Removing cement concrete curb, WSDOT
Low bidders on WSDOT contracts carried a median of $10.00 per LF for this item, from 16 MAR 2000 to 29 MAR 2023, across 70 low bids. Half of all 276 bids fell between $5.00 and $20.00.
- Owner
- Washington State DOT
- Item
- No code published
- Unit
- LF
- Data through
- 07 OCT 2026
WSDOT prints this item as “REMOVING CEMENT CONC. CURB”.
By year of letting
| Year | Contracts | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|---|
| 2000 | 1 | 1 | $5.00 | 2 | $3.50 |
| 2002 | 1 | 1 | $10.00 | 2 | $8.50 |
| 2003 | 4 | 4 | $1.95 | 10 | $2.25 |
| 2004 | 3 | 3 | $15.00 | 11 | $8.00 |
| 2005 | 2 | 2 | $3.55 | 11 | $4.00 |
| 2006 | 2 | 2 | $16.00 | 8 | $9.50 |
| 2007 | 6 | 6 | $5.50 | 25 | $6.20 |
| 2008 | 3 | 3 | $20.00 | 11 | $17.50 |
| 2009 | 2 | 2 | $4.00 | 8 | $8.72 |
| 2010 | 3 | 3 | $4.20 | 20 | $5.00 |
| 2011 | 5 | 5 | $12.00 | 24 | $9.00 |
| 2012 | 3 | 3 | $5.00 | 22 | $8.50 |
| 2013 | 3 | 3 | $20.00 | 12 | $37.50 |
| 2014 | 2 | 2 | $15.00 | 6 | $15.00 |
| 2015 | 4 | 4 | $5.49 | 11 | $10.00 |
| 2016 | 3 | 3 | $14.85 | 10 | $14.93 |
| 2017 | 4 | 4 | $13.00 | 21 | $11.00 |
| 2018 | 8 | 8 | $19.25 | 27 | $19.00 |
| 2019 | 2 | 2 | $17.50 | 6 | $13.93 |
| 2020 | 2 | 2 | $10.50 | 9 | $10.00 |
| 2021 | 2 | 2 | $19.25 | 5 | $20.00 |
| 2022 | 2 | 2 | $63.00 | 3 | $100.00 |
| 2023 | 3 | 3 | $15.00 | 12 | $20.00 |
Bid prices as published, not adjusted for inflation.
By region
| Region | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|
| NWR region | 20 | $13.00 | 98 | $8.62 |
| ER region | 24 | $5.99 | 74 | $7.47 |
| NCR region | 9 | $10.00 | 32 | $12.50 |
| SWR region | 6 | $9.75 | 29 | $9.50 |
| OR region | 6 | $17.43 | 27 | $20.00 |
| Region 9 | 3 | $15.00 | 8 | $28.07 |
Regions with at least three low bids, over all lettings.
By quantity
| Quantity (LF) | Low bids | Low-bid median |
|---|---|---|
| 6 to 56 | 17 | $15.00 |
| 57 to 136 | 18 | $12.50 |
| 138 to 345 | 17 | $5.00 |
| 371 to 5,554 | 18 | $6.75 |
The low bids split into four bands of equal count by the quantity on the contract. Larger quantities usually carry lower unit prices.
Who is lowest on this line
| Bidder | Lines bid | Lowest on the line |
|---|---|---|
| Poe Asphalt Paving, Inc. | 9 | 5 (56%) |
| Granite Construction Company | 16 | 4 (25%) |
| Wilder Construction Company | 8 | 4 (50%) |
| Lakeside Industries, Inc. | 12 | 3 (25%) |
| Scarsella Bros., Inc. | 8 | 2 (25%) |
| Shamrock Paving, Inc. | 7 | 2 (29%) |
The lowest unit price on each line, whoever won the contract, over all lettings in the data, for firms with five lines or more.
Latest contracts with this item
| Let | Contract | Region | Quantity | Low bidder's price | Median | Estimate | Bids | Low bidder | Source |
|---|---|---|---|---|---|---|---|---|---|
| 29 MAR 2023 | 009941 | OR region | 431 | $12.35 | $10.68 | $13.00 | 6 | Johansen Construction Company, | WSDOT |
| 29 MAR 2023 | 009953 | NCR region | 92 | $45.00 | $20.00 | $12.50 | 4 | M2 Industrial Inc. | WSDOT |
| 23 FEB 2023 | 009925 | ER region | 870 | $15.00 | $17.50 | $5.50 | 2 | Max J. Kuney Company | WSDOT |
| 23 MAR 2022 | 009784 | ER region | 637 | $26.00 | $26.00 | $7.50 | 1 | Central Washington Asphalt, In | WSDOT |
| 16 MAR 2022 | 009782 | Region 9 | 10 | $100.00 | $113.00 | $30.00 | 2 | Lakeside Industries, Inc. | WSDOT |
| 24 MAR 2021 | 009664 | SWR region | 4,834 | $9.50 | $11.00 | $10.00 | 3 | McDonald Excavating, Inc. | WSDOT |
| 18 FEB 2021 | 009650 | NWR region | 16 | $29.00 | $61.50 | $15.50 | 2 | Lakeside Industries, Inc. | WSDOT |
| 04 MAR 2020 | 009525 | NCR region | 136 | $10.00 | $15.00 | $15.00 | 4 | Frank Gurney, Inc. | WSDOT |
| 05 FEB 2020 | 009501 | NWR region | 2,107 | $11.00 | $9.00 | $20.00 | 5 | Titan Earthwork LLC | WSDOT |
| 20 MAR 2019 | 009407 | ER region | 144 | $25.00 | $25.00 | $10.00 | 3 | Central Washington Asphalt, In | WSDOT |
| 30 JAN 2019 | 009375 | ER region | 135 | $10.00 | $10.00 | $6.00 | 3 | CPM Development Corporation | WSDOT |
| 25 APR 2018 | 009265 | SWR region | 274 | $19.50 | $13.75 | $15.00 | 4 | Granite Construction Company | WSDOT |
| 11 APR 2018 | 009245 | NWR region | 18 | $50.00 | $36.00 | $15.00 | 5 | KLB Construction, Inc. | WSDOT |
| 11 APR 2018 | 009246 | NCR region | 42 | $15.00 | $17.50 | $14.00 | 4 | Coral Construction Company | WSDOT |
| 04 APR 2018 | 009239 | NWR region | 170 | $20.00 | $30.00 | $17.00 | 3 | Tucci & Sons, Inc. | WSDOT |
Filter this item by your own quantity, region and period, or check your price against it, in the WSDOT explorer.
How these prices were read
WSDOT bid tabulation PDFs, one per contract: 2026 tabulations from wsdot.wa.gov and the legacy Bid Check and Bid Tabulation reports of 1999 to 2023. 2000 to 2003 lettings use metric units. Only bids matching their published total are kept.
- Statistics leave out bids over three times the low bid, zero or negative prices and token prices under 5% of the median.
- Item codes and units are WSDOT's own: this item is compared with WSDOT contracts only.
- Prices are bid prices, not paid prices. Use them as a reference range, never as a quote.
- The data runs to the WSDOT letting of 07 OCT 2026 and was rebuilt on 26 NOV 2026.