TxDOT contract A00139927 bid tabulation
Bridge Replacement, FM 72 (At Spring Creek Bridge to -). Let by Texas DOT on May 6, 2026, Irion, San Angelo District. 10 bids received; low bid $4,405,521 by Delgado'S Contractors, LLC, -15% against the engineer's estimate of $5,202,797.
- Owner
- Texas DOT
- Letting
- 06 MAY 2026
- Pay items
- 82
- Data through
- 19 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | Delgado'S Contractors, LLC | $4,405,521 | Low | -15% |
| 2 | Skyline Bridge LLC | $4,543,261 | +3.0% | -13% |
| 3 | Relmco, Inc. | $4,940,157 | +12% | -5.0% |
| 4 | E-Z Bel Construction, LLC | $5,308,258 | +20% | +2.0% |
| 5 | Tucan Contracting, LLC | $5,534,673 | +26% | +6.0% |
| 6 | Texas Steel Industrial Placing, LLC | $5,539,335 | +26% | +6.0% |
| 7 | Altus Construction LLC | $5,958,483 | +35% | +15% |
| 8 | Earth Builders, L.P. | $7,647,572 | +74% | +47% |
| 9 | Acme Bridge Company, Inc. | $7,656,518 | +74% | +47% |
| 10 | Hodges and Son Construction Company, Inc. | $7,703,009 | +75% | +48% |
Engineer's estimate: $5,202,797.
Bid tabulation
| Line | Pay item | Unit | Quantity | Estimate | 1. Delgado'S Contractors, LLC | 2. Skyline Bridge LLC | 3. Relmco, Inc. | 4. E-Z Bel Construction, LLC | 5. Tucan Contracting, LLC | 6. Texas Steel Industrial Placing, LLC |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Preparing row (100-7002) | STA | 8 | $4,500.00 | $1,200.00 | $3,000.00 | $10,000 | $9,000.00 | $1,650.00 | $10,000 |
| 2 | Remove (8") TRT/untrt base & asphalt pavement (105-7028) | SY | 1,589 | $10.00 | $21.00 | $9.00 | $18.00 | $2.40 | $15.40 | $15.00 |
| 3 | Excavation (roadway) (110-7001) | CY | 4,223 | $20.00 | $25.00 | $12.65 | $30.00 | $23.00 | $16.50 | $17.00 |
| 4 | Embankment (final)(DC)(type B) (132-7004) | CY | 1,861 | $30.00 | $50.00 | $32.00 | $25.00 | $12.00 | $24.20 | $17.00 |
| 5 | Broadcast seed (permanent_rural_clay) (164-7002) | SY | 1,848 | $1.00 | $1.00 | $3.20 | $3.00 | $3.00 | $1.10 | $3.50 |
| 6 | Soil ret BLKT(SL_mod_clay_short_roll) (169-7009) | SY | 13 | $200.00 | $5.00 | $22.00 | $100.00 | $20.00 | $22.00 | $25.00 |
| 7 | Proof rolling (216-7001) | HR | 20 | $115.00 | $25.00 | $100.00 | $115.00 | $105.00 | $220.00 | $150.00 |
| 8 | FL BS (compacted in place)(tya GR1-2)(final pos) (247-7176) | CY | 792 | $125.00 | $100.00 | $132.50 | $105.00 | $95.00 | $38.50 | $100.00 |
| 9 | Prime coat(MC-30 or AE-P) (310-7013) | GAL | 471 | $10.50 | $10.00 | $32.00 | $12.00 | $10.00 | $5.71 | $16.00 |
| 10 | Asphalt (AC-20-5TR) (316-7007) | GAL | 964 | $10.50 | $25.00 | $22.00 | $12.00 | $8.00 | $6.84 | $16.00 |
| 11 | Aggregate (type-B, GR-3)(sac-B) (316-7171) | CY | 22 | $500.00 | $500.00 | $2,300.00 | $250.00 | $1,900.00 | $167.50 | $1,100.00 |
| 12 | D-GR HMA type-C sac-B PG70-22 (exempt) (341-7037) | TON | 369 | $180.00 | $275.00 | $300.00 | $165.00 | $160.00 | $318.60 | $400.00 |
| 13 | Cem stabil BKFL (400-7010) | CY | 260 | $200.00 | $200.00 | $250.00 | $200.00 | $225.00 | $220.00 | $200.00 |
| 14 | Temporary special shoring (403-7001) | SF | 779 | $35.00 | $35.00 | $25.00 | $30.00 | $32.00 | $11.00 | $23.00 |
| 15 | Drilled shaft (18 in) (416-7002) | LF | 116 | $150.00 | $200.00 | $225.00 | $300.00 | $133.00 | $247.50 | $300.00 |
| 16 | Drilled shaft (36 in) (416-7006) | LF | 200 | $300.00 | $465.00 | $340.00 | $450.00 | $475.00 | $302.50 | $600.00 |
| 17 | Drilled shaft (42 in) (416-7007) | LF | 256 | $500.00 | $500.00 | $375.00 | $575.00 | $305.00 | $385.00 | $600.00 |
| 18 | Class C concrete (abutment) (420-7012) | CY | 78 | $1,500.00 | $1,800.00 | $1,325.00 | $1,503.00 | $1,475.00 | $1,430.00 | $1,500.00 |
| 19 | Class C concrete (cap) (420-7022) | CY | 40.80 | $1,900.00 | $2,000.00 | $1,850.00 | $2,347.00 | $2,070.00 | $1,595.00 | $3,000.00 |
| 20 | Class C concrete (column) (420-7038) | CY | 18.40 | $2,100.00 | $1,500.00 | $2,100.00 | $1,972.00 | $1,565.00 | $1,760.00 | $3,500.00 |
| 21 | Reinforced concrete slab (422-7001) | SF | 13,680 | $35.00 | $30.50 | $26.00 | $27.60 | $32.00 | $38.50 | $30.00 |
| 22 | Approach slab (422-7013) | CY | 92.20 | $700.00 | $1,200.00 | $800.00 | $1,121.00 | $725.00 | $1,045.00 | $550.00 |
| 23 | Silicone resin paint finish (427-7004) | SF | 1,685.40 | $25.00 | $12.00 | $9.00 | $14.00 | $43.00 | $12.10 | $10.70 |
| 24 | Riprap (concrete)(5 in) (432-7002) | CY | 273.60 | $650.00 | $650.00 | $475.00 | $737.80 | $482.00 | $715.00 | $550.00 |
| 25 | Riprap (mow strip)(4 in) (432-7013) | CY | 53 | $750.00 | $650.00 | $700.00 | $737.80 | $525.00 | $715.00 | $600.00 |
| 26 | Elastomeric bearing (E4) (434-7024) | EACH | 6 | $3,500.00 | $3,350.00 | $5,000.00 | $2,300.00 | $3,200.00 | $3,312.10 | $3,750.00 |
| 27 | Elastomeric bearing (F4) (434-7034) | EACH | 6 | $3,500.00 | $3,350.00 | $5,000.00 | $2,300.00 | $3,200.00 | $3,312.10 | $3,750.00 |
| 28 | Sliding elastomeric bearing (ES 3) (434-7043) | EACH | 12 | $3,500.00 | $3,350.00 | $4,000.00 | $2,300.00 | $3,300.00 | $3,089.90 | $3,750.00 |
| 29 | STR steel (plate girder) (442-7001) | LB | 701,199.60 | $2.75 | $2.40 | $2.35 | $2.50 | $3.25 | $2.90 | $3.00 |
| 30 | Rail (type T223) (450-7008) | LF | 796 | $150.00 | $150.00 | $125.00 | $115.00 | $191.00 | $187.00 | $160.00 |
| 31 | Sealed expansion joint (4 in) (SEJ - M) (454-7004) | LF | 89 | $250.00 | $200.00 | $325.00 | $285.00 | $340.00 | $330.00 | $235.00 |
| 32 | Removing structure (bridge 100 - 499 FT length) (496-7010) | EACH | 1 | $60,000 | $75,000 | $78,000 | $200,000 | $170,000 | $330,000 | $300,000 |
| 33 | Mobilization (500-7001) | LS | 1 | $513,000 | $200,000 | $400,000 | $450,000 | $502,000 | $550,000 | $553,973 |
| 34 | Barricades, signs and traffic handling (502-7001) | MO | 13 | $15,000 | $3,000.00 | $2,500.00 | $4,500.00 | $2,100.00 | $2,200.00 | $3,000.00 |
| 35 | Portable changeable message sign (503-7001) | DAY | 560 | $100.00 | $35.00 | $60.00 | $125.00 | $115.00 | $275.00 | $65.00 |
| 36 | TMA (stationary) (505-7001) | DAY | 60 | $350.00 | $250.00 | $300.00 | $300.00 | $300.00 | $550.00 | $300.00 |
| 37 | TMA (mobile operation) (505-7003) | DAY | 12 | $350.00 | $250.00 | $50.00 | $300.00 | $550.00 | $550.00 | $1.00 |
| 38 | Rock filter dams (install) (type 2) (506-7002) | LF | 175 | $50.00 | $44.00 | $40.00 | $35.00 | $89.00 | $33.00 | $40.00 |
| 39 | Rock filter dams (remove) (506-7011) | LF | 175 | $20.00 | $4.00 | $10.00 | $15.00 | $30.00 | $11.00 | $10.00 |
| 40 | Temporary sediment control fence (install) (506-7039) | LF | 1,331 | $9.00 | $5.00 | $4.00 | $6.00 | $6.00 | $4.40 | $4.00 |
| 41 | Temporary sediment control fence (remove) (506-7041) | LF | 1,331 | $4.50 | $1.00 | $1.50 | $3.00 | $3.00 | $1.10 | $1.00 |
| 42 | Constructing detours (508-7001) | SY | 687 | $175.00 | $75.00 | $135.00 | $145.00 | $66.00 | $110.00 | $80.00 |
| 43 | One-way traffic control (port traffic signal) (510-7003) | MO | 12 | $4,000.00 | $3,575.00 | $4,800.00 | $3,500.00 | $2,111.00 | $8,800.00 | $4,000.00 |
| 44 | Portable concrete traffic barrier (furnish and install)(single slope)(type 1) (512-7001) | LF | 420 | $55.00 | $50.00 | $100.00 | $35.00 | $29.50 | $93.50 | $87.06 |
| 45 | Portable concrete traffic barrier (furnish and install)(low prof)(type 1) (512-7009) | LF | 920 | $55.00 | $50.00 | $100.00 | $30.00 | $29.50 | $88.00 | $72.34 |
| 46 | Portable concrete traffic barrier (furnish and install)(low prof)(type 2) (512-7010) | LF | 120 | $55.00 | $45.00 | $135.00 | $30.00 | $29.50 | $77.00 | $72.34 |
| 47 | Portable concrete traffic barrier (move)(single slope)(type 1) (512-7025) | LF | 330 | $25.00 | $15.00 | $50.00 | $15.00 | $31.00 | $16.50 | $20.00 |
| 48 | Portable concrete traffic barrier (move)(low prof)(type 1) (512-7033) | LF | 600 | $10.00 | $15.00 | $15.00 | $14.00 | $17.50 | $16.50 | $20.00 |
| 49 | Portable concrete traffic barrier (move)(low prof)(type 2) (512-7034) | LF | 40 | $50.00 | $15.00 | $15.00 | $14.00 | $17.50 | $16.50 | $20.00 |
| 50 | Portable concrete traffic barrier (remove)(single slope)(type 1) (512-7049) | LF | 420 | $25.00 | $15.00 | $67.75 | $25.00 | $29.50 | $16.50 | $33.00 |
| 51 | Portable concrete traffic barrier (remove)(low prof)(type 1) (512-7057) | LF | 920 | $15.00 | $15.00 | $20.00 | $25.00 | $29.50 | $16.50 | $26.00 |
| 52 | Portable concrete traffic barrier (remove)(low prof)(type 2) (512-7058) | LF | 120 | $20.00 | $15.00 | $20.00 | $25.00 | $29.50 | $16.50 | $17.00 |
| 53 | Driveways (ACP) (530-7010) | SY | 37 | $200.00 | $50.00 | $200.00 | $100.00 | $86.00 | $79.31 | $65.00 |
| 54 | Metal W-beam guard fence (steel post) (540-7002) | LF | 650 | $40.00 | $40.00 | $32.00 | $42.90 | $39.00 | $42.72 | $28.00 |
| 55 | Metal thrie-beam guard fence (steel post) (540-7020) | EACH | 4 | $800.00 | $2,500.00 | $2,300.00 | $2,970.00 | $2,653.00 | $2,918.30 | $2,000.00 |
| 56 | Remove metal beam guard fence (542-7001) | LF | 544 | $4.00 | $2.00 | $5.00 | $5.06 | $4.50 | $4.95 | $3.00 |
| 57 | RM metal beam guard fence trans (thrie-beam) (542-7004) | EACH | 4 | $350.00 | $150.00 | $250.00 | $275.00 | $250.00 | $275.00 | $200.00 |
| 58 | Guardrail end treatment (install) (544-7001) | EACH | 4 | $4,000.00 | $3,500.00 | $3,550.00 | $4,042.00 | $3,671.00 | $4,038.10 | $2,850.00 |
| 59 | Guardrail end treatment (remove) (544-7003) | EACH | 4 | $350.00 | $250.00 | $250.00 | $302.50 | $275.00 | $302.50 | $200.00 |
| 60 | Install small roadside sign support and assembly type 10BWG(1)SA(T) (644-7004) | EACH | 6 | $1,000.00 | $800.00 | $1,600.00 | $825.00 | $1,000.00 | $1,100.00 | $600.00 |
| 61 | Removing SM RD SN&AM (wayfinding) (644-7076) | EACH | 4 | $500.00 | $100.00 | $250.00 | $110.00 | $150.00 | $165.00 | $200.00 |
| 62 | Install delineator assembly (D-SW)SZ 1(BRF)GF2(BI) (658-7019) | EACH | 17 | $30.00 | $35.00 | $26.50 | $38.50 | $35.00 | $34.12 | $40.00 |
| 63 | Install object marker assembly (OM-2Y)(WC)GND (658-7056) | EACH | 4 | $50.00 | $35.00 | $150.00 | $71.50 | $100.00 | $98.68 | $100.00 |
| 64 | Remove delin & object marker assms (658-7078) | EACH | 16 | $100.00 | $5.00 | $10.00 | $55.00 | $5.00 | $38.12 | $20.00 |
| 65 | Work zone pavement marking removing (reflectorized) type II-A-A (662-7051) | EACH | 74 | $10.00 | $11.00 | $10.60 | $11.00 | $10.00 | $7.45 | $10.00 |
| 66 | Work zone pavement marking removing (W)6"(solid) (662-7068) | LF | 5,234 | $2.00 | $2.00 | $1.75 | $1.82 | $1.65 | $1.71 | $1.65 |
| 67 | Work zone pavement marking removing (W)24"(solid) (662-7077) | LF | 40 | $20.00 | $22.00 | $21.20 | $22.00 | $20.00 | $15.92 | $20.00 |
| 68 | Work zone pavement marking removing (Y)6"(solid) (662-7100) | LF | 2,908 | $10.00 | $2.00 | $1.75 | $1.82 | $1.65 | $1.42 | $1.65 |
| 69 | Reflectorized pavement marking type I (W)6"(DOT)(100MIL) (666-7009) | LF | 715 | $2.00 | $5.50 | $5.30 | $5.50 | $5.00 | $0.99 | $5.00 |
| 70 | Reflectorized pavement marking type I (W)24"(solid)(100MIL) (666-7036) | LF | 50 | $15.00 | $27.00 | $26.50 | $27.50 | $25.00 | $16.06 | $25.00 |
| 71 | RE PV marking type I(black)6"(shadow)(100MIL) (666-7138) | LF | 357 | $2.00 | $6.50 | $6.50 | $6.60 | $6.00 | $2.32 | $6.00 |
| 72 | Reflectorized pavement marking type II (W) 6" (solid) (666-7175) | LF | 5,917 | $1.75 | $1.10 | $1.15 | $1.10 | $1.00 | $0.39 | $1.00 |
| 73 | Reflectorized pavement marking type II (Y) 6" (solid) (666-7213) | LF | 4,482 | $2.00 | $1.20 | $1.15 | $1.10 | $1.00 | $0.39 | $1.00 |
| 74 | Prefabricated PM type C (W)(RR crossing) (668-7108) | EACH | 1 | $750.00 | $1,250.00 | $1,275.00 | $1,320.00 | $1,200.00 | $385.00 | $1,200.00 |
| 75 | Reflectorized pavement marker type II-A-A (672-7004) | EACH | 28 | $25.00 | $22.00 | $21.20 | $22.00 | $20.00 | $9.46 | $20.00 |
| 76 | Eliminating existing PM & markers (6") (677-7002) | LF | 1,964 | $1.50 | $5.00 | $4.25 | $4.40 | $4.00 | $4.10 | $4.00 |
| 77 | Pavement surface preparation for marking (6") (678-7002) | LF | 3,956 | $1.00 | $2.00 | $2.15 | $2.20 | $2.00 | $0.37 | $2.00 |
| 78 | Pavement surface preparation for marking (24") (678-7008) | LF | 30 | $5.00 | $10.00 | $10.60 | $11.00 | $10.00 | $0.66 | $10.00 |
| 79 | Pavement surface preparation for marking (RR crossing) (678-7020) | EACH | 1 | $60.00 | $350.00 | $325.00 | $330.00 | $300.00 | $56.85 | $300.00 |
| 80 | Tree removal (12" - 18" diameter) (752-7006) | EACH | 13 | $500.00 | $200.00 | $750.00 | $1,500.00 | $1,100.00 | $550.00 | $950.00 |
| 81 | Install FTB (5002-7001) | LF | 136 | $100.00 | $100.00 | $35.00 | $50.00 | $55.00 | $55.00 | $90.00 |
| 82 | Remove FTB (5002-7002) | LF | 136 | $50.00 | $10.00 | $10.00 | $20.00 | $20.00 | $4.95 | $15.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from TxDOT's tabulation for this contract. TxDOT Bid Tabulations open-data export (data.texas.gov) from September 2024, read 21 November 2026, and TxDOT's legacy Tabulation of Bids pages for January 2020 to August 2024. The legacy pages are a large sample, not every contract: their file names were reused from year to year. Their district is the one TxDOT gives the county. Bids that did not match their published total are left out.
Every contract let that day: TxDOT letting of May 6, 2026. Compiled by Mirage Metrics.