TxDOT contract A00214454 bid tabulation
Bridge Replacement, COUNTY ROAD 1590 (AT BIG SANDY CREEK to .). Let by Texas DOT on August 6, 2026, Wise, Fort Worth District. 8 bids received; low bid $961,912 by Hodges and Son Construction Company, Inc., +13% against the engineer's estimate of $854,302.
- Owner
- Texas DOT
- Letting
- 06 AUG 2026
- Pay items
- 56
- Data through
- 19 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | Hodges and Son Construction Company, Inc. | $961,912 | Low | +13% |
| 2 | Garret Shields Infrastructure | $967,631 | +1.0% | +13% |
| 3 | Texas Steel Industrial Placing, LLC | $999,854 | +4.0% | +17% |
| 4 | Scott Tucker Construction Company, LLC | $1,013,241 | +5.0% | +19% |
| 5 | Coppell Construction Co., Inc. | $1,140,751 | +19% | +34% |
| 6 | Ed Bell Construction Company | $1,265,000 | +32% | +48% |
| 7 | Earth Builders, L.P. | $1,372,184 | +43% | +61% |
| 8 | THK Construction LLC | $1,590,868 | +65% | +86% |
Engineer's estimate: $854,302.
Bid tabulation
| Line | Pay item | Unit | Quantity | Estimate | 1. Hodges and Son Construction Company, Inc. | 2. Garret Shields Infrastructure | 3. Texas Steel Industrial Placing, LLC | 4. Scott Tucker Construction Company, LLC | 5. Coppell Construction Co., Inc. | 6. Ed Bell Construction Company |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Preparing row (100-7002) | STA | 4 | $7,000.00 | $9,000.00 | $1,000.00 | $1,000.00 | $4,013.00 | $3,500.00 | $5,000.00 |
| 2 | Obliterating abandoned road (106-7002) | SY | 956 | $8.00 | $15.00 | $40.00 | $18.08 | $14.00 | $29.00 | $16.00 |
| 3 | Excavation (roadway) (110-7001) | CY | 35 | $37.00 | $35.00 | $30.00 | $50.00 | $14.00 | $59.00 | $175.00 |
| 4 | Excavation (channel) (110-7002) | CY | 928 | $28.00 | $20.00 | $30.00 | $17.00 | $8.00 | $29.00 | $65.00 |
| 5 | Embankment (final)(DC)(type B) (132-7004) | CY | 1,560 | $30.00 | $30.00 | $30.00 | $22.00 | $56.00 | $30.00 | $50.00 |
| 6 | Compost manuf topsoil (4") (161-7002) | SY | 2,677 | $3.00 | $10.00 | $5.00 | $2.30 | $9.00 | $2.50 | $1.36 |
| 7 | Straw/hay mulch seed(permanent_rural_sand) (164-7025) | SY | 2,677 | $3.00 | $3.00 | $0.10 | $1.78 | $0.70 | $1.80 | $0.65 |
| 8 | Straw/hay mulch seed (temporary_warm) (164-7029) | SY | 1,339 | $1.00 | $3.00 | $0.10 | $2.33 | $0.70 | $2.50 | $0.60 |
| 9 | Straw/hay mulch seed (temporary_warm_cool) (164-7031) | SY | 1,339 | $1.80 | $3.00 | $0.10 | $2.33 | $0.70 | $2.50 | $0.61 |
| 10 | Vegetative watering (168-7001) | TGL | 21 | $10.00 | $1.00 | $10.00 | $103.59 | $452.00 | $50.00 | $365.21 |
| 11 | FL BS (compacted in place)(type A GR 1-2) (8") (247-7067) | SY | 900 | $43.00 | $48.00 | $25.00 | $29.00 | $23.00 | $37.00 | $50.00 |
| 12 | Prime coat(MC-30 or AE-P) (310-7013) | GAL | 270 | $15.00 | $10.00 | $8.00 | $30.47 | $33.00 | $15.00 | $7.63 |
| 13 | SP mixes SP-C PG70-28 (344-7023) | TON | 95.50 | $160.00 | $450.00 | $450.00 | $699.00 | $745.00 | $433.00 | $471.97 |
| 14 | Tack coat (344-7077) | GAL | 88 | $4.00 | $5.00 | $6.00 | $5.00 | $9.00 | $5.00 | $5.45 |
| 15 | Cem stabil BKFL (400-7010) | CY | 66 | $300.00 | $300.00 | $200.00 | $150.00 | $218.00 | $330.00 | $575.00 |
| 16 | Drilled shaft (36 in) (416-7006) | LF | 300 | $290.00 | $310.00 | $350.00 | $340.00 | $376.00 | $350.00 | $375.00 |
| 17 | Class C concrete (abutment)(HPC) (420-7013) | CY | 31 | $1,210.00 | $1,900.00 | $1,200.00 | $1,100.00 | $1,131.00 | $1,350.00 | $2,000.00 |
| 18 | Reinforced concrete slab (HPC) (422-7002) | SF | 1,820 | $18.00 | $32.00 | $30.00 | $22.00 | $33.00 | $39.00 | $40.00 |
| 19 | Approach slab (HPC) (422-7014) | CY | 38.50 | $810.00 | $1,000.00 | $1,200.00 | $700.00 | $886.00 | $920.00 | $1,500.00 |
| 20 | Prestressed concrete girder (TX28) (425-7001) | LF | 278 | $55.00 | $65.00 | $250.00 | $300.00 | $137.00 | $330.00 | $200.00 |
| 21 | Riprap (mow strip)(4 in) (432-7013) | CY | 24 | $745.00 | $750.00 | $600.00 | $550.00 | $786.00 | $750.00 | $1,250.00 |
| 22 | Riprap (stone protection)(24 in) (432-7045) | CY | 320 | $196.00 | $180.00 | $180.00 | $140.00 | $122.00 | $160.00 | $275.00 |
| 23 | Rail (type T631) (450-7020) | LF | 172 | $122.00 | $90.00 | $150.00 | $99.25 | $112.00 | $100.00 | $108.18 |
| 24 | Armor joint (sealed) (454-7003) | LF | 48 | $200.00 | $150.00 | $300.00 | $120.00 | $95.00 | $225.00 | $150.00 |
| 25 | Removing structure (bridge 0 - 99 FT length) (496-7009) | EACH | 1 | $20,000 | $30,000 | $20,000 | $10,000 | $18,905 | $30,000 | $30,000 |
| 26 | Mobilization (500-7001) | LS | 1 | $78,000 | $85,000 | $100,000 | $96,000 | $100,000 | $95,000 | $103,939 |
| 27 | Barricades, signs and traffic handling (502-7001) | MO | 5 | $3,265.00 | $2,000.00 | $5,000.00 | $3,000.00 | $2,191.00 | $15,000 | $8,500.00 |
| 28 | Portable changeable message sign (503-7001) | DAY | 75 | $91.00 | $95.00 | $100.00 | $115.00 | $98.00 | $55.00 | $275.00 |
| 29 | Rock filter dams (install) (type 2) (506-7002) | LF | 100 | $45.00 | $1.00 | $20.00 | $58.57 | $47.00 | $59.00 | $72.66 |
| 30 | Rock filter dams (remove) (506-7011) | LF | 100 | $11.00 | $1.00 | $5.00 | $20.20 | $15.00 | $21.00 | $14.99 |
| 31 | Temporary sediment control fence (install) (506-7039) | LF | 1,864 | $4.00 | $1.00 | $5.00 | $5.40 | $3.70 | $5.50 | $4.15 |
| 32 | Temporary sediment control fence (remove) (506-7041) | LF | 1,864 | $1.20 | $1.00 | $1.00 | $1.03 | $1.10 | $1.10 | $1.27 |
| 33 | Biodegradable erosion control logs (install) (18") (506-7045) | LF | 100 | $8.00 | $5.00 | $5.00 | $10.84 | $7.00 | $11.00 | $8.07 |
| 34 | Biodegradable erosion control logs (remove) (506-7046) | LF | 100 | $1.50 | $1.00 | $1.00 | $1.03 | $1.30 | $1.00 | $1.50 |
| 35 | Constructing detours (508-7001) | SY | 1,094 | $125.00 | $100.00 | $60.00 | $175.00 | $103.00 | $105.00 | $94.00 |
| 36 | Driveways (ACP) (530-7010) | SY | 131 | $75.00 | $90.00 | $120.00 | $112.00 | $125.00 | $66.00 | $265.00 |
| 37 | Metal W-beam guard fence (timber post) (540-7001) | LF | 225 | $25.00 | $26.00 | $40.00 | $26.90 | $31.00 | $27.00 | $29.32 |
| 38 | Metal beam guard fence trans (T6) (540-7008) | EACH | 4 | $500.00 | $1,500.00 | $500.00 | $1,199.00 | $1,335.00 | $1,200.00 | $1,306.91 |
| 39 | Metal thrie-beam guard fence adjustment (540-7010) | LF | 25 | $12.00 | $20.00 | $40.00 | $29.55 | $34.00 | $30.00 | $32.21 |
| 40 | Short radius (28") (540-7013) | LF | 43.75 | $42.00 | $40.00 | $30.00 | $59.45 | $67.00 | $60.00 | $64.80 |
| 41 | Downstream anchor terminal section (540-7015) | EACH | 1 | $1,400.00 | $1,600.00 | $1,500.00 | $1,678.00 | $1,896.00 | $1,700.00 | $1,829.02 |
| 42 | Guardrail end treatment (install) (544-7001) | EACH | 3 | $3,200.00 | $3,300.00 | $3,500.00 | $3,398.00 | $3,761.00 | $3,400.00 | $3,703.82 |
| 43 | Gate (remove) (550-7016) | EACH | 1 | $500.00 | $50.00 | $500.00 | $500.00 | $40.00 | $500.00 | $545.00 |
| 44 | Wire fence (type C) (552-7003) | LF | 96 | $23.00 | $35.00 | $10.00 | $23.00 | $54.00 | $23.00 | $25.07 |
| 45 | Gate (type 1) (552-7006) | EACH | 1 | $1,781.00 | $2,000.00 | $1,000.00 | $1,800.00 | $1,049.00 | $1,800.00 | $1,962.00 |
| 46 | Remove SM RD SN sup&AM (644-7073) | EACH | 4 | $100.00 | $50.00 | $100.00 | $100.00 | $63.00 | $250.00 | $163.50 |
| 47 | Install delineator assembly (D-SW)SZ 1(WFLX)GND(BI) (658-7004) | EACH | 6 | $49.00 | $500.00 | $40.00 | $79.00 | $79.00 | $79.00 | $86.11 |
| 48 | Install delineator assembly (D-SW)SZ 1(BRF)GF2(BI) (658-7019) | EACH | 19 | $48.00 | $25.00 | $40.00 | $30.00 | $30.00 | $30.00 | $32.70 |
| 49 | Work zone pavement marking non-removing (W)4"(solid) (662-7004) | LF | 2,684 | $1.00 | $1.00 | $0.70 | $0.55 | $3.10 | $0.55 | $1.09 |
| 50 | Work zone pavement marking non-removing (Y)4"(solid) (662-7035) | LF | 6,210 | $1.00 | $1.00 | $0.70 | $0.55 | $3.10 | $0.55 | $1.09 |
| 51 | Work zone pavement marking SHT terminal (tab)type Y-2 (662-7114) | EACH | 220 | $1.60 | $5.00 | $1.25 | $1.00 | $2.40 | $15.00 | $1.09 |
| 52 | Pavement sler 6" (666-7347) | LF | 140 | $1.50 | $1.00 | $1.25 | $1.00 | $3.80 | $1.00 | $2.18 |
| 53 | Reflectorized pavement marking type I (W)6"(solid)(100MIL) (666-7411) | LF | 140 | $2.50 | $5.00 | $5.00 | $4.00 | $3.80 | $4.00 | $2.18 |
| 54 | Reflectorized pavement marking type I (Y)6"(solid)(100MIL) (666-7423) | LF | 740 | $2.50 | $5.00 | $5.00 | $4.00 | $3.20 | $4.00 | $2.18 |
| 55 | Tree removal (18" - 24" diameter) (752-7007) | EACH | 54 | $150.00 | $370.00 | $750.00 | $565.00 | $413.00 | $1,210.00 | $615.85 |
| 56 | Post and cable fence (removal) (772-7001) | LF | 123 | $7.00 | $8.00 | $5.00 | $4.50 | $4.00 | $15.00 | $4.91 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from TxDOT's tabulation for this contract. TxDOT Bid Tabulations open-data export (data.texas.gov) from September 2024, read 21 November 2026, and TxDOT's legacy Tabulation of Bids pages for January 2020 to August 2024. The legacy pages are a large sample, not every contract: their file names were reused from year to year. Their district is the one TxDOT gives the county. Bids that did not match their published total are left out.
Every contract let that day: TxDOT letting of August 6, 2026. Compiled by Mirage Metrics.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.