FDOT contract T2A24 bid tabulation
SR 23 (FIRST COAST XWAY) FROM SR 9 (I-95) TO E OF CR 2209. Let by Florida DOT on September 24, 2025, St Johns, District 2. 8 bids received; low bid $205,250,003 by Mastec Civil LLC.
- Owner
- Florida DOT
- Letting
- 24 SEP 2025
- Pay items
- 325
- Data through
- 28 OCT 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | Mastec Civil LLC | $205,250,003 | Low |
| 2 | Sacyr Construccion Sa | $210,019,944 | +2.0% |
| 3 | Superior Construction Company Southeast, LLC | $216,496,489 | +5.0% |
| 4 | Webber, LLC | $223,726,671 | +9.0% |
| 5 | De Moya Asphalt Joint Venture | $229,507,821 | +12% |
| 6 | Hubbard Construction Company | $243,407,591 | +19% |
| 7 | Watson Civil Construction, Inc. | $256,756,324 | +25% |
| 8 | Coxwell, J.B. Contracting, Inc. | $263,463,042 | +28% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Mastec Civil LLC | 2. Sacyr Construccion Sa | 3. Superior Construction Company Southeast, LLC | 4. Webber, LLC | 5. De Moya Asphalt Joint Venture | 6. Hubbard Construction Company |
|---|---|---|---|---|---|---|---|---|---|
| 0005 | Removal of existing structures/bridges (0110-3) | SF | 1 | $175,000 | $168,700 | $200,000 | $63,500 | $150,000 | $90,000 |
| 0010 | Removal of existing structures/bridges (0110-3) | SF | 1 | $175,000 | $168,700 | $200,000 | $63,900 | $150,000 | $80,000 |
| 0015 | Concrete, class I (seal) (0400-1-30) | CY | 364.10 | $2,100.00 | $1,700.00 | $1.00 | $401.00 | $100.00 | $723.13 |
| 0020 | Conc class II, bridge superstructure (0400-2-4) | CY | 6,105.10 | $875.00 | $900.00 | $1,400.00 | $792.00 | $2,000.00 | $805.20 |
| 0025 | Concrete class II, approach slabs (0400-2-10) | CY | 690.50 | $780.00 | $810.00 | $1,400.00 | $470.00 | $2,000.00 | $423.48 |
| 0030 | Concrete class IV, culverts (0400-4-1) | CY | 1,537 | $1,200.00 | $1,100.00 | $1,900.00 | $1,280.00 | $1,400.00 | $1,397.91 |
| 0035 | Concrete class IV, bridge substructure (0400-4-5) | CY | 346 | $1,330.00 | $1,400.00 | $3,400.00 | $1,570.00 | $2,000.00 | $1,574.32 |
| 0040 | Concrete class IV, mass, substructure (0400-4-25) | CY | 2,055.30 | $1,485.00 | $1,200.00 | $2,100.00 | $1,470.00 | $2,000.00 | $1,049.84 |
| 0045 | Bridge deck grooving (0400-7-1) | SY | 21,540 | $8.75 | $6.50 | $6.00 | $2.70 | $6.00 | $5.05 |
| 0050 | Concrete class V, bridge substructure (0400-8-5) | CY | 223.50 | $1,330.00 | $1,500.00 | $4,600.00 | $2,130.00 | $2,200.00 | $1,848.23 |
| 0055 | Conc class V mass - substructure (0400-8-25) | CY | 4,321.40 | $1,290.00 | $1,000.00 | $2,200.00 | $1,130.00 | $2,000.00 | $1,066.81 |
| 0060 | Bridge deck planing (0400-9-1) | SY | 21,540 | $5.80 | $6.50 | $6.00 | $6.05 | $6.00 | $5.05 |
| 0065 | Composite neoprene pads (0400-147) | CF | 144.80 | $945.00 | $2,100.00 | $1,200.00 | $1,630.00 | $1,000.00 | $1,427.44 |
| 0070 | Reinforcing steel- roadway (0415-1-1) | LB | 271,950 | $1.65 | $1.40 | $0.10 | $1.70 | $0.01 | $1.58 |
| 0075 | Reinforcing steel - bridge superstructure (0415-1-4) | LB | 1,128,927 | $1.35 | $1.30 | $1.35 | $1.20 | $1.38 | $1.13 |
| 0080 | Reinforcing steel- bridge substructure (0415-1-5) | LB | 1,427,593 | $1.50 | $1.30 | $1.35 | $1.30 | $1.24 | $1.29 |
| 0085 | Reinforcing steel- approach slabs (0415-1-9) | LB | 132,405 | $1.35 | $1.30 | $1.35 | $1.20 | $1.33 | $1.15 |
| 0090 | Prest beams: florida-I beam 45" (0450-2-45) | LF | 10,863 | $285.94 | $300.00 | $300.00 | $256.00 | $450.00 | $256.00 |
| 0095 | Prest beams: florida-I beam 54" (0450-2-54) | LF | 586 | $380.23 | $360.00 | $350.00 | $365.00 | $400.00 | $342.62 |
| 0100 | Prest beams: florida-I beam 63" (0450-2-63) | LF | 8,636 | $316.50 | $360.00 | $400.00 | $311.00 | $400.00 | $314.80 |
| 0105 | Prest beams: florida-I beam 72" (0450-2-72) | LF | 2,602 | $319.50 | $360.00 | $450.00 | $300.00 | $425.00 | $367.17 |
| 0110 | Preformed pile holes, 36" to 43" drill/punch size (0455-15-16) | LF | 1,508 | $79.50 | $130.00 | $160.00 | $143.00 | $100.00 | $28.20 |
| 0115 | Preformed pile holes casing, to 43" drill/punch size (0455-15-26) | LF | 1,508 | $200.00 | $250.00 | $185.00 | $243.00 | $100.00 | $245.90 |
| 0120 | Pre-planned pile splice, concrete square, 24" (0455-17124) | EACH | 29 | $5,000.00 | $7,300.00 | $900.00 | $2,060.00 | $1.00 | $6,324.19 |
| 0125 | Pile inspection, driven pile (0455-20-1) | EACH | 444 | $530.00 | $1,200.00 | $1,000.00 | $280.00 | $1,600.00 | $398.78 |
| 0130 | Prestressed concrete piling, SQ (0455-34-5) | LF | 31,780 | $161.93 | $165.00 | $185.00 | $208.00 | $150.00 | $155.55 |
| 0135 | Pile redrive (0455-115) | EACH | 338 | $3,850.00 | $500.00 | $500.00 | $949.00 | $2,500.00 | $2,607.77 |
| 0140 | Load test (dynamic), data collection and analysis (0455-137) | EACH | 444 | $1,085.00 | $830.00 | $1,000.00 | $1,240.00 | $1,800.00 | $1,330.00 |
| 0145 | Load test (dynamic), test (0455-137-2) | EACH | 43 | $3,860.00 | $3,600.00 | $1,000.00 | $5,000.00 | $5,000.00 | $3,707.77 |
| 0150 | Test piles-prestressed concrete,24" SQ (0455-143-5) | LF | 4,495 | $400.00 | $400.00 | $500.00 | $378.00 | $375.00 | $246.23 |
| 0155 | Bridge deck expansion joint, construction, F&I poured joint with backer rod (0458-1-11) | LF | 1,565 | $82.75 | $39.00 | $55.00 | $73.25 | $100.00 | $72.19 |
| 0160 | Piles, polyethylene sheeting (0459-71) | SY | 1,406 | $13.15 | $17.00 | $5.00 | $10.10 | $10.00 | $8.70 |
| 0165 | Post tensioning tendons, substructure strand flexible filler (0462-2-23) | LB | 173,154 | $5.60 | $10.00 | $12.00 | $7.15 | $4.60 | $11.44 |
| 0170 | Concrete traffic railing- 36" single-slope (0521-5-13) | LF | 4,054 | $125.00 | $110.00 | $135.00 | $65.00 | $130.00 | $115.08 |
| 0175 | Concrete traffic railing- 42" single-slope (0521-5-14) | LF | 4,335 | $125.00 | $150.00 | $150.00 | $90.00 | $150.00 | $155.79 |
| 0180 | Concrete slope pavement,non reinforced, 4" (0524-2-2) | SY | 3,846 | $80.00 | $89.00 | $200.00 | $80.00 | $120.00 | $123.91 |
| 0185 | Riprap, sand-cement bags (0530-1100) | CY | 77.50 | $1,070.00 | $1,100.00 | $850.00 | $937.00 | $1,500.00 | $692.03 |
| 0190 | Riprap- rubble, bank and shore (0530-3-3) | TN | 4,045 | $155.00 | $120.00 | $130.00 | $124.00 | $125.00 | $150.60 |
| 0195 | Bedding stone (0530-74) | TN | 1,500 | $145.00 | $130.00 | $145.00 | $77.00 | $165.00 | $175.67 |
| 0200 | Conduit, furnish & install, embedded concrete barriers and traffic railings (0630-2-16) | LF | 25,169 | $8.25 | $16.00 | $16.00 | $16.10 | $9.00 | $10.54 |
| 0205 | Junction box, furnish & install, embedded (0635-3-13) | EACH | 120 | $715.00 | $1,200.00 | $985.00 | $994.00 | $775.00 | $1,201.49 |
| 0210 | Mobilization (0101-1) | LS | 1 | $20,500,000 | $20,202,000 | $21,741,330 | $22,300,000 | $22,850,000 | $24,300,000 |
| 0215 | Maintenance of traffic (0102-1) | DA | 1 | $1,600,000 | $4,000,000 | $1,000,000 | $4,558,100 | $6,000,000 | $20,950,000 |
| 0220 | Special detour- temporary pavement (0102-2200) | SY | 1 | $4,620,000 | $4,500,000 | $5,500,000 | $5,022,000 | $15,000,000 | $15,000,000 |
| 0225 | Special detour- temporary earthwork/base (0102-2300) | CY | 1 | $3,925,000 | $4,000,000 | $5,500,000 | $8,541,700 | $10,000,000 | $3,000,000 |
| 0230 | Traffic control officer (0102-14) | HR | 702 | $100.00 | $110.00 | $100.00 | $101.00 | $100.00 | $170.00 |
| 0235 | Work zone sign (0102-60) | ED | 84,164 | $0.20 | $0.20 | $0.20 | $0.20 | $0.17 | $0.17 |
| 0240 | Barrier mounted work zone sign- index 700-013 (0102-62-13) | ED | 4,160 | $0.45 | $0.50 | $0.30 | $0.40 | $0.30 | $0.31 |
| 0244 | Temporary barrier, F&I, anchored (0102-71-15) | LF | 3,838 | $39.00 | $47.00 | $75.00 | $39.00 | $38.95 | $44.54 |
| 0245 | Temporary barrier, F&I, free standing (0102-71-16) | LF | 23,608 | $25.00 | $30.00 | $70.00 | $25.00 | $24.95 | $42.88 |
| 0250 | Temporary barrier, relocate, free standing (0102-71-26) | LF | 67,829 | $9.65 | $12.00 | $21.00 | $9.50 | $9.50 | $18.57 |
| 0255 | Channelizing device- types I, II, VP, drum, or LCD (0102-74-1) | ED | 262,990 | $0.10 | $0.10 | $0.10 | $0.10 | $0.09 | $0.09 |
| 0260 | Arrow board / advance warning arrow panel (0102-76) | ED | 80 | $6.30 | $7.00 | $250.00 | $6.00 | $25.00 | $5.10 |
| 0265 | Temporary crash cushion, redirective option (0102-89-1) | LO | 34 | $2,600.00 | $1,200.00 | $1,700.00 | $975.00 | $2,200.00 | $867.35 |
| 0270 | Portable changeable message sign, temporary (0102-99) | ED | 6,776 | $9.45 | $11.00 | $25.00 | $9.00 | $8.50 | $8.67 |
| 0275 | Type III barricade (0102-115) | ED | 10,638 | $0.25 | $0.30 | $0.20 | $0.25 | $0.20 | $0.20 |
| 0277 | Portable regulatory, sign (0102-150-1) | ED | 128 | $5.25 | $9.50 | $150.00 | $4.20 | $4.00 | $4.08 |
| 0278 | Radar speed display unit (0102-150-2) | ED | 128 | $5.25 | $9.50 | $150.00 | $4.20 | $4.00 | $4.08 |
| 0280 | Temporary work structure (0103-1100) | LS | 1 | $4,200,000 | $5,000,000 | $2,000,000 | $6,752,400 | $250,000 | $3,000,000 |
| 0285 | Artificial coverings /rolled erosion control products (0104-1) | SY | 6,801 | $4.20 | $1.80 | $10.00 | $1.45 | $5.00 | $2.60 |
| 0290 | Sediment barrier (0104-10-3) | LF | 24,678 | $6.00 | $1.70 | $12.00 | $1.10 | $3.00 | $1.77 |
| 0295 | Floating turbidity barrier (0104-11) | LF | 6,013 | $16.65 | $18.00 | $18.00 | $15.10 | $18.00 | $12.50 |
| 0300 | Staked turbidity barrier- nylon reinforced PVC (0104-12) | LF | 16,362 | $11.00 | $6.50 | $17.00 | $5.25 | $8.00 | $5.00 |
| 0305 | Soil tracking prevention device (0104-15) | EACH | 4 | $8,250.00 | $9,000.00 | $12,500 | $2,620.00 | $4,000.00 | $4,200.00 |
| 0310 | Inlet protection system (0104-18) | EACH | 18 | $295.00 | $150.00 | $395.00 | $125.00 | $200.00 | $125.00 |
| 0315 | Litter removal (0107-1) | ACRE | 9,177.48 | $1.00 | $20.00 | $1.00 | $79.25 | $35.00 | $50.00 |
| 0320 | Mowing (0107-2) | ACRE | 7,561.22 | $1.00 | $35.00 | $1.00 | $118.00 | $35.00 | $60.00 |
| 0325 | Clearing & grubbing (0110-1-1) | ACRE | 1 | $6,200,000 | $8,000,000 | $20,975,576 | $32,293,329 | $17,000,000 | $5,900,000 |
| 0330 | Removal of existing concrete (0110-4-10) | SY | 33 | $180.00 | $200.00 | $125.00 | $388.00 | $100.00 | $64.60 |
| 0335 | Regular excavation (0120-1) | CY | 389,755.50 | $4.00 | $6.00 | $8.00 | $4.85 | $10.00 | $6.90 |
| 0340 | Subsoil excavation (0120-4) | CY | 98,261.70 | $20.00 | $15.00 | $20.00 | $9.95 | $20.00 | $30.08 |
| 0345 | Embankment (0120-6) | CY | 1,849,295.40 | $20.00 | $20.00 | $10.00 | $17.00 | $12.00 | $25.36 |
| 0350 | Surcharge embankment (0120-74) | CY | 54,389.30 | $3.50 | $46.00 | $17.00 | $5.85 | $20.00 | $14.54 |
| 0355 | Settlement plate assembly (0141-70) | AS | 54 | $2,100.00 | $2,300.00 | $1,000.00 | $2,960.00 | $1,500.00 | $1,250.00 |
| 0360 | Type B stabilization (0160-4) | SY | 229,323 | $7.25 | $12.00 | $5.00 | $3.60 | $2.00 | $4.06 |
| 0365 | Optional base, base group 01 (0285-701) | SY | 4,981 | $14.65 | $22.00 | $21.00 | $11.00 | $15.00 | $11.74 |
| 0370 | Optional base, base group 04 (0285-704) | SY | 17,912 | $16.00 | $24.00 | $21.00 | $12.90 | $22.00 | $15.50 |
| 0375 | Optional base, base group 06 (0285-706) | SY | 54,012 | $21.45 | $25.00 | $24.00 | $15.70 | $24.00 | $18.84 |
| 0380 | Optional base, base group 07 (0285-707) | SY | 3,515 | $52.75 | $59.00 | $47.00 | $56.25 | $50.00 | $66.14 |
| 0385 | Optional base, base group 09 (0285-709) | SY | 43,224 | $24.28 | $31.00 | $30.00 | $20.60 | $26.00 | $23.16 |
| 0390 | Optional base, base group 10 (0285-710) | SY | 53,570 | $25.10 | $32.00 | $29.00 | $21.40 | $28.00 | $23.86 |
| 0395 | Optional base, base group 12 (0285-712) | SY | 28,667 | $31.80 | $37.00 | $34.00 | $24.30 | $30.00 | $26.68 |
| 0400 | Optional base, base group 13 (0285-713) | SY | 8,055 | $87.75 | $98.00 | $79.00 | $83.50 | $80.00 | $87.64 |
| 0405 | Milling existing asphalt pavement, 3" avg depth (0327-70-4) | SY | 24,161 | $3.30 | $3.70 | $3.00 | $5.15 | $3.00 | $7.20 |
| 0410 | Milling existing asphalt pavement, 1 3/4" avg depth (0327-70-13) | SY | 24,689 | $2.75 | $3.10 | $3.00 | $4.50 | $3.00 | $6.15 |
| 0415 | Milling existing asphalt pavement, 3 3/4" avg depth (0327-70-20) | SY | 45,610 | $4.35 | $5.00 | $4.00 | $6.30 | $4.00 | $9.75 |
| 0420 | Superpave asphaltic conc, traffic C (0334-1-13) | TN | 15,191 | $164.05 | $160.00 | $150.00 | $150.00 | $150.00 | $230.90 |
| 0425 | Superpave asphaltic conc, traffic E (0334-1-15) | TN | 25,033.40 | $173.42 | $160.00 | $145.00 | $145.00 | $145.00 | $175.40 |
| 0430 | Superpave asphaltic concrete, traffic C, PG76-22 (0334-1-53) | TN | 1,152.50 | $227.55 | $220.00 | $210.00 | $200.00 | $210.00 | $237.20 |
| 0435 | Superpave asphaltic concrete, traffic E, PG76-22 (0334-1-55) | TN | 33,456.40 | $216.50 | $190.00 | $180.00 | $175.00 | $180.00 | $214.80 |
| 0440 | Asphalt concrete friction course, inc bit, FC-5, PG 76-22 (0337-7-25) | TN | 8,117.30 | $353.10 | $310.00 | $295.00 | $295.00 | $295.00 | $337.30 |
| 0445 | Asphalt concrete friction course,traffic C, FC-12.5, PG (0337-7-83) | TN | 690.30 | $271.00 | $260.00 | $250.00 | $250.00 | $250.00 | $223.30 |
| 0450 | Miscellaneous asphalt (0339-1) | TN | 1,735.90 | $486.00 | $450.00 | $475.00 | $366.00 | $360.00 | $380.60 |
| 0455 | Concrete class NS, gravity index 400-011 (0400-0-11) | CY | 3 | $1,670.00 | $1,700.00 | $4,300.00 | $4,930.00 | $2,000.00 | $2,329.10 |
| 0460 | Concrete class IV, culverts (0400-4-1) | CY | 858 | $2,435.00 | $1,600.00 | $1,900.00 | $1,350.00 | $1,400.00 | $1,490.56 |
| 0465 | Reinforcing steel- roadway (0415-1-1) | LB | 137,250 | $1.75 | $1.40 | $0.10 | $1.70 | $0.01 | $1.58 |
| 0470 | Inlets, DT bot, type B, <10' (0425-1511) | EACH | 46 | $12,000 | $9,500.00 | $9,100.00 | $8,230.00 | $8,500.00 | $8,380.82 |
| 0475 | Inlets, DT bot, type B, >10' (0425-1512) | EACH | 4 | $16,200 | $11,200 | $11,600 | $9,290.00 | $13,000 | $12,675 |
| 0480 | Inlets, DT bot, type B, J bot, <10' (0425-1513) | EACH | 3 | $15,400 | $12,600 | $12,000 | $9,640.00 | $10,000 | $12,647 |
| 0485 | Inlets, DT bot, type B, J bot, >10' (0425-1514) | EACH | 12 | $22,000 | $17,900 | $14,600 | $14,440 | $13,000 | $17,147 |
| 0490 | Inlets, DT bot, type D, modify (0425-1549) | EACH | 1 | $16,400 | $14,000 | $12,600 | $10,750 | $10,000 | $11,027 |
| 0495 | Inlets, gutter, type S, <10' (0425-1701) | EACH | 49 | $7,500.00 | $8,800.00 | $6,400.00 | $7,450.00 | $6,500.00 | $5,615.67 |
| 0500 | Inlets, gutter, type S, >10' (0425-1702) | EACH | 8 | $11,300 | $11,200 | $8,800.00 | $9,090.00 | $8,500.00 | $9,245.18 |
| 0505 | Inlets, gutter, type S, J bottom <10' (0425-1703) | EACH | 2 | $10,650 | $11,700 | $8,800.00 | $9,060.00 | $13,000 | $9,128.85 |
| 0510 | Inlets, gutter, type S, J bottom, >10' (0425-1704) | EACH | 7 | $15,200 | $18,000 | $11,400 | $13,400 | $18,000 | $14,190 |
| 0515 | Inlets, gutter, type V, <10' (0425-1711) | EACH | 5 | $8,500.00 | $10,100 | $7,800.00 | $8,270.00 | $8,500.00 | $5,404.13 |
| 0520 | Inlets, gutter, type V, J bottom, >10' (0425-1714) | EACH | 2 | $19,650 | $16,400 | $15,000 | $12,200 | $13,000 | $12,674 |
| 0525 | Inlets, adjacent barrier, <=10' (0425-1921) | EACH | 25 | $8,900.00 | $11,000 | $8,000.00 | $7,910.00 | $8,500.00 | $7,861.29 |
| 0530 | Inlets, adjacent barrier, >10' (0425-1922) | EACH | 1 | $41,650 | $15,400 | $35,000 | $11,300 | $18,000 | $27,641 |
| 0535 | Inlets, adjacent barrier, J bottom, < 10' (0425-1923) | EACH | 7 | $10,850 | $13,800 | $9,400.00 | $8,990.00 | $13,000 | $10,010 |
| 0540 | Inlets, adjacent barrier, J bottom, >10' (0425-1924) | EACH | 1 | $18,300 | $12,400 | $17,500 | $11,300 | $25,000 | $16,270 |
| 0545 | Manholes, J-8, <10' (0425-2-91) | EACH | 6 | $12,750 | $14,500 | $11,000 | $9,830.00 | $13,000 | $9,197.86 |
| 0550 | Manholes, J-8, >10' (0425-2-92) | EACH | 9 | $27,200 | $17,100 | $15,800 | $11,810 | $18,000 | $13,360 |
| 0555 | Junction box, drainage, P-7, partial (0425-3-43) | EACH | 2 | $4,900.00 | $7,200.00 | $3,700.00 | $3,480.00 | $8,000.00 | $4,221.98 |
| 0560 | Pipe culvert optional material, round, 18", gutter drain (0430-173118) | LF | 312 | $200.00 | $140.00 | $148.00 | $96.50 | $160.00 | $163.68 |
| 0565 | Pipe culvert optional material, round, 24", gutter drain (0430-173124) | LF | 159 | $210.00 | $180.00 | $154.00 | $132.00 | $160.00 | $195.28 |
| 0570 | Pipe culvert, optional material, round, 30"SD (0430-174130) | LF | 95 | $240.00 | $280.00 | $189.00 | $155.00 | $170.00 | $216.12 |
| 0575 | Pipe culvert, optional material, round, 36"SD (0430-174136) | LF | 103 | $290.00 | $320.00 | $222.00 | $179.00 | $190.00 | $251.96 |
| 0580 | Pipe culvert,optional material,round, 18"S/CD (0430-175118) | LF | 8,529 | $110.00 | $120.00 | $91.00 | $94.75 | $110.00 | $105.50 |
| 0585 | Pipe culvert,optional material,round, 24"S/CD (0430-175124) | LF | 3,306 | $143.00 | $180.00 | $108.00 | $108.00 | $125.00 | $123.65 |
| 0590 | Pipe culvert, opt material, round, 30"S/CD (0430-175130) | LF | 2,559 | $192.00 | $250.00 | $152.00 | $151.00 | $150.00 | $185.60 |
| 0595 | Pipe culvert, opt material, round, 36"S/CD (0430-175136) | LF | 1,203 | $240.00 | $340.00 | $200.00 | $179.00 | $170.00 | $267.31 |
| 0600 | Pipe culvert, opt material, round, 42"S/CD (0430-175142) | LF | 1,451 | $260.00 | $390.00 | $232.00 | $214.00 | $220.00 | $260.10 |
| 0605 | Pipe culvert, opt material, round, 48"S/CD (0430-175148) | LF | 3,517 | $340.00 | $360.00 | $278.00 | $250.00 | $250.00 | $311.63 |
| 0610 | Pipe culvert, opt material, round, 54"S/CD (0430-175154) | LF | 1,483 | $595.00 | $570.00 | $400.00 | $391.00 | $340.00 | $651.88 |
| 0615 | Pipe culvert, opt material, round, 60"S/CD (0430-175160) | LF | 1,534 | $525.00 | $550.00 | $377.00 | $333.00 | $450.00 | $470.03 |
| 0620 | Pipe culvert,optional material,round, jack & bore, 30", storm and cross drain (0430-185130) | LF | 92 | $2,220.00 | $1,100.00 | $1,500.00 | $1,190.00 | $800.00 | $1,324.54 |
| 0625 | Pipe culvert,optional material,round, jack & bore, 48", storm and cross drain (0430-185148) | LF | 147 | $6,500.00 | $1,600.00 | $1,800.00 | $1,580.00 | $1,300.00 | $1,428.91 |
| 0630 | Pipe culvert,optional material,round, jack & bore, 66" storm and cross drain (0430-185166) | LF | 184 | $8,175.00 | $5,000.00 | $2,700.00 | $2,360.00 | $4,000.00 | $4,388.25 |
| 0635 | Straight concrete endwalls, single, 0 degrees, round (0430-518100) | EACH | 1 | $3,000.00 | $4,600.00 | $4,700.00 | $7,950.00 | $4,000.00 | $3,042.40 |
| 0640 | Straight concrete endwalls, single, 0 degrees, round (0430-524100) | EACH | 2 | $4,350.00 | $5,000.00 | $5,400.00 | $8,520.00 | $6,500.00 | $4,121.22 |
| 0645 | Straight concrete endwalls, single, 0 degrees, round (0430-530100) | EACH | 1 | $5,650.00 | $6,300.00 | $5,800.00 | $9,120.00 | $8,000.00 | $6,809.08 |
| 0650 | Straight concrete endwalls, single, 30 degrees, round (0430-530120) | EACH | 3 | $5,650.00 | $6,600.00 | $5,800.00 | $9,120.00 | $8,000.00 | $5,869.13 |
| 0655 | U-endwall, index 261/430-011, baffles, 1:6 slope, 18"pipe (0430-611025) | EACH | 1 | $3,200.00 | $6,500.00 | $5,000.00 | $4,630.00 | $3,500.00 | $3,564.30 |
| 0660 | U-endwall with baffles, index 261/430-011, 1:4 slope, 18"pipe (0430-611125) | EACH | 2 | $3,200.00 | $5,800.00 | $4,600.00 | $3,970.00 | $3,500.00 | $3,564.30 |
| 0665 | U-endwall, with baffles & index 261/430-011,1:6 slope, 24"pipe (0430-613029) | EACH | 1 | $4,250.00 | $6,600.00 | $6,300.00 | $5,430.00 | $6,500.00 | $9,962.53 |
| 0670 | Pipe filling and plugging- place out of service (0430-830) | CY | 5.50 | $1,000.00 | $900.00 | $1,000.00 | $512.00 | $1,000.00 | $2,027.66 |
| 0675 | Mitered end section, optional round, 18" CD (0430-982125) | EACH | 19 | $7,900.00 | $3,100.00 | $4,400.00 | $2,530.00 | $2,500.00 | $2,146.71 |
| 0680 | Mitered end section, optional round, 24" CD (0430-982129) | EACH | 4 | $7,900.00 | $3,400.00 | $6,100.00 | $2,830.00 | $3,000.00 | $2,878.79 |
| 0685 | Mitered end section, optional round, 30" CD (0430-982133) | EACH | 3 | $10,750 | $5,600.00 | $7,300.00 | $4,500.00 | $6,000.00 | $4,686.09 |
| 0690 | Mitered end section, optional round, 36" CD (0430-982138) | EACH | 2 | $8,750.00 | $6,500.00 | $7,800.00 | $5,600.00 | $6,500.00 | $5,923.70 |
| 0695 | Mitered end section, optional round, 42" CD (0430-982140) | EACH | 1 | $10,500 | $7,100.00 | $17,000 | $6,520.00 | $8,000.00 | $7,818.68 |
| 0700 | Mitered end section, optional round, 48" CD (0430-982141) | EACH | 8 | $13,500 | $8,400.00 | $18,000 | $7,630.00 | $10,000 | $8,641.34 |
| 0705 | Mitered end section, optional round, 54" CD (0430-982142) | EACH | 1 | $17,250 | $13,500 | $37,000 | $12,220 | $13,000 | $13,301 |
| 0710 | Mitered end section, optional round, 60" CD (0430-982143) | EACH | 1 | $23,750 | $15,700 | $26,000 | $14,630 | $18,000 | $15,584 |
| 0715 | Mitered end section , optional round, 30" SD (0430-984133) | EACH | 2 | $9,950.00 | $8,900.00 | $8,500.00 | $4,610.00 | $6,000.00 | $7,638.41 |
| 0720 | Mitered end section , optional round, 36" side drain (0430-984138) | EACH | 2 | $12,500 | $10,900 | $10,500 | $5,710.00 | $6,000.00 | $9,698.13 |
| 0725 | Concrete curb, toll header curb (0520-2-10) | LF | 200 | $45.00 | $45.00 | $51.00 | $50.00 | $37.00 | $32.87 |
| 0730 | Shoulder gutter- concrete (0520-6) | LF | 12,917 | $40.00 | $43.00 | $36.00 | $45.00 | $33.00 | $29.43 |
| 0735 | Median concrete barrier, grade-separated (0521-1-12) | LF | 2,457 | $220.00 | $260.00 | $290.00 | $210.00 | $400.00 | $191.44 |
| 0740 | Concrete barrier, with slab, 36" single slope (0521-8-7) | LF | 4,750 | $525.00 | $320.00 | $440.00 | $350.00 | $400.00 | $507.01 |
| 0745 | Opaque visual barrier, index 010 concrete (0521-9-1) | LF | 2,457 | $70.00 | $110.00 | $96.00 | $60.00 | $80.00 | $63.47 |
| 0750 | Shoulder concrete barrier, 38" or 44" height (0521-72-40) | LF | 3,001 | $350.00 | $360.00 | $545.00 | $515.00 | $370.00 | $326.64 |
| 0755 | Shoulder concrete barrier, 38" wall shielding barrier (0521-72-60) | LF | 76 | $365.00 | $220.00 | $405.00 | $435.00 | $150.00 | $947.81 |
| 0760 | Concrete sidewalk and driveways, 6" thick (0522-2) | SY | 221 | $88.00 | $110.00 | $110.00 | $210.00 | $75.00 | $68.66 |
| 0765 | Concrete ditch pavt, non reinforced, 3" (0524-1-1) | SY | 7,782 | $76.50 | $80.00 | $108.00 | $80.00 | $77.00 | $70.73 |
| 0770 | Riprap- rubble, bank and shore (0530-3-3) | TN | 1,070.30 | $155.00 | $150.00 | $130.00 | $143.00 | $125.00 | $157.70 |
| 0775 | Riprap, rubble, F&I, ditch lining (0530-3-4) | TN | 235.40 | $155.00 | $94.00 | $240.00 | $331.00 | $125.00 | $193.24 |
| 0780 | Bedding stone (0530-74) | TN | 567.50 | $145.00 | $130.00 | $215.00 | $135.00 | $125.00 | $197.28 |
| 0785 | Sound/noise barrier-inc foundation, permanent (0534-72101) | SF | 110,952 | $50.35 | $52.00 | $65.00 | $42.50 | $60.00 | $61.55 |
| 0790 | Guardrail -roadway, general (0536-1-1) | LF | 8,763 | $23.50 | $27.00 | $22.00 | $21.90 | $22.00 | $25.00 |
| 0795 | Guardrail- roadway, double (0536-1-3) | LF | 11,510 | $36.20 | $42.00 | $34.00 | $33.75 | $34.00 | $35.00 |
| 0800 | Rub rail for guardrail, single sided rub rail (0536-5-1) | LF | 11,412 | $13.65 | $16.00 | $12.75 | $12.80 | $13.00 | $15.00 |
| 0805 | Guardrail transition to rigid barrier, F&I- index 536- 001, approach TL-3 (0536-8112) | EACH | 19 | $3,280.00 | $3,800.00 | $3,100.00 | $3,060.00 | $3,100.00 | $3,000.00 |
| 0810 | Guardrail transition to rigid barrier, F&I- index 536- 001, trailing (0536-8113) | EACH | 6 | $1,245.00 | $1,400.00 | $1,200.00 | $1,160.00 | $1,200.00 | $2,000.00 |
| 0815 | Guardrail removal (0536-73) | LF | 9,406 | $2.35 | $2.70 | $2.20 | $2.15 | $2.50 | $2.50 |
| 0820 | Guardrail end treatment- trailing anchorage (0536-85-20) | EACH | 16 | $1,230.00 | $1,400.00 | $1,150.00 | $1,150.00 | $1,145.00 | $2,000.00 |
| 0825 | Guardrail end treatment- parallel approach terminal (0536-85-24) | EACH | 14 | $3,100.00 | $3,600.00 | $2,900.00 | $2,900.00 | $2,900.00 | $3,000.00 |
| 0830 | Guardrail end treatment- double face approach terminal (0536-85-27) | EACH | 1 | $9,850.00 | $11,300 | $9,200.00 | $9,180.00 | $9,200.00 | $10,000 |
| 0835 | Crash cushion, TL-3, narrow (0544-3-1) | EACH | 1 | $31,000 | $32,400 | $26,500 | $26,200 | $30,000 | $35,813 |
| 0840 | Retaining wall system, permanent, excluding barrier (0548-12) | SF | 107,968 | $49.65 | $56.00 | $65.00 | $57.25 | $55.00 | $44.70 |
| 0845 | Fencing, type A, 8.1-10.0', (0550-10150) | LF | 23,029 | $20.20 | $23.00 | $19.25 | $23.30 | $20.00 | $23.30 |
| 0850 | Fencing, type B, 7.1-8.0', standard (0550-10240) | LF | 7,091 | $19.15 | $22.00 | $18.25 | $29.30 | $20.00 | $29.27 |
| 0855 | Fence gate, type A, double, 12.1- 18.0' opening (0550-60123) | EACH | 8 | $2,300.00 | $2,600.00 | $2,200.00 | $2,150.00 | $2,200.00 | $2,154.42 |
| 0860 | Fence gate, type B, double, 12.1- 18.0' opening (0550-60223) | EACH | 4 | $2,125.00 | $2,400.00 | $2,025.00 | $2,820.00 | $2,100.00 | $2,820.28 |
| 0865 | Performance turf (0570-1-1) | SY | 542,262 | $1.65 | $1.40 | $3.75 | $0.45 | $1.00 | $1.44 |
| 0870 | Performance turf, sod (0570-1-2) | SY | 137,850 | $3.75 | $4.00 | $5.75 | $2.25 | $3.00 | $3.70 |
| 0875 | Conduit, furnish & install, open trench (0630-2-11) | LF | 56 | $17.25 | $20.00 | $16.25 | $16.30 | $41.00 | $25.13 |
| 0880 | Conduit, furnish & install, embedded concrete barriers and traffic railings (0630-2-16) | LF | 14,210 | $17.10 | $19.00 | $16.00 | $16.10 | $9.00 | $10.54 |
| 0885 | Pull & splice box, F&I, 13" X 24" cover size (0635-2-11) | EACH | 2 | $1,650.00 | $1,900.00 | $1,550.00 | $1,560.00 | $1,256.00 | $1,716.29 |
| 0890 | Junction box, furnish & install, embedded (0635-3-13) | EACH | 66 | $1,050.00 | $1,200.00 | $985.00 | $994.00 | $775.00 | $1,201.49 |
| 0895 | Electrical power service- contribution in aid of construction (ciac), FPL (DO not bid) (0639-8130) | LS | 1 | $2,575.00 | $2,575.00 | $2,575.00 | $2,575.00 | $2,575.00 | $2,575.00 |
| 0900 | Traffic monitoring site vehicle sensor-non-weight, furnish & install (0695-1-1) | EACH | 6 | $1,865.00 | $2,100.00 | $1,750.00 | $1,760.00 | $2,042.00 | $2,385.79 |
| 0905 | Traffic monitoring site inductive loop assembly, & install, 2 loops (0695-6-12) | EACH | 6 | $1,815.00 | $2,100.00 | $1,700.00 | $1,710.00 | $1,775.00 | $2,473.11 |
| 0910 | Traffic monitoring site cabinet, furnish & install, type 3, pedestal mount (0695-7132) | EACH | 2 | $8,485.00 | $9,700.00 | $7,925.00 | $8,000.00 | $7,735.00 | $7,009.95 |
| 0915 | Traffic monitoring site cabinet, remove existing cabinet (0695-7600) | EACH | 2 | $805.00 | $910.00 | $750.00 | $758.00 | $615.00 | $860.16 |
| 0920 | Raised pavement marker, type B (0706-1-3) | EACH | 21,172 | $5.25 | $6.00 | $5.00 | $5.00 | $5.00 | $5.00 |
| 0925 | Painted pavement markings, standard, white, solid, 6" (0710-11101) | GM | 23.84 | $1,680.00 | $1,900.00 | $1,600.00 | $1,600.00 | $1,600.00 | $1,599.60 |
| 0930 | Painted pavement markings, standard, white, skip, 10-30 or skip, 6" wide (0710-11131) | GM | 22.12 | $1,050.00 | $1,200.00 | $1,000.00 | $1,000.00 | $1,000.00 | $1,000.45 |
| 0935 | Painted pavement markings, standard, yellow, solid, 6" (0710-11201) | GM | 15.31 | $1,680.00 | $1,900.00 | $1,600.00 | $1,600.00 | $1,600.00 | $1,599.27 |
| 0940 | Partnering, DO not bid (0999-16) | LS | 1 | $10,000 | $10,000 | $10,000 | $10,000 | $10,000 | $10,000 |
| 0945 | Disputes review board, meeting- DO not bid (0999-20-1) | DA | 30 | $4,800.00 | $4,800.00 | $4,800.00 | $4,800.00 | $4,800.00 | $4,800.00 |
| 0950 | Disputes review board, hearing- DO not bid (0999-20-2) | EACH | 6 | $5,750.00 | $5,750.00 | $5,750.00 | $5,750.00 | $5,750.00 | $5,750.00 |
| 0955 | Initial contingency amount, DO not bid (0999-25) | LS | 1 | $150,000 | $150,000 | $150,000 | $150,000 | $150,000 | $150,000 |
| 0960 | Ground-in rumble strips, 16" (0546-72-1) | GM | 11.84 | $1,980.00 | $3,400.00 | $1,350.00 | $1,300.00 | $3,000.00 | $3,984.58 |
| 0965 | Single column ground sign assembly, F&I ground mount, than 12 SF (0700-1111) | EACH | 11 | $800.00 | $820.00 | $685.00 | $758.00 | $682.00 | $650.00 |
| 0970 | Single column ground sign assembly, F&I ground mount, 20.0 SF (0700-1112) | EACH | 31 | $3,200.00 | $2,800.00 | $2,280.00 | $3,000.00 | $2,280.00 | $2,200.00 |
| 0975 | Single column ground sign assembly, F&I barrier 12.0-20.0 SF (0700-1212) | EACH | 1 | $4,700.00 | $5,200.00 | $4,335.00 | $4,430.00 | $4,333.00 | $2,800.00 |
| 0980 | Single column ground sign assembly, F&I barrier 12.0-20.0 SF (0700-1312) | EACH | 1 | $4,800.00 | $9,100.00 | $7,510.00 | $4,480.00 | $7,510.00 | $3,000.00 |
| 0985 | Single column ground sign assembly, relocate (0700-1500) | EACH | 7 | $305.00 | $410.00 | $342.00 | $288.00 | $342.00 | $100.00 |
| 0990 | Single column ground sign assembly, remove (0700-1600) | EACH | 1 | $160.00 | $140.00 | $114.00 | $150.00 | $114.00 | $80.00 |
| 0995 | Multi-column ground sign assembly, F&I ground mount, 50.0 SF (0700-2114) | EACH | 6 | $9,900.00 | $9,300.00 | $7,675.00 | $9,300.00 | $7,675.00 | $8,000.00 |
| 1000 | Multi-column ground sign assembly, F&I ground mount, 100.0 SF (0700-2115) | EACH | 3 | $14,400 | $14,100 | $11,680 | $13,510 | $11,680 | $13,500 |
| 1005 | Multi-column ground sign assembly, F&I ground mount, 1-200.0 SF (0700-2116) | EACH | 3 | $18,500 | $16,200 | $13,465 | $17,430 | $13,465 | $15,000 |
| 1010 | Sign panel, furnish & install overhead mount, 21-30 SF (0700-3203) | EACH | 10 | $1,395.00 | $2,400.00 | $1,988.00 | $1,310.00 | $1,988.00 | $2,150.27 |
| 1015 | Sign panel, furnish & install overhead mount, 51-100 SF (0700-3205) | EACH | 2 | $2,700.00 | $4,400.00 | $3,610.00 | $2,550.00 | $3,610.00 | $3,723.46 |
| 1020 | Sign panel, furnish & install overhead mount, 101-200 SF (0700-3206) | EACH | 6 | $7,590.00 | $10,000 | $8,270.00 | $7,120.00 | $8,270.00 | $8,740.22 |
| 1025 | Sign panel, furnish & install overhead mount, 201-300 SF (0700-3207) | EACH | 4 | $9,345.00 | $12,300 | $10,225 | $8,770.00 | $10,225 | $11,273 |
| 1030 | Sign panel, furnish & install overhead mount, 301-400 SF (0700-3208) | EACH | 2 | $13,100 | $16,900 | $14,025 | $12,290 | $14,025 | $15,071 |
| 1035 | Sign panel, furnish & install overhead mount, 601 SF and greater (0700-3211) | EACH | 2 | $38,000 | $44,400 | $36,815 | $35,690 | $36,815 | $35,077 |
| 1040 | Overhead static sign furnish & install, cantilever, 30 FT (0700-4112) | EACH | 1 | $100,700 | $102,600 | $85,050 | $94,500 | $85,050 | $94,525 |
| 1045 | Overhead static sign furnish & install, cantilever, 40 FT (0700-4113) | EACH | 3 | $152,600 | $149,000 | $123,500 | $143,200 | $123,500 | $137,925 |
| 1050 | Overhead static sign furnish & install, span, 51-100 FT (0700-4125) | EACH | 4 | $288,000 | $250,000 | $248,750 | $259,000 | $248,750 | $224,857 |
| 1055 | Overhead static sign furnish & install, span, 101-150 (0700-4126) | EACH | 2 | $311,000 | $260,000 | $263,000 | $292,400 | $263,000 | $401,813 |
| 1060 | Retroreflective sign strip- furnish and install, 2' (0700-13-12) | EACH | 2 | $125.00 | $80.00 | $66.00 | $118.00 | $66.00 | $75.00 |
| 1065 | Delineator, non-flexible (0705-11-2) | EACH | 157 | $63.00 | $140.00 | $60.00 | $60.00 | $100.00 | $60.00 |
| 1070 | Raised pavement marker, type B (0706-1-3) | EACH | 4,204 | $5.25 | $6.00 | $5.00 | $5.00 | $5.00 | $5.00 |
| 1075 | Painted pavement markings, surface (0710-90) | LS | 1 | $94,500 | $108,600 | $90,000 | $90,000 | $90,000 | $90,000 |
| 1080 | Thermoplastic, standard, solid, 12" for interchange markings (0711-11103) | GM | 0.06 | $11,000 | $12,000 | $12,000 | $12,000 | $12,000 | $12,632 |
| 1085 | Thermoplastic, standard, solid, 18" for diagonals and chevrons (0711-11124) | LF | 2,095 | $7.35 | $8.50 | $7.00 | $7.00 | $7.00 | $7.00 |
| 1090 | Thermoplastic, standard, message or symbol (0711-11160) | EACH | 14 | $315.00 | $360.00 | $300.00 | $300.00 | $300.00 | $300.00 |
| 1095 | Thermoplastic, standard, arrow (0711-11170) | EACH | 18 | $94.50 | $110.00 | $90.00 | $90.00 | $90.00 | $90.00 |
| 1100 | Thermoplastic, standard, yellow, solid, 18" for diagonal or chevron (0711-11224) | LF | 55 | $7.35 | $8.50 | $7.00 | $7.00 | $7.00 | $7.00 |
| 1105 | Thermoplastic, preformed, white, message (0711-14160) | EACH | 4 | $1,260.00 | $1,400.00 | $1,200.00 | $1,200.00 | $1,200.00 | $1,200.00 |
| 1110 | Thermoplastic, standard-open graded asphalt surfaces solid, 6" (0711-15101) | GM | 9.61 | $6,085.00 | $7,000.00 | $5,800.00 | $5,800.00 | $5,800.00 | $5,800.60 |
| 1115 | Thermoplastic, standard-open graded asphalt surfaces, solid, 8" (0711-15102) | GM | 1.67 | $6,800.00 | $7,800.00 | $6,500.00 | $6,500.00 | $6,500.00 | $6,492.22 |
| 1120 | Thermoplastic, standard-open graded asphalt surfaces, skip, 6",10-30 skip or 3-9 lane (0711-15131) | GM | 15.75 | $3,650.00 | $4,200.00 | $3,500.00 | $3,500.00 | $3,500.00 | $3,501.11 |
| 1125 | Thermoplastic, standard-open graded asphalt surfaces, skip, 12"- approach to toll plaza or 3-9 lane drop (0711-15133) | GM | 0.67 | $6,200.00 | $8,000.00 | $6,000.00 | $6,000.00 | $6,000.00 | $5,982.14 |
| 1130 | Thermoplastic, standard-open graded asphalt surfaces, yellow, solid, 6" (0711-15201) | GM | 9.61 | $6,000.00 | $7,000.00 | $5,800.00 | $5,800.00 | $5,800.00 | $5,798.79 |
| 1135 | Thermoplastic, standard-other surfaces, white, solid, 6" (0711-16101) | GM | 0.58 | $5,700.00 | $6,000.00 | $5,500.00 | $5,500.00 | $5,500.00 | $5,519.03 |
| 1140 | Thermoplastic, standard-other surfaces, yellow, solid, 6" (0711-16201) | GM | 0.46 | $5,700.00 | $6,000.00 | $5,500.00 | $5,500.00 | $5,500.00 | $5,548.25 |
| 1145 | Permanent tape, white, solid, 6" for concrete bridges (0713-103101) | GM | 0.73 | $33,500 | $40,000 | $32,000 | $32,000 | $32,000 | $31,913 |
| 1150 | Permanent tape, white, 3-9 dotted, 12" wide, for concrete surfaces (0713-103173) | GM | 0.15 | $26,600 | $30,000 | $25,000 | $25,000 | $25,000 | $25,338 |
| 1155 | Permanent tape, white, 10-30 6" wide, for concrete surfaces (0713-103181) | GM | 0.88 | $12,650 | $15,000 | $12,000 | $12,000 | $12,000 | $12,041 |
| 1160 | Permanent tape, yellow, solid, for concrete bridges (0713-103201) | GM | 0.73 | $33,300 | $35,000 | $32,000 | $32,000 | $32,000 | $32,132 |
| 1165 | Permanent tape, black, 3-9 dotted, 12" wide, for concrete surfaces (0713-103373) | GM | 0.15 | $26,600 | $28,000 | $25,000 | $25,000 | $25,000 | $25,338 |
| 1170 | Permanent tape, black, 10-30 6" wide, for concrete surfaces (0713-103381) | GM | 0.88 | $12,650 | $14,000 | $12,000 | $12,000 | $12,000 | $12,041 |
| 1175 | Conduit, furnish & install, open trench (0630-2-11) | LF | 41,113 | $17.25 | $17.00 | $16.25 | $16.30 | $15.00 | $10.01 |
| 1180 | Conduit, furnish & install, directional bore (0630-2-12) | LF | 3,878 | $32.00 | $36.00 | $30.00 | $30.25 | $24.00 | $17.13 |
| 1185 | Conduit, furnish & install, aboveground (0630-2-14) | LF | 269 | $46.00 | $52.00 | $43.00 | $43.50 | $60.00 | $37.78 |
| 1190 | Pull & splice box, F&I, 13" X 24" cover size (0635-2-11) | EACH | 285 | $1,650.00 | $1,500.00 | $1,550.00 | $1,560.00 | $2,290.00 | $1,162.89 |
| 1195 | Junction box, furnish & install, mounted (0635-3-12) | EACH | 8 | $1,350.00 | $1,500.00 | $1,270.00 | $1,280.00 | $721.00 | $1,631.57 |
| 1200 | Electrical power service, F&I, underground, meter by contractor (0639-1122) | AS | 3 | $5,800.00 | $6,700.00 | $5,480.00 | $5,530.00 | $7,490.00 | $5,168.13 |
| 1205 | Electrical service wire, & install (0639-2-1) | LF | 463 | $15.25 | $17.00 | $14.25 | $14.40 | $20.50 | $15.69 |
| 1210 | Prestressed concrete pole, type P-II service pole (0641-2-12) | EACH | 3 | $2,800.00 | $3,200.00 | $2,615.00 | $2,640.00 | $2,725.00 | $1,888.30 |
| 1215 | Lighting conductors, F&I, insulated, no.8 - 6 (0715-1-12) | LF | 390,148 | $2.60 | $2.50 | $2.50 | $2.45 | $2.92 | $1.99 |
| 1220 | Lighting conductors, F&I, insulated, no 4 to no 2 (0715-1-13) | LF | 18,670 | $4.30 | $5.00 | $4.00 | $4.05 | $3.50 | $3.29 |
| 1225 | Load center, F&I, secondary voltage (0715-7-11) | EACH | 3 | $21,000 | $24,400 | $20,000 | $20,200 | $28,440 | $24,262 |
| 1230 | Luminaire, F&I, roadway, wall mount (0715-11115) | EACH | 16 | $1,450.00 | $1,700.00 | $1,375.00 | $1,390.00 | $1,473.00 | $1,562.56 |
| 1235 | Light pole complete, F&I, standard pole standard foundation, 40' mounting height, 0' arm length (0715-61300) | EACH | 1 | $9,000.00 | $10,300 | $8,470.00 | $8,550.00 | $6,237.34 | $5,698.98 |
| 1240 | Light pole complete, F&I, standard pole standard foundation, 40' mounting height, 15' arm length (0715-61352) | EACH | 94 | $9,000.00 | $8,500.00 | $8,425.00 | $8,510.00 | $8,785.00 | $8,735.75 |
| 1245 | Light pole complete, F&I, standard pole standard foundation, 45' mounting height, 0' arm length (0715-61400) | EACH | 126 | $9,800.00 | $8,500.00 | $9,175.00 | $9,270.00 | $9,735.00 | $7,577.64 |
| 1250 | Light pole complete, F&I, standard pole standard foundation, 45' mounting height, 10' arm length (0715-61421) | EACH | 29 | $9,800.00 | $9,000.00 | $9,175.00 | $9,270.00 | $10,170 | $9,417.49 |
| 1255 | Light pole complete, F&I, standard pole standard foundation, 45' mounting height, 12' arm length (0715-61442) | EACH | 1 | $10,000 | $11,500 | $9,415.00 | $9,510.00 | $10,235 | $9,693.87 |
| 1260 | Light pole complete, F&I, standard pole standard foundation, 45' mounting height, 15' arm length (0715-61452) | EACH | 4 | $12,500 | $14,200 | $11,635 | $11,750 | $9,615.00 | $9,693.87 |
| 1265 | Pole cable distribution system, furnish and install, conventional (0715-500-1) | EACH | 255 | $640.00 | $730.00 | $600.00 | $606.00 | $865.00 | $687.96 |
| 1270 | Pole cable distribution system, wall mount (0715-500-3) | EACH | 16 | $620.00 | $700.00 | $580.00 | $582.00 | $946.00 | $626.54 |
| 1275 | Reinforced concrete, toll site equipment slab, 12" thick (0400-45-5) | SY | 58 | $285.00 | $390.00 | $1,760.00 | $700.00 | $350.00 | $1,227.06 |
| 1280 | Bollards (0519-78) | EACH | 30 | $2,500.00 | $1,800.00 | $1,400.00 | $900.00 | $1,000.00 | $2,800.00 |
| 1285 | Bumper guards, concrete (0542-70) | EACH | 4 | $156.00 | $180.00 | $150.00 | $315.00 | $500.00 | $280.00 |
| 1290 | Conduit, furnish & install, open trench (0630-2-11) | LF | 1,909 | $20.00 | $39.00 | $16.00 | $16.30 | $39.00 | $27.87 |
| 1295 | Conduit, furnish & install, directional bore (0630-2-12) | LF | 480 | $45.00 | $75.00 | $38.00 | $38.00 | $24.40 | $54.04 |
| 1300 | Pull & splice box, install (0635-2-30) | EACH | 5 | $1,950.00 | $1,900.00 | $1,600.00 | $1,610.00 | $2,000.00 | $2,562.56 |
| 1305 | Toll site pull box, furnish & install, 12"W X 12"L X 12"D (0635-5-11) | EACH | 4 | $1,465.00 | $1,500.00 | $1,200.00 | $1,210.00 | $1,500.00 | $1,606.36 |
| 1310 | Toll site pull box, furnish & install, 24"W X 36"L X 24"D (0635-5-12) | EACH | 4 | $3,200.00 | $3,200.00 | $2,650.00 | $2,660.00 | $2,500.00 | $2,682.40 |
| 1315 | Toll site pull box, furnish & install, 30"W X 48"L X 24"D (0635-5-13) | EACH | 14 | $5,500.00 | $5,500.00 | $4,520.00 | $4,560.00 | $5,000.00 | $5,882.24 |
| 1320 | Emergency generator- permanent 76-100 KW (0639-5-32) | EACH | 2 | $260,000 | $210,000 | $210,100 | $212,200 | $200,000 | $259,940 |
| 1325 | Electrical power service, toll site electric metering and utility service entrance (0639-7122) | EACH | 2 | $27,200 | $27,100 | $22,210 | $22,430 | $60,000 | $50,932 |
| 1330 | Toll gantry, non-accessible, furnish and install, cantilever, 41' to 50' (0735-1114) | EACH | 2 | $327,000 | $250,000 | $266,915 | $269,600 | $400,000 | $357,714 |
| 1335 | Toll plaza, location 1 (0735-74-1) | LS | 1 | $945,000 | $750,000 | $750,500 | $750,300 | $750,000 | $763,280 |
| 1340 | Toll plaza, location 2 (0735-74-2) | LS | 1 | $945,000 | $750,000 | $750,500 | $750,300 | $750,000 | $763,280 |
| 1345 | Temporary intelligent transportation system (0102-25101) | DA | 1,600 | $221.00 | $240.00 | $88.00 | $199.00 | $100.00 | $124.47 |
| 1350 | Existing ITS maintenance (0102-112) | DA | 1,600 | $171.00 | $190.00 | $75.00 | $154.00 | $100.00 | $270.00 |
| 1355 | Itsfm subsurface documentation- project length (0611-1-1) | MI | 1.10 | $4,380.00 | $4,800.00 | $3,900.00 | $3,940.00 | $4,330.00 | $4,717.93 |
| 1360 | Itsfm location documentation- ITS site (0611-2-2) | EACH | 15 | $2,125.00 | $2,300.00 | $1,891.00 | $1,910.00 | $2,200.00 | $1,944.00 |
| 1365 | Itsfm location documentation- communications building (0611-2-3) | EACH | 2 | $4,380.00 | $4,800.00 | $3,900.00 | $3,940.00 | $4,330.50 | $3,780.00 |
| 1370 | Conduit, furnish & install, open trench (0630-2-11) | LF | 24,260 | $18.00 | $16.00 | $16.25 | $16.30 | $24.10 | $25.15 |
| 1375 | Conduit, furnish & install, directional bore (0630-2-12) | LF | 19,553 | $46.50 | $40.00 | $41.25 | $41.75 | $59.10 | $52.07 |
| 1380 | Conduit, furnish & install, aboveground (0630-2-14) | LF | 435 | $57.00 | $62.00 | $51.00 | $51.25 | $48.00 | $50.94 |
| 1385 | Fiber optic cable, F&I, underground,2-12 fibers (0633-1121) | LF | 7,698 | $4.50 | $4.80 | $4.00 | $4.00 | $4.30 | $3.76 |
| 1390 | Fiber optic cable, F&I, underground,13-48 fibers (0633-1122) | LF | 1,352 | $4.85 | $5.50 | $4.50 | $4.35 | $4.70 | $4.09 |
| 1395 | Fiber optic cable, F&I, underground, 97 - 144 fibers (0633-1124) | LF | 38,489 | $5.50 | $6.00 | $5.00 | $4.95 | $5.25 | $4.63 |
| 1400 | Fiber optic cable, relocate, underground (0633-1420) | LF | 200 | $3.85 | $5.00 | $3.50 | $3.50 | $3.70 | $3.24 |
| 1405 | Fiber optic cable, remove, underground (0633-1620) | LF | 10,581 | $1.30 | $2.00 | $1.25 | $1.15 | $1.25 | $1.08 |
| 1410 | Fiber optic connection, install, splice (0633-2-31) | EACH | 644 | $58.00 | $63.00 | $52.00 | $52.25 | $56.00 | $48.60 |
| 1415 | Fiber optic connection, install, termination (0633-2-32) | EACH | 1,056 | $110.00 | $120.00 | $98.00 | $98.75 | $105.00 | $91.80 |
| 1420 | Fiber optic connection hardware, F&I, splice (0633-3-11) | EACH | 11 | $1,800.00 | $2,000.00 | $1,605.00 | $1,620.00 | $1,725.00 | $1,506.60 |
| 1425 | Fiber optic connection hardware, F&I, splice tray (0633-3-12) | EACH | 149 | $65.00 | $70.00 | $58.00 | $58.00 | $61.00 | $54.00 |
| 1430 | Fiber optic connection hardware, F&I, preterminated connector assembly (0633-3-13) | EACH | 88 | $58.00 | $63.00 | $52.00 | $52.25 | $55.00 | $48.60 |
| 1435 | Fiber optic connection hardware, F&I, patch panel- terminated (0633-3-16) | EACH | 19 | $3,420.00 | $3,700.00 | $3,047.00 | $3,080.00 | $3,450.00 | $2,862.00 |
| 1440 | Fiber optic connection hardware, F&I, connector panel (0633-3-17) | EACH | 75 | $160.00 | $180.00 | $144.00 | $145.00 | $155.00 | $135.00 |
| 1445 | Fiber optic cable locator (0633-6) | DA | 1,600 | $320.00 | $290.00 | $285.00 | $288.00 | $50.00 | $307.80 |
| 1450 | Pull & splice box, F&I, 13" X 24" cover size (0635-2-11) | EACH | 68 | $1,740.00 | $1,900.00 | $1,547.00 | $1,560.00 | $1,249.00 | $1,654.99 |
| 1455 | Pull & splice box, F&I, 24" X 36" cover size (0635-2-12) | EACH | 38 | $3,325.00 | $3,600.00 | $2,962.00 | $2,990.00 | $3,350.00 | $3,081.13 |
| 1460 | Pull & splice box, install (0635-2-30) | EACH | 29 | $1,800.00 | $1,900.00 | $1,597.00 | $1,610.00 | $1,370.00 | $1,602.72 |
| 1465 | Fiber optic splice vault, & install, 54"W X 54"L X 48"D (0635-4-11) | EACH | 13 | $12,300 | $13,300 | $10,949 | $11,060 | $16,000 | $20,355 |
| 1470 | Electrical power service, F&I, underground, meter by contractor (0639-1122) | AS | 4 | $6,150.00 | $6,700.00 | $5,478.00 | $5,530.00 | $11,850 | $13,751 |
| 1475 | Electrical service wire, & install (0639-2-1) | LF | 12,021 | $16.00 | $15.00 | $14.00 | $14.40 | $18.80 | $15.53 |
| 1480 | Electrical service wire, (0639-2-6) | LF | 7,680 | $1.25 | $1.30 | $1.00 | $1.10 | $3.50 | $0.52 |
| 1485 | Electrical service disconnect, F&I, pole mount (0639-3-11) | EACH | 14 | $2,900.00 | $3,100.00 | $2,580.00 | $2,610.00 | $4,205.00 | $2,781.55 |
| 1490 | Emergency generator- permanent 26-50 KW (0639-5-2) | EACH | 2 | $150,000 | $161,300 | $132,415 | $133,800 | $197,000 | $208,937 |
| 1495 | Electrical power service- transformer, F&I, 5-10 kva, phase, copper windings (0639-6121) | EACH | 8 | $3,000.00 | $3,200.00 | $2,608.00 | $2,630.00 | $3,135.00 | $3,435.47 |
| 1500 | Electrical power service- transformer, F&I, 26-50 kva, single phase, copper windings (0639-6151) | EACH | 2 | $12,000 | $12,900 | $10,584 | $10,690 | $13,225 | $6,870.49 |
| 1505 | Prestressed concrete pole, type P-II service pole (0641-2-12) | EACH | 8 | $2,930.00 | $3,200.00 | $2,613.00 | $2,640.00 | $3,175.00 | $1,820.86 |
| 1510 | Prestressed concrete pole, type P-V (0641-2-15) | EACH | 4 | $26,000 | $28,600 | $23,496 | $23,730 | $20,485 | $16,429 |
| 1515 | Concrete CCTV pole, furnish & install with lowering device, (0641-3169) | EACH | 5 | $47,000 | $45,000 | $41,546 | $41,970 | $35,850 | $37,405 |
| 1520 | Concrete CCTV pole, furnish & install with lowering device, (0641-3186) | EACH | 2 | $48,000 | $53,000 | $43,460 | $43,900 | $39,500 | $46,001 |
| 1525 | Concrete CCTV pole, complete pole removal (0641-3800) | EACH | 2 | $11,000 | $11,900 | $9,778.00 | $9,850.00 | $24,325 | $13,578 |
| 1530 | Vehicle detection system- avi, bluetooth, furnish & install, cabinet equipment (0660-6121) | EACH | 3 | $1,325.00 | $1,400.00 | $1,182.00 | $1,190.00 | $3,070.00 | $1,063.80 |
| 1535 | Vehicle detection system- avi, bluetooth, furnish & install, above ground equipment (0660-6122) | EACH | 3 | $12,200 | $13,200 | $10,838 | $10,950 | $9,520.00 | $10,179 |
| 1540 | Traffic data detection system- microwave, furnish and install, cabinet equipment (0660-8-11) | EACH | 10 | $7,740.00 | $8,400.00 | $6,895.00 | $6,960.00 | $7,400.00 | $3,711.02 |
| 1545 | Traffic data detection system- microwave, furnish and install, above ground equipment (0660-8-12) | EACH | 10 | $15,250 | $16,500 | $13,565 | $13,700 | $11,635 | $8,636.90 |
| 1550 | ITS cabinet, furnish & install, pole mount with sunshield, 24" W X 46" H X 22" D (0676-2122) | EACH | 7 | $10,300 | $11,100 | $9,149.00 | $9,240.00 | $10,665 | $10,323 |
| 1555 | ITS cabinet, furnish & install, base mount with sunshield, 332D 66" H X 48" W X 30" D (0676-2147) | EACH | 1 | $18,300 | $19,900 | $16,320 | $16,300 | $21,000 | $19,436 |
| 1560 | Small equipment enclosure, furnish and install, less than 10"W X 13"H X 11" D (0676-3-10) | EACH | 3 | $2,350.00 | $2,600.00 | $2,094.00 | $2,110.00 | $1,045.00 | $1,281.84 |
| 1565 | Equipment shelter, furnish & install, UP to 120 SF (0677-1-11) | EACH | 2 | $254,000 | $225,000 | $226,669 | $229,000 | $318,750 | $455,763 |
| 1570 | ITS CCTV camera, non- pressurized, IP, high definition (0682-1173) | EACH | 12 | $7,350.00 | $8,000.00 | $6,549.00 | $6,620.00 | $7,700.00 | $6,150.60 |
| 1575 | Managed field ethernet switch, furnish & install (0684-1-1) | EACH | 8 | $16,650 | $18,100 | $14,830 | $14,980 | $13,600 | $13,927 |
| 1580 | Device server, furnish & install (0684-2-1) | EACH | 11 | $1,575.00 | $1,700.00 | $1,403.00 | $1,420.00 | $1,215.00 | $999.00 |
| 1585 | Media converter, furnish & install (0684-5-1) | EACH | 14 | $2,100.00 | $2,200.00 | $1,842.00 | $1,860.00 | $1,190.00 | $912.60 |
| 1590 | Managed hub ethernet switch, furnish & install (0684-7-1) | EACH | 6 | $10,800 | $11,700 | $44,800 | $9,730.00 | $40,379 | $43,200 |
| 1595 | Uninterruptible power supply, furnish and install, line interactive (0685-1-11) | EACH | 10 | $6,450.00 | $7,000.00 | $5,778.00 | $5,840.00 | $6,560.00 | $6,559.86 |
| 1600 | Remote power management rpmu, furnish and install (0685-2-1) | EACH | 13 | $1,200.00 | $1,300.00 | $1,067.00 | $1,080.00 | $1,550.00 | $716.69 |
| 1605 | Walk-in dynamic message sign, furnish & install- with UPS full color, 201-300 SF (0700-9137) | EACH | 1 | $145,000 | $158,100 | $129,786 | $131,100 | $145,000 | $135,161 |
| 1610 | DMS support structure, cantilever, 41-50 FT (0700-10124) | EACH | 1 | $175,000 | $190,100 | $155,990 | $157,600 | $144,000 | $140,733 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from FDOT's tabulation for this contract. FDOT Tabulation of Bids PDFs from its central office lettings, January 2018 to October 2026, all pay items. On A+B contracts the cost part is kept (the total the pay items add up to). Bidders listed without a rank or total are left out.
Every contract let that day: FDOT letting of September 24, 2025. Compiled by Mirage Metrics.