48" RC pipe culverts, class III, NCDOT 0402000000-E

Low bidders on NCDOT contracts carried a median of $388.50 per LF for this item, over the 24 months to 20 OCT 2026, across 6 low bids. Half of all 34 bids fell between $377.75 and $600.00.

Owner
North Carolina DOT
Item
0402000000-E
Unit
LF
Data through
20 OCT 2026

NCDOT prints this item as “48" RC PIPE CULV III”.

$388.50Low bidder's median, per LF
$431.67Median of all bids, per LF
6Contracts in the window

By year of letting

48" RC pipe culverts, class III, NCDOT: unit prices by year
YearContractsLow bidsLow-bid medianAll bidsMedian, all bids
201388$98.6945$113.00
20141212$119.0094$115.00
201566$132.6937$153.51
201633$171.0018$166.00
201744$139.0129$155.00
201855$182.0018$192.76
201977$164.0022$173.50
202177$215.0020$224.00
202299$302.0034$310.00
202366$363.5031$380.00
202444$385.9417$394.89
202522$321.887$380.00
202633$411.6923$468.04

Bid prices as published, not adjusted for inflation.

By county

CountyLow bidsLow-bid medianAll bidsMedian, all bids
Cleveland4$130.5140$132.00
Guilford5$113.0039$140.00
Forsyth5$312.3633$300.00
Cumberland5$302.0025$232.50
Robeson4$206.0717$310.70
Graham3$500.9310$500.47
Clay3$315.008$330.81
Columbus3$285.226$410.60
48" RC pipe culverts, class III, NCDOT: unit prices by county, all lettings

Countys with at least three low bids, over all lettings.

By quantity

Quantity (LF)Low bidsLow-bid median
8 to 9219$278.00
96 to 17619$239.14
192 to 43219$169.25
504 to 1,97219$160.00
48" RC pipe culverts, class III, NCDOT: low bidder's median by quantity band

The low bids split into four bands of equal count by the quantity on the contract. Larger quantities usually carry lower unit prices.

Who is lowest on this line

48" RC pipe culverts, class III, NCDOT: bidders most often lowest on this line

The lowest unit price on each line, whoever won the contract, over all lettings in the data, for firms with five lines or more.

Latest contracts with this item

LetContractCountyQuantityLow bidder's priceMedianBidsLow bidderSource
20 OCT 2026C204338Wake12$411.69$487.508Blythe Construction IncNCDOT
16 JUN 2026C205157Randolph24$999.00$438.3411Branch Civil IncNCDOT
19 MAY 2026C205153Hertford16$300.00$412.004FSC II LLC DBA Fred Smith CompanyNCDOT
16 SEP 2025C204836Clay128$400.00$644.403Watson Contracting IncNCDOT
21 JAN 2025C204992Hoke248$243.75$306.504Barnhill Contracting CompanyNCDOT
17 DEC 2024C204988Cumberland112$377.00$348.504Highland Paving Co LLCNCDOT
15 OCT 2024C204348Iredell, Catawba144$377.00$385.005Blythe Development Co.NCDOT
28 MAY 2024C204913Forsyth132$394.89$394.895Apac Atlantic Inc Smith Rowe LLC JVNCDOT
20 FEB 2024C204912Columbus8$1,500.00$925.003S T Wooten CorporationNCDOT
19 DEC 2023C204887Cherokee776$373.00$389.002Wright Brothers Construction Company IncNCDOT
21 NOV 2023C204880Forsyth32$311.00$375.508Triangle Grading & Paving IncNCDOT
21 NOV 2023C204471Wilkes20$565.50$487.752Branch Civil IncNCDOT
21 NOV 2023C204852Iredell60$354.00$398.005The Lane Construction CorpNCDOT
18 JUL 2023C204851Cleveland112$400.00$412.504Ames Construction IncNCDOT
21 FEB 2023C204772Robeson104$340.00$345.0010C. M. Lindsay & Sons, Inc.NCDOT
Latest NCDOT contracts carrying 48" RC pipe culverts, class III

Filter this item by your own quantity, county and period, or check your price against it, in the NCDOT explorer.

How these prices were read

NCDOT central letting bid tab workbooks, January 2013 to October 2026, each contract linked to the workbook it was read from. Bids that did not match their published total are left out.

  • Statistics leave out bids over three times the low bid, zero or negative prices and token prices under 5% of the median.
  • Item codes and units are NCDOT's own: this item is compared with NCDOT contracts only.
  • Prices are bid prices, not paid prices. Use them as a reference range, never as a quote.
  • The data runs to the NCDOT letting of 20 OCT 2026 and was rebuilt on 26 NOV 2026.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy