IDOT contract 62L30 bid tabulation
Section 2020-142-C&DR. Let by Illinois DOT on June 12, 2026, Cook, District 01. 6 bids received; low bid $13,940,412 by D. Construction, Inc..
- Owner
- Illinois DOT
- Letting
- 12 JUN 2026
- Pay items
- 205
- Data through
- 18 SEP 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | D. Construction, Inc. | $13,940,412 | Low |
| 2 | Martam Construction Incorporated | $15,122,173 | +8.0% |
| 3 | Austin Tyler Construction, Inc. | $15,216,031 | +9.0% |
| 4 | OHLA Central, Inc. | $16,574,638 | +19% |
| 5 | P. T. Ferro Construction Co. | $16,772,291 | +20% |
| 6 | R. W. Dunteman Company | $16,856,570 | +21% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. D. Construction, Inc. | 2. Martam Construction Incorporated | 3. Austin Tyler Construction, Inc. | 4. OHLA Central, Inc. | 5. P. T. Ferro Construction Co. | 6. R. W. Dunteman Company |
|---|---|---|---|---|---|---|---|---|---|
| 1 | T-amelan can CG 3G (A2C007G3) | EACH | 15 | $128.70 | $125.00 | $121.00 | $117.00 | $117.00 | $117.00 |
| 2 | T-carya cordif CG 5G (A2C020G5) | EACH | 5 | $363.00 | $350.00 | $234.00 | $330.00 | $330.00 | $330.00 |
| 3 | T-cercis canad CG 5G (A2C025G5) | EACH | 12 | $247.50 | $250.00 | $178.00 | $225.00 | $225.00 | $225.00 |
| 4 | T-tilia amer 1-1/4 CG (A2C07800) | EACH | 6 | $495.00 | $480.00 | $327.00 | $450.00 | $450.00 | $450.00 |
| 5 | T-betul NG HRT CL 10' (A2002474) | EACH | 18 | $635.25 | $650.00 | $431.00 | $577.50 | $577.50 | $577.50 |
| 6 | T-celtis occid 2 (A2002916) | EACH | 9 | $589.88 | $600.00 | $381.00 | $536.25 | $536.25 | $536.25 |
| 7 | T-ostrya virg 1-3/4 (A2005614) | EACH | 18 | $680.63 | $700.00 | $390.00 | $618.75 | $618.75 | $618.75 |
| 8 | T-quercus alba 1-3/4 (A2006414) | EACH | 11 | $559.63 | $600.00 | $390.00 | $508.75 | $508.75 | $508.75 |
| 9 | T-quercus imbr 1-3/4 (A2006614) | EACH | 7 | $559.63 | $600.00 | $374.00 | $508.75 | $508.75 | $508.75 |
| 10 | T-quercus rubra 1-3/4 (A2007114) | EACH | 4 | $559.63 | $600.00 | $374.00 | $508.75 | $508.75 | $508.75 |
| 11 | T-aesculus pavia 6' (A2022166) | EACH | 13 | $1,058.75 | $1,300.00 | $374.00 | $962.50 | $962.50 | $962.50 |
| 12 | T-amelan X GF SF 5' (B2000664) | EACH | 26 | $544.50 | $550.00 | $359.00 | $495.00 | $495.00 | $495.00 |
| 13 | T-cercis can CL 5' (B2001164) | EACH | 26 | $453.75 | $550.00 | $351.00 | $412.50 | $412.50 | $412.50 |
| 14 | T-cratae cru-I SF 5' (B2001664) | EACH | 21 | $453.75 | $550.00 | $351.00 | $412.50 | $412.50 | $412.50 |
| 15 | S-rhus aroma 18C (C2C05718) | EACH | 40 | $95.70 | $100.00 | $90.00 | $87.00 | $87.00 | $87.00 |
| 16 | E-picea glau den 4' (D2001948) | EACH | 15 | $414.70 | $460.00 | $327.00 | $377.00 | $377.00 | $377.00 |
| 17 | E-pinus flexilis 5' (D2002360) | EACH | 18 | $843.70 | $950.00 | $612.00 | $767.00 | $767.00 | $767.00 |
| 18 | E-pinus strobus 4' (D2002948) | EACH | 15 | $357.50 | $400.00 | $295.00 | $325.00 | $325.00 | $325.00 |
| 19 | E-psuedo menzi 5' (D2003160) | EACH | 18 | $614.90 | $700.00 | $438.00 | $559.00 | $559.00 | $559.00 |
| 20 | Weed contr pre-EM GRN (K0029634) | LB | 18 | $55.00 | $30.00 | $25.00 | $50.00 | $50.00 | $50.00 |
| 21 | Weed cont basal TRTMT (X0325222) | GAL | 50 | $330.00 | $1,000.00 | $3,000.00 | $300.00 | $300.00 | $300.00 |
| 22 | Weed CTRL NTV LSCP EN (X0327120) | ACRE | 3 | $2,200.00 | $1,000.00 | $1,360.00 | $2,000.00 | $2,000.00 | $2,000.00 |
| 23 | Tree remov acres SPL (X2010350) | ACRE | 3 | $6,050.00 | $5,500.00 | $5,500.00 | $17,000 | $5,500.00 | $9,800.00 |
| 24 | Selective clearing (X2010516) | UNIT | 51 | $385.00 | $350.00 | $350.00 | $350.00 | $350.00 | $255.00 |
| 25 | Mowing SPL (X2503110) | ACRE | 3 | $1,650.00 | $900.00 | $750.00 | $1,500.00 | $1,500.00 | $1,500.00 |
| 26 | Interseed CL 5A mod (X2503323) | ACRE | 3 | $4,620.00 | $3,500.00 | $2,168.00 | $4,200.00 | $4,200.00 | $4,200.00 |
| 27 | Inlet filter cleaning (X2800510) | EACH | 102 | $22.00 | $60.00 | $50.00 | $17.50 | $20.00 | $17.50 |
| 28 | Temp access- com ent (X4022000) | EACH | 28 | $1,200.00 | $900.00 | $2,250.00 | $4,330.29 | $0.01 | $286.62 |
| 29 | Cofferdam typ 1 IS WW (X5021512) | EACH | 4 | $0.01 | $22,000 | $0.01 | $3,403.99 | $50,000 | $1,000.00 |
| 30 | Remov EX flar end sec (X5427602) | EACH | 6 | $500.00 | $300.00 | $420.00 | $210.00 | $700.00 | $210.00 |
| 31 | Memb WTRPRF sys B STR (X5810103) | SY | 487 | $65.00 | $48.00 | $61.00 | $55.00 | $65.00 | $35.00 |
| 32 | Grates SPL (X6040171) | EACH | 6 | $600.00 | $3,800.00 | $575.00 | $2,300.85 | $3,000.00 | $2,887.54 |
| 33 | SPBGR (short radius) (X6330725) | LF | 231.25 | $38.72 | $36.00 | $35.20 | $35.92 | $35.20 | $57.00 |
| 34 | Fence removal (X6640104) | LF | 52 | $11.44 | $12.00 | $10.40 | $10.61 | $10.40 | $37.86 |
| 35 | Fence rem & reinstall (X6640108) | LF | 50 | $64.00 | $60.00 | $58.18 | $59.37 | $58.10 | $78.00 |
| 36 | Engr FLD off A SPL (X6700410) | CAL MO | 24 | $6,000.00 | $5,800.00 | $3,250.00 | $6,000.00 | $4,000.00 | $4,500.00 |
| 37 | Traf cont & prot SPL (X7010216) | LS | 1 | $257,822 | $595,000 | $80,000 | $1,250,000 | $550,000 | $955,777 |
| 38 | Temp info signing (X7200061) | SF | 238.90 | $32.50 | $18.00 | $30.00 | $30.00 | $20.00 | $16.00 |
| 39 | Detour signing (X7200203) | LS | 1 | $50,000 | $50,000 | $50,000 | $50,000 | $100,000 | $50,000 |
| 40 | Construction layout (Z0013798) | LS | 1 | $214,536 | $134,000 | $165,000 | $350,000 | $70,000 | $117,000 |
| 41 | Drainage STR cleaned (Z0018500) | EACH | 5 | $450.00 | $800.00 | $250.00 | $624.49 | $1,000.00 | $220.00 |
| 42 | Rock fill (Z0054400) | CY | 44 | $60.00 | $88.00 | $85.00 | $92.81 | $60.00 | $161.08 |
| 43 | Storm sew WM req 12 (Z0056608) | LF | 960 | $152.00 | $122.00 | $163.00 | $101.25 | $75.00 | $101.25 |
| 44 | Storm sew WM req 24 (Z0056616) | LF | 335 | $271.00 | $225.00 | $296.00 | $212.15 | $115.00 | $212.15 |
| 45 | Temp pavement (Z0062456) | SY | 10,913 | $45.00 | $53.00 | $48.00 | $53.00 | $65.00 | $56.60 |
| 46 | Trainees (Z0076600) | HR | 1,500 | $0.80 | $0.80 | $0.80 | $0.80 | $0.80 | $0.80 |
| 47 | Trainees TPG (Z0076604) | HR | 1,500 | $15.00 | $15.00 | $15.00 | $15.00 | $15.00 | $15.00 |
| 48 | Tree remov 6-15 (20100110) | UNIT | 1,542 | $22.00 | $20.00 | $20.00 | $20.00 | $20.00 | $20.00 |
| 49 | Tree remov over 15 (20100210) | UNIT | 295 | $30.36 | $28.00 | $27.60 | $27.60 | $27.60 | $22.00 |
| 50 | Temporary fence (20101000) | LF | 31,164 | $2.48 | $3.30 | $3.00 | $2.25 | $2.25 | $2.85 |
| 51 | Tree trunk protection (20101100) | EACH | 80 | $110.00 | $60.00 | $100.00 | $120.00 | $100.00 | $100.00 |
| 52 | Tree prun 1-10 (20101300) | EACH | 10 | $55.00 | $60.00 | $50.00 | $50.00 | $50.00 | $50.00 |
| 53 | Tree prun over 10 (20101350) | EACH | 20 | $55.00 | $60.00 | $50.00 | $50.00 | $50.00 | $95.00 |
| 54 | Earth excavation (20200100) | CY | 14,048 | $30.00 | $32.00 | $50.00 | $23.54 | $60.00 | $39.83 |
| 55 | Rem & disp uns matl (20201200) | CY | 1,005 | $30.00 | $32.00 | $56.00 | $50.00 | $85.00 | $33.59 |
| 56 | Trench backfill (20800150) | CY | 1,114 | $50.00 | $78.00 | $80.00 | $90.00 | $0.01 | $49.60 |
| 57 | Porous gran backfill (20900110) | CY | 428 | $60.00 | $75.00 | $65.00 | $80.00 | $92.00 | $92.00 |
| 58 | Geotech fab F/GR stab (21001000) | SY | 3,016 | $3.00 | $2.00 | $2.67 | $2.33 | $4.00 | $2.89 |
| 59 | Topsoil exc & plac (21101505) | CY | 4,827 | $21.00 | $23.00 | $20.00 | $17.79 | $35.00 | $28.40 |
| 60 | Grading & shap ditch (21400100) | LF | 10,194 | $16.00 | $18.00 | $13.00 | $3.51 | $5.00 | $3.79 |
| 61 | Seeding CL 2A (25000210) | ACRE | 6 | $1,760.00 | $3,300.00 | $3,720.00 | $1,600.00 | $1,600.00 | $1,600.00 |
| 62 | Nitrogen fert nutr (25000400) | LB | 755 | $3.30 | $3.00 | $3.00 | $3.00 | $3.00 | $3.00 |
| 63 | Potassium fert nutr (25000600) | LB | 755 | $3.30 | $3.00 | $3.00 | $3.00 | $3.00 | $3.00 |
| 64 | Interseed CL 4 (25003310) | ACRE | 3 | $1,760.00 | $2,900.00 | $1,594.00 | $1,600.00 | $1,600.00 | $1,600.00 |
| 65 | Erosion contr blanket (25100630) | SY | 27,057 | $1.76 | $1.60 | $1.40 | $1.60 | $1.60 | $1.60 |
| 66 | Turf reinf mat (25100900) | SY | 228 | $8.80 | $22.00 | $4.70 | $8.00 | $8.00 | $8.00 |
| 67 | Temp eros contr seed (28000250) | LB | 559 | $1.10 | $6.00 | $4.00 | $1.00 | $1.00 | $1.00 |
| 68 | Temp ditch checks (28000305) | LF | 510 | $9.90 | $16.00 | $4.30 | $9.00 | $9.00 | $9.00 |
| 69 | Agg ditch checks (28000315) | TON | 3 | $220.00 | $220.00 | $100.00 | $145.06 | $300.00 | $1,283.79 |
| 70 | Perimeter eros bar (28000400) | LF | 31,164 | $2.53 | $3.50 | $2.10 | $2.30 | $2.30 | $2.30 |
| 71 | Inlet & pipe protect (28000500) | EACH | 102 | $132.00 | $100.00 | $66.00 | $120.00 | $120.00 | $120.00 |
| 72 | Inlet filters (28000510) | EACH | 102 | $154.00 | $210.00 | $150.00 | $114.35 | $140.00 | $140.00 |
| 73 | Temp eros contr blank (28001100) | SY | 27,057 | $1.21 | $1.40 | $4.00 | $1.10 | $1.10 | $1.10 |
| 74 | Stone riprap CL A5 (28100109) | SY | 731 | $90.00 | $95.00 | $134.00 | $91.76 | $135.00 | $208.26 |
| 75 | Filter fabric (28200200) | SY | 731 | $7.50 | $3.00 | $4.00 | $6.35 | $3.25 | $7.16 |
| 76 | Agg subgrade improve (30300001) | CY | 1,310 | $55.00 | $54.00 | $56.00 | $70.00 | $90.00 | $72.37 |
| 77 | Agg subgrade impr 12 (30300112) | SY | 25,157 | $21.00 | $16.00 | $25.00 | $30.00 | $26.00 | $20.50 |
| 78 | Sub gran mat B 4 (31101200) | SY | 10,913 | $8.00 | $6.00 | $12.00 | $7.63 | $0.01 | $8.85 |
| 79 | HMA base cse 6 (35501308) | SY | 349 | $43.00 | $46.00 | $44.00 | $46.00 | $85.00 | $58.93 |
| 80 | HMA base cse 8 (35501316) | SY | 1,991 | $50.00 | $61.00 | $58.00 | $61.00 | $80.00 | $68.93 |
| 81 | HMA base cse 8 1/2 (35501318) | SY | 4,963 | $44.50 | $78.00 | $46.00 | $78.00 | $52.00 | $53.99 |
| 82 | HMA BC wid 8 1/2 (35600710) | SY | 1,441 | $45.00 | $79.00 | $46.00 | $79.00 | $60.00 | $60.09 |
| 83 | Bit matls PR CT (40600275) | LB | 56,604 | $0.01 | $0.01 | $0.01 | $0.01 | $0.01 | $0.27 |
| 84 | Bit matls tack CT (40600290) | LB | 28,241 | $0.01 | $0.01 | $0.01 | $0.01 | $0.01 | $1.07 |
| 85 | Long joint sealant (40600370) | LF | 16,937 | $3.75 | $3.35 | $3.50 | $3.35 | $4.35 | $3.36 |
| 86 | Mix CR JTS flangewys (40600400) | TON | 90 | $0.01 | $50.00 | $375.00 | $50.00 | $100.00 | $442.01 |
| 87 | HMA surf rem butt JT (40600982) | SY | 240 | $0.01 | $0.01 | $24.00 | $0.01 | $0.01 | $35.92 |
| 88 | P HMA BC IL-4.75 N50 (40603200) | TON | 1,990 | $111.50 | $125.00 | $117.00 | $125.00 | $130.00 | $126.49 |
| 89 | HMA SC IL-9.5 D N50 (40604060) | TON | 262 | $115.00 | $240.00 | $150.00 | $240.00 | $110.00 | $196.76 |
| 90 | P HMA SC IL-9.5 E N70 (40604172) | TON | 4,728 | $113.00 | $138.00 | $116.00 | $138.00 | $125.00 | $137.91 |
| 91 | Protective coat (42001300) | SY | 2,001 | $1.00 | $1.00 | $3.00 | $1.42 | $0.01 | $0.01 |
| 92 | PC conc sidewalk 5 (42400200) | SF | 25 | $50.00 | $28.00 | $12.00 | $30.00 | $50.00 | $23.24 |
| 93 | Pavement rem (44000100) | SY | 20,042 | $13.00 | $21.00 | $28.00 | $25.00 | $26.00 | $22.96 |
| 94 | HMA surf rem 2 1/2 (44000159) | SY | 41,838 | $2.40 | $5.00 | $2.75 | $4.50 | $4.85 | $4.23 |
| 95 | Drive pavement rem (44000200) | SY | 2,340 | $10.00 | $15.00 | $12.00 | $20.00 | $28.00 | $34.35 |
| 96 | Comb curb gutter rem (44000500) | LF | 116 | $10.00 | $12.00 | $15.00 | $20.00 | $25.00 | $21.65 |
| 97 | Sidewalk rem (44000600) | SF | 25 | $6.50 | $10.00 | $6.00 | $20.00 | $50.00 | $16.21 |
| 98 | Paved SHLD removal (44004250) | SY | 487 | $11.00 | $23.00 | $19.00 | $3.11 | $50.00 | $45.71 |
| 99 | CL D patch T1 13 (44201798) | SY | 293 | $145.00 | $55.00 | $160.00 | $105.57 | $200.00 | $199.47 |
| 100 | CL D patch T2 13 (44201803) | SY | 586 | $145.00 | $55.00 | $145.00 | $68.18 | $160.00 | $176.12 |
| 101 | CL D patch T3 13 (44201807) | SY | 1,025 | $140.00 | $55.00 | $142.00 | $52.35 | $145.00 | $166.03 |
| 102 | CL D patch T4 13 (44201809) | SY | 1,295 | $140.00 | $55.00 | $140.00 | $46.86 | $120.00 | $144.20 |
| 103 | Aggregate SHLDS B 6 (48101500) | SY | 6,175 | $11.00 | $17.00 | $16.00 | $20.00 | $17.00 | $11.93 |
| 104 | Aggregate SHLDS B 10 (48101620) | SY | 2,417 | $16.50 | $28.00 | $33.00 | $20.00 | $28.00 | $20.03 |
| 105 | HMA shoulders 11 (48203041) | SY | 18,753 | $56.50 | $74.15 | $58.00 | $79.00 | $72.00 | $63.49 |
| 106 | Rem exist struct (50100100) | EACH | 7 | $27,000 | $32,800 | $21,000 | $85,000 | $27,000 | $105,511 |
| 107 | Conc headwall removal (50104400) | EACH | 10 | $500.00 | $1,500.00 | $625.00 | $1,800.00 | $1,500.00 | $2,242.20 |
| 108 | Rem/disp uns matl-STR (50200450) | CY | 305 | $35.00 | $65.00 | $75.00 | $100.00 | $75.00 | $108.00 |
| 109 | Conc struct (50300225) | CY | 39.30 | $1,800.00 | $3,200.00 | $1,600.00 | $2,000.00 | $1,800.00 | $2,975.00 |
| 110 | Stud shear connectors (50500505) | EACH | 196 | $20.00 | $35.00 | $40.00 | $30.00 | $20.00 | $35.00 |
| 111 | Reinf bars, epoxy CTD (50800205) | LB | 123,542 | $2.30 | $2.00 | $2.00 | $2.00 | $2.30 | $2.12 |
| 112 | Name plates (51500100) | EACH | 4 | $1,300.00 | $1,400.00 | $1,000.00 | $1,485.84 | $1,300.00 | $2,500.00 |
| 113 | Temp soil reten systm (52200020) | SF | 140 | $90.00 | $265.00 | $0.01 | $25.00 | $90.00 | $350.00 |
| 114 | Fur soldier piles WS (52200105) | LF | 620 | $180.00 | $275.00 | $193.00 | $200.00 | $180.00 | $175.00 |
| 115 | Drill set SLD PI soil (52200200) | CF | 618 | $47.00 | $125.00 | $28.00 | $230.00 | $47.00 | $155.00 |
| 116 | Drill set SLD PI rock (52200205) | CF | 1,500 | $84.00 | $150.00 | $244.00 | $200.00 | $84.00 | $328.00 |
| 117 | Untreated timber lag (52200250) | SF | 920 | $35.00 | $22.00 | $30.00 | $21.38 | $35.00 | $10.00 |
| 118 | Conc box cul (54003000) | CY | 531.20 | $1,300.00 | $1,100.00 | $1,845.00 | $2,450.00 | $1,300.00 | $2,975.00 |
| 119 | P cul CL A 1 18 (542A0223) | LF | 40 | $108.00 | $75.00 | $110.00 | $59.50 | $250.00 | $59.50 |
| 120 | P cul CL A 1 24 (542A0229) | LF | 135 | $124.00 | $115.00 | $144.00 | $98.40 | $250.00 | $98.40 |
| 121 | P cul CL A 1 36 (542A0241) | LF | 217 | $166.00 | $160.00 | $203.00 | $133.35 | $345.00 | $133.35 |
| 122 | P cul CL A 1 eqrs 18 (542A5473) | LF | 120 | $143.00 | $224.00 | $144.00 | $90.75 | $300.00 | $90.75 |
| 123 | PRC flar end sec 12 (54213657) | EACH | 2 | $1,200.00 | $1,200.00 | $1,230.00 | $975.00 | $1,700.00 | $975.00 |
| 124 | PRC flar end sec 15 (54213660) | EACH | 2 | $1,500.00 | $1,300.00 | $1,275.00 | $1,025.00 | $1,750.00 | $1,025.00 |
| 125 | PRC flar end sec 18 (54213663) | EACH | 2 | $2,000.00 | $1,400.00 | $1,450.00 | $1,165.00 | $1,900.00 | $1,165.00 |
| 126 | PRC flar end sec 24 (54213669) | EACH | 4 | $2,200.00 | $1,600.00 | $1,675.00 | $1,305.00 | $2,100.00 | $1,305.00 |
| 127 | PRC flar end sec 36 (54213681) | EACH | 1 | $3,500.00 | $2,400.00 | $2,475.00 | $2,070.00 | $3,000.00 | $2,070.00 |
| 128 | PRC flar end sec 48 (54213693) | EACH | 2 | $4,000.00 | $3,600.00 | $3,650.00 | $3,095.00 | $5,100.00 | $3,095.00 |
| 129 | PRC flar end sec 54 (54213699) | EACH | 1 | $7,000.00 | $5,500.00 | $5,600.00 | $4,830.00 | $7,000.00 | $4,830.00 |
| 130 | PRC FL end S EQ RS 18 (54214503) | EACH | 6 | $2,000.00 | $1,500.00 | $1,525.00 | $1,224.00 | $2,000.00 | $1,224.00 |
| 131 | Storm sew CL A 1 12 (550A0050) | LF | 2,165 | $84.00 | $61.88 | $75.00 | $56.95 | $99.00 | $56.95 |
| 132 | Storm sew CL A 1 15 (550A0070) | LF | 1,515 | $89.00 | $65.45 | $69.00 | $61.25 | $124.00 | $61.25 |
| 133 | Storm sew CL A 1 24 (550A0120) | LF | 619 | $123.00 | $115.78 | $99.00 | $84.25 | $190.00 | $84.25 |
| 134 | Storm sew CL A 1 36 (550A0160) | LF | 341 | $161.00 | $162.25 | $158.00 | $131.50 | $190.00 | $131.50 |
| 135 | Storm sew CL A 1 42 (550A0180) | LF | 64 | $184.00 | $195.80 | $198.00 | $155.10 | $235.00 | $155.10 |
| 136 | Storm sew CL A 1 48 (550A0190) | LF | 207 | $214.00 | $224.95 | $247.00 | $250.00 | $300.00 | $182.70 |
| 137 | Storm sew CL A 1 54 (550A0200) | LF | 1,927 | $310.00 | $268.95 | $299.00 | $227.70 | $380.00 | $227.70 |
| 138 | Storm sew CL A 2 12 (550A0340) | LF | 100 | $84.00 | $83.88 | $75.00 | $56.95 | $115.00 | $56.95 |
| 139 | Storm sew CL A 2 15 (550A0360) | LF | 60 | $89.00 | $87.45 | $69.00 | $61.25 | $170.00 | $61.25 |
| 140 | Storm sewer rem 10 (55100400) | LF | 136 | $20.00 | $10.00 | $35.00 | $12.00 | $27.00 | $12.00 |
| 141 | Storm sewer rem 12 (55100500) | LF | 931 | $20.00 | $10.00 | $35.00 | $12.00 | $28.00 | $12.00 |
| 142 | Storm sewer rem 15 (55100700) | LF | 50 | $20.00 | $10.00 | $35.00 | $12.00 | $30.00 | $12.00 |
| 143 | Storm sewer rem 24 (55101200) | LF | 137 | $30.00 | $20.00 | $40.00 | $17.00 | $40.00 | $17.00 |
| 144 | Storm sewer rem 36 (55101600) | LF | 6 | $50.00 | $50.00 | $40.00 | $20.00 | $100.00 | $20.00 |
| 145 | Water valves adjust (56109210) | EACH | 13 | $300.00 | $400.00 | $500.00 | $450.00 | $250.00 | $450.00 |
| 146 | Fire hydnts relocated (56400400) | EACH | 3 | $3,500.00 | $5,600.00 | $3,250.00 | $3,640.00 | $7,000.00 | $3,640.00 |
| 147 | Geocomposite wall DR (59100100) | SY | 550 | $40.00 | $45.00 | $34.00 | $18.60 | $40.00 | $35.00 |
| 148 | Conc HDWL for P drain (60100060) | EACH | 20 | $500.00 | $550.00 | $480.00 | $516.70 | $1,000.00 | $516.70 |
| 149 | Pipe underdrain 4 SP (60108100) | LF | 1,040 | $20.00 | $21.00 | $40.00 | $16.70 | $50.00 | $16.70 |
| 150 | Pipe underdr T 2 4 (60108204) | LF | 24,939 | $16.00 | $17.00 | $20.00 | $13.25 | $28.00 | $13.25 |
| 151 | CB TA 4 dia T24F&G (60201340) | EACH | 1 | $4,780.00 | $4,200.00 | $3,800.00 | $3,600.00 | $5,500.00 | $3,600.00 |
| 152 | CB TB T7G (60206600) | EACH | 6 | $10,825 | $8,900.00 | $7,650.00 | $9,580.70 | $10,500 | $9,580.70 |
| 153 | CB TC T8G (60207605) | EACH | 4 | $2,800.00 | $2,100.00 | $1,950.00 | $1,482.00 | $2,500.00 | $1,482.00 |
| 154 | CB TD 3 dia T23F&G (60211613) | EACH | 13 | $4,400.00 | $3,800.00 | $3,000.00 | $3,830.85 | $4,600.00 | $3,830.85 |
| 155 | CB TD 4 dia T24F&G (60212814) | EACH | 2 | $4,900.00 | $4,900.00 | $3,825.00 | $4,380.00 | $5,000.00 | $4,380.00 |
| 156 | Man TA 4 dia T1F OL (60218300) | EACH | 12 | $7,225.00 | $3,500.00 | $3,500.00 | $3,024.00 | $8,575.00 | $3,024.00 |
| 157 | Man TA 4 dia T1F CL (60218400) | EACH | 9 | $5,513.00 | $3,500.00 | $3,025.00 | $3,024.00 | $6,200.00 | $3,024.00 |
| 158 | Man TA 4 dia T8G (60219000) | EACH | 4 | $4,460.00 | $3,200.00 | $3,400.00 | $2,770.00 | $4,600.00 | $2,770.00 |
| 159 | Man TA 4 dia T24F&G (60219540) | EACH | 8 | $4,460.00 | $3,800.00 | $3,575.00 | $3,235.00 | $4,800.00 | $3,235.00 |
| 160 | Man TA 5 dia T1F CL (60221100) | EACH | 1 | $5,800.00 | $5,900.00 | $5,050.00 | $5,220.00 | $6,500.00 | $5,220.00 |
| 161 | Man TA 6 dia T1F CL (60223800) | EACH | 1 | $10,330 | $8,900.00 | $8,150.00 | $8,210.00 | $11,000 | $8,210.00 |
| 162 | Man TA 7 dia T5F OL (60224436) | EACH | 2 | $13,300 | $13,600 | $11,925 | $13,100 | $18,000 | $13,100 |
| 163 | Man TA 7 dia T8G (60224448) | EACH | 1 | $13,300 | $13,400 | $11,750 | $13,100 | $17,500 | $13,100 |
| 164 | Man TA 8 dia T1F OL (60224457) | EACH | 8 | $20,870 | $17,800 | $15,100 | $15,970 | $22,500 | $15,970 |
| 165 | Inlets TA T8G (60236200) | EACH | 2 | $2,000.00 | $2,200.00 | $1,815.00 | $1,225.00 | $2,350.00 | $1,225.00 |
| 166 | Remov manholes (60500040) | EACH | 5 | $1,000.00 | $600.00 | $600.00 | $850.00 | $500.00 | $850.00 |
| 167 | Remov catch bas (60500050) | EACH | 3 | $1,000.00 | $600.00 | $600.00 | $1,100.00 | $325.00 | $1,100.00 |
| 168 | Remov inlets (60500060) | EACH | 2 | $800.00 | $300.00 | $400.00 | $135.00 | $325.00 | $135.00 |
| 169 | Comb CC&G TB6.12 (60603800) | LF | 297 | $40.00 | $39.00 | $39.00 | $29.00 | $50.00 | $29.98 |
| 170 | Comb CC&G TY B-6.24 (60605000) | LF | 4,346 | $38.00 | $45.00 | $30.00 | $39.00 | $42.00 | $40.01 |
| 171 | SPBGR TY A 6FT posts (63000001) | LF | 4,531.25 | $35.43 | $33.00 | $32.21 | $32.87 | $32.21 | $37.00 |
| 172 | SPGR att to culvert (63000030) | LF | 206.25 | $226.88 | $260.00 | $251.00 | $256.12 | $251.00 | $220.00 |
| 173 | LSG OV cul 12'6" span (63000350) | LF | 75 | $38.13 | $36.00 | $34.66 | $35.37 | $34.66 | $47.00 |
| 174 | LSG over cul 25' span (63000370) | LF | 100 | $37.18 | $36.00 | $33.80 | $34.49 | $33.80 | $37.00 |
| 175 | TR bar TRM T1 SPL tan (63100167) | EACH | 24 | $3,549.70 | $3,400.00 | $3,227.00 | $3,292.86 | $3,227.00 | $4,000.00 |
| 176 | Guardrail remov (63200310) | LF | 5,792 | $10.85 | $10.00 | $9.86 | $5.95 | $9.86 | $5.00 |
| 177 | Non SPL waste disposl (66900200) | CY | 4,982 | $80.00 | $104.00 | $94.00 | $60.00 | $96.00 | $82.62 |
| 178 | Soil disposal analy (66900530) | EACH | 5 | $1,815.00 | $1,600.00 | $920.00 | $920.00 | $920.00 | $920.00 |
| 179 | Reg sub P-const plan (66901001) | LS | 1 | $2,750.00 | $3,500.00 | $4,900.00 | $4,900.00 | $4,900.00 | $4,900.00 |
| 180 | Reg sub F con report (66901003) | LS | 1 | $2,750.00 | $1,500.00 | $500.00 | $500.00 | $500.00 | $500.00 |
| 181 | Reg sub mon (66901006) | CAL DAY | 10 | $2,000.00 | $1,800.00 | $2,000.00 | $740.00 | $740.00 | $740.00 |
| 182 | Mobilization (67100100) | LS | 1 | $789,000 | $900,000 | $825,000 | $994,478 | $1,000,000 | $1,020,545 |
| 183 | TR cont surveillance (70103815) | CAL DAY | 180 | $0.01 | $200.00 | $50.00 | $50.00 | $300.00 | $200.00 |
| 184 | Changeable message SN (70107025) | CAL DAY | 360 | $50.00 | $35.00 | $21.74 | $20.00 | $35.00 | $35.00 |
| 185 | Short term pavt mking (70300100) | LF | 26,316 | $0.01 | $0.60 | $1.00 | $1.00 | $0.01 | $1.07 |
| 186 | SHRT TRM pavt MK rem (70300150) | SF | 50,028 | $0.01 | $0.40 | $1.00 | $0.75 | $0.01 | $0.40 |
| 187 | Temp PVT MK L4 T4 tape (70307120) | LF | 123,768 | $1.10 | $1.30 | $1.25 | $1.25 | $1.40 | $0.50 |
| 188 | Temp conc barrier (70400100) | LF | 15,595 | $30.00 | $28.00 | $25.00 | $16.12 | $28.00 | $28.00 |
| 189 | Rel temp conc barrier (70400200) | LF | 13,570 | $12.50 | $3.00 | $24.00 | $3.40 | $10.00 | $3.00 |
| 190 | Imp attn temp FRN TL3 (70600260) | EACH | 37 | $10,000 | $5,500.00 | $5,771.00 | $5,888.78 | $5,771.00 | $5,500.00 |
| 191 | Imp attn rel FRN TL3 (70600332) | EACH | 34 | $2,000.00 | $2,000.00 | $2,423.00 | $2,472.45 | $2,423.00 | $2,000.00 |
| 192 | Reloc sin pan assy TA (72400500) | EACH | 31 | $330.00 | $250.00 | $250.00 | $250.00 | $150.00 | $225.00 |
| 193 | Reloc sin pan assy TB (72400600) | EACH | 1 | $360.00 | $250.00 | $400.00 | $400.00 | $250.00 | $225.00 |
| 194 | Reloc sign panel T1 (72400710) | SF | 6.25 | $16.50 | $44.00 | $30.00 | $30.00 | $35.00 | $40.00 |
| 195 | Terminal marker - DA (72501000) | EACH | 24 | $55.00 | $45.00 | $40.00 | $40.82 | $40.00 | $50.00 |
| 196 | THPL PVT MK LTR & sym (78000100) | SF | 182 | $7.15 | $7.00 | $7.00 | $7.00 | $6.00 | $7.00 |
| 197 | THPL PVT MK line 4 (78000200) | LF | 68,173 | $0.99 | $0.80 | $0.60 | $0.60 | $0.80 | $0.60 |
| 198 | THPL PVT MK line 6 (78000400) | LF | 702 | $1.27 | $1.10 | $2.00 | $2.00 | $0.90 | $2.00 |
| 199 | THPL PVT MK line 12 (78000600) | LF | 1,581 | $3.58 | $3.00 | $3.50 | $3.50 | $3.32 | $3.50 |
| 200 | THPL PVT MK line 24 (78000650) | LF | 120 | $7.15 | $8.00 | $7.00 | $7.00 | $6.00 | $7.00 |
| 201 | Raised refl pavt MKR (78100100) | EACH | 398 | $52.80 | $46.00 | $50.00 | $50.00 | $39.00 | $50.00 |
| 202 | Grdrail ref type A (78200005) | EACH | 78 | $11.00 | $12.00 | $10.00 | $10.20 | $10.00 | $10.00 |
| 203 | Raised ref PVT MK rem (78300200) | EACH | 398 | $10.00 | $20.00 | $10.00 | $19.00 | $0.01 | $11.97 |
| 204 | PVT MKG rem grinding (78300201) | SF | 25,078 | $1.25 | $1.10 | $1.00 | $1.00 | $0.90 | $1.00 |
| 205 | PVT MKG rem WTR blast (78300202) | SF | 3,762 | $2.48 | $4.60 | $1.00 | $1.00 | $2.00 | $4.20 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from IDOT's tabulation for this contract. IDOT Unit Price Tabulation of Bids reports for every letting from January 2021 to September 2026 posted on IDOT's letting site. Contracts with alternate bid groups are left out, and so are bids that did not match their published total.
Every contract let that day: IDOT letting of June 12, 2026. Compiled by Mirage Metrics.