FDOT contract T7607 bid tabulation
SR 93 (I-75) AT CR 54. Let by Florida DOT on May 20, 2026, Pasco, District 7. 6 bids received; low bid $1,685,246 by Blacktip Services Incorporated.
- Owner
- Florida DOT
- Letting
- 20 MAY 2026
- Pay items
- 144
- Data through
- 28 OCT 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | Blacktip Services Incorporated | $1,685,246 | Low |
| 2 | Cone & Graham, Inc. | $1,719,000 | +2.0% |
| 3 | PCS Civil, Inc. | $1,792,756 | +6.0% |
| 4 | Preferred Materials Inc. | $1,845,310 | +9.0% |
| 5 | Ajax Paving Industries of Florida LLC | $1,913,893 | +14% |
| 6 | Nelson, David, Construction Co. | $2,184,072 | +30% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Blacktip Services Incorporated | 2. Cone & Graham, Inc. | 3. PCS Civil, Inc. | 4. Preferred Materials Inc. | 5. Ajax Paving Industries of Florida LLC | 6. Nelson, David, Construction Co. |
|---|---|---|---|---|---|---|---|---|---|
| 0005 | Mobilization (0101-1) | LS | 1 | $80,000 | $179,100 | $174,200 | $191,365 | $185,000 | $160,000 |
| 0010 | Maintenance of traffic (0102-1) | DA | 1 | $33,000 | $102,600 | $65,850 | $90,100 | $185,000 | $200,000 |
| 0015 | Special detour- temporary pavement (0102-2200) | SY | 1 | $19,850 | $25,000 | $85,250 | $17,425 | $25,000 | $80,000 |
| 0020 | Traffic control officer (0102-14) | HR | 364 | $85.00 | $90.00 | $75.00 | $86.49 | $113.35 | $82.00 |
| 0025 | Work zone sign (0102-60) | ED | 9,826 | $0.54 | $0.22 | $0.35 | $0.24 | $0.24 | $0.50 |
| 0030 | Temporary barrier, F&I, low profile, concrete (0102-71-13) | LF | 80 | $102.60 | $45.00 | $90.35 | $48.65 | $48.58 | $90.00 |
| 0035 | Temporary barrier, F&I, anchored (0102-71-15) | LF | 766 | $73.44 | $38.00 | $62.50 | $41.08 | $41.02 | $65.00 |
| 0040 | Channelizing device- types I, II, VP, drum, or LCD (0102-74-1) | ED | 8,472 | $0.10 | $0.10 | $0.18 | $0.11 | $0.11 | $1.00 |
| 0045 | Channelizing device- pedestrian LCD (longitudinal channelizing device) (0102-74-8) | FD | 1,435 | $0.08 | $0.05 | $0.08 | $0.05 | $0.05 | $2.35 |
| 0050 | Arrow board / advance warning arrow panel (0102-76) | ED | 225 | $5.40 | $5.00 | $8.75 | $5.41 | $5.40 | $11.00 |
| 0055 | Temporary crash cushion, redirective option (0102-89-1) | LO | 1 | $1,134.00 | $900.00 | $1,750.00 | $972.97 | $1,079.52 | $3,500.00 |
| 0060 | Portable changeable message sign, temporary (0102-99) | ED | 696 | $10.80 | $12.00 | $17.50 | $12.97 | $12.95 | $17.50 |
| 0065 | Temporary signalization and maintenance, intersection (0102-104) | ED | 160 | $29.00 | $37.20 | $47.75 | $40.22 | $40.16 | $49.00 |
| 0070 | Temporary traffic detection and maintenance, intersection (0102-107-1) | ED | 160 | $27.00 | $18.60 | $24.00 | $20.11 | $20.08 | $25.00 |
| 0075 | Existing ITS maintenance (0102-112) | DA | 160 | $135.94 | $150.00 | $192.00 | $162.16 | $161.93 | $200.00 |
| 0080 | Type III barricade (0102-115) | ED | 190 | $0.33 | $0.35 | $0.35 | $0.38 | $0.38 | $8.50 |
| 0085 | Sediment barrier (0104-10-3) | LF | 160 | $5.00 | $4.50 | $2.00 | $4.76 | $1.08 | $3.00 |
| 0090 | Soil tracking prevention device (0104-15) | EACH | 1 | $500.00 | $4,243.21 | $3,200.00 | $6,735.35 | $3,011.22 | $11,000 |
| 0095 | Inlet protection system (0104-18) | EACH | 10 | $50.00 | $175.00 | $6.50 | $224.10 | $53.98 | $200.00 |
| 0100 | Litter removal (0107-1) | ACRE | 10.52 | $80.00 | $570.34 | $1,175.00 | $616.58 | $615.70 | $100.00 |
| 0105 | Mowing (0107-2) | ACRE | 8.69 | $80.00 | $690.50 | $1,425.00 | $746.43 | $745.35 | $500.00 |
| 0110 | Clearing & grubbing (0110-1-1) | ACRE | 1 | $90,000 | $75,000 | $10,500 | $64,287 | $15,000 | $60,200 |
| 0115 | Removal of existing concrete (0110-4-10) | SY | 75 | $50.00 | $46.00 | $46.25 | $48.98 | $44.80 | $34.00 |
| 0120 | Regular excavation (0120-1) | CY | 131.30 | $40.00 | $32.50 | $49.00 | $45.96 | $99.56 | $20.00 |
| 0125 | Subsoil excavation (0120-4) | CY | 892.40 | $40.00 | $38.50 | $68.00 | $29.02 | $35.77 | $25.00 |
| 0130 | Embankment (0120-6) | CY | 1,063.10 | $22.00 | $38.00 | $38.25 | $48.03 | $84.07 | $30.00 |
| 0135 | Type B stabilization (0160-4) | SY | 1,792 | $32.00 | $20.00 | $20.00 | $29.02 | $18.23 | $15.00 |
| 0140 | Optional base, base group 15 (0285-715) | SY | 1,500 | $81.00 | $75.00 | $88.75 | $76.02 | $79.67 | $110.00 |
| 0145 | Milling existing asphalt pavement, 3" avg depth (0327-70-4) | SY | 2,967 | $5.94 | $5.50 | $4.35 | $7.58 | $7.34 | $9.00 |
| 0150 | Milling existing asphalt pavement, 1 1/2" avg depth (0327-70-6) | SY | 3,004 | $9.18 | $8.50 | $4.75 | $9.80 | $9.23 | $12.00 |
| 0155 | Superpave asphaltic concrete, traffic C, PG76-22 (0334-1-53) | TN | 346.80 | $237.60 | $220.00 | $210.00 | $220.17 | $292.73 | $310.00 |
| 0160 | Asphalt concrete friction course,traffic C, FC-12.5, PG (0337-7-83) | TN | 594.90 | $221.40 | $205.00 | $300.00 | $231.42 | $223.53 | $300.00 |
| 0165 | Miscellaneous asphalt (0339-1) | TN | 19.40 | $297.00 | $410.00 | $275.00 | $468.16 | $598.44 | $604.52 |
| 0170 | Inlets, DT bot, type D, <10' (0425-1541) | EACH | 2 | $8,500.00 | $9,700.00 | $10,350 | $10,526 | $8,745.96 | $8,000.00 |
| 0175 | Inlets, gutter, type S, <10' (0425-1701) | EACH | 4 | $7,500.00 | $8,700.00 | $8,800.00 | $10,230 | $9,695.79 | $9,000.00 |
| 0180 | Pipe culvert,optional material,round, 18"S/CD (0430-175118) | LF | 587 | $150.00 | $130.00 | $165.00 | $174.95 | $201.82 | $150.00 |
| 0185 | Pipe culvert,optional material,round, 24"S/CD (0430-175124) | LF | 8 | $165.00 | $372.00 | $750.00 | $285.46 | $456.42 | $300.00 |
| 0190 | Pipe culvert,optional material,other-elip/arch, (0430-175218) | LF | 11 | $165.00 | $202.00 | $255.00 | $331.65 | $388.57 | $150.00 |
| 0195 | Pipe handrail - guiderail, steel (0515-1-1) | LF | 9 | $135.00 | $50.00 | $70.00 | $54.05 | $279.13 | $65.00 |
| 0200 | Concrete curb & gutter, type E (0520-1-7) | LF | 13 | $65.00 | $53.54 | $95.00 | $81.46 | $98.74 | $75.00 |
| 0205 | Concrete curb & gutter, type F (0520-1-10) | LF | 65 | $65.00 | $53.54 | $95.00 | $61.22 | $81.48 | $75.00 |
| 0210 | Shoulder gutter- concrete (0520-6) | LF | 599 | $37.00 | $53.54 | $65.00 | $60.55 | $48.44 | $120.00 |
| 0215 | Concrete sidewalk and driveways, 6" thick (0522-2) | SY | 35 | $85.00 | $101.52 | $150.00 | $141.66 | $152.38 | $130.00 |
| 0220 | Concrete ditch pavement, non reinforced, 4" (0524-1-2) | SY | 3 | $85.00 | $101.52 | $425.00 | $263.60 | $724.66 | $200.00 |
| 0225 | Detectable warnings (0527-2) | SF | 18 | $37.00 | $65.99 | $40.00 | $54.91 | $21.59 | $35.00 |
| 0230 | Guardrail -roadway, general (0536-1-1) | LF | 566 | $28.08 | $25.00 | $19.00 | $27.03 | $27.98 | $35.00 |
| 0235 | Special guardrail post- post for shallow mount (0536-7-3) | EACH | 3 | $253.80 | $250.00 | $225.00 | $270.27 | $148.87 | $350.00 |
| 0240 | Guardrail end treatment- trailing anchorage (0536-85-20) | EACH | 1 | $2,052.00 | $2,000.00 | $1,500.00 | $2,162.15 | $1,539.45 | $2,700.00 |
| 0245 | Guardrail end treatment- parallel approach terminal (0536-85-24) | EACH | 1 | $3,996.00 | $3,300.00 | $3,000.00 | $3,567.54 | $3,452.62 | $4,500.00 |
| 0250 | Performance turf, sod (0570-1-2) | SY | 1,044 | $6.00 | $5.30 | $5.25 | $10.39 | $9.05 | $10.00 |
| 0255 | Plastic erosion mat, turf reinforced mat, type 1 (0571-1-11) | SY | 453 | $6.00 | $10.00 | $2.75 | $8.15 | $17.07 | $18.00 |
| 0260 | Raised pavement marker, type B (0706-1-3) | EACH | 569 | $6.48 | $3.98 | $4.00 | $4.30 | $4.30 | $6.00 |
| 0265 | Painted pavement markings, standard, white, solid, 6" (0710-11101) | GM | 1.25 | $1,512.00 | $1,764.35 | $1,775.00 | $1,907.39 | $1,910.75 | $2,800.00 |
| 0270 | Painted pavement markings, standard, white, solid for interchange and urban island, (0710-11102) | GM | 0.08 | $1,620.00 | $2,601.95 | $2,625.00 | $2,812.93 | $2,879.08 | $2,700.00 |
| 0275 | Painted pavement markings, standard, white, solid for crosswalk and roundabout, 12" (0710-11123) | LF | 233 | $1.08 | $1.30 | $1.35 | $1.41 | $1.40 | $2.00 |
| 0280 | Painted pavement markings, standard, white, solid for stop line or crosswalk, 24" (0710-11125) | LF | 186 | $2.16 | $1.70 | $1.75 | $1.84 | $1.84 | $3.00 |
| 0285 | Painted pavement markings, standard, white, skip, 10-30 or skip, 6" wide (0710-11131) | GM | 0.26 | $648.00 | $500.00 | $500.00 | $540.54 | $539.76 | $900.00 |
| 0290 | Painted pavement markings, standard, white, arrows (0710-11170) | EACH | 51 | $32.40 | $35.00 | $35.00 | $37.84 | $37.78 | $45.00 |
| 0295 | Painted pavement markings, standard, yellow, solid, 6" (0710-11201) | GM | 0.67 | $1,620.00 | $1,756.69 | $1,775.00 | $1,899.11 | $1,910.75 | $2,500.00 |
| 0300 | Initial contingency amount, DO not bid (0999-25) | LS | 1 | $50,000 | $50,000 | $50,000 | $50,000 | $50,000 | $50,000 |
| 0305 | Single column ground sign assembly, F&I ground mount, than 12 SF (0700-1111) | EACH | 10 | $648.00 | $600.00 | $625.00 | $662.43 | $647.71 | $700.00 |
| 0310 | Single column ground sign assembly, F&I ground mount, 20.0 SF (0700-1112) | EACH | 2 | $2,592.00 | $2,500.00 | $2,600.00 | $2,007.45 | $2,590.85 | $3,000.00 |
| 0315 | Single column ground sign assembly, F&I ground mount, 30.0 SF (0700-1113) | EACH | 3 | $3,240.00 | $2,600.00 | $3,200.00 | $2,828.77 | $3,238.56 | $3,600.00 |
| 0320 | Single column ground sign assembly, remove (0700-1600) | EACH | 15 | $54.00 | $35.00 | $110.00 | $114.42 | $53.98 | $130.00 |
| 0325 | Retroreflective sign strip- furnish and install, 2' (0700-13-12) | EACH | 4 | $86.40 | $95.00 | $85.00 | $137.68 | $86.36 | $100.00 |
| 0330 | Retroreflective sign strip- furnish and install, 5' (0700-13-15) | EACH | 3 | $108.00 | $125.00 | $125.00 | $163.70 | $107.95 | $140.00 |
| 0335 | Tubular marker, 36" yellow (0704-1-4) | EACH | 1 | $216.00 | $250.00 | $325.00 | $199.61 | $215.90 | $380.00 |
| 0340 | Delineator, flexible tubular (0705-11-1) | EACH | 13 | $216.00 | $100.00 | $135.00 | $168.11 | $134.94 | $160.00 |
| 0345 | Raised pavement marker, type B (0706-1-3) | EACH | 313 | $6.48 | $3.98 | $4.00 | $4.30 | $4.30 | $5.50 |
| 0350 | Painted pavement markings, durable paint, yellow, island nose (0710-12290) | SF | 101 | $10.80 | $4.00 | $4.00 | $4.32 | $4.32 | $6.50 |
| 0355 | Painted pavement markings, surface (0710-90) | LS | 1 | $4,752.00 | $5,522.00 | $5,550.00 | $5,969.69 | $12,438 | $9,500.00 |
| 0360 | Thermoplastic, standard, solid, 12" for crosswalk and roundabout (0711-11123) | LF | 69 | $6.48 | $2.90 | $3.00 | $3.14 | $3.13 | $10.00 |
| 0365 | Thermoplastic, standard, solid, 18" for diagonals and chevrons (0711-11124) | LF | 63 | $8.64 | $4.35 | $4.50 | $4.70 | $4.70 | $15.00 |
| 0370 | Thermoplastic, standard, solid, 24" for stop line and crosswalk (0711-11125) | LF | 87 | $10.80 | $5.80 | $6.00 | $6.27 | $6.26 | $22.00 |
| 0375 | Thermoplastic, standard, 2-4 dotted guideline/ 6-10 gap extension, 6" (0711-11141) | GM | 0.11 | $5,400.00 | $2,861.98 | $2,900.00 | $3,094.05 | $3,117.66 | $7,500.00 |
| 0380 | Thermoplastic, standard, message or symbol (0711-11160) | EACH | 5 | $243.00 | $64.00 | $65.00 | $69.19 | $69.09 | $780.00 |
| 0385 | Thermoplastic, standard, arrow (0711-11170) | EACH | 24 | $97.20 | $54.00 | $55.00 | $58.38 | $58.29 | $390.00 |
| 0390 | Thermoplastic, standard, yellow, solid, 18" for diagonal or chevron (0711-11224) | LF | 5 | $8.64 | $4.35 | $4.50 | $4.70 | $4.70 | $15.00 |
| 0395 | Thermoplastic, standard, yellow, 2-4 dotted guide line dotted extension line, 6" (0711-11241) | GM | 0.02 | $5,400.00 | $2,750.48 | $2,775.00 | $2,973.81 | $3,117.66 | $7,500.00 |
| 0400 | Thermoplastic, preformed, white, solid, 24" for crosswalk (0711-14125) | LF | 51 | $18.36 | $14.68 | $14.75 | $15.84 | $15.82 | $23.00 |
| 0405 | Thermoplastic, preformed, white, message (0711-14160) | EACH | 2 | $324.00 | $195.00 | $200.00 | $210.81 | $210.51 | $380.00 |
| 0410 | Thermoplastic, preformed, white, arrow (0711-14170) | EACH | 2 | $216.00 | $80.00 | $80.00 | $86.49 | $86.36 | $250.00 |
| 0415 | Thermoplastic, standard-other surfaces, white, solid, 6" (0711-16101) | GM | 0.56 | $8,100.00 | $7,571.11 | $7,725.00 | $8,184.92 | $8,306.91 | $16,500 |
| 0420 | Thermoplastic, standard-other surfaces, white, solid, 8" (0711-16102) | GM | 0.03 | $9,720.00 | $7,075.86 | $10,625 | $7,649.66 | $11,076 | $9,000.00 |
| 0425 | Thermoplastic, standard-other surfaces, yellow, solid, 6" (0711-16201) | GM | 0.25 | $8,100.00 | $6,825.00 | $6,850.00 | $7,378.32 | $7,367.73 | $13,500 |
| 0430 | Conduit, furnish & install, open trench (0630-2-11) | LF | 174 | $14.57 | $24.75 | $26.00 | $26.76 | $26.72 | $30.00 |
| 0435 | Conduit, furnish & install, directional bore (0630-2-12) | LF | 481 | $31.86 | $38.15 | $40.00 | $41.24 | $41.18 | $40.00 |
| 0440 | Pull & splice box, F&I, 13" X 24" cover size (0635-2-11) | EACH | 8 | $2,523.96 | $1,700.00 | $1,775.00 | $1,837.83 | $1,835.19 | $1,800.00 |
| 0445 | Pull & splice box, F&I, 17" X 30" cover size (0635-2-14) | EACH | 1 | $3,368.95 | $2,368.00 | $2,500.00 | $2,559.98 | $2,556.31 | $2,500.00 |
| 0450 | Electrical power service, F&I, underground, meter not required (0639-1123) | AS | 1 | $1,749.60 | $5,000.00 | $5,200.00 | $5,405.37 | $5,397.61 | $5,200.00 |
| 0455 | Electrical power service, remove underground (0639-1620) | AS | 1 | $1,942.06 | $735.00 | $775.00 | $794.59 | $793.45 | $765.00 |
| 0460 | Electrical service wire, & install (0639-2-1) | LF | 17 | $14.12 | $11.10 | $11.75 | $12.00 | $11.98 | $12.00 |
| 0465 | Electrical service wire, (0639-2-6) | LF | 33 | $4.86 | $1.45 | $1.55 | $1.57 | $1.57 | $1.60 |
| 0470 | Lighting conductors, F&I, insulated, no. 10 or < (0715-1-11) | LF | 378 | $10.29 | $1.25 | $1.50 | $1.35 | $1.35 | $1.40 |
| 0475 | Lighting conductors, F&I, insulated, no.8 - 6 (0715-1-12) | LF | 894 | $11.02 | $2.76 | $3.00 | $2.98 | $2.98 | $3.00 |
| 0480 | Lighting conductors, F&I, no.1/0 3/0 (0 to 000) (0715-1-15) | LF | 2,875 | $14.89 | $7.25 | $7.75 | $7.84 | $7.83 | $8.00 |
| 0485 | Lighting conductors, remove & dispose, contractor owns (0715-1-60) | LF | 3,356 | $4.89 | $0.35 | $0.40 | $0.38 | $0.38 | $0.40 |
| 0490 | Light pole complete, F&I, standard pole standard foundation, 35' mounting height, 0' arm length (0715-61200) | EACH | 5 | $10,425 | $9,942.00 | $10,350 | $10,748 | $10,733 | $12,000 |
| 0495 | Pole cable distribution system, furnish and install, conventional (0715-500-1) | EACH | 5 | $498.96 | $875.00 | $925.00 | $945.94 | $944.58 | $1,000.00 |
| 0500 | Conduit, furnish & install, open trench (0630-2-11) | LF | 74 | $19.75 | $42.75 | $45.00 | $46.22 | $46.15 | $50.00 |
| 0505 | Conduit, furnish & install, directional bore (0630-2-12) | LF | 267 | $31.86 | $52.75 | $55.00 | $57.03 | $56.94 | $55.00 |
| 0510 | Signal cable- new or reconstructed intersection, furnish & install (0632-7-1) | PI | 1 | $9,066.18 | $3,325.00 | $3,475.00 | $3,594.57 | $3,589.41 | $3,500.00 |
| 0515 | Signal cable, remove- intersection (0632-7-6) | PI | 1 | $2,913.09 | $800.00 | $835.00 | $864.86 | $863.62 | $850.00 |
| 0520 | Pull & splice box, F&I, 13" X 24" cover size (0635-2-11) | EACH | 6 | $2,064.37 | $1,884.00 | $1,975.00 | $2,036.74 | $2,033.82 | $2,000.00 |
| 0525 | Electrical power service, F&I, underground, meter not required (0639-1123) | AS | 1 | $5,633.72 | $5,000.00 | $5,200.00 | $5,405.37 | $5,397.61 | $5,300.00 |
| 0530 | Electrical power service, remove underground (0639-1620) | AS | 1 | $1,942.06 | $736.00 | $775.00 | $795.67 | $794.53 | $800.00 |
| 0535 | Electrical service wire, & install (0639-2-1) | LF | 122 | $18.97 | $8.80 | $9.25 | $9.51 | $9.50 | $9.25 |
| 0540 | Electrical service wire, (0639-2-6) | LF | 10 | $1.17 | $0.90 | $1.00 | $0.97 | $0.97 | $1.00 |
| 0545 | Prestressed concrete pole, type P-II service pole (0641-2-12) | EACH | 1 | $3,108.46 | $2,398.00 | $2,500.00 | $2,592.41 | $2,588.69 | $2,500.00 |
| 0550 | Aluminum signals pole, (0646-1-11) | EACH | 1 | $2,662.63 | $2,960.00 | $3,100.00 | $3,199.98 | $3,195.38 | $3,100.00 |
| 0555 | Aluminum signals pole, remove (0646-1-60) | EACH | 1 | $1,942.06 | $1,085.00 | $1,130.00 | $1,172.97 | $1,171.28 | $1,200.00 |
| 0560 | Vehicular signal auxiliaries, repair/replace/retrofit- & install, backplate- flexible required (0650-2109) | EACH | 11 | $1,192.65 | $718.00 | $750.00 | $776.21 | $775.10 | $750.00 |
| 0565 | Pedestrian signal, furnish & install LED countdown, 1 way (0653-1-11) | AS | 1 | $1,475.17 | $982.00 | $1,025.00 | $1,061.62 | $1,060.09 | $1,050.00 |
| 0570 | Loop detector inductive, F&I, type 10 (0660-1110) | EACH | 1 | $806.92 | $375.00 | $395.00 | $405.40 | $404.82 | $350.00 |
| 0575 | Loop assembly, F&I, type F (0660-2106) | AS | 7 | $3,519.83 | $2,100.00 | $2,200.00 | $2,270.26 | $2,266.99 | $2,200.00 |
| 0580 | Pedestrian detector, furnish & install, standard (0665-1-11) | EACH | 1 | $351.62 | $314.00 | $330.00 | $339.46 | $338.97 | $350.00 |
| 0585 | Traffic controller, modify (0671-2-40) | EACH | 1 | $1,456.54 | $530.00 | $555.00 | $572.97 | $572.15 | $550.00 |
| 0590 | Traffic signal controller cabinet, adjust/modify (0676-1500) | EACH | 1 | $971.03 | $2,562.00 | $2,675.00 | $2,769.71 | $2,765.73 | $2,700.00 |
| 0595 | Sign panel, furnish & install ground mount, UP to 12 SF (0700-3101) | EACH | 5 | $260.00 | $192.00 | $200.00 | $207.57 | $1,619.28 | $200.00 |
| 0600 | Sign panel, remove, UP to 12 SF (0700-3601) | EACH | 5 | $50.00 | $36.00 | $37.50 | $38.92 | $269.88 | $38.00 |
| 0605 | Itsfm subsurface documentation- project length (0611-1-1) | MI | 0.24 | $4,358.45 | $6,054.00 | $6,300.00 | $6,544.83 | $6,535.42 | $6,300.00 |
| 0610 | Itsfm location documentation- ITS site (0611-2-2) | EACH | 2 | $2,402.24 | $2,624.00 | $2,750.00 | $2,836.74 | $2,832.66 | $2,800.00 |
| 0615 | Conduit, furnish & install, open trench (0630-2-11) | LF | 832 | $27.19 | $44.45 | $46.25 | $48.05 | $47.98 | $50.00 |
| 0620 | Conduit, furnish & install, directional bore (0630-2-12) | LF | 400 | $35.68 | $47.00 | $49.00 | $50.81 | $50.74 | $50.00 |
| 0625 | Conduit, furnish & install, aboveground (0630-2-14) | LF | 5 | $17.16 | $282.00 | $295.00 | $304.86 | $304.43 | $300.00 |
| 0630 | Fiber optic cable, relocate, underground (0633-1420) | LF | 1,214 | $5.03 | $5.90 | $6.25 | $6.38 | $6.37 | $6.50 |
| 0635 | Fiber optic connection, install, splice (0633-2-31) | EACH | 72 | $57.35 | $61.00 | $65.00 | $65.95 | $65.85 | $65.00 |
| 0640 | Fiber optic connection, install, termination (0633-2-32) | EACH | 12 | $95.58 | $102.00 | $110.00 | $110.27 | $110.11 | $107.00 |
| 0645 | Fiber optic connection hardware, relocate patch panel- field terminated (0633-3-46) | EACH | 1 | $242.76 | $508.00 | $535.00 | $549.18 | $548.40 | $530.00 |
| 0650 | Fiber optic cable locator (0633-6) | DA | 160 | $127.44 | $156.00 | $165.00 | $168.65 | $168.41 | $165.00 |
| 0655 | Pull & splice box, F&I, 13" X 24" cover size (0635-2-11) | EACH | 8 | $2,549.88 | $1,884.00 | $1,975.00 | $2,036.74 | $2,033.82 | $2,000.00 |
| 0660 | Pull & splice box, F&I, 24" X 36" cover size (0635-2-12) | EACH | 5 | $4,365.90 | $2,712.00 | $2,825.00 | $2,931.87 | $2,927.66 | $2,900.00 |
| 0665 | Electrical power service, F&I, underground, meter not required (0639-1123) | AS | 1 | $5,633.72 | $5,000.00 | $5,200.00 | $5,405.37 | $5,397.61 | $5,200.00 |
| 0670 | Electrical power service, remove underground (0639-1620) | AS | 1 | $1,942.06 | $736.00 | $775.00 | $795.67 | $794.53 | $765.00 |
| 0675 | Electrical service wire, & install (0639-2-1) | LF | 701 | $18.97 | $9.75 | $10.25 | $10.54 | $10.53 | $11.00 |
| 0680 | Electrical service wire, relocate (0639-2-4) | LF | 363 | $19.42 | $4.45 | $4.75 | $4.81 | $4.80 | $5.00 |
| 0685 | Electrical service wire, (0639-2-6) | LF | 651 | $0.97 | $1.15 | $1.25 | $1.24 | $1.24 | $1.50 |
| 0690 | Prestressed concrete pole, type P-II service pole (0641-2-12) | EACH | 1 | $3,108.46 | $2,398.00 | $2,500.00 | $2,592.41 | $2,588.69 | $2,500.00 |
| 0695 | Prestressed concrete pole, complete pole removal- pedestal/service pole (0641-2-60) | EACH | 1 | $1,942.06 | $1,798.00 | $1,900.00 | $1,943.77 | $1,940.98 | $1,900.00 |
| 0700 | Vehicle detection system- wrong way for exit ramp, 3 or more lanes, AC powered (0660-7-22) | EACH | 1 | $49,236 | $65,200 | $4,100.00 | $70,486 | $4,251.15 | $84,000 |
| 0705 | Vehicle detection system- wrong way, remove (0660-7-90) | EACH | 1 | $3,884.12 | $1,008.00 | $1,050.00 | $1,089.72 | $1,088.16 | $1,050.00 |
| 0710 | ITS cabinet, relocate (0676-2400) | EACH | 1 | $16,190 | $7,000.00 | $7,300.00 | $7,567.52 | $7,556.65 | $7,300.00 |
| 0715 | Managed field ethernet switch, relocate (0684-1-4) | EACH | 1 | $485.51 | $530.00 | $555.00 | $572.97 | $572.15 | $560.00 |
| 0720 | Enhanced highway sign AC powered, relocate - ground mount (0700-141802) | EACH | 1 | $4,532.12 | $735.00 | $765.00 | $794.59 | $793.45 | $765.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from FDOT's tabulation for this contract. FDOT Tabulation of Bids PDFs from its central office lettings, January 2018 to October 2026, all pay items. On A+B contracts the cost part is kept (the total the pay items add up to). Bidders listed without a rank or total are left out.
Every contract let that day: FDOT letting of May 20, 2026. Compiled by Mirage Metrics.