ODOT letting results, June 16, 2022
25 contracts let by Ohio DOT on June 16, 2022, $33,365,653 in low bids, a median of 2 bidders per contract. On the 25 with an engineer's estimate, the low bid came in under it 12 times; median low bid +1.0% against the estimate.
- Owner
- Ohio DOT
- Contracts
- 25
- Low bids, total
- $33,365,653
- Data through
- 12 NOV 2026
Contracts let that day
| Contract | Project | County | Bids | Low bidder | Low bid | Second bid | Gap | Against estimate | Source |
|---|---|---|---|---|---|---|---|---|---|
| 220375 | MOT-W Springfield St Recon (MINOR RECONSTRUCTION) | MOT | 4 | Brumbaugh Construction Inc | $4,080,840 | $4,297,487 | +5.0% | +11% | ODOT |
| 220374 | MEG-US 33-10.72 (FOUR LANE RESURFACING) | MEG | 1 | Shelly Company | $3,624,876 | +2.0% | ODOT | ||
| 220385 | D11-PM-FY2023(B) (PAVEMENT MARKING) | District 11 | 2 | The Aero-Mark Company LLC | $2,662,262 | $3,089,465 | +16% | +39% | ODOT |
| 220387 | FRA-IR 270/IR 70-SP FY23 CONCRETE (SPOT PATCHING / PAVEMENT REPAIR) | FRA | 2 | Perk Company Inc | $2,546,977 | $2,815,482 | +11% | +8.0% | ODOT |
| 220370 | ERI-/LOR-MICRO FY2023 (MICROSURFACING) | ERI | 2 | Strawser Construction Inc | $2,412,700 | $2,641,696 | +9.0% | +23% | ODOT |
| 220377 | PAU-US 24-13.52 (SLIDE REPAIR) | PAU | 4 | Miller Bros Const Inc | $2,153,179 | $2,182,233 | +1.0% | -1.0% | ODOT |
| 220350 | MOT-IR 75-VAR (SIGNALIZATION) | MOT | 4 | Perram Electric Inc | $1,897,150 | $2,248,287 | +19% | +3.0% | ODOT |
| 220382 | CRA-/RIC-CHIP FY2023 (CHIP SEAL) | CRA | 2 | Henry W Bergman Inc | $1,689,945 | $1,800,187 | +7.0% | +28% | ODOT |
| 220388 | FRA-GR FY23 (GUARDRAIL REBUILDING) | FRA | 2 | M P Dory Co | $1,497,879 | $1,672,975 | +12% | -14% | ODOT |
| 220352 | ROS-SR 772-06.31 (TWO LANE RESURFACING) | ROS | 2 | Shelly & Sands Inc | $1,283,637 | $1,326,484 | +3.0% | -3.0% | ODOT |
| 220383 | D05-SP FY2023 (SPOT PATCHING / PAVEMENT REPAIR) | District 5 | 2 | Shelly Company | $1,113,711 | $1,133,466 | +2.0% | -21% | ODOT |
| 220372 | HAM-IR 74-11.20 (SPOT PATCHING / PAVEMENT REPAIR) | HAM | 2 | Barrett Paving Materials Inc | $1,098,590 | $1,801,136 | +64% | -3.0% | ODOT |
| 220379 | BEL-SR 149-08.15 (PART 1 AND PART 2) (SLIDE REPAIR) | BEL | 4 | Ohio-West Virginia Excavating Co | $1,078,236 | $1,176,999 | +9.0% | -7.0% | ODOT |
| 220368 | COL-SR 170-11.42 (TWO LANE RESURFACING) | COL | 4 | Shelly Company | $1,062,054 | $1,259,882 | +19% | +11% | ODOT |
| 220367 | BEL-CR 4-23.62/25.79 (SLIDE REPAIR) | BEL | 3 | Shelly & Sands Inc | $731,923 | $732,239 | 0.0% | +34% | ODOT |
| 220386 | FRA-Litter/Mow FY23 (MOWING) | FRA | 2 | Bladecutters Inc | $632,111 | $720,816 | +14% | +47% | ODOT |
| 220384 | D06-GR FY23 (GUARDRAIL REBUILDING) | District 6 | 2 | Lake Erie Construction Company | $581,675 | $697,995 | +20% | -10% | ODOT |
| 220391 | TUS-IR 77-31.54 (PARKING AREAS) | TUS | 3 | Shelly & Sands Inc | $556,161 | $640,655 | +15% | -11% | ODOT |
| 220389 | HAS-SR 519-06.38 (MINOR RECONSTRUCTION) | HAS | 3 | Ohio-West Virginia Excavating Co | $509,178 | $661,821 | +30% | -6.0% | ODOT |
| 220371 | HAM-SR 128-05.70 (TWO LANE RESURFACING) | HAM | 2 | Barrett Paving Materials Inc | $476,964 | $483,438 | +1.0% | +19% | ODOT |
| 220373 | LIC-SR 310-09.88 (CULVERT REPLACEMENT) | LIC | 4 | Buds Inc | $423,341 | $494,124 | +17% | +1.0% | ODOT |
| 220380 | BEL-US 250-04.49 (SLIDE REPAIR) | BEL | 4 | Alan Stone Co Inc | $353,149 | $361,279 | +2.0% | -3.0% | ODOT |
| 220390 | HAS-US 22-01.86 (SLIDE REPAIR) | HAS | 5 | Ohio-West Virginia Excavating Co | $332,293 | $343,079 | +3.0% | -19% | ODOT |
| 220376 | OTT-SR 269-04.55 Culvert (CULVERT REPLACEMENT) | OTT | 2 | Great Lakes Demolition Company | $294,598 | $383,441 | +30% | +3.0% | ODOT |
| 220381 | BEL-US 250-08.10 (SLIDE REPAIR) | BEL | 5 | Dennison Bridge Inc | $272,224 | $296,280 | +9.0% | -11% | ODOT |
Gap is the second bid over the low bid. Where a contract shows fewer bids than ODOT received, the others did not match their published totals and are left out.
Your own bid history, read the same way