Sacyr Construccion Sa: FDOT bid record
Sacyr Construccion Sa submitted 11 bids on Florida DOT contracts in the data, from 31 JAN 2018 to 24 SEP 2025, and was the low bidder on 3 of them (27%). When it was not low, its total sat a median +11% above the low bid.
- Owner
- Florida DOT
- Low bid volume
- $362,964,654
- Latest bid
- 24 SEP 2025
- Data through
- 28 OCT 2026
By year
| Year | Bids | Low bids | Win rate |
|---|---|---|---|
| 2018 | 6 | 2 | 33% |
| 2019 | 1 | 0 | 0% |
| 2021 | 1 | 1 | 100% |
| 2024 | 1 | 0 | 0% |
| 2025 | 2 | 0 | 0% |
By district
| District | Bids | Low bids | Win rate |
|---|---|---|---|
| District 2 | 5 | 1 | 20% |
| District 1 | 3 | 2 | 67% |
| District 4 | 2 | 0 | 0% |
| District 6 | 1 | 0 | 0% |
Pay items where it is most often lowest
A line counts when the firm priced it and at least one other bidder did too; the lowest unit price on the line counts whoever won the contract. Token prices and bids over three times the low bid are left out.
Who it meets most
| Firm | Contracts in common | That firm ranked ahead |
|---|---|---|
| Prince Contracting, LLC. | 6 | 0 of 6 |
| Superior Construction Company Southeast, LLC | 4 | 1 of 4 |
| Watson Civil Construction, Inc. | 4 | 1 of 4 |
| Ranger Construction Industries, Inc. | 3 | 3 of 3 |
| Community Asphalt Corp. | 3 | 2 of 3 |
| Anderson Columbia Co., Inc. | 3 | 1 of 3 |
| Lane Construction Corporation (the) | 3 | 0 of 3 |
| Ajax Paving Industries of Florida LLC | 3 | 1 of 3 |
| Bergeron Land Development, Inc | 2 | 1 of 2 |
| Condotte America, Inc. | 2 | 1 of 2 |
Latest bids
| Let | Contract | District | Project | Rank | Its bid | Against the low bid |
|---|---|---|---|---|---|---|
| 24 SEP 2025 | T2A24 | District 2 | SR 23 (FIRST COAST XWAY) FROM SR 9 (I-95) TO E OF CR 2209 | 2 of 8 | $210,019,944 | +2.0% |
| 28 MAY 2025 | T1926 | District 1 | SR 93 (I-75) AT CR 876 (DANIELS PKWY) | 5 of 5 | $50,947,532 | +19% |
| 25 SEP 2024 | T2987 | District 2 | SR 23 (FIRST COAST XWAY) FROM E OF CR 2209 TO E OF CR 16A | 3 of 4 | $269,684,875 | +11% |
| 31 MAR 2021 | T1783 | District 1 | SR 93 (I-75) | 1 of 7 | $52,688,829 | Low, 5.0% under the second |
| 25 SEP 2019 | T2736 | District 2 | SR 20 | 3 of 6 | $59,610,528 | +21% |
| 05 DEC 2018 | T2724 | District 2 | SR 23 (FIRST COAST EXPRESSWAY) | 2 of 8 | $181,990,234 | +2.0% |
| 31 OCT 2018 | T2717 | District 2 | SR 23 (FIRST COAST EXPRESSWAY) | 1 of 6 | $229,435,652 | Low, 6.0% under the second |
| 23 MAY 2018 | T1709 | District 1 | SR 93 (I-75) | 1 of 4 | $80,840,173 | Low, 5.0% under the second |
| 23 MAY 2018 | T6422 | District 6 | SR 997 (KROME AVE) (SW 177TH AVE) | 9 of 9 | $44,480,877 | +19% |
| 25 APR 2018 | T4459 | District 4 | SR 7 | 3 of 8 | $54,361,919 | +10% |
| 31 JAN 2018 | T4472 | District 4 | SR 80 (US 98/US 441/SOUTHERN BLVD) | 5 of 7 | $35,936,735 | +8.0% |
How this record was read
FDOT Tabulation of Bids PDFs from its central office lettings, January 2018 to October 2026, all pay items. On A+B contracts the cost part is kept (the total the pay items add up to). Bidders listed without a rank or total are left out.
- Every bid counted here matched its published total to within one dollar; FDOT's rank decides who was low.
- The gap to the low bid is the firm's total over the low total, minus one, on contracts it did not win, leaving out bids over three times the low bid.
- A record covers the lettings in the data, not every contract the firm ever bid. Coverage by year is on the state page.
A name split in two, or a figure that does not match the owner's tabulation? Write to mehdi@miragemetrics.com and we correct it.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.