FDOT contract T7607 bid tabulation

SR 93 (I-75) AT CR 54. Let by Florida DOT on May 20, 2026, Pasco, District 7. 6 bids received; low bid $1,685,246 by Blacktip Services Incorporated.

Owner
Florida DOT
Letting
20 MAY 2026
Pay items
144
Data through
28 OCT 2026

Bidders

RankBidderTotal bidAgainst the low bid
1Blacktip Services Incorporated$1,685,246Low
2Cone & Graham, Inc.$1,719,000+2.0%
3PCS Civil, Inc.$1,792,756+6.0%
4Preferred Materials Inc.$1,845,310+9.0%
5Ajax Paving Industries of Florida LLC$1,913,893+14%
6Nelson, David, Construction Co.$2,184,072+30%
FDOT contract T7607: bids by rank

Bid tabulation

LinePay itemUnitQuantity1. Blacktip Services Incorporated2. Cone & Graham, Inc.3. PCS Civil, Inc.4. Preferred Materials Inc.5. Ajax Paving Industries of Florida LLC6. Nelson, David, Construction Co.
0005Mobilization (0101-1)LS1$80,000$179,100$174,200$191,365$185,000$160,000
0010Maintenance of traffic (0102-1)DA1$33,000$102,600$65,850$90,100$185,000$200,000
0015Special detour- temporary pavement (0102-2200)SY1$19,850$25,000$85,250$17,425$25,000$80,000
0020Traffic control officer (0102-14)HR364$85.00$90.00$75.00$86.49$113.35$82.00
0025Work zone sign (0102-60)ED9,826$0.54$0.22$0.35$0.24$0.24$0.50
0030Temporary barrier, F&I, low profile, concrete (0102-71-13)LF80$102.60$45.00$90.35$48.65$48.58$90.00
0035Temporary barrier, F&I, anchored (0102-71-15)LF766$73.44$38.00$62.50$41.08$41.02$65.00
0040Channelizing device- types I, II, VP, drum, or LCD (0102-74-1)ED8,472$0.10$0.10$0.18$0.11$0.11$1.00
0045Channelizing device- pedestrian LCD (longitudinal channelizing device) (0102-74-8)FD1,435$0.08$0.05$0.08$0.05$0.05$2.35
0050Arrow board / advance warning arrow panel (0102-76)ED225$5.40$5.00$8.75$5.41$5.40$11.00
0055Temporary crash cushion, redirective option (0102-89-1)LO1$1,134.00$900.00$1,750.00$972.97$1,079.52$3,500.00
0060Portable changeable message sign, temporary (0102-99)ED696$10.80$12.00$17.50$12.97$12.95$17.50
0065Temporary signalization and maintenance, intersection (0102-104)ED160$29.00$37.20$47.75$40.22$40.16$49.00
0070Temporary traffic detection and maintenance, intersection (0102-107-1)ED160$27.00$18.60$24.00$20.11$20.08$25.00
0075Existing ITS maintenance (0102-112)DA160$135.94$150.00$192.00$162.16$161.93$200.00
0080Type III barricade (0102-115)ED190$0.33$0.35$0.35$0.38$0.38$8.50
0085Sediment barrier (0104-10-3)LF160$5.00$4.50$2.00$4.76$1.08$3.00
0090Soil tracking prevention device (0104-15)EACH1$500.00$4,243.21$3,200.00$6,735.35$3,011.22$11,000
0095Inlet protection system (0104-18)EACH10$50.00$175.00$6.50$224.10$53.98$200.00
0100Litter removal (0107-1)ACRE10.52$80.00$570.34$1,175.00$616.58$615.70$100.00
0105Mowing (0107-2)ACRE8.69$80.00$690.50$1,425.00$746.43$745.35$500.00
0110Clearing & grubbing (0110-1-1)ACRE1$90,000$75,000$10,500$64,287$15,000$60,200
0115Removal of existing concrete (0110-4-10)SY75$50.00$46.00$46.25$48.98$44.80$34.00
0120Regular excavation (0120-1)CY131.30$40.00$32.50$49.00$45.96$99.56$20.00
0125Subsoil excavation (0120-4)CY892.40$40.00$38.50$68.00$29.02$35.77$25.00
0130Embankment (0120-6)CY1,063.10$22.00$38.00$38.25$48.03$84.07$30.00
0135Type B stabilization (0160-4)SY1,792$32.00$20.00$20.00$29.02$18.23$15.00
0140Optional base, base group 15 (0285-715)SY1,500$81.00$75.00$88.75$76.02$79.67$110.00
0145Milling existing asphalt pavement, 3" avg depth (0327-70-4)SY2,967$5.94$5.50$4.35$7.58$7.34$9.00
0150Milling existing asphalt pavement, 1 1/2" avg depth (0327-70-6)SY3,004$9.18$8.50$4.75$9.80$9.23$12.00
0155Superpave asphaltic concrete, traffic C, PG76-22 (0334-1-53)TN346.80$237.60$220.00$210.00$220.17$292.73$310.00
0160Asphalt concrete friction course,traffic C, FC-12.5, PG (0337-7-83)TN594.90$221.40$205.00$300.00$231.42$223.53$300.00
0165Miscellaneous asphalt (0339-1)TN19.40$297.00$410.00$275.00$468.16$598.44$604.52
0170Inlets, DT bot, type D, <10' (0425-1541)EACH2$8,500.00$9,700.00$10,350$10,526$8,745.96$8,000.00
0175Inlets, gutter, type S, <10' (0425-1701)EACH4$7,500.00$8,700.00$8,800.00$10,230$9,695.79$9,000.00
0180Pipe culvert,optional material,round, 18"S/CD (0430-175118)LF587$150.00$130.00$165.00$174.95$201.82$150.00
0185Pipe culvert,optional material,round, 24"S/CD (0430-175124)LF8$165.00$372.00$750.00$285.46$456.42$300.00
0190Pipe culvert,optional material,other-elip/arch, (0430-175218)LF11$165.00$202.00$255.00$331.65$388.57$150.00
0195Pipe handrail - guiderail, steel (0515-1-1)LF9$135.00$50.00$70.00$54.05$279.13$65.00
0200Concrete curb & gutter, type E (0520-1-7)LF13$65.00$53.54$95.00$81.46$98.74$75.00
0205Concrete curb & gutter, type F (0520-1-10)LF65$65.00$53.54$95.00$61.22$81.48$75.00
0210Shoulder gutter- concrete (0520-6)LF599$37.00$53.54$65.00$60.55$48.44$120.00
0215Concrete sidewalk and driveways, 6" thick (0522-2)SY35$85.00$101.52$150.00$141.66$152.38$130.00
0220Concrete ditch pavement, non reinforced, 4" (0524-1-2)SY3$85.00$101.52$425.00$263.60$724.66$200.00
0225Detectable warnings (0527-2)SF18$37.00$65.99$40.00$54.91$21.59$35.00
0230Guardrail -roadway, general (0536-1-1)LF566$28.08$25.00$19.00$27.03$27.98$35.00
0235Special guardrail post- post for shallow mount (0536-7-3)EACH3$253.80$250.00$225.00$270.27$148.87$350.00
0240Guardrail end treatment- trailing anchorage (0536-85-20)EACH1$2,052.00$2,000.00$1,500.00$2,162.15$1,539.45$2,700.00
0245Guardrail end treatment- parallel approach terminal (0536-85-24)EACH1$3,996.00$3,300.00$3,000.00$3,567.54$3,452.62$4,500.00
0250Performance turf, sod (0570-1-2)SY1,044$6.00$5.30$5.25$10.39$9.05$10.00
0255Plastic erosion mat, turf reinforced mat, type 1 (0571-1-11)SY453$6.00$10.00$2.75$8.15$17.07$18.00
0260Raised pavement marker, type B (0706-1-3)EACH569$6.48$3.98$4.00$4.30$4.30$6.00
0265Painted pavement markings, standard, white, solid, 6" (0710-11101)GM1.25$1,512.00$1,764.35$1,775.00$1,907.39$1,910.75$2,800.00
0270Painted pavement markings, standard, white, solid for interchange and urban island, (0710-11102)GM0.08$1,620.00$2,601.95$2,625.00$2,812.93$2,879.08$2,700.00
0275Painted pavement markings, standard, white, solid for crosswalk and roundabout, 12" (0710-11123)LF233$1.08$1.30$1.35$1.41$1.40$2.00
0280Painted pavement markings, standard, white, solid for stop line or crosswalk, 24" (0710-11125)LF186$2.16$1.70$1.75$1.84$1.84$3.00
0285Painted pavement markings, standard, white, skip, 10-30 or skip, 6" wide (0710-11131)GM0.26$648.00$500.00$500.00$540.54$539.76$900.00
0290Painted pavement markings, standard, white, arrows (0710-11170)EACH51$32.40$35.00$35.00$37.84$37.78$45.00
0295Painted pavement markings, standard, yellow, solid, 6" (0710-11201)GM0.67$1,620.00$1,756.69$1,775.00$1,899.11$1,910.75$2,500.00
0300Initial contingency amount, DO not bid (0999-25)LS1$50,000$50,000$50,000$50,000$50,000$50,000
0305Single column ground sign assembly, F&I ground mount, than 12 SF (0700-1111)EACH10$648.00$600.00$625.00$662.43$647.71$700.00
0310Single column ground sign assembly, F&I ground mount, 20.0 SF (0700-1112)EACH2$2,592.00$2,500.00$2,600.00$2,007.45$2,590.85$3,000.00
0315Single column ground sign assembly, F&I ground mount, 30.0 SF (0700-1113)EACH3$3,240.00$2,600.00$3,200.00$2,828.77$3,238.56$3,600.00
0320Single column ground sign assembly, remove (0700-1600)EACH15$54.00$35.00$110.00$114.42$53.98$130.00
0325Retroreflective sign strip- furnish and install, 2' (0700-13-12)EACH4$86.40$95.00$85.00$137.68$86.36$100.00
0330Retroreflective sign strip- furnish and install, 5' (0700-13-15)EACH3$108.00$125.00$125.00$163.70$107.95$140.00
0335Tubular marker, 36" yellow (0704-1-4)EACH1$216.00$250.00$325.00$199.61$215.90$380.00
0340Delineator, flexible tubular (0705-11-1)EACH13$216.00$100.00$135.00$168.11$134.94$160.00
0345Raised pavement marker, type B (0706-1-3)EACH313$6.48$3.98$4.00$4.30$4.30$5.50
0350Painted pavement markings, durable paint, yellow, island nose (0710-12290)SF101$10.80$4.00$4.00$4.32$4.32$6.50
0355Painted pavement markings, surface (0710-90)LS1$4,752.00$5,522.00$5,550.00$5,969.69$12,438$9,500.00
0360Thermoplastic, standard, solid, 12" for crosswalk and roundabout (0711-11123)LF69$6.48$2.90$3.00$3.14$3.13$10.00
0365Thermoplastic, standard, solid, 18" for diagonals and chevrons (0711-11124)LF63$8.64$4.35$4.50$4.70$4.70$15.00
0370Thermoplastic, standard, solid, 24" for stop line and crosswalk (0711-11125)LF87$10.80$5.80$6.00$6.27$6.26$22.00
0375Thermoplastic, standard, 2-4 dotted guideline/ 6-10 gap extension, 6" (0711-11141)GM0.11$5,400.00$2,861.98$2,900.00$3,094.05$3,117.66$7,500.00
0380Thermoplastic, standard, message or symbol (0711-11160)EACH5$243.00$64.00$65.00$69.19$69.09$780.00
0385Thermoplastic, standard, arrow (0711-11170)EACH24$97.20$54.00$55.00$58.38$58.29$390.00
0390Thermoplastic, standard, yellow, solid, 18" for diagonal or chevron (0711-11224)LF5$8.64$4.35$4.50$4.70$4.70$15.00
0395Thermoplastic, standard, yellow, 2-4 dotted guide line dotted extension line, 6" (0711-11241)GM0.02$5,400.00$2,750.48$2,775.00$2,973.81$3,117.66$7,500.00
0400Thermoplastic, preformed, white, solid, 24" for crosswalk (0711-14125)LF51$18.36$14.68$14.75$15.84$15.82$23.00
0405Thermoplastic, preformed, white, message (0711-14160)EACH2$324.00$195.00$200.00$210.81$210.51$380.00
0410Thermoplastic, preformed, white, arrow (0711-14170)EACH2$216.00$80.00$80.00$86.49$86.36$250.00
0415Thermoplastic, standard-other surfaces, white, solid, 6" (0711-16101)GM0.56$8,100.00$7,571.11$7,725.00$8,184.92$8,306.91$16,500
0420Thermoplastic, standard-other surfaces, white, solid, 8" (0711-16102)GM0.03$9,720.00$7,075.86$10,625$7,649.66$11,076$9,000.00
0425Thermoplastic, standard-other surfaces, yellow, solid, 6" (0711-16201)GM0.25$8,100.00$6,825.00$6,850.00$7,378.32$7,367.73$13,500
0430Conduit, furnish & install, open trench (0630-2-11)LF174$14.57$24.75$26.00$26.76$26.72$30.00
0435Conduit, furnish & install, directional bore (0630-2-12)LF481$31.86$38.15$40.00$41.24$41.18$40.00
0440Pull & splice box, F&I, 13" X 24" cover size (0635-2-11)EACH8$2,523.96$1,700.00$1,775.00$1,837.83$1,835.19$1,800.00
0445Pull & splice box, F&I, 17" X 30" cover size (0635-2-14)EACH1$3,368.95$2,368.00$2,500.00$2,559.98$2,556.31$2,500.00
0450Electrical power service, F&I, underground, meter not required (0639-1123)AS1$1,749.60$5,000.00$5,200.00$5,405.37$5,397.61$5,200.00
0455Electrical power service, remove underground (0639-1620)AS1$1,942.06$735.00$775.00$794.59$793.45$765.00
0460Electrical service wire, & install (0639-2-1)LF17$14.12$11.10$11.75$12.00$11.98$12.00
0465Electrical service wire, (0639-2-6)LF33$4.86$1.45$1.55$1.57$1.57$1.60
0470Lighting conductors, F&I, insulated, no. 10 or < (0715-1-11)LF378$10.29$1.25$1.50$1.35$1.35$1.40
0475Lighting conductors, F&I, insulated, no.8 - 6 (0715-1-12)LF894$11.02$2.76$3.00$2.98$2.98$3.00
0480Lighting conductors, F&I, no.1/0 3/0 (0 to 000) (0715-1-15)LF2,875$14.89$7.25$7.75$7.84$7.83$8.00
0485Lighting conductors, remove & dispose, contractor owns (0715-1-60)LF3,356$4.89$0.35$0.40$0.38$0.38$0.40
0490Light pole complete, F&I, standard pole standard foundation, 35' mounting height, 0' arm length (0715-61200)EACH5$10,425$9,942.00$10,350$10,748$10,733$12,000
0495Pole cable distribution system, furnish and install, conventional (0715-500-1)EACH5$498.96$875.00$925.00$945.94$944.58$1,000.00
0500Conduit, furnish & install, open trench (0630-2-11)LF74$19.75$42.75$45.00$46.22$46.15$50.00
0505Conduit, furnish & install, directional bore (0630-2-12)LF267$31.86$52.75$55.00$57.03$56.94$55.00
0510Signal cable- new or reconstructed intersection, furnish & install (0632-7-1)PI1$9,066.18$3,325.00$3,475.00$3,594.57$3,589.41$3,500.00
0515Signal cable, remove- intersection (0632-7-6)PI1$2,913.09$800.00$835.00$864.86$863.62$850.00
0520Pull & splice box, F&I, 13" X 24" cover size (0635-2-11)EACH6$2,064.37$1,884.00$1,975.00$2,036.74$2,033.82$2,000.00
0525Electrical power service, F&I, underground, meter not required (0639-1123)AS1$5,633.72$5,000.00$5,200.00$5,405.37$5,397.61$5,300.00
0530Electrical power service, remove underground (0639-1620)AS1$1,942.06$736.00$775.00$795.67$794.53$800.00
0535Electrical service wire, & install (0639-2-1)LF122$18.97$8.80$9.25$9.51$9.50$9.25
0540Electrical service wire, (0639-2-6)LF10$1.17$0.90$1.00$0.97$0.97$1.00
0545Prestressed concrete pole, type P-II service pole (0641-2-12)EACH1$3,108.46$2,398.00$2,500.00$2,592.41$2,588.69$2,500.00
0550Aluminum signals pole, (0646-1-11)EACH1$2,662.63$2,960.00$3,100.00$3,199.98$3,195.38$3,100.00
0555Aluminum signals pole, remove (0646-1-60)EACH1$1,942.06$1,085.00$1,130.00$1,172.97$1,171.28$1,200.00
0560Vehicular signal auxiliaries, repair/replace/retrofit- & install, backplate- flexible required (0650-2109)EACH11$1,192.65$718.00$750.00$776.21$775.10$750.00
0565Pedestrian signal, furnish & install LED countdown, 1 way (0653-1-11)AS1$1,475.17$982.00$1,025.00$1,061.62$1,060.09$1,050.00
0570Loop detector inductive, F&I, type 10 (0660-1110)EACH1$806.92$375.00$395.00$405.40$404.82$350.00
0575Loop assembly, F&I, type F (0660-2106)AS7$3,519.83$2,100.00$2,200.00$2,270.26$2,266.99$2,200.00
0580Pedestrian detector, furnish & install, standard (0665-1-11)EACH1$351.62$314.00$330.00$339.46$338.97$350.00
0585Traffic controller, modify (0671-2-40)EACH1$1,456.54$530.00$555.00$572.97$572.15$550.00
0590Traffic signal controller cabinet, adjust/modify (0676-1500)EACH1$971.03$2,562.00$2,675.00$2,769.71$2,765.73$2,700.00
0595Sign panel, furnish & install ground mount, UP to 12 SF (0700-3101)EACH5$260.00$192.00$200.00$207.57$1,619.28$200.00
0600Sign panel, remove, UP to 12 SF (0700-3601)EACH5$50.00$36.00$37.50$38.92$269.88$38.00
0605Itsfm subsurface documentation- project length (0611-1-1)MI0.24$4,358.45$6,054.00$6,300.00$6,544.83$6,535.42$6,300.00
0610Itsfm location documentation- ITS site (0611-2-2)EACH2$2,402.24$2,624.00$2,750.00$2,836.74$2,832.66$2,800.00
0615Conduit, furnish & install, open trench (0630-2-11)LF832$27.19$44.45$46.25$48.05$47.98$50.00
0620Conduit, furnish & install, directional bore (0630-2-12)LF400$35.68$47.00$49.00$50.81$50.74$50.00
0625Conduit, furnish & install, aboveground (0630-2-14)LF5$17.16$282.00$295.00$304.86$304.43$300.00
0630Fiber optic cable, relocate, underground (0633-1420)LF1,214$5.03$5.90$6.25$6.38$6.37$6.50
0635Fiber optic connection, install, splice (0633-2-31)EACH72$57.35$61.00$65.00$65.95$65.85$65.00
0640Fiber optic connection, install, termination (0633-2-32)EACH12$95.58$102.00$110.00$110.27$110.11$107.00
0645Fiber optic connection hardware, relocate patch panel- field terminated (0633-3-46)EACH1$242.76$508.00$535.00$549.18$548.40$530.00
0650Fiber optic cable locator (0633-6)DA160$127.44$156.00$165.00$168.65$168.41$165.00
0655Pull & splice box, F&I, 13" X 24" cover size (0635-2-11)EACH8$2,549.88$1,884.00$1,975.00$2,036.74$2,033.82$2,000.00
0660Pull & splice box, F&I, 24" X 36" cover size (0635-2-12)EACH5$4,365.90$2,712.00$2,825.00$2,931.87$2,927.66$2,900.00
0665Electrical power service, F&I, underground, meter not required (0639-1123)AS1$5,633.72$5,000.00$5,200.00$5,405.37$5,397.61$5,200.00
0670Electrical power service, remove underground (0639-1620)AS1$1,942.06$736.00$775.00$795.67$794.53$765.00
0675Electrical service wire, & install (0639-2-1)LF701$18.97$9.75$10.25$10.54$10.53$11.00
0680Electrical service wire, relocate (0639-2-4)LF363$19.42$4.45$4.75$4.81$4.80$5.00
0685Electrical service wire, (0639-2-6)LF651$0.97$1.15$1.25$1.24$1.24$1.50
0690Prestressed concrete pole, type P-II service pole (0641-2-12)EACH1$3,108.46$2,398.00$2,500.00$2,592.41$2,588.69$2,500.00
0695Prestressed concrete pole, complete pole removal- pedestal/service pole (0641-2-60)EACH1$1,942.06$1,798.00$1,900.00$1,943.77$1,940.98$1,900.00
0700Vehicle detection system- wrong way for exit ramp, 3 or more lanes, AC powered (0660-7-22)EACH1$49,236$65,200$4,100.00$70,486$4,251.15$84,000
0705Vehicle detection system- wrong way, remove (0660-7-90)EACH1$3,884.12$1,008.00$1,050.00$1,089.72$1,088.16$1,050.00
0710ITS cabinet, relocate (0676-2400)EACH1$16,190$7,000.00$7,300.00$7,567.52$7,556.65$7,300.00
0715Managed field ethernet switch, relocate (0684-1-4)EACH1$485.51$530.00$555.00$572.97$572.15$560.00
0720Enhanced highway sign AC powered, relocate - ground mount (0700-141802)EACH1$4,532.12$735.00$765.00$794.59$793.45$765.00
FDOT contract T7607: unit prices by line

The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.

Source

Read from FDOT's tabulation for this contract. FDOT Tabulation of Bids PDFs from its central office lettings, January 2018 to October 2026, all pay items. On A+B contracts the cost part is kept (the total the pay items add up to). Bidders listed without a rank or total are left out.

Every contract let that day: FDOT letting of May 20, 2026. Compiled by Mirage Metrics.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy