM (644-7073)EACH16$100.00$50.00$86.90$100.00$79.00$130.00$136.53
48Install delineator assembly (D-SW)SZ 1(BRF)CTB (BI) (658-7013)EACH10$45.00$20.00$16.50$21.69$22.00$20.00$19.35
49Install delineator assembly (D-SW)SZ 1(BRF)GF2(BI) (658-7019)EACH12$45.00$25.00$27.50$54.22$24.00$30.00$26.88
50Work zone pavement marking non-removing (W)6"(solid) (662-7008)LF3,200$0.27$0.50$0.50$0.54$1.00$1.10$0.91
51Work zone pavement marking non-removing (Y)6"(solid) (662-7038)LF3,200$0.27$0.50$0.50$0.54$1.00$1.10$0.91
52Work zone pavement marking SHT terminal (tab)type Y-2 (662-7114)EACH162$0.50$2.00$2.28$2.00$1.00$3.00$1.00
53Pavement sler 6" (666-7347)LF1,200$1.00$0.20$0.22$0.24$1.00$1.10$0.22
54Reflectorized pavement marking type I (W)6"(solid)(090MIL) (666-7410)LF3,200$1.50$0.75$0.79$0.87$1.25$1.40$0.78
55Reflectorized pavement marking type I (Y)6"(solid)(090MIL) (666-7422)LF3,200$1.50$0.75$0.79$0.87$1.25$1.40$0.78
56Reflectorized pavement marker type II-A-A (672-7004)EACH40$7.50$6.00$6.11$6.69$10.00$11.00$5.97
57Pavement surface preparation for marking (6") (678-7002)LF1,200$2.00$0.10$0.11$0.12$0.50$0.55$0.11
58Remove lead-containing coating (other) (5011-7002)LS2$15,000$15,000$10,900$23,229$22,000$8,000.00$10,000
TxDOT contract A00195344: unit prices by line, the 6 lowest bidders (all in the CSV)

The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.

Source

Read from TxDOT's tabulation for this contract. TxDOT Bid Tabulations open-data export (data.texas.gov) from September 2024, read 21 November 2026, and TxDOT's legacy Tabulation of Bids pages for January 2020 to August 2024. The legacy pages are a large sample, not every contract: their file names were reused from year to year. Their district is the one TxDOT gives the county. Bids that did not match their published total are left out.

Every contract let that day: TxDOT letting of March 5, 2026. Compiled by Mirage Metrics.

Your own bid history, read the same way