TDOT contract CN262026 bid tabulation

The resurfacing on s.r. 17 from campbell street (l.m. 5.63) to near s.r. 153 (l.m. 8.75). Let by Tennessee DOT on March 20, 2026, Hamilton County. 2 bids received; low bid $1,596,482 by Wright Brothers Construction Company, Inc..

Owner
Tennessee DOT
Letting
20 MAR 2026
Pay items
41
Data through
02 OCT 2026

Bidders

RankBidderTotal bidAgainst the low bid
1Wright Brothers Construction Company, Inc.$1,596,482Low
2APAC-Atlantic, Inc.$1,709,336+7.0%
TDOT contract CN262026: bids by rank

Bid tabulation

LinePay itemUnitQuantity1. Wright Brothers Construction Company, Inc.2. APAC-Atlantic, Inc.
1Brooming & degrassing shoulders (208-01.05)LM4$1,370.00$1,569.12
2Asphalt concrete mix (PG64-22) (BPMB-HM) grading A (307-01.01)TON43$245.00$588.54
3Asphalt concrete mix (PG64-22) (BPMB-HM) grading B-M2 (307-01.08)TON90$169.00$360.39
4Trackless tack coat (403-02.01)TON33$900.00$900.00
5Acs mix(PG64-22) grading D (411-01.10)TON4,499$164.00$191.03
6Longitudinal joint sealant (411-01.21)LM8$3,050.00$3,300.00
7Cold planing bituminous pavement (415-01.01)TON4,539$46.00$37.16
8Adjustment of existing manhole (611-01.20)EACH3$4,400.00$5,280.00
9Gray iron castings (catchbasin) (611-03.04)LB3,250$6.00$7.20
10Adjustment of existing catchbasin (611-09.01)EACH10$2,775.00$3,330.00
11Concrete curb ramp (retrofit) (701-02.01)SF1,600$55.75$66.90
12Concrete curb ramp (701-02.03)SF175$55.75$66.90
13Guardrail transition 27IN to 31IN (705-02.10)EACH5$140.00$150.00
14Earth pad for type 38 GR end treatment (705-04.09)EACH5$1,450.00$1,560.00
15Tangent energy absorbing term MASH TL-3 (705-06.20)EACH5$3,775.00$3,960.00
16Guardrail removed (706-01)LF375$1.00$1.20
17Traffic control (712-01)LS1$107,000$73,557
18Flexible drums (channelizing) (712-04.01)EACH17$28.50$30.00
19Warning lights (type A) (712-05.01)EACH17$1.00$1.20
20Warning lights (type C) (712-05.03)EACH14$1.00$1.20
21Signs (construction) (712-06)SF2,450$7.25$7.74
22Arrow board (type C) (712-08.03)EACH2$900.00$960.00
23Changeable message sign unit (713-16.01)EACH2$5,600.00$6,000.00
24Snowplowable raised pavement markers (BI-dir) (1 color) (716-01.21)EACH206$42.50$45.60
25Snowplowable raised pavment markers (mono-dir)(1 color) (716-01.22)EACH90$42.50$45.60
26Removal of snowplowable reflective marker (716-01.30)EACH196$13.25$14.40
27Plastic pavement marking(channelization striping) (716-02.04)SY417$24.50$26.40
28Plastic pavement marking (stop line) (716-02.05)LF654$11.00$12.00
29Plastic pavement marking (turn lane arrow) (716-02.06)EACH6$168.00$180.00
30Plastic pavement marking (24" barrier line) (716-02.07)LF82$8.25$9.00
31Plastic pavement marking (longitudinal cross-walk) (716-02.09)LF1,024$28.00$30.00
32Plastic word pavement marking (DO not block) (716-03.09)EACH1$500.00$540.00
33Plastic pavement marking (straight arrow) (716-04.05)EACH4$168.00$180.00
34Plastic pavement marking (bicycle symbol W/rider) (716-04.11)EACH10$475.00$510.00
35Plastic pavement marking (yield line) (716-04.12)SF50$16.70$18.00
36Plastic pavement marking (bikelane symbol & arrow) (716-04.13)EACH6$475.00$510.00
37Painted pavement marking (4" line) (716-05.01)LM10$1,385.00$1,500.00
38Enhanced flatline thermo PVMT MRKNG (6IN line) (716-12.02)LM10$7,275.00$7,800.00
39Mobilization (717-01)LS1$79,000$61,387
40Saw slot (730-14.02)LF117$7.75$8.34
41Loop wire (730-14.03)LF234$2.50$2.70
TDOT contract CN262026: unit prices by line

The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.

Source

Read from TDOT's tabulation for this contract. TDOT Summary of Bids PDFs: every letting posted for February 2024 to October 2026, and nine lettings of 2018 to 2023 recovered from archived copies of the tn.gov files. Cost-plus-time bids, and bids that did not match their published total, are left out.

Every contract let that day: TDOT letting of March 20, 2026. Compiled by Mirage Metrics.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy