ARDOT contract 030531 bid tabulation
THE PURPOSE OF THIS PROJECT IS TO RAISE THE ROADWAY GRADE ON HIGHWAY 71 IN LITTLE RIVER COUNTY. THIS PROJECT CONSISTS OF CLEARING AND GRUBBING, REMOVAL AND DISPOSAL ITEMS, TRENCHING AND SHOULDER PREPARATION, EARTHWORK, AGGREGATE BASE COURSE, ACHM BASE, BINDER, AND SURFACE COURSES, COLD MILLING ASPHALT PAVEMENT, ACHM PATCHING OF EXISTING ROADWAY, MAINTENANCE OF TRAFFIC, CONCRETE DITCH PAVING, MINOR DRAINAGE, GUARDRAIL, EROSION CONTROL, RUMBLE STRIPS, PAVEMENT MARKING, AND MISC. ITEMS. Let by Arkansas DOT on August 12, 2026, Little River. 6 bids received; low bid $17,063,675 by McGeorge Contracting Co., Inc..
- Owner
- Arkansas DOT
- Letting
- 12 AUG 2026
- Pay items
- 99
- Data through
- 04 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | McGeorge Contracting Co., Inc. | $17,063,675 | Low |
| 2 | Grant Garrett Excavating, Inc. | $21,448,418 | +26% |
| 3 | Capital Paving & Construction, LLC | $21,478,287 | +26% |
| 4 | Redstone Construction Group, Inc. | $22,934,421 | +34% |
| 5 | Robinson Construction, LLC | $25,998,065 | +52% |
| 6 | WL Bass Construction, Inc. | $33,576,243 | +97% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. McGeorge Contracting Co., Inc. | 2. Grant Garrett Excavating, Inc. | 3. Capital Paving & Construction, LLC | 4. Redstone Construction Group, Inc. | 5. Robinson Construction, LLC | 6. WL Bass Construction, Inc. |
|---|---|---|---|---|---|---|---|---|---|
| 0001 | Clearing (201011) | STA | 78 | $288.70 | $7,051.41 | $1,538.22 | $1,595.00 | $5,500.00 | $3,150.00 |
| 0002 | Grubbing (201111) | STA | 78 | $369.77 | $7,136.20 | $1,025.72 | $1,160.00 | $5,500.00 | $7,700.00 |
| 0003 | Removal and disposal of curb and gutter (202003) | LF | 3,985 | $5.04 | $3.60 | $3.78 | $10.50 | $20.00 | $8.00 |
| 0004 | Removal and disposal of fence (202011) | LF | 14,755 | $1.58 | $1.75 | $1.06 | $4.20 | $3.00 | $2.00 |
| 0005 | Removal and disposal of gates (202017) | EACH | 2 | $131.48 | $383.00 | $838.77 | $262.50 | $200.00 | $200.00 |
| 0006 | Removal and disposal of walls (202031) | LF | 28 | $13.25 | $128.50 | $237.53 | $105.00 | $320.00 | $60.00 |
| 0007 | Removal and disposal of concrete pavement (202042) | SY | 16,531 | $3.43 | $12.70 | $4.12 | $14.00 | $22.00 | $25.00 |
| 0008 | Removal and disposal of concrete islands (202047) | SY | 1,367 | $3.37 | $12.00 | $9.89 | $15.75 | $28.00 | $17.00 |
| 0009 | Removal and disposal of sign foundations (202084) | EACH | 17 | $153.29 | $635.00 | $368.16 | $200.00 | $150.00 | $800.00 |
| 0010 | Removal and disposal of drop inlets (202093) | EACH | 4 | $268.26 | $899.50 | $1,669.14 | $2,500.00 | $2,500.00 | $3,000.00 |
| 0011 | Removal and disposal of pipe culverts (202096) | EACH | 30 | $1,064.04 | $899.50 | $1,034.89 | $300.00 | $800.00 | $2,000.00 |
| 0012 | Removal and disposal of box culverts (202097) | EACH | 5 | $9,671.44 | $899.50 | $10,680 | $6,750.00 | $8,000.00 | $25,000 |
| 0013 | Removal and disposal of concrete ditch paving (202125) | SY | 601 | $21.46 | $12.00 | $21.51 | $25.00 | $24.00 | $14.00 |
| 0014 | Removal and disposal of guardrail (202132) | LF | 1,415 | $6.32 | $18.00 | $6.80 | $35.00 | $5.00 | $9.00 |
| 0015 | Removal and disposal of septic tank (202162) | EACH | 1 | $396.21 | $8,304.00 | $9,926.41 | $1,500.00 | $2,500.00 | $2,500.00 |
| 0016 | Removal and disposal of well house (202164) | EACH | 1 | $396.21 | $11,072 | $6,077.21 | $250.00 | $5,500.00 | $1,000.00 |
| 0017 | Removal and disposal of radio tower (202168) | EACH | 1 | $1.00 | $899.50 | $2,093.41 | $250.00 | $10,000 | $1,000.00 |
| 0018 | Removal and disposal of buildings (202171) | EACH | 1 | $10,730 | $13,563 | $6,535.79 | $2,500.00 | $65,000 | $25,000 |
| 0019 | Removal and disposal of weigh scales (202181) | EACH | 2 | $4,718.07 | $2,699.00 | $6,601.48 | $3,750.00 | $12,500 | $15,000 |
| 0020 | Removal and disposal of signs (202191) | EACH | 17 | $79.24 | $191.50 | $181.41 | $250.00 | $25.00 | $500.00 |
| 0021 | Flowable select material (206021) | CY | 38 | $268.79 | $225.00 | $348.19 | $246.40 | $265.00 | $350.00 |
| 0022 | Unclassified excavation (210213) | CY | 28,036 | $13.19 | $7.76 | $12.27 | $17.05 | $18.85 | $14.00 |
| 0023 | Compacted embankment (210611) | CY | 337,971 | $12.75 | $14.88 | $17.53 | $15.60 | $22.88 | $30.00 |
| 0024 | Soil stabilization (210702) | TON | 1,000 | $98.31 | $393.89 | $330.59 | $500.00 | $410.00 | $600.00 |
| 0025 | Trenching and shoulder preparation (215011) | STA | 16 | $1,784.01 | $578.00 | $1,437.13 | $1,000.00 | $1,255.00 | $5,500.00 |
| 0026 | Aggregate base course (class 7) (303117) | TON | 64,900 | $46.23 | $62.56 | $48.13 | $56.75 | $42.55 | $97.00 |
| 0027 | Tack coat (401011) | GAL | 8,873 | $4.30 | $5.52 | $12.34 | $5.00 | $4.20 | $10.50 |
| 0028 | Mineral aggregate in achm base course (1 1/2") (405161) | TON | 10,444 | $138.98 | $152.11 | $163.94 | $138.00 | $165.00 | $140.00 |
| 0029 | Asphalt binder (PG 70-22) in achm base course (1 1/2") (minimum bid $120.00) (405412) | TON | 492 | $121.56 | $132.28 | $881.64 | $120.00 | $135.00 | $750.00 |
| 0030 | Mineral aggregate in achm binder course (1") (406161) | TON | 8,494 | $147.54 | $163.14 | $166.18 | $148.00 | $172.00 | $142.00 |
| 0031 | Asphalt binder (PG 64-22) in achm binder course (1") (minimum bid $120.00) (406402) | TON | 40 | $121.56 | $132.28 | $764.10 | $120.00 | $125.00 | $650.00 |
| 0032 | Asphalt binder (PG 70-22) in achm binder course (1") (minimum bid $120.00) (406412) | TON | 380 | $145.96 | $132.28 | $881.64 | $120.00 | $135.00 | $750.00 |
| 0033 | Mineral aggregate in achm surface course (1/2") (407162) | TON | 16,524 | $155.49 | $178.02 | $158.11 | $161.50 | $160.00 | $135.00 |
| 0034 | Asphalt binder (PG 64-22) in achm surface course (1/2") (minimum bid $120.00) (407432) | TON | 171 | $121.56 | $132.28 | $764.10 | $120.00 | $125.00 | $650.00 |
| 0035 | Asphalt binder (PG 70-22) in achm surface course (1/2") (minimum bid $120.00) (407442) | TON | 878 | $152.06 | $132.28 | $881.64 | $120.00 | $135.00 | $750.00 |
| 0036 | Cold milling asphalt pavement (412002) | SY | 1,689 | $14.02 | $6.65 | $4.29 | $15.00 | $5.80 | $22.00 |
| 0037 | Asphalt concrete patching for maintenance of traffic (414011) | TON | 75 | $391.89 | $277.00 | $344.89 | $500.00 | $265.00 | $280.00 |
| 0038 | Achm patching of existing roadway (415011) | TON | 75 | $250.00 | $277.00 | $307.23 | $475.00 | $285.00 | $320.00 |
| 0039 | Mobilization (unit bid amount may not exceed 5% of subtotal) (601001) | LS | 1 | $390,657 | $900,000 | $565,843 | $1,085,000 | $1,200,000 | $1,503,000 |
| 0040 | Furnishing field office (602011) | EACH | 1 | $34,976 | $121,426 | $65,366 | $395,000 | $120,000 | $28,000 |
| 0041 | Maintenance of traffic (603009) | LS | 1 | $269,943 | $155,240 | $313,550 | $1,805,000 | $255,000 | $2,012,000 |
| 0042 | 18" temporary culvert (603018) | LF | 741 | $62.28 | $72.90 | $109.55 | $107.00 | $90.00 | $90.00 |
| 0043 | 24" temporary culvert (603024) | LF | 719 | $78.47 | $79.00 | $116.78 | $214.00 | $140.00 | $110.00 |
| 0044 | Signs (604003) | SF | 1,912 | $30.00 | $33.20 | $36.32 | $30.00 | $19.00 | $15.00 |
| 0045 | Construction project information sign update (604010) | EACH | 10 | $30.00 | $33.20 | $36.32 | $30.00 | $65.00 | $100.00 |
| 0046 | Barricades (604013) | LF | 200 | $25.00 | $27.70 | $30.27 | $25.00 | $32.00 | $25.00 |
| 0047 | Traffic drums (604023) | EACH | 522 | $30.00 | $33.20 | $36.32 | $30.00 | $75.00 | $65.00 |
| 0048 | Furnishing and installing precast concrete barrier (604031) | LF | 433 | $53.00 | $76.40 | $81.11 | $69.00 | $75.00 | $69.00 |
| 0049 | Relocating precast concrete barrier (max. bid 25% of item number ) (604036) | LF | 433 | $12.00 | $19.10 | $20.28 | $17.25 | $18.75 | $17.25 |
| 0050 | Construction pavement markings (604041) | LF | 71,659 | $0.17 | $0.19 | $0.21 | $0.17 | $1.25 | $1.00 |
| 0051 | Tubular markers (604049) | EACH | 582 | $50.00 | $55.40 | $6.05 | $125.00 | $230.00 | $195.00 |
| 0052 | Removal of construction pavement markings (604055) | LF | 281 | $1.98 | $2.20 | $2.40 | $2.18 | $1.85 | $1.50 |
| 0053 | Removal of permanent pavement markings (604061) | LF | 8,644 | $1.98 | $2.20 | $2.40 | $2.18 | $1.85 | $1.50 |
| 0054 | Advance warning arrow panel (604071) | DAY | 1,092 | $50.00 | $55.40 | $60.54 | $55.00 | $18.50 | $16.00 |
| 0055 | Portable changeable message sign (604078) | WEEK | 156 | $500.00 | $553.50 | $605.40 | $550.00 | $315.00 | $255.00 |
| 0056 | Portable construction lighting (604096) | DAY | 1,456 | $60.55 | $44.30 | $122.54 | $160.00 | $52.00 | $50.00 |
| 0057 | Mobile speed notification system (special) (604160) | EACH | 2 | $15,000 | $16,608 | $18,162 | $19,500 | $75,000 | $9,500.00 |
| 0058 | Concrete ditch paving (type B) (605012) | SY | 884 | $170.50 | $106.00 | $57.74 | $175.00 | $65.00 | $110.00 |
| 0059 | 18" reinforced concrete pipe culverts (class III) (605601) | LF | 280 | $78.30 | $147.00 | $107.53 | $58.59 | $95.00 | $262.00 |
| 0060 | 24" reinforced concrete pipe culverts (class III) (605606) | LF | 312 | $94.31 | $167.00 | $106.91 | $78.87 | $135.00 | $150.00 |
| 0061 | 30" reinforced concrete pipe culverts (class III) (605611) | LF | 392 | $112.82 | $200.50 | $118.62 | $101.39 | $138.00 | $270.00 |
| 0062 | 54" reinforced concrete pipe culverts (class III) (605631) | LF | 1,236 | $327.78 | $380.00 | $316.57 | $425.86 | $288.00 | $450.00 |
| 0063 | 18" flared end sections for reinforced concrete pipe culverts (605856) | EACH | 3 | $1,525.77 | $1,382.00 | $3,121.94 | $1,267.45 | $85.00 | $2,100.00 |
| 0064 | 24" flared end sections for reinforced concrete pipe culverts (605858) | EACH | 6 | $1,771.15 | $1,635.00 | $3,222.30 | $1,436.44 | $110.00 | $3,200.00 |
| 0065 | 30" flared end sections for reinforced concrete pipe culverts (605860) | EACH | 4 | $2,295.74 | $2,168.00 | $3,496.50 | $2,112.41 | $2,500.00 | $3,000.00 |
| 0066 | 54" flared end sections for reinforced concrete pipe culverts (605868) | EACH | 20 | $5,225.32 | $6,544.00 | $5,917.97 | $3,126.36 | $2,650.00 | $9,500.00 |
| 0067 | 18" side drain (606703) | LF | 60 | $66.05 | $129.00 | $19.26 | $109.74 | $3,200.00 | $120.00 |
| 0068 | 24" side drain (606704) | LF | 520 | $78.46 | $153.50 | $31.76 | $113.37 | $4,200.00 | $140.00 |
| 0069 | Selected pipe bedding (606994) | CY | 300 | $75.01 | $40.40 | $123.26 | $70.50 | $65.00 | $200.00 |
| 0070 | Drop inlets (type RM) (609136) | EACH | 5 | $6,784.05 | $10,057 | $8,608.87 | $6,677.65 | $8,800.00 | $11,000 |
| 0071 | 4" pipe underdrains (611008) | LF | 4,000 | $22.71 | $24.10 | $14.06 | $22.40 | $25.00 | $55.00 |
| 0072 | Underdrain outlet protectors (611013) | EACH | 16 | $765.34 | $732.50 | $1,032.82 | $820.34 | $1,200.00 | $1,000.00 |
| 0073 | Guardrail (type A) (617005) | LF | 400 | $32.00 | $35.70 | $39.02 | $33.20 | $42.00 | $50.00 |
| 0074 | Guardrail terminal (type 2) (617312) | EACH | 2 | $3,300.00 | $3,322.00 | $3,632.37 | $3,090.00 | $4,300.00 | $4,500.00 |
| 0075 | Wire fence (type A) (619025) | LF | 14,293 | $11.59 | $13.10 | $13.94 | $12.22 | $16.65 | $12.00 |
| 0076 | Wire fence (type D-1) (619029) | LF | 816 | $9.50 | $8.50 | $9.04 | $7.92 | $16.75 | $8.00 |
| 0077 | Lime (620001) | TON | 75 | $135.00 | $122.00 | $129.31 | $113.30 | $155.00 | $425.00 |
| 0078 | Seeding (620011) | ACRE | 37.39 | $1,500.00 | $1,626.00 | $1,726.14 | $1,468.39 | $850.00 | $1,500.00 |
| 0079 | Mulch cover (620022) | ACRE | 102.02 | $1,000.00 | $1,428.00 | $1,515.77 | $1,289.44 | $1,150.00 | $1,300.00 |
| 0080 | Water (620030) | MGAL | 5,144.20 | $11.47 | $5.55 | $5.88 | $5.00 | $5.00 | $6.00 |
| 0081 | Temporary seeding (621001) | ACRE | 64.63 | $700.00 | $1,092.00 | $1,159.59 | $986.44 | $950.00 | $1,000.00 |
| 0082 | Silt fence (621021) | LF | 21,545 | $3.50 | $4.05 | $4.33 | $3.68 | $5.55 | $5.00 |
| 0083 | Sediment removal and disposal (621111) | CY | 1,291 | $22.04 | $27.70 | $5.29 | $40.00 | $35.00 | $25.00 |
| 0084 | Rock ditch checks (621151) | CY | 1,481 | $96.47 | $102.00 | $88.95 | $133.75 | $88.00 | $240.00 |
| 0085 | Filter sock (12") (621168) | LF | 253 | $10.25 | $10.40 | $11.01 | $10.03 | $45.00 | $10.00 |
| 0086 | Second seeding application (623001) | ACRE | 37.39 | $250.00 | $415.00 | $440.83 | $375.00 | $555.00 | $400.00 |
| 0087 | Solid sodding (624001) | SY | 950 | $9.33 | $6.50 | $6.92 | $6.30 | $6.80 | $7.00 |
| 0088 | Erosion control matting (class 3) (626003) | SY | 1,975 | $6.70 | $6.25 | $6.64 | $6.05 | $24.00 | $6.00 |
| 0089 | Roadway construction control (635001) | LS | 1 | $302,761 | $168,663 | $180,852 | $365,000 | $180,000 | $1,032,000 |
| 0090 | Rumble strips in asphalt shoulders (642001) | LF | 27,231 | $0.19 | $0.28 | $0.22 | $0.33 | $0.22 | $0.30 |
| 0091 | Thermoplastic pavement marking white (6") (719002) | LF | 21,368 | $0.73 | $0.81 | $0.88 | $0.75 | $1.85 | $1.50 |
| 0092 | Thermoplastic pavement marking yellow (6") (719102) | LF | 15,464 | $0.73 | $0.81 | $0.88 | $0.75 | $1.85 | $1.50 |
| 0093 | Thermoplastic pavement marking (words) (719201) | EACH | 6 | $300.00 | $332.00 | $363.24 | $309.00 | $625.00 | $500.00 |
| 0094 | Thermoplastic pavement marking (arrows) (719202) | EACH | 12 | $275.00 | $304.50 | $332.97 | $283.25 | $550.00 | $450.00 |
| 0095 | Raised pavement markers (type II) (721002) | EACH | 197 | $10.00 | $11.10 | $12.11 | $10.30 | $12.50 | $10.00 |
| 0096 | Temporary impact attenuation barrier (731071) | EACH | 1 | $6,000.00 | $13,840 | $7,264.76 | $15,067 | $9,500.00 | $20,000 |
| 0097 | Temporary impact attenuation barrier (repair) (731072) | EACH | 2 | $1,000.00 | $1,107.00 | $1,210.79 | $1,150.00 | $1,300.00 | $1,000.00 |
| 0098 | Temporary impact attenuation barrier (relocation) (731075) | EACH | 1 | $1,000.00 | $1,107.00 | $1,210.79 | $10,067 | $4,900.00 | $6,000.00 |
| 0099 | 16' steel gates (619332) | EACH | 11 | $750.00 | $929.00 | $985.84 | $863.80 | $650.00 | $850.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from ARDOT's tabulation for this contract. ARDOT monthly bid tab PDFs (morning and afternoon sessions), January 2022 to November 2026. Base bids are printed in whole dollars; on A+B and A+C jobs the base bid is kept, and the published rank follows the award amount.
Every contract let that day: ARDOT letting of August 12, 2026. Compiled by Mirage Metrics.