FDOT contract T4693 bid tabulation

SR 7 (US 441) FROM N OF GLADES RD TO N OF BRIDGE BROOK DR. Let by Florida DOT on February 26, 2025, Palm Beach, District 4. 6 bids received; low bid $9,521,050 by Weekley Asphalt Paving, Inc..

Owner
Florida DOT
Letting
26 FEB 2025
Pay items
140
Data through
28 OCT 2026

Bidders

RankBidderTotal bidAgainst the low bid
1Weekley Asphalt Paving, Inc.$9,521,050Low
2General Asphalt Company, LLC$10,065,703+6.0%
3Ohla USA Inc$10,131,010+6.0%
4Ranger Construction Industries, Inc.$10,756,829+13%
5Halley Engineering Contractors, Inc.$11,095,261+17%
6Asphalt Group, Inc.$12,778,094+34%
FDOT contract T4693: bids by rank

Bid tabulation

LinePay itemUnitQuantity1. Weekley Asphalt Paving, Inc.2. General Asphalt Company, LLC3. Ohla USA Inc4. Ranger Construction Industries, Inc.5. Halley Engineering Contractors, Inc.6. Asphalt Group, Inc.
0005Mobilization (0101-1)LS1$323,475$270,000$1,000,000$1,000,000$1,100,000$1,200,000
0010Maintenance of traffic (0102-1)DA1$546,338$1,000,000$420,000$750,000$925,000$1,200,000
0015Traffic control officer (0102-14)HR364$89.00$82.50$75.00$106.25$85.00$100.00
0020Work zone sign (0102-60)ED2,552$0.24$0.26$0.30$0.31$0.25$0.25
0025Channelizing device- types I, II, VP, drum, or LCD (0102-74-1)ED77,307$0.11$0.12$0.11$0.12$0.25$0.12
0030Channelizing device- pedestrian LCD (longitudinal channelizing device) (0102-74-8)FD1,830$0.10$0.11$0.20$0.22$0.15$1.00
0035Arrow board / advance warning arrow panel (0102-76)ED475$6.00$5.83$5.00$5.59$7.00$7.00
0040Portable changeable message sign, temporary (0102-99)ED489$11.00$12.10$10.00$11.20$14.00$14.00
0045Temporary signalization and maintenance, intersection (0102-104)ED2,346$15.54$11.55$26.25$20.10$18.00$15.54
0050Temporary traffic detection and maintenance, intersection (0102-107-1)ED2,346$1.20$1.10$25.25$20.10$18.00$1.20
0055Type III barricade (0102-115)ED1,006$0.35$0.34$0.35$0.39$0.30$0.30
0060Sediment barrier (0104-10-3)LF4,376$1.60$0.01$2.30$1.72$3.00$2.00
0065Floating turbidity barrier (0104-11)LF215$38.00$11.00$25.00$13.95$10.00$20.00
0070Inlet protection system (0104-18)EACH35$150.00$154.00$250.00$151.00$125.00$120.00
0075Litter removal (0107-1)ACRE740.15$10.00$0.01$39.00$33.55$35.00$15.00
0080Mowing (0107-2)ACRE496.36$10.00$0.01$90.00$34.65$100.00$15.00
0085Monitor existing structures- inspection and settlement monitoring (0108-1)LS1$7,230.00$1.10$8,000.00$6,595.00$5,000.00$5,000.00
0090Monitor existing structures- vibration monitoring (0108-2)LS1$4,350.00$1.10$5,000.00$4,359.00$5,000.00$5,000.00
0095Clearing & grubbing (0110-1-1)ACRE1$137,720$52,932$900,000$282,500$70,000$793,000
0100Selective clearing and areas with trees to remain (0110-2-2)ACRE0.01$445,600$1,100,000$1,000,000$39,120$20,000$750,000
0105Removal of existing concrete (0110-4-10)SY1,281$40.00$35.20$23.00$41.55$25.00$35.00
0110Regular excavation (0120-1)CY563.30$48.00$25.77$21.00$39.85$20.00$25.00
0115Embankment (0120-6)CY1,976.60$32.50$52.58$23.00$43.85$40.00$35.00
0120Milling existing asphalt pavement, 2" avg depth (0327-70-5)SY209,601$2.75$3.51$3.00$2.71$4.30$8.00
0125Asphalt concrete friction course,traffic C, FC-12.5, PG (0337-7-83)TN23,056.10$180.00$183.65$160.00$180.00$202.00$170.00
0130Miscellaneous asphalt (0339-1)TN76.20$250.00$316.60$450.00$221.75$250.00$300.00
0135Concrete class NS, gravity index 400-011 (0400-0-11)CY2.20$29.00$1,650.00$965.00$1,079.00$3,000.00$2,000.00
0140Inlets, DT bot, type C,jbot, <10' (0425-1523)EACH1$10,600$8,580.00$12,100$8,383.00$7,500.00$20,000
0145Inlets, ditch bottom, type D, J bot, <10' (0425-1543)EACH6$12,460$10,296$15,200$10,060$9,000.00$20,000
0150Inlets, closed flume (0425-1910)EACH2$7,813.00$11,440$10,350$11,180$10,000$6,000.00
0155Manhole, adjust (0425-5)EACH4$700.00$858.00$1,320.00$838.25$750.00$2,000.00
0160Pipe culvert, optional material, round, 18"SD (0430-174118)LF212$304.25$354.64$215.00$346.50$310.00$500.00
0165Pipe culvert, optional material, round, 24"SD (0430-174124)LF9$410.25$755.04$230.00$737.75$660.00$1,000.00
0170Mitered end section, optional round, 24" SD (0430-984129)EACH1$7,105.00$6,864.00$5,060.00$6,707.00$6,000.00$5,000.00
0175Pipe handrail - guiderail, aluminum (0515-1-2)LF51$60.00$117.70$94.00$105.00$52.00$120.00
0180Concrete curb & gutter, type F (0520-1-10)LF693$49.00$59.28$62.00$51.90$44.00$52.00
0185Concrete curb, type D (0520-2-4)LF128$44.00$49.24$67.00$54.20$63.00$55.00
0190Concrete sidewalk and driveways, 4" thick (0522-1)SY2,908$49.50$64.08$56.00$65.20$76.00$100.00
0195Concrete sidewalk and driveways, 6" thick (0522-2)SY1,031$59.00$120.45$82.00$93.20$86.00$100.00
0200Detectable warnings (0527-2)SF837$48.00$39.60$45.00$50.30$63.00$45.00
0205Guardrail -roadway, general (0536-1-1)LF705$27.10$30.80$23.75$23.35$24.32$20.88
0210Special guardrail post- post for shallow mount (0536-7-3)EACH6$192.00$209.00$113.00$111.50$172.13$99.84
0215Guardrail transition to rigid barrier, F&I- index 536- 002, approach TL-3 (0536-8122)EACH2$4,170.00$4,620.00$3,100.00$3,056.00$3,752.00$2,734.00
0220Guardrail transition to rigid barrier, F&I- index 536- 002, trailing (0536-8123)EACH1$1,486.00$4,730.00$1,800.00$1,780.00$1,337.00$1,592.00
0225Guardrail removal (0536-73)LF1,150$3.45$2.15$2.45$2.40$3.10$2.15
0230Guardrail end treatment- parallel approach terminal (0536-85-24)EACH4$3,528.00$3,795.00$3,365.00$3,309.00$3,175.00$2,960.00
0235Performance turf, sod (0570-1-2)SY11,344$3.60$2.92$3.70$9.60$5.00$3.00
0240Performance turf, sod and shoulder treatment index (0570-1-3)SY10,366$7.10$6.22$3.20$9.60$7.00$5.00
0245Irrigation system- modify existing system (0590-70-5)LS1$12,800$12,650$11,500$18,440$21,000$11,500
0250Conduit, furnish & install, open trench (0630-2-11)LF229$32.69$45.10$27.00$25.15$22.50$32.69
0255Conduit, furnish & install, directional bore (0630-2-12)LF185$66.36$48.40$55.00$26.25$23.50$66.36
0260Pull & splice box, F&I, 13" X 24" cover size (0635-2-11)EACH9$1,772.89$1,468.50$950.00$2,080.00$1,111.00$1,772.00
0265Traffic monitoring site vehicle sensor-non-weight, furnish & install (0695-1-1)EACH18$2,227.80$2,244.00$1,900.00$2,222.00$1,989.00$2,227.00
0270Traffic monitoring site inductive loop assembly, & install, 2 loops (0695-6-12)EACH18$2,382.68$1,578.50$1,200.00$2,557.00$2,288.00$2,382.00
0275Traffic monitoring site cabinet, furnish & install, type 4, base mount (0695-7141)EACH2$8,293.76$13,200$6,885.00$12,840$11,489$8,293.00
0280Painted pavement markings, standard, white, solid, 6" (0710-11101)GM13.60$1,350.00$440.00$1,350.00$447.00$400.00$400.00
0285Painted pavement markings, standard, white, solid for crosswalk and roundabout, 12" (0710-11123)LF3,500$1.00$0.28$1.00$0.28$0.25$0.25
0290Painted pavement markings, standard, white, solid for stop line or crosswalk, 24" (0710-11125)LF1,200$3.00$0.39$3.00$0.39$0.35$0.35
0295Painted pavement markings, standard, white, arrows (0710-11170)EACH25$35.00$11.00$35.00$11.20$10.00$10.00
0300Painted pavement markings, standard, yellow, solid, 6" (0710-11201)GM6.50$1,350.00$440.00$1,400.00$447.00$400.00$400.00
0305Partnering, DO not bid (0999-16)LS1$6,000.00$6,000.00$6,000.00$6,000.00$6,000.00$6,000.00
0310Initial contingency amount, DO not bid (0999-25)LS1$107,501$107,501$107,501$107,501$107,501$107,501
0315Single column ground sign assembly, F&I ground mount, than 12 SF (0700-1111)EACH130$510.00$605.28$550.00$615.00$525.00$550.25
0320Single column ground sign assembly, F&I ground mount, 20.0 SF (0700-1112)EACH40$1,900.00$1,853.76$1,685.00$1,884.00$1,385.00$1,685.00
0325Single column ground sign assembly, remove (0700-1600)EACH119$35.00$55.00$50.00$55.90$30.00$50.00
0330Multi-column ground sign assembly, F&I ground mount, 30.0 SF (0700-2113)EACH5$8,000.00$6,431.03$5,850.00$6,535.00$4,500.00$5,846.00
0335Multi-column ground sign assembly, F&I ground mount, 50.0 SF (0700-2114)EACH3$9,000.00$7,176.87$6,525.00$7,293.00$5,850.00$6,524.00
0340Multi-column ground sign assembly, F&I ground mount, 100.0 SF (0700-2115)EACH2$9,500.00$9,951.45$9,050.00$10,110$6,950.00$9,046.00
0345Multi-column ground sign assembly, remove (0700-2600)EACH9$2,000.00$1,320.00$1,200.00$1,341.00$650.00$1,200.00
0350Retroreflective sign strip- furnish and install, 5' (0700-13-15)EACH50$125.00$154.00$140.00$156.50$100.00$140.00
0355Tubular marker, 36" yellow (0704-1-4)EACH28$225.00$242.23$220.00$246.25$220.00$220.00
0360Object marker, type 1 (0705-10-1)EACH15$325.00$220.00$200.00$223.50$225.00$200.00
0365Raised pavement marker, type B (0706-1-3)EACH3,999$5.00$4.40$5.00$4.47$4.00$5.00
0370Painted pavement markings, durable paint, yellow, island nose (0710-12290)SF109$10.00$4.40$10.00$4.47$4.00$10.00
0375Painted pavement markings, surface (0710-90)LS1$60,000$113,758$60,000$115,600$103,416$103,416
0380Thermoplastic, standard, solid, 12" for crosswalk and roundabout (0711-11123)LF6,883$4.00$3.50$4.00$3.55$3.18$3.18
0385Thermoplastic, standard, solid, 18" for diagonals and chevrons (0711-11124)LF696$5.00$5.25$5.00$5.33$4.77$4.77
0390Thermoplastic, standard, solid, 24" for stop line and crosswalk (0711-11125)LF2,933$6.00$7.00$6.00$7.11$6.36$6.36
0395Thermoplastic, standard, 2-4 dotted guideline/ 6-10 gap extension, 6" (0711-11141)GM3.46$3,000.00$2,200.00$3,000.00$2,236.00$2,000.00$2,000.00
0400Thermoplastic, standard, arrow (0711-11170)EACH179$90.00$59.40$90.00$60.40$54.00$54.90
0405Thermoplastic, standard, yellow, solid, 18" for diagonal or chevron (0711-11224)LF800$7.00$4.90$7.00$4.97$4.45$4.45
0410Thermoplastic, standard, yellow, 2-4 dotted guide line dotted extension line, 6" (0711-11241)GM0.61$3,000.00$2,200.00$3,000.00$2,236.00$2,000.00$2,000.00
0415Thermoplastic, preformed, white, solid, 24" for crosswalk (0711-14125)LF3,819$16.00$17.47$16.00$17.75$15.88$15.88
0420Thermoplastic, preformed, white, message (0711-14160)EACH91$200.00$280.50$200.00$285.00$255.00$255.00
0425Thermoplastic, preformed, white, arrow (0711-14170)EACH159$225.00$119.90$225.00$121.75$109.00$109.00
0430Thermoplastic, standard-other surfaces, white, solid, 6" (0711-16101)GM16.24$5,200.00$5,001.70$5,200.00$5,083.00$4,547.00$4,547.00
0435Thermoplastic, standard-other surfaces, white, solid, 8" (0711-16102)GM0.34$6,000.00$6,669.30$5,850.00$6,777.00$6,063.00$6,063.00
0440Thermoplastic, standard-other surfaces, white, skip, 6",10-30 or 3-9 lane drop (0711-16131)GM12.25$2,500.00$1,250.70$2,500.00$1,271.00$1,137.00$1,137.00
0445Thermoplastic, standard-other surfaces, yellow, solid, 6" (0711-16201)GM7.03$5,200.00$4,688.20$5,200.00$4,764.00$4,262.00$4,262.00
0450Green-colored pavement markings, bike lane (0714-10)SF19,301$8.00$9.35$8.00$9.50$6.00$8.50
0455Conduit, furnish & install, open trench (0630-2-11)LF4,259$20.59$15.40$16.00$18.45$16.50$20.59
0460Conduit, furnish & install, directional bore (0630-2-12)LF173$44.63$37.40$38.00$39.10$35.00$44.63
0465Conduit, furnish & install, mount (0630-2-15)LF240$55.55$51.70$55.00$83.60$74.80$55.55
0470Conduit, remove, bridge mount (0630-2-65)LF180$11.95$18.70$16.00$29.85$26.70$11.95
0475Pull & splice box, F&I, 13" X 24" cover size (0635-2-11)EACH39$1,772.89$2,607.00$1,075.00$2,096.00$1,125.00$1,772.00
0480Pull & splice box, install (0635-2-30)EACH1$1,422.97$2,200.00$555.00$2,459.00$1,450.00$1,422.00
0485Electrical power service, F&I, underground, meter by contractor (0639-1122)AS1$6,034.16$7,617.50$5,850.00$9,222.00$8,250.00$6,034.00
0490Electrical power service, remove underground (0639-1620)AS1$956.40$962.50$1,100.00$715.50$641.00$956.00
0495Lighting conductors, F&I, insulated, no.8 - 6 (0715-1-12)LF1,713$3.76$3.30$2.00$3.69$3.30$3.76
0500Lighting conductors, F&I, insulated, no 4 to no 2 (0715-1-13)LF15,307$5.47$3.58$6.00$5.25$4.70$5.47
0505Lighting conductors, remove & dispose, contractor owns (0715-1-60)LF15,983$0.60$1.10$1.00$0.22$0.20$0.60
0510Luminaire & bracket arm- aluminum, furnish & install new luminaire and arm on new/existing pole (0715-5-31)EACH1$2,908.21$2,695.00$2,300.00$2,929.00$2,620.00$2,908.00
0515Load center, F&I, secondary voltage (0715-7-11)EACH1$21,501$25,025$15,500$20,850$18,650$21,500
0520Load center, remove, voltage (0715-7-41)EACH1$956.40$960.30$825.00$950.00$850.00$956.00
0525Luminaire, F&I- replace existing luminaire on existing pole/arm, roadway, cobra head (0715-11211)EACH29$1,951.74$1,353.00$1,500.00$1,453.00$1,300.00$1,951.00
0530Light pole complete, F&I, standard pole standard foundation, 50' mounting height, 15' arm length (0715-61552)EACH18$14,007$13,398$9,950.00$9,892.00$8,850.00$14,007
0535Light pole complete, remove pole and foundation (0715-69000)EACH19$1,195.49$1,540.00$2,100.00$726.50$650.00$1,195.00
0540Pole cable distribution system, furnish and install, conventional (0715-500-1)EACH48$1,219.84$968.00$640.00$827.25$740.00$1,219.00
0545Conduit, furnish & install, open trench (0630-2-11)LF1,321$22.71$18.70$27.00$35.20$31.50$22.71
0550Conduit, furnish & install, directional bore (0630-2-12)LF2,263$50.38$39.60$55.00$35.20$31.50$50.80
0555Signal cable- new or reconstructed intersection, furnish & install (0632-7-1)PI5$9,268.90$6,424.00$3,690.00$13,970$12,500$9,268.00
0560Signal cable, remove- intersection (0632-7-6)PI5$1,912.79$1,820.50$1,325.00$596.25$534.00$1,912.00
0565Pull & splice box, F&I, 17" X 30" cover size (0635-2-14)EACH113$1,878.52$2,200.00$1,225.00$2,347.00$1,350.00$1,878.00
0570Pull & splice box, F&I, 30" X 48" cover size (0635-2-15)EACH5$4,329.29$4,361.50$4,680.00$4,024.00$2,850.00$4,329.00
0575Pull & splice box, install (0635-2-30)EACH6$1,267.44$1,430.00$555.00$1,900.00$950.00$1,267.00
0580Electrical power service, F&I, underground, meter by contractor (0639-1122)AS6$4,789.97$4,889.50$5,800.00$6,434.00$5,757.00$4,789.00
0585Electrical power service, remove underground (0639-1620)AS6$717.30$962.50$1,100.00$447.25$401.00$717.00
0590Electrical service wire, & install (0639-2-1)LF585$11.28$9.90$4.00$11.85$10.60$11.28
0595Electrical service wire, (0639-2-6)LF739$0.48$4.13$1.00$0.28$0.25$0.48
0600Electrical service disconnect, F&I, pole mount (0639-3-11)EACH6$3,701.31$2,986.50$1,450.00$2,388.00$2,137.00$3,701.00
0605Prestressed concrete pole, type P-II service pole (0641-2-12)EACH6$4,090.12$3,025.00$2,050.00$2,307.00$2,064.00$4,090.00
0610Aluminum signals pole, (0646-1-11)EACH28$2,812.53$2,876.50$3,175.00$2,042.00$1,828.00$2,812.00
0615Aluminum signals pole, remove (0646-1-60)EACH8$478.20$374.00$875.00$447.25$401.00$478.00
0620Vehicular signal auxiliaries, repair/replace/retrofit- & install, backplate- flexible required (0650-2109)EACH94$1,106.10$742.50$750.00$592.50$530.00$1,106.00
0625Pedestrian signal, furnish & install LED countdown, 1 way (0653-1-11)AS26$1,013.20$880.00$840.00$726.50$650.00$1,013.00
0630Pedestrian signal, furnish & install LED countdown, 2 ways (0653-1-12)AS3$1,805.96$2,090.00$1,700.00$1,509.00$1,350.00$1,805.00
0635Pedestrian signal, remove ped signal- pole/pedestal to remain (0653-1-60)AS19$119.55$198.00$137.00$149.00$134.00$119.55
0640Loop detector inductive, F&I, type 9 (0660-1109)EACH8$525.26$489.50$370.00$357.75$320.00$525.00
0645Loop assembly, F&I, type F (0660-2106)AS82$2,032.68$1,666.50$1,165.00$2,459.00$2,201.00$2,032.00
0650Pedestrian detector, furnish & install, standard (0665-1-11)EACH31$433.50$379.50$485.00$391.25$350.00$433.00
0655Pedestrian detector, relocate (0665-1-40)EACH3$517.08$242.00$275.00$189.00$170.00$517.00
0660Pedestrian detector, remove- pole/pedestal to remain (0665-1-60)EACH19$119.55$121.00$70.00$74.60$67.00$119.00
0665Traffic controller, modify (0671-2-40)EACH5$3,257.99$2,365.00$830.00$6,371.00$5,700.00$3,257.00
0670Sign panel, furnish & install overhead mount, UP to 12 SF (0700-3201)EACH6$1,289.22$880.00$945.00$952.00$852.00$1,289.00
0675Sign panel, remove, UP to 12 SF (0700-3601)EACH6$119.22$126.50$66.00$149.00$134.00$119.00
0680Internally illuminated sign, furnish & install, overhead mount, 12-18 SF (0700-5-22)EACH4$4,723.13$7,502.00$6,875.00$4,248.00$3,800.00$4,723.00
0685Internally illuminated sign, remove (0700-5-60)EACH4$717.30$363.00$400.00$149.00$134.00$717.00
0690Manhole, adjust, utilities (0425-5-1)EACH7$800.00$915.20$1,000.00$894.25$800.00$2,000.00
0695Valve boxes, adjust (0425-6)EACH25$500.00$743.60$1,000.00$726.50$650.00$500.00
0700Local agency initial amount (DO not bid) (0999-26)LS1$1,238.75$1,238.75$1,238.75$1,238.75$1,238.75$1,238.75
FDOT contract T4693: unit prices by line

The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.

Source

Read from FDOT's tabulation for this contract. FDOT Tabulation of Bids PDFs from its central office lettings, January 2018 to October 2026, all pay items. On A+B contracts the cost part is kept (the total the pay items add up to). Bidders listed without a rank or total are left out.

Every contract let that day: FDOT letting of February 26, 2025. Compiled by Mirage Metrics.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy