TDOT contract CN264022 bid tabulation

The resurfacing on s.r. 43 from the weakley county line (l.m. 0.00) to the kentucky state line (l.m. 6.60). Let by Tennessee DOT on March 20, 2026, Obion County. 1 bid received; low bid $8,056,626 by Ford Construction Company.

Owner
Tennessee DOT
Letting
20 MAR 2026
Pay items
45
Data through
02 OCT 2026

Bidders

RankBidderTotal bidAgainst the low bid
1Ford Construction Company$8,056,626Low
TDOT contract CN264022: bids by rank

Bid tabulation

LinePay itemUnitQuantity1. Ford Construction Company
1Removal of rigid pavement, sidewalk, etc. (202-03)SY25$115.00
2Removal of asphalt pavement (202-03.01)SY374$40.00
3Removal of curb and gutter (curb ramps) (202-08.15)LF95$18.00
4Water (203-06)MG10$1.00
5Brooming & degrassing shoulders (208-01.05)LM15$1,355.00
6Mineral aggregate, type B base, grading (C or D) (303-02)TON1,465$41.00
7Asphalt concrete mix (PG64-22) (BPMB-HM) grading A (307-01.01)TON173$160.00
8Asphalt concrete mix (PG64-22) (BPMB-HM) grading B-M2 (307-01.08)TON22,399$121.00
9Trackless tack coat (403-02.01)TON183$1,307.00
10Acs mix (PG64-22) grading E shoulder (411-01.07)TON3,569$137.00
11Acs mix(PG64-22) grading D (411-01.10)TON14,636$158.00
12Longitudinal joint sealant (411-01.21)LM26$3,310.00
13Scoring shoulders (continuous) (16IN width) (411-12.01)LM6.50$1,305.00
14Scoring shoulders (non-continuous) (16IN width) (411-12.02)LM5.50$1,305.00
15Cold planing bituminous pavement (415-01.01)TON39,903$25.10
16Gray iron castings (catchbasin) (611-03.04)LB750$7.70
17Adjustment of existing catchbasin (611-09.01)EACH3$3,100.00
18Concrete sidewalk (4 ") (701-01.01)SF230$57.00
19Concrete curb ramp (retrofit) (701-02.01)SF700$83.00
20Concrete curb (702-01)CY2.60$2,150.00
21Concrete combined curb & gutter (702-03)CY3.90$2,415.00
22Guardrail transition 27IN to 31IN (705-02.10)EACH7$135.00
23Tangent energy absorbing term MASH TL-3 (705-06.20)EACH7$3,570.00
24Guardrail removed (706-01)LF350$3.15
25Traffic control (712-01)LS1$195,000
26Flexible drums (channelizing) (712-04.01)EACH94$1.05
27Signs (construction) (712-06)SF2,388.38$6.75
28Temporary barricades (type II) (712-07.02)LF36$26.25
29Arrow board (type C) (712-08.03)EACH2$1,050.00
30Snowplowable raised pavement markers (BI-dir) (1 color) (716-01.21)EACH474$50.40
31Snowplowable raised pavment markers (mono-dir)(1 color) (716-01.22)EACH312$50.40
32Snowplowable raised pavement markers (BI-dir)(2 color) (716-01.23)EACH442$50.40
33Plastic pavement marking(channelization striping) (716-02.04)SY250$39.90
34Plastic pavement marking (stop line) (716-02.05)LF448$31.50
35Plastic pavement marking (turn lane arrow) (716-02.06)EACH30$262.50
36Plastic pavement marking (8" dotted line) (716-02.08)LF535$4.20
37Plastic pavement marking (longitudinal cross-walk) (716-02.09)LF49$54.60
38Plastic pavement marking (8IN line) (716-02.12)LM0.23$22,200
39Plastic word pavement marking (only) (716-03.01)EACH1$290.00
40Plastic pavement marking (transverse shoulder) (716-04.04)LF50$17.00
41Painted pavement marking (stop line) (716-05.05)LF448$18.90
42Painted pavement marking (6" line) (716-05.20)LM62$2,310.00
43Enhanced flatline thermo PVMT MRKNG (6IN line) (716-12.02)LM31$8,295.00
44Enhanced flatline thermo PVMT MRKNG (6IN dotted line) (716-12.05)LF325$4.20
45Mobilization (717-01)LS1$217,000
TDOT contract CN264022: unit prices by line

The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.

Source

Read from TDOT's tabulation for this contract. TDOT Summary of Bids PDFs: every letting posted for February 2024 to October 2026, and nine lettings of 2018 to 2023 recovered from archived copies of the tn.gov files. Cost-plus-time bids, and bids that did not match their published total, are left out.

Every contract let that day: TDOT letting of March 20, 2026. Compiled by Mirage Metrics.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy