FDOT contract T5855 bid tabulation

SR 530 (US 192) FROM SR 25 (US 27) TO ORANGE CO LINE. Let by Florida DOT on June 11, 2025, Lake, District 5. 7 bids received; low bid $6,118,855 by Atlantic Civil Constructors Corp.

Owner
Florida DOT
Letting
11 JUN 2025
Pay items
146
Data through
28 OCT 2026

Bidders

RankBidderTotal bidAgainst the low bid
1Atlantic Civil Constructors Corp$6,118,855Low
2Ranger Construction Industries, Inc.$6,196,436+1.0%
3Hubbard Construction Company$6,304,871+3.0%
4Watson Civil Construction, Inc.$6,548,366+7.0%
5Preferred Materials Inc.$6,616,864+8.0%
6C.W. Roberts Contracting, Inc.$6,718,139+10%
7Superior Asphalt, Inc.$7,374,001+21%
FDOT contract T5855: bids by rank

Bid tabulation

LinePay itemUnitQuantity1. Atlantic Civil Constructors Corp2. Ranger Construction Industries, Inc.3. Hubbard Construction Company4. Watson Civil Construction, Inc.5. Preferred Materials Inc.6. C.W. Roberts Contracting, Inc.
0005Mobilization (0101-1)LS1$526,256$481,125$328,203$650,000$753,913$661,000
0010Maintenance of traffic (0102-1)DA1$407,109$600,000$263,098$575,000$398,994$550,000
0015Traffic control officer (0102-14)HR96$90.00$104.40$88.47$95.00$112.50$116.00
0020Work zone sign (0102-60)ED11,028$0.22$0.25$0.26$0.35$0.22$0.24
0025Temporary barrier, F&I, low profile, concrete (0102-71-13)LF84$65.00$71.40$41.21$68.00$39.00$42.00
0030Temporary barrier, relocate, low profile concrete (0102-71-23)LF72$48.00$52.80$19.02$50.00$18.00$20.00
0035Channelizing device- types I, II, VP, drum, or LCD (0102-74-1)ED26,814$0.09$0.10$0.12$0.15$0.10$0.11
0040Arrow board / advance warning arrow panel (0102-76)ED451$5.00$5.50$5.90$8.00$5.00$5.55
0045Portable changeable message sign, temporary (0102-99)ED822$10.00$11.00$11.80$16.00$10.00$11.10
0050Temporary signalization and maintenance, intersection (0102-104)ED220$15.81$17.35$46.37$25.00$15.81$17.70
0055Temporary traffic detection and maintenance, intersection (0102-107-1)ED220$15.81$17.35$1.05$25.00$15.81$17.70
0060Type III barricade (0102-115)ED958$0.35$0.40$0.31$0.55$0.26$0.29
0065Sediment barrier (0104-10-3)LF2,201$2.70$3.05$1.05$1.10$1.50$3.00
0070Staked turbidity barrier- nylon reinforced PVC (0104-12)LF2,015$5.04$7.50$4.98$5.00$4.75$9.60
0075Litter removal (0107-1)ACRE108.39$95.82$109.90$54.90$55.00$100.00$50.00
0080Mowing (0107-2)ACRE28.28$162.10$742.00$140.31$139.00$700.00$125.00
0085Clearing & grubbing (0110-1-1)ACRE1$296,711$179,000$280,738$275,000$30,800$223,000
0090Removal of existing concrete (0110-4-10)SY246$24.16$67.80$58.27$35.00$24.00$34.20
0095Regular excavation (0120-1)CY4,019.70$41.09$16.25$42.38$12.00$22.00$30.25
0100Embankment (0120-6)CY2,228.40$62.13$12.05$37.08$8.00$45.00$47.35
0105Type B stabilization (0160-4)SY5,018$18.18$27.90$23.31$26.00$40.00$16.25
0110Optional base, base group 01 (0285-701)SY612$27.82$42.15$31.78$39.00$60.00$44.45
0115Optional base, base group 02 (0285-702)SY988$23.83$37.30$34.96$35.00$40.00$36.25
0120Optional base, base group 03 (0285-703)SY586$56.96$52.40$48.58$62.00$40.00$105.00
0125Optional base, base group 09 (0285-709)SY1,274$38.64$39.50$40.26$60.00$60.00$47.60
0130Optional base, base group 10 (0285-710)SY1,325$65.12$52.60$65.78$61.00$40.00$61.70
0135Milling existing asphalt pavement, 1 1/2" avg depth (0327-70-6)SY5,140$8.00$8.45$8.11$9.75$20.93$9.70
0140Milling existing asphalt pavement, 4" avg depth (0327-70-7)SY35,007$10.00$7.05$6.53$4.20$6.23$6.77
0145Milling existing asphalt pavement, 2 1/4" avg depth (0327-70-11)SY13,135$8.00$4.95$5.74$5.35$6.73$8.50
0150Superpave asphaltic conc, traffic C (0334-1-13)TN8,369.30$150.00$148.90$174.51$168.00$191.08$157.35
0155Asphalt concrete friction course, inc bit, FC-5, PG 76-22 (0337-7-25)TN2,071.50$220.00$251.30$263.59$278.00$315.94$254.50
0160Inlets, DT bot, type D, <10' (0425-1541)EACH7$7,032.90$7,330.00$10,329$6,900.00$9,500.00$13,411
0165Inlets, DT bot, type E, modify (0425-1559)EACH2$7,786.18$14,400$13,772$8,200.00$4,000.00$13,392
0170Manholes, P-7, >10' (0425-2-42)EACH1$7,516.53$12,200$16,738$9,900.00$10,200$17,441
0175Pipe culvert, optional material, round, 18"SD (0430-174118)LF27$131.21$257.00$169.50$136.00$95.00$103.00
0180Pipe culvert, optional material, other shape - ellip/arch, 18"SD (0430-174218)LF258$184.56$160.30$180.10$175.00$110.00$162.00
0185Pipe culvert,optional material,round, 18"S/CD (0430-175118)LF109$114.02$109.30$169.50$133.00$95.00$103.00
0190Pipe culvert,optional material,round, 24"S/CD (0430-175124)LF1,569$117.47$160.80$169.50$164.00$130.00$156.00
0195Pipe culvert, opt material, round, 30"S/CD (0430-175130)LF246$172.26$223.00$238.36$198.00$180.00$215.00
0200Mitered end section, optional round, 18" CD (0430-982125)EACH1$1,910.22$3,850.00$2,648.47$2,000.00$2,000.00$2,820.00
0205Mitered end section, optional round, 18" SD (0430-984125)EACH2$1,910.22$4,610.00$2,648.48$2,000.00$2,250.00$3,028.00
0210Mitered end sect, optional - elliptical / arch, 18" SD (0430-984625)EACH8$2,014.06$4,880.00$2,648.47$2,200.00$2,250.00$2,845.00
0215Concrete curb & gutter, type E (0520-1-7)LF141$53.75$109.40$58.27$75.00$50.00$82.70
0220Concrete curb, type A (0520-2-1)LF257$42.92$65.30$42.38$54.00$62.00$45.55
0225Concrete curb, type B (0520-2-2)LF32$65.72$118.40$47.67$125.00$50.00$86.15
0230Concrete traffic separator, special- variable width (0520-70)SY8$298.52$333.00$370.79$144.00$150.00$605.00
0235Concrete sidewalk and driveways, 4" thick (0522-1)SY5,494$48.43$48.75$74.16$58.00$44.00$59.00
0240Concrete sidewalk and driveways, 6" thick (0522-2)SY131$119.69$99.90$116.53$93.00$65.00$132.25
0245Concrete slope pavement,non reinforced, 3" (0524-2-1)SY11$164.09$376.00$68.86$189.00$180.00$265.00
0250Detectable warnings (0527-2)SF646$24.49$53.40$47.67$45.00$25.00$35.50
0255Fencing, type B, 5.1-6.0', standard (0550-10220)LF8$56.26$61.80$59.75$58.00$300.00$33.80
0260Fencing, type B, 5.1-6.0, reset existing (0550-10228)LF591$15.98$17.55$16.97$16.50$50.00$33.80
0265Fence gate, type B, double, 18.1- 20.0' opening (0550-60224)EACH1$2,237.03$2,460.00$2,375.93$2,300.00$2,500.00$2,666.00
0270Performance turf, sod (0570-1-2)SY21,435$6.21$5.70$7.25$6.60$6.93$6.20
0275Conduit, furnish & install, open trench (0630-2-11)LF3$12.79$14.05$84.90$15.00$12.79$14.35
0280Conduit, furnish & install, directional bore (0630-2-12)LF165$28.91$31.75$32.33$34.00$28.91$32.45
0285Pull & splice box, F&I, 13" X 24" cover size (0635-2-11)EACH3$1,651.91$1,820.00$1,319.46$1,900.00$1,651.91$1,854.00
0290Traffic monitoring site vehicle sensor-non-weight, furnish & install (0695-1-1)EACH6$2,786.11$3,060.00$2,888.10$3,200.00$2,786.11$3,126.00
0295Traffic monitoring site inductive loop assembly, & install, 1 loop (0695-6-11)EACH12$1,199.55$1,320.00$1,051.36$1,370.00$1,199.55$1,346.00
0300Traffic monitoring site cabinet, F&I, type 3, 2 pane back, pedestal mount (0695-7162)EACH1$7,182.42$7,890.00$6,770.78$8,200.00$7,182.42$8,061.00
0305Traffic monitoring site cabinet, remove existing cabinet (0695-7600)EACH1$920.00$1,010.00$3,637.72$1,050.00$920.00$1,032.50
0310Raised pavement marker, type B (0706-1-3)EACH4,434$4.25$4.95$4.73$4.60$4.75$4.70
0315Painted pavement markings, standard, white, solid, 6" (0710-11101)GM9.18$2,400.00$1,650.00$1,575.84$1,520.00$1,600.52$2,665.00
0320Painted pavement markings, standard, white, solid for interchange and urban island, (0710-11102)GM2.06$2,700.00$2,630.00$2,518.38$2,450.00$2,106.10$2,994.00
0325Painted pavement markings, standard, white, solid for interchange markings, 12" (0710-11103)GM0.20$10,400$4,430.00$4,237.32$4,100.00$3,232.32$11,089
0330Painted pavement markings, standard, white, solid for crosswalk and roundabout, 12" (0710-11123)LF7,971$2.00$1.10$1.05$1.05$1.35$2.20
0335Painted pavement markings, standard, white, solid for diagonal or chevron, 18" (0710-11124)LF4,269$2.50$1.65$1.58$1.55$2.25$2.80
0340Painted pavement markings, standard, white, solid for stop line or crosswalk, 24" (0710-11125)LF3,126$3.00$1.90$1.84$1.80$2.65$3.30
0345Painted pavement markings, standard, white, skip, 10-30 or skip, 6" wide (0710-11131)GM7.46$600.00$714.00$683.02$660.00$420.34$666.30
0350Painted pavement marking, standard,white, 3'-9' skip drop line and approach to toll 12" wide, (0710-11133)GM0.94$800.00$1,310.00$1,249.54$1,200.00$2,602.77$880.35
0355Painted pavement markings, standard, white, 2-4 dotted guideline/ 6-10 dotted 6" (0710-11141)GM2.96$800.00$823.00$787.19$760.00$726.23$887.40
0360Painted pavement markings, standard, white, message or symbol (0710-11160)EACH78$65.00$49.45$47.31$46.00$65.00$72.20
0365Painted pavement markings, standard, white, arrows (0710-11170)EACH339$40.00$38.45$36.80$36.00$42.00$44.45
0370Painted pavement markings, standard, yellow, solid, 6" (0710-11201)GM5.26$2,400.00$1,650.00$1,574.35$1,520.00$1,600.30$2,662.00
0375Painted pavement markings, standard, yellow, solid for diagonal or chevron, 18" (0710-11224)LF672$2.50$1.65$1.58$1.55$2.25$2.80
0380Painted pavement markings, standard, yellow, 2-4 dotted guideline/6-10 dotted extension, 6" (0710-11241)GM0.33$800.00$824.00$788.52$760.00$730.00$889.00
0385Painted pavement markings, durable paint, yellow, island nose (0710-12290)SF51$5.00$5.50$5.26$5.10$6.00$5.55
0390Initial contingency amount, DO not bid (0999-25)LS1$60,000$60,000$60,000$60,000$60,000$60,000
0395Ground-in rumble strips, 8" sinusoidal (0546-72-3)GM0.42$8,962.60$15,500$1,051.71$41,400$23,552$5,923.00
0400Single column ground sign assembly, F&I ground mount, than 12 SF (0700-1111)EACH27$499.00$780.00$641.33$523.00$709.79$560.00
0405Single column ground sign assembly, F&I ground mount, 20.0 SF (0700-1112)EACH15$2,046.00$1,980.00$2,256.23$2,200.00$1,799.75$2,296.00
0410Single column ground sign assembly, relocate (0700-1500)EACH7$310.00$505.50$340.64$325.00$460.00$348.00
0415Single column ground sign assembly, remove (0700-1600)EACH10$50.00$126.40$113.55$53.00$115.00$56.00
0420Multi-column ground sign assembly, F&I ground mount, 100.0 SF (0700-2115)EACH1$8,677.00$17,000$10,349$9,100.00$15,427$9,738.50
0425Multi-column ground sign assembly, remove (0700-2600)EACH1$1,000.00$2,020.00$1,974.46$1,100.00$1,840.00$1,122.00
0430Sign panel, furnish & install overhead mount, 101-200 SF (0700-3206)EACH1$8,783.00$8,390.00$6,282.95$9,250.00$7,634.93$9,857.50
0435Sign panel, furnish & install overhead mount, 201-300 SF (0700-3207)EACH1$12,506$11,500$8,928.18$13,200$10,490$14,035
0440Sign panel, furnish & install overhead mount, 401-500 SF (0700-3209)EACH1$24,093$18,800$15,386$25,300$17,084$27,040
0445Sign panel, remove panel, SF with lighting (0700-3629)EACH2$1,000.00$6,320.00$7,113.53$1,100.00$5,750.00$1,122.00
0450Retroreflective sign strip- furnish and install, 5' (0700-13-15)EACH32$77.00$35.15$222.89$81.00$158.07$86.50
0455Object marker, type 1 (0705-10-1)EACH2$210.00$2.20$367.98$221.00$169.14$235.69
0460Raised pavement marker, type B (0706-1-3)EACH1,478$4.25$4.95$4.73$4.60$4.70$4.75
0465Painted pavement markings, durable paint, yellow, island nose (0710-12290)SF17$5.00$5.50$5.26$5.10$6.00$5.55
0470Painted pavement markings, surface (0710-90)LS1$12,600$27,500$26,284$23,000$40,000$38,889
0475Thermoplastic, standard, solid, 12" for interchange markings (0711-11103)GM0.07$18,480$15,000$14,337$13,800$21,212$18,667
0480Thermoplastic, standard, solid, 12" for crosswalk and roundabout (0711-11123)LF2,657$3.50$3.85$3.68$3.55$4.00$3.90
0485Thermoplastic, standard, solid, 18" for diagonals and chevrons (0711-11124)LF1,423$4.50$5.10$4.89$4.75$6.00$5.00
0490Thermoplastic, standard, solid, 24" for stop line and crosswalk (0711-11125)LF211$6.00$7.70$7.36$7.10$8.50$6.65
0495Thermoplastic, standard, 2-4 dotted guideline/ 6-10 gap extension, 6" (0711-11141)GM0.99$1,650.00$2,730.00$2,615.07$2,520.00$2,512.69$1,824.00
0500Thermoplastic, standard, message or symbol (0711-11160)EACH14$185.00$164.80$157.70$155.00$150.00$205.50
0505Thermoplastic, standard, arrow (0711-11170)EACH101$100.00$109.90$105.14$102.00$80.00$111.00
0510Thermoplastic, standard, yellow, solid, 18" for diagonal or chevron (0711-11224)LF224$4.50$5.10$4.89$4.75$6.00$5.00
0515Thermoplastic, standard, yellow, 2-4 dotted guide line dotted extension line, 6" (0711-11241)GM0.11$1,550.00$2,750.00$2,628.45$2,570.00$2,500.00$1,722.00
0520Thermoplastic, preformed, white, solid, 24" for crosswalk (0711-14125)LF831$15.00$17.60$16.82$16.20$14.00$16.65
0525Thermoplastic, preformed, white, message (0711-14160)EACH12$225.00$219.80$210.27$203.00$210.00$250.00
0530Thermoplastic, preformed, white, arrow (0711-14170)EACH12$150.00$109.90$105.14$102.00$150.00$166.65
0535Thermoplastic, preformed, color route shield (0711-14660)EACH6$1,500.00$2,200.00$2,102.73$2,050.00$2,000.00$1,666.00
0540Thermoplastic, standard-open graded asphalt surfaces solid, 6" (0711-15101)GM3.06$7,392.00$6,570.00$6,289.62$6,100.00$4,501.47$8,189.00
0545Thermoplastic, standard-open graded asphalt surfaces, solid, 8" (0711-15102)GM0.69$7,950.00$9,990.00$9,560.07$9,200.00$18,052$8,730.00
0550Thermoplastic, standard-open graded asphalt surfaces, skip, 6",10-30 skip or 3-9 lane (0711-15131)GM2.49$1,475.00$1,860.00$1,781.57$1,750.00$1,801.45$1,633.00
0555Thermoplastic, standard-open graded asphalt surfaces, skip, 12"- approach to toll plaza or 3-9 lane drop (0711-15133)GM0.31$1,750.00$3,810.00$3,644.50$3,550.00$16,358$1,926.00
0560Thermoplastic, standard-open graded asphalt surfaces, yellow, solid, 6" (0711-15201)GM1.75$7,028.00$6,580.00$6,297.39$6,075.00$4,517.97$7,795.00
0565Itsfm location documentation- intersection (0611-2-1)EACH1$1,840.00$2,020.00$1,792.57$2,100.00$1,840.00$2,065.00
0570Conduit, furnish & install, open trench (0630-2-11)LF261$12.79$14.05$28.18$15.00$12.79$14.35
0575Conduit, furnish & install, directional bore (0630-2-12)LF452$28.91$31.75$33.01$34.00$28.91$32.45
0580Signal cable- new or reconstructed intersection, furnish & install (0632-7-1)PI1$11,739$14,500$17,176$15,000$13,177$14,788
0585Signal cable, remove- intersection (0632-7-6)PI1$3,450.00$3,790.00$1,640.13$3,900.00$3,450.00$3,872.00
0590Fiber optic cable locator (0633-6)DA220$180.00$197.80$284.81$205.00$180.00$202.00
0595Span wire assembly, F&I, two point, box or drop box (0634-4153)PI1$10,748$13,400$10,609$13,800$12,185$13,975
0600Pull & splice box, F&I, 13" X 24" cover size (0635-2-11)EACH20$1,651.91$1,820.00$1,319.46$1,900.00$1,651.91$1,854.00
0605Electrical power service, F&I, underground, meter by contractor (0639-1122)AS1$3,501.18$3,850.00$6,198.84$4,000.00$3,501.18$3,929.00
0610Electrical service wire, & install (0639-2-1)LF33$5.44$6.00$8.62$6.20$5.44$6.10
0615Electrical service disconnect, F&I, pole mount (0639-3-11)EACH1$2,442.03$2,680.00$1,997.59$2,800.00$2,442.03$2,740.00
0620Prestressed concrete pole, type P-II service pole (0641-2-12)EACH1$2,157.78$2,370.00$2,667.31$2,450.00$2,157.78$2,422.00
0625Prestressed concrete pole, shallow pole removal- pole 30' and greater (0641-2-70)EACH4$9,430.00$10,400$9,892.28$10,700$9,430.00$10,583
0630Aluminum signals pole, (0646-1-11)EACH8$3,032.35$3,330.00$2,688.34$3,500.00$3,032.35$3,403.00
0635Steel strain pole, F&I, type PS- VIII (0649-1-15)EACH4$53,545$58,800$66,312$60,500$53,545$60,095
0640Vehicular traffic signal, furnish & install aluminum, 3 section, 1 way (0650-1-14)AS13$2,289.21$2,520.00$2,076.44$2,600.00$2,289.21$2,569.00
0645Vehicular traffic signal, furnish & install aluminum, 4 section, 1 way (0650-1-16)AS1$2,717.21$2,990.00$2,597.92$3,100.00$2,717.21$3,049.00
0650Pedestrian signal, furnish & install LED countdown, 1 way (0653-1-11)AS8$1,237.57$1,360.00$983.03$1,400.00$1,237.57$1,389.00
0655Vehicle detection system- furnish & install cabinet equipment (0660-4-11)EACH2$17,876$19,600$24,131$20,200$17,876$20,062
0660Vehicle detection system- furnish & install above ground equipment (0660-4-12)EACH6$11,773$12,900$8,910.31$13,350$11,773$13,213
0665Signal priority and preemption system, F&I, optical, cabinet electronics (0663-1111)EACH1$9,587.27$10,500$9,285.64$10,900$9,587.27$10,760
0670Signal priority and preemption system, F&I, optical, detector (0663-1112)EACH4$3,108.16$3,420.00$2,618.95$3,550.00$3,108.16$3,488.00
0675Pedestrian detector, furnish & install, accessible (0665-1-12)EACH8$1,917.78$2,110.00$1,934.51$2,200.00$1,917.78$2,152.40
0680Traffic controller, relocate- without cabinet (0671-2-50)EACH1$1,725.00$1,900.00$2,116.39$2,000.00$1,725.00$1,936.00
0685Traffic signal controller cabinet, furnish & install without controller, NEMA 44" W X 52" H X 24" D (0676-1116)EACH1$30,151$33,100$36,413$34,100$30,151$33,840
0690Traffic signal controller cabinet, remove (0676-1600)EACH1$2,530.00$2,780.00$1,027.18$2,900.00$2,530.00$2,839.50
0695ITS CCTV camera, F&I, dome PTZ enclosure - pressurized, IP, definition (0682-1113)EACH1$7,503.75$8,250.00$8,662.18$8,500.00$7,503.75$8,421.00
0700Managed field ethernet switch, furnish & install (0684-1-1)EACH1$6,066.25$6,670.00$4,958.23$6,900.00$6,066.25$6,808.00
0705Wireless communication device, relocate (0684-6-40)EACH1$1,725.00$1,900.00$1,358.36$1,950.00$1,725.00$1,936.00
0710Uninterruptible power supply, furnish and install, line interactive with cabinet (0685-1-13)EACH1$10,470$11,500$13,358$11,900$10,470$11,750
0715Remote power management rpmu, furnish and install (0685-2-1)EACH1$839.10$922.00$2,093.26$950.00$839.10$941.75
0720Sign panel, furnish & install overhead mount, UP to 12 SF (0700-3201)EACH1$699.72$769.00$809.55$795.00$699.72$785.00
0725Internally illuminated sign, furnish & install overhead mount, UP to 12 SF (0700-5-21)EACH2$7,361.38$8,090.00$7,316.44$8,350.00$7,361.38$8,262.00
0730Internally illuminated sign, furnish & install, overhead mount, 12-18 SF (0700-5-22)EACH2$7,808.05$8,580.00$7,811.63$8,850.00$7,808.05$8,763.00
FDOT contract T5855: unit prices by line, the 6 lowest bidders (all in the CSV)

The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.

Source

Read from FDOT's tabulation for this contract. FDOT Tabulation of Bids PDFs from its central office lettings, January 2018 to October 2026, all pay items. On A+B contracts the cost part is kept (the total the pay items add up to). Bidders listed without a rank or total are left out.

Every contract let that day: FDOT letting of June 11, 2025. Compiled by Mirage Metrics.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy