The resurfacing (either microsurface or thin mix overlay) on u.s. 64 (s.r. 15) from near west gaines street (l.m. 12.64) to near eagle factory road (l.m. 17.18), including thin epoxy overlay on bridges. Let by Tennessee DOT on December 5, 2025, Lawrence County. 3 bids received; low bid $2,082,782 by Rogers Group, Inc..

Owner
Tennessee DOT
Letting
05 DEC 2025
Pay items
43
Data through
02 OCT 2026

Bidders

RankBidderTotal bidAgainst the low bid
1Rogers Group, Inc.$2,082,782Low
2Wiregrass Construction Company, Inc$2,360,401+13%
3Intermountain Slurry Seal, Inc.$2,779,442+33%
TDOT contract CNZ301: bids by rank

Bid tabulation

LinePay itemUnitQuantity1. Rogers Group, Inc.2. Wiregrass Construction Company, Inc3. Intermountain Slurry Seal, Inc.
1Brooming & degrassing shoulders (208-01.05)LM17.20$1,600.00$1,179.92$4,500.00
2Mineral aggregate, type A base, grading D (303-01)TON2,271$29.00$85.49$68.00
3Scoring shoulders (continuous) (16IN width) (411-12.01)LM8.60$960.00$955.42$750.00
4Scoring shoulders (non-continuous) (16IN width) (411-12.02)LM6.90$960.00$955.41$750.00
5Traffic control (712-01)LS1$81,702$25,143$75,000
6Flexible drums (channelizing) (712-04.01)EACH100$31.00$28.16$45.00
7Warning lights (type C) (712-05.03)EACH25$16.00$1.01$45.00
8Arrow board (type C) (712-08.03)EACH2$1,200.00$1,005.70$2,500.00
9Flexible delineator (white) (713-02.14)EACH26$56.00$60.34$75.00
10Remove and replace sign (R4-7) (713-16.50)EACH2$221.00$352.00$250.00
11Remove and replace sign (R1-1, R5-1, R6-1L, R6-1R, & R6-3A) (713-16.51)EACH1$306.00$502.85$250.00
12Remove and replace sign (R5-1, R6-1L, & R6-1R) (713-16.52)EACH1$275.00$427.42$250.00
13Snowplowable raised pavment markers (mono-dir)(1 color) (716-01.22)EACH367$41.00$40.23$50.00
14Snowplowable raised pavement markers (BI-dir)(2 color) (716-01.23)EACH602$41.00$40.23$50.00
15Removal of snowplowable reflective marker (716-01.30)EACH969$16.00$15.09$15.00
16Plastic pavement marking(channelization striping) (716-02.04)SY54$36.00$35.20$30.00
17Plastic pavement marking (stop line) (716-02.05)LF144$26.00$25.14$15.00
18Plastic pavement marking (turn lane arrow) (716-02.06)EACH39$251.00$251.43$225.00
19Plastic pavement marking (24" barrier line) (716-02.07)LF91$16.00$15.09$15.00
20Plastic pavement marking (8" dotted line) (716-02.08)LF2,376$3.50$3.02$4.00
21Plastic pavement marking (8IN line) (716-02.12)LM1.40$10,030$10,057$10,000
22Plastic pavement marking (yield line) (716-04.12)SF444$40.50$40.23$15.00
23Contrast pavement marking 6" (716-09.86)LM1$20,100$20,114$49,000
24Contrast pavement shadow marking 6" (716-09.94)LM0.30$20,100$20,114$31,000
25Enhanced flatline thermo PVMT MRKNG (6IN line) (716-12.02)LM20.20$8,030.00$8,045.60$7,000.00
26Mobilization (717-01)LS1$50,244$100,677$225,000
27Type 1 thin epoxy overlay (epoxy-urethane) (617-04.01)SY10,270$32.00$31.93$45.00
28Bituminous material for tack coat (micro-surfacing) (403-01.01)TON31$1,769.44$1,500.00
29Emulsified asphalt for micro-surfacing (414-03.01)TON432$1,078.83$1,000.00
30Aggregate for micro surfacing (414-03.02)TON3,590$209.90$225.00
31Signs (construction) (712-06)SF688$7.29$10.00
32Painted pavement marking (6" line) (716-05.20)LM20.20$1,810.26$1,600.00
33Removal of pavement marking (channelization striping) (716-08.04)SY54$20.11$15.00
34Removal of pavement marking (stop line) (716-08.05)LF144$8.05$5.00
35Removal of pavement marking (turn lane arrow) (716-08.06)EACH51$100.57$75.00
36Removal of pavement marking (dotted line) (716-08.09)LF792$0.91$1.25
37Removal of pavement marking (yield line) (716-08.19)SF180$3.02$2.25
38Removal of pavement marking (line) (716-08.20)LM22.80$2,011.40$5,300.00
39Removal of pavement marking (24IN barrier line) (716-08.21)LF91$8.05$5.00
40Bituminous material for tack coat (TC) (403-01)TON75$837.00
41Acs mix(PG64-22) thin lift asphalt (411-03.07)TON9,612$112.00
42Cold planing bituminous pavement (415-01.01)TON686$87.00
43Signs (construction) (712-06)SF762$7.50
TDOT contract CNZ301: unit prices by line

The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.

Source

Read from TDOT's tabulation for this contract. TDOT Summary of Bids PDFs: every letting posted for February 2024 to October 2026, and nine lettings of 2018 to 2023 recovered from archived copies of the tn.gov files. Cost-plus-time bids, and bids that did not match their published total, are left out.

Every contract let that day: TDOT letting of December 5, 2025. Compiled by Mirage Metrics.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy