FDOT contract T2A37 bid tabulation
SR 228 FROM HART BRIDGE TO BEACH BLVD. Let by Florida DOT on February 25, 2026, Duval, District 2. 5 bids received; low bid $17,205,225 by Gosalia Concrete Constructors, Inc..
- Owner
- Florida DOT
- Letting
- 25 FEB 2026
- Pay items
- 156
- Data through
- 28 OCT 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | Gosalia Concrete Constructors, Inc. | $17,205,225 | Low |
| 2 | Superior Construction Company Southeast, LLC | $18,727,378 | +9.0% |
| 3 | Webber, LLC | $19,248,697 | +12% |
| 4 | Watson Civil Construction, Inc. | $20,786,026 | +21% |
| 5 | De Moya Contracting LLC | $20,867,054 | +21% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Gosalia Concrete Constructors, Inc. | 2. Superior Construction Company Southeast, LLC | 3. Webber, LLC | 4. Watson Civil Construction, Inc. | 5. De Moya Contracting LLC |
|---|---|---|---|---|---|---|---|---|
| 0005 | Removal of existing structures/bridges (0110-3) | SF | 1 | $35,000 | $74,000 | $22,070 | $32,000 | $150,000 |
| 0010 | Removal of existing structures/bridges SF (0110-3) | SF | 1 | $35,000 | $76,000 | $21,110 | $35,000 | $150,000 |
| 0015 | Removal of existing structures/bridges SF (0110-3) | SF | 1 | $35,000 | $61,000 | $20,600 | $25,500 | $150,000 |
| 0020 | Removal of existing structures/bridges SF (0110-3) | SF | 1 | $35,000 | $80,000 | $13,640 | $25,000 | $150,000 |
| 0025 | Removal of existing structures/bridges SF (0110-3) | SF | 1 | $35,000 | $79,000 | $13,970 | $30,000 | $150,000 |
| 0030 | Removal of existing structures/bridges SF (0110-3) | SF | 1 | $35,000 | $79,000 | $20,670 | $32,000 | $150,000 |
| 0035 | Removal of existing structures/bridges SF (0110-3) | SF | 1 | $35,000 | $60,000 | $13,970 | $25,200 | $150,000 |
| 0040 | Removal of existing structures/bridges SF (0110-3) | SF | 1 | $35,000 | $64,000 | $20,680 | $25,000 | $150,000 |
| 0045 | Removal of existing structures/bridges SF (0110-3) | SF | 1 | $15,000 | $76,000 | $14,550 | $28,000 | $150,000 |
| 0050 | Concrete class II, approach slabs (0400-2-10) | CY | 998.40 | $600.00 | $1,500.00 | $493.00 | $1,240.00 | $1,200.00 |
| 0055 | Concrete class IV, superstructure (0400-4-4) | CY | 4 | $2,500.00 | $4,000.00 | $3,250.00 | $3,050.00 | $2,000.00 |
| 0060 | Bridge deck grooving (0400-7-1) | SY | 2,770 | $9.85 | $6.00 | $16.40 | $2.45 | $20.00 |
| 0065 | Reinforcing steel - bridge superstructure (0415-1-4) | LB | 621 | $3.10 | $1.20 | $1.20 | $3.10 | $5.00 |
| 0070 | Reinforcing steel- approach slabs (0415-1-9) | LB | 189,748 | $1.90 | $1.20 | $1.20 | $1.90 | $2.00 |
| 0075 | Bridge deck expansion joint, construction, F&I poured joint with backer rod (0458-1-11) | LF | 969 | $79.40 | $50.00 | $78.75 | $82.20 | $100.00 |
| 0080 | Metal traffic railing, thrie retrofit (0460-71-1) | LF | 4,301 | $190.97 | $200.00 | $191.00 | $193.00 | $200.00 |
| 0085 | Mobilization (0101-1) | LS | 1 | $1,300,000 | $1,800,000 | $1,800,000 | $2,070,000 | $2,000,000 |
| 0090 | Maintenance of traffic (0102-1) | DA | 1 | $550,000 | $491,000 | $1,050,000 | $618,472 | $500,000 |
| 0095 | Special detour- temporary pavement (0102-2200) | SY | 1 | $1.00 | $455,000 | $562,534 | $290,000 | $462,000 |
| 0100 | Special detour- temporary earthwork/base (0102-2300) | CY | 1 | $1.00 | $700,000 | $144,325 | $442,000 | $60,000 |
| 0105 | Traffic control officer (0102-14) | HR | 8,700 | $15.00 | $94.00 | $120.00 | $110.00 | $1.00 |
| 0110 | Work zone sign (0102-60) | ED | 362,870 | $0.20 | $0.12 | $0.15 | $0.25 | $0.15 |
| 0115 | Barrier mounted work zone sign- index 700-012 (0102-62-12) | ED | 1,856 | $0.50 | $0.40 | $0.50 | $6.00 | $5.00 |
| 0120 | Barrier mounted work zone sign- index 700-013 (0102-62-13) | ED | 1,338 | $0.50 | $0.35 | $0.45 | $0.70 | $0.45 |
| 0125 | Temporary barrier, F&I, free standing (0102-71-16) | LF | 9,141 | $1.00 | $75.00 | $25.00 | $36.00 | $35.00 |
| 0130 | Temporary barrier, relocate, free standing (0102-71-26) | LF | 22,497 | $1.00 | $7.00 | $10.00 | $15.50 | $15.00 |
| 0135 | Channelizing device- types I, II, VP, drum, or LCD (0102-74-1) | ED | 33,868 | $0.35 | $0.10 | $0.15 | $0.14 | $0.15 |
| 0140 | Channelizing device- pedestrian LCD (longitudinal channelizing device) (0102-74-8) | FD | 2,544 | $0.05 | $0.03 | $0.05 | $0.04 | $0.06 |
| 0145 | Arrow board / advance warning arrow panel (0102-76) | ED | 640 | $10.00 | $4.00 | $5.00 | $7.50 | $5.00 |
| 0150 | Temporary crash cushion, redirective option (0102-89-1) | LO | 31 | $950.00 | $1,900.00 | $1,300.00 | $970.00 | $2,100.00 |
| 0155 | Portable changeable message sign, temporary (0102-99) | ED | 4,064 | $10.00 | $9.75 | $12.00 | $13.00 | $12.00 |
| 0160 | Temporary signalization and maintenance, intersection (0102-104) | ED | 1,200 | $17.50 | $19.00 | $19.90 | $35.00 | $19.87 |
| 0165 | Temporary traffic detection and maintenance, intersection (0102-107-1) | ED | 1,200 | $17.50 | $4.00 | $4.95 | $40.00 | $4.97 |
| 0170 | Type III barricade (0102-115) | ED | 91,600 | $0.20 | $0.14 | $0.30 | $0.33 | $0.30 |
| 0175 | Removable tape, white, solid 6" (0102-913-21) | GM | 0.38 | $14,921 | $11,500 | $11,940 | $11,500 | $11,500 |
| 0180 | Removable tape, yellow, solid, (0102-913-31) | GM | 0.36 | $15,000 | $11,500 | $12,000 | $11,600 | $11,500 |
| 0185 | Sediment barrier (0104-10-3) | LF | 754 | $2.56 | $5.00 | $6.00 | $1.40 | $3.00 |
| 0190 | Inlet protection system (0104-18) | EACH | 182 | $179.41 | $82.00 | $66.75 | $60.00 | $200.00 |
| 0195 | Litter removal (0107-1) | ACRE | 504.13 | $15.00 | $145.00 | $60.00 | $66.00 | $75.00 |
| 0200 | Mowing (0107-2) | ACRE | 297.64 | $15.00 | $230.00 | $125.00 | $126.00 | $75.00 |
| 0205 | Clearing & grubbing (0110-1-1) | ACRE | 1 | $43,827 | $244,534 | $1,500,000 | $170,000 | $150,000 |
| 0210 | Removal of existing concrete (0110-4-10) | SY | 23,987 | $40.00 | $36.00 | $59.20 | $43.00 | $65.00 |
| 0215 | Borrow excavation, truck measure (0120-2-2) | CY | 367.20 | $40.00 | $40.00 | $74.25 | $80.00 | $20.00 |
| 0220 | Regular excavation (3-R projects only) (0120-71) | LS | 1 | $25,000 | $1,000.00 | $6,680.00 | $16,000 | $1,500.00 |
| 0225 | Geosynthetic reinforced foundation over soft soil (0145-2) | SY | 3,363 | $12.98 | $20.00 | $7.35 | $7.80 | $20.00 |
| 0230 | Type B stabilization (0160-4) | SY | 3,989 | $30.07 | $25.00 | $40.50 | $21.00 | $25.00 |
| 0235 | Optional base, base group 09 (0285-709) | SY | 3,989 | $61.85 | $32.00 | $26.60 | $31.00 | $30.00 |
| 0240 | Milling existing asphalt pavement, 3" avg depth (0327-70-4) | SY | 43,978 | $6.67 | $6.50 | $5.50 | $5.35 | $4.20 |
| 0245 | Milling existing asphalt pavement, 1 1/2" avg depth (0327-70-6) | SY | 43 | $75.20 | $73.00 | $230.00 | $231.00 | $216.00 |
| 0250 | Superpave asphaltic concrete, traffic C, PG76-22 (0334-1-53) | TN | 6,808.80 | $199.29 | $192.00 | $180.00 | $191.00 | $207.00 |
| 0255 | Asphalt concrete friction course,traffic C, FC-12.5, PG (0337-7-83) | TN | 1,571.80 | $229.83 | $221.00 | $205.00 | $216.00 | $227.00 |
| 0260 | Miscellaneous asphalt (0339-1) | TN | 664.70 | $187.85 | $238.00 | $570.00 | $604.00 | $293.00 |
| 0265 | Cleaning & sealing joints- concrete pavement (0350-5) | LF | 164,221 | $4.01 | $2.50 | $2.55 | $4.15 | $2.50 |
| 0270 | Grinding concrete pavement (0352-70) | SY | 105,364 | $4.34 | $5.00 | $3.90 | $4.20 | $4.00 |
| 0275 | Concrete pavement slab replacement (0353-70) | CY | 4,960 | $1,177.00 | $600.00 | $684.70 | $1,040.00 | $1,100.00 |
| 0280 | Inlets, curb, type P-1, <10' (0425-1311) | EACH | 2 | $6,100.00 | $12,500 | $7,660.00 | $8,500.00 | $10,000 |
| 0285 | Inlets, curb, type P-5, partial (0425-1355) | EACH | 1 | $3,700.00 | $4,200.00 | $5,530.00 | $6,700.00 | $10,000 |
| 0290 | Inlets, DT bot, type D, <10' (0425-1541) | EACH | 2 | $7,100.00 | $13,000 | $830.00 | $7,200.00 | $10,000 |
| 0295 | Grate for existing drainage structure, furnish and install (0425-14-1) | SF | 43 | $100.00 | $175.00 | $280.00 | $249.00 | $1,000.00 |
| 0300 | Pipe culvert,optional material,round, 18"S/CD (0430-175118) | LF | 246 | $120.00 | $135.00 | $153.00 | $129.00 | $135.00 |
| 0305 | Straight concrete endwalls, single, 0 degrees, round (0430-518100) | EACH | 1 | $6,000.00 | $6,320.00 | $7,420.00 | $2,650.00 | $5,000.00 |
| 0310 | Pipe filling and plugging- place out of service (0430-830) | CY | 0.60 | $5,400.00 | $5,000.00 | $1,620.00 | $6,500.00 | $1,000.00 |
| 0315 | Edgedrain draincrete, (0446-1-1) | LF | 68 | $41.00 | $45.00 | $97.75 | $56.00 | $50.00 |
| 0320 | Edgedrain outlet pipe, 4" (0446-71-1) | LF | 88 | $151.00 | $30.00 | $91.50 | $80.02 | $100.00 |
| 0325 | Concrete curb & gutter, type F (0520-1-10) | LF | 708 | $46.00 | $45.00 | $59.25 | $41.00 | $35.00 |
| 0330 | Median concrete barrier, 38" height (0521-1-11) | LF | 395 | $0.01 | $70.00 | $140.00 | $45.00 | $300.00 |
| 0335 | Concrete ditch pavement, non reinforced, 4" (0524-1-2) | SY | 126 | $65.00 | $120.00 | $61.75 | $74.00 | $125.00 |
| 0340 | Concrete slope pavement,non reinforced, 4" (0524-2-2) | SY | 48 | $75.00 | $600.00 | $72.75 | $100.00 | $160.00 |
| 0345 | Riprap, rubble, F&I, ditch lining (0530-3-4) | TN | 3.60 | $200.00 | $300.00 | $848.00 | $695.00 | $150.00 |
| 0350 | Guardrail -roadway, general/low speed TL-2 (0536-1-0) | LF | 1,292 | $17.31 | $18.00 | $17.30 | $17.50 | $17.31 |
| 0355 | Guardrail -roadway, general (0536-1-1) | LF | 13,648 | $20.69 | $21.00 | $20.70 | $21.00 | $20.69 |
| 0360 | Guardrail- roadway, double (0536-1-3) | LF | 1,825 | $29.49 | $30.00 | $29.50 | $30.00 | $29.49 |
| 0365 | Special guardrail post- special steel post for concrete structure mount (0536-7-2) | EACH | 62 | $267.55 | $270.00 | $268.00 | $271.00 | $209.61 |
| 0370 | Special guardrail post- frangible leave-out for mounting through concrete surface (0536-7-4) | EACH | 214 | $59.67 | $60.00 | $59.75 | $61.00 | $46.75 |
| 0375 | Guardrail transition to rigid barrier, F&I- index 536- 002, approach TL-3 (0536-8122) | EACH | 27 | $2,879.16 | $2,900.00 | $2,880.00 | $2,900.00 | $2,879.16 |
| 0380 | Guardrail removal (0536-73) | LF | 19,696 | $1.00 | $1.00 | $1.00 | $1.05 | $1.00 |
| 0385 | Guardrail end treatment- trailing anchorage (0536-85-20) | EACH | 16 | $1,175.41 | $1,175.00 | $1,180.00 | $1,200.00 | $1,175.41 |
| 0390 | Guardrail end treatment- parallel approach terminal (0536-85-24) | EACH | 25 | $2,907.32 | $2,900.00 | $2,910.00 | $3,000.00 | $2,907.32 |
| 0395 | Guardrail end treatment- double face approach terminal (0536-85-27) | EACH | 8 | $9,374.26 | $9,375.00 | $9,370.00 | $9,500.00 | $9,374.26 |
| 0400 | Performance turf, sod (0570-1-2) | SY | 11,582 | $0.01 | $6.00 | $3.15 | $5.40 | $3.50 |
| 0405 | Performance turf, sod and shoulder treatment index (0570-1-3) | SY | 19,218 | $1.00 | $7.00 | $3.15 | $5.90 | $3.50 |
| 0410 | Raised pavement marker, type B (0706-1-3) | EACH | 20,589 | $4.00 | $4.00 | $5.00 | $4.00 | $4.00 |
| 0415 | Painted pavement markings, standard, white, solid, 6" (0710-11101) | GM | 9.33 | $1,200.00 | $1,500.00 | $2,700.00 | $1,500.00 | $1,500.00 |
| 0420 | Painted pavement markings, standard, white, solid for interchange and urban island, (0710-11102) | GM | 1.73 | $3,491.93 | $1,600.00 | $2,000.00 | $1,600.00 | $1,600.00 |
| 0425 | Painted pavement markings, standard, white, solid for diagonal or chevron, 18" (0710-11124) | LF | 1,692 | $2.00 | $1.50 | $2.00 | $1.55 | $1.50 |
| 0430 | Painted pavement markings, standard, white, solid for stop line or crosswalk, 24" (0710-11125) | LF | 2,316 | $3.00 | $2.00 | $2.60 | $2.05 | $2.00 |
| 0435 | Painted pavement markings, standard, white, skip, 10-30 or skip, 6" wide (0710-11131) | GM | 0.86 | $891.60 | $800.00 | $402.00 | $795.00 | $800.00 |
| 0440 | Painted pavement markings, standard, white, message or symbol (0710-11160) | EACH | 2 | $70.00 | $100.00 | $200.00 | $100.00 | $100.00 |
| 0445 | Painted pavement markings, standard, yellow, solid, 6" (0710-11201) | GM | 1.63 | $2,584.05 | $1,500.00 | $2,690.00 | $1,500.00 | $1,500.00 |
| 0450 | Fiber reinforced polymer patching material (0916-351) | LB | 321 | $25.00 | $20.00 | $200.00 | $20.50 | $20.00 |
| 0455 | Disputes review board, meeting- DO not bid (0999-20-1) | DA | 20 | $4,800.00 | $4,800.00 | $4,800.00 | $4,800.00 | $4,800.00 |
| 0460 | Disputes review board, hearing- DO not bid (0999-20-2) | EACH | 3 | $5,750.00 | $5,750.00 | $5,750.00 | $5,750.00 | $5,750.00 |
| 0465 | Initial contingency amount, DO not bid (0999-25) | LS | 1 | $150,000 | $150,000 | $150,000 | $150,000 | $150,000 |
| 0470 | Single column ground sign assembly, F&I ground mount, than 12 SF (0700-1111) | EACH | 10 | $528.08 | $820.00 | $816.00 | $665.00 | $815.77 |
| 0475 | Single column ground sign assembly, F&I ground mount, 20.0 SF (0700-1112) | EACH | 3 | $2,350.57 | $1,400.00 | $1,380.00 | $1,800.00 | $1,384.29 |
| 0480 | Single column ground sign assembly, remove (0700-1600) | EACH | 8 | $59.56 | $200.00 | $199.00 | $42.00 | $198.72 |
| 0485 | Retroreflective sign strip- furnish and install, 5' (0700-13-15) | EACH | 27 | $87.51 | $225.00 | $64.75 | $89.00 | $64.70 |
| 0490 | Raised pavement marker, type B (0706-1-3) | EACH | 1,521 | $0.01 | $4.00 | $5.00 | $4.05 | $4.00 |
| 0495 | Painted pavement markings, surface (0710-90) | LS | 1 | $125,000 | $90,000 | $110,000 | $85,000 | $90,000 |
| 0500 | Thermoplastic, standard, solid, 12" for crosswalk and roundabout (0711-11123) | LF | 127 | $5.00 | $4.00 | $6.50 | $4.05 | $4.00 |
| 0505 | Thermoplastic, standard, solid, 18" for diagonals and chevrons (0711-11124) | LF | 5,030 | $9.00 | $5.00 | $4.50 | $5.05 | $5.00 |
| 0510 | Thermoplastic, standard, solid, 24" for stop line and crosswalk (0711-11125) | LF | 80 | $10.00 | $8.00 | $12.00 | $8.05 | $8.00 |
| 0515 | Thermoplastic, standard, message or symbol (0711-11160) | EACH | 2 | $150.00 | $300.00 | $140.00 | $305.00 | $300.00 |
| 0520 | Thermoplastic, standard, arrow (0711-11170) | EACH | 11 | $100.00 | $125.00 | $95.00 | $126.00 | $125.00 |
| 0525 | Thermoplastic, standard, yellow, solid, 18" for diagonal or chevron (0711-11224) | LF | 441 | $9.00 | $5.00 | $3.50 | $5.05 | $5.00 |
| 0530 | Thermoplastic, preformed, white, solid, 12" for crosswalk (0711-14123) | LF | 331 | $9.00 | $12.00 | $5.00 | $12.50 | $12.00 |
| 0535 | Thermoplastic, preformed, white, solid, 24" for crosswalk (0711-14125) | LF | 426 | $17.00 | $20.00 | $12.00 | $21.00 | $20.00 |
| 0540 | Thermoplastic, preformed, white, message (0711-14160) | EACH | 11 | $300.00 | $800.00 | $500.00 | $805.00 | $800.00 |
| 0545 | Thermoplastic, preformed, white, arrow (0711-14170) | EACH | 13 | $250.00 | $600.00 | $640.00 | $605.00 | $600.00 |
| 0550 | Thermoplastic, standard-other surfaces, white, solid, 6" (0711-16101) | GM | 7.12 | $6,198.26 | $6,000.00 | $3,500.00 | $6,000.00 | $6,000.00 |
| 0555 | Thermoplastic, standard-other surfaces, white, solid, 8" (0711-16102) | GM | 1.27 | $9,485.06 | $6,500.00 | $5,800.00 | $6,500.00 | $6,500.00 |
| 0560 | Thermoplastic, standard-other surfaces, yellow, solid, 6" (0711-16201) | GM | 7.08 | $6,192.12 | $6,000.00 | $3,675.00 | $6,000.00 | $6,000.00 |
| 0565 | Permanent tape, white, solid, 6" for concrete bridges (0713-103101) | GM | 0.69 | $47,931 | $35,000 | $29,960 | $35,000 | $35,000 |
| 0570 | Permanent tape, white, solid, 8" exit lane at interchange on concrete pavement (0713-103102) | GM | 0.03 | $50,000 | $45,000 | $36,360 | $41,000 | $45,000 |
| 0575 | Permanent tape, white, 3-9 dotted, 6" wide, for concrete surfaces (0713-103171) | GM | 0.78 | $14,943 | $12,500 | $15,440 | $12,500 | $12,500 |
| 0580 | Permanent tape, white, 10-30 6" wide, for concrete surfaces (0713-103181) | GM | 6.67 | $9,491.45 | $12,500 | $9,490.00 | $12,500 | $12,500 |
| 0585 | Permanent tape, yellow, solid, for concrete bridges (0713-103201) | GM | 0.69 | $14,804 | $35,000 | $29,610 | $34,600 | $35,000 |
| 0590 | Permanent tape, black, 3-9 dotted, 6" wide, for concrete surfaces (0713-103371) | GM | 0.78 | $47,816 | $12,500 | $15,440 | $12,500 | $12,500 |
| 0595 | Permanent tape, black, 10-30 6" wide, for concrete surfaces (0713-103381) | GM | 6.61 | $9,487.06 | $12,500 | $9,490.00 | $12,500 | $12,500 |
| 0600 | Conduit, furnish & install, open trench (0630-2-11) | LF | 430 | $14.71 | $13.00 | $12.90 | $23.00 | $12.87 |
| 0605 | Pull & splice box, F&I, 13" X 24" cover size (0635-2-11) | EACH | 5 | $1,536.71 | $1,258.00 | $1,260.00 | $1,300.00 | $1,257.80 |
| 0610 | Lighting conductors, F&I, insulated, no.8 - 6 (0715-1-12) | LF | 1,370 | $2.94 | $8.00 | $7.75 | $2.30 | $7.74 |
| 0615 | Luminaire & bracket arm- aluminum, furnish & install new luminaire and arm on new/existing pole (0715-5-31) | EACH | 1 | $2,979.49 | $2,918.00 | $2,920.00 | $1,600.00 | $2,917.62 |
| 0620 | Light pole complete, F&I, standard pole standard foundation, 30' mounting height, 8' arm length (0715-61111) | EACH | 4 | $9,068.64 | $12,022 | $12,020 | $9,300.00 | $12,021 |
| 0625 | Light pole complete, remove pole and foundation (0715-69000) | EACH | 3 | $714.73 | $994.00 | $994.00 | $1,400.00 | $993.60 |
| 0630 | Vehicular traffic signal, furnish & install aluminum, 3 section, 1 way (0650-1-14) | AS | 2 | $2,181.56 | $2,049.00 | $250.00 | $2,500.00 | $2,049.30 |
| 0635 | Vehicular traffic signal, remove- poles to remain (0650-1-60) | AS | 2 | $238.24 | $373.00 | $273.00 | $175.00 | $372.60 |
| 0640 | Vehicular signal auxiliaries, repair/replace/retrofit- & install, backplate- flexible required (0650-2109) | EACH | 6 | $577.32 | $934.00 | $934.00 | $550.00 | $934.17 |
| 0645 | Utility work- jpa/utility agreement, power (1000-7) | LS | 1 | $43,289 | $60,000 | $54,398 | $51,000 | $54,398 |
| 0650 | Itsfm subsurface documentation- project length (0611-1-1) | MI | 3.00 | $3,263.22 | $3,105.00 | $3,100.00 | $4,050.00 | $3,105.00 |
| 0655 | Itsfm location documentation- ITS site (0611-2-2) | EACH | 2 | $2,355.99 | $2,106.00 | $2,110.00 | $2,800.00 | $2,106.00 |
| 0660 | Conduit, furnish & install, open trench (0630-2-11) | LF | 431 | $22.12 | $23.50 | $23.40 | $23.00 | $23.39 |
| 0665 | Conduit, furnish & install, directional bore (0630-2-12) | LF | 740 | $42.41 | $44.00 | $44.00 | $41.00 | $44.12 |
| 0670 | Conduit, furnish & install, aboveground (0630-2-14) | LF | 36 | $39.86 | $41.25 | $41.25 | $40.00 | $41.19 |
| 0675 | Fiber optic cable, F&I, underground,2-12 fibers (0633-1121) | LF | 1,591 | $4.57 | $4.05 | $4.05 | $5.70 | $4.05 |
| 0680 | Fiber optic connection, install, splice (0633-2-31) | EACH | 48 | $58.78 | $54.00 | $54.00 | $70.00 | $54.00 |
| 0685 | Fiber optic connection hardware, F&I, splice tray (0633-3-12) | EACH | 3 | $58.78 | $54.00 | $54.00 | $70.00 | $54.00 |
| 0690 | Fiber optic connection hardware, F&I, buffer tube fan out kit (0633-3-14) | EACH | 4 | $97.96 | $92.00 | $91.75 | $120.00 | $91.80 |
| 0695 | Fiber optic connection hardware, F&I, patch panel- terminated (0633-3-16) | EACH | 3 | $1,730.67 | $1,431.00 | $1,430.00 | $1,875.00 | $1,431.00 |
| 0700 | Fiber optic cable locator (0633-6) | DA | 400 | $0.50 | $149.00 | $149.00 | $305.00 | $1.00 |
| 0705 | Pull & splice box, F&I, 13" X 24" cover size (0635-2-11) | EACH | 19 | $1,536.64 | $1,582.00 | $1,580.00 | $1,300.00 | $1,581.80 |
| 0710 | Pull & splice box, F&I, 24" X 36" cover size (0635-2-12) | EACH | 6 | $3,081.56 | $2,672.00 | $2,670.00 | $2,050.00 | $2,671.75 |
| 0715 | Electrical power service, adjust/modify (0639-1500) | AS | 1 | $952.98 | $3,760.00 | $3,760.00 | $3,100.00 | $3,760.02 |
| 0720 | Electrical service wire, & install (0639-2-1) | LF | 1,733 | $16.52 | $7.00 | $6.95 | $5.70 | $6.93 |
| 0725 | Electrical service disconnect, F&I, pole mount (0639-3-11) | EACH | 3 | $2,692.01 | $3,760.00 | $3,760.00 | $3,900.00 | $3,760.02 |
| 0730 | Electrical service disconnect, remove- pole or cabinet to remain (0639-3-60) | EACH | 1 | $476.49 | $596.00 | $596.00 | $175.00 | $596.16 |
| 0735 | Electrical power service- transformer, F&I, <5 kva, single phase, copper windings (0639-6111) | EACH | 4 | $2,630.09 | $2,413.00 | $2,410.00 | $2,650.00 | $2,412.72 |
| 0740 | Prestressed concrete pole, type P-II service pole (0641-2-12) | EACH | 2 | $2,630.09 | $2,064.00 | $2,060.00 | $1,550.00 | $2,063.64 |
| 0745 | Vehicle detection system- wrong way for exit ramp, 1 or 2 lanes, AC powered (0660-7-21) | EACH | 2 | $43,485 | $50,196 | $50,200 | $58,000 | $50,196 |
| 0750 | ITS cabinet, furnish & install, base mount with sunshield, 24" W X 46" H X 22" D (0676-2142) | EACH | 2 | $9,370.43 | $11,570 | $11,570 | $14,500 | $11,570 |
| 0755 | Managed field ethernet switch, furnish & install (0684-1-1) | EACH | 2 | $6,765.67 | $7,500.00 | $7,500.00 | $9,700.00 | $7,500.60 |
| 0760 | Uninterruptible power supply, furnish and install, line interactive (0685-1-11) | EACH | 2 | $6,295.72 | $5,678.00 | $5,680.00 | $7,600.00 | $5,678.10 |
| 0765 | Remote power management rpmu, furnish and install (0685-2-1) | EACH | 2 | $937.04 | $518.00 | $518.00 | $1,950.00 | $517.70 |
| 0770 | Single column ground sign assembly, remove (0700-1600) | EACH | 4 | $89.34 | $199.00 | $199.00 | $60.00 | $198.72 |
| 0775 | Retroreflective sign strip- furnish and install, 5' (0700-13-15) | EACH | 4 | $101.49 | $65.00 | $64.75 | $120.00 | $64.70 |
| 0780 | Enhanced highway sign AC powered, F&I ground mount, highlighted sign <12 SF (0700-141140) | EACH | 4 | $8,183.39 | $8,070.00 | $8,070.00 | $7,600.00 | $8,070.27 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from FDOT's tabulation for this contract. FDOT Tabulation of Bids PDFs from its central office lettings, January 2018 to October 2026, all pay items. On A+B contracts the cost part is kept (the total the pay items add up to). Bidders listed without a rank or total are left out.
Every contract let that day: FDOT letting of February 25, 2026. Compiled by Mirage Metrics.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.