ODOT contract 250128 bid tabulation

MEG-US 33-13.98 (MAJOR WIDENING). Let by Ohio DOT on February 27, 2025, MEG. 6 bids received; low bid $31,149,716 by Kokosing Construction Company Inc, -1.1% against the engineer's estimate of $31,509,000.

Owner
Ohio DOT
Letting
27 FEB 2025
Pay items
201
Data through
12 NOV 2026

Bidders

RankBidderTotal bidAgainst the low bidAgainst the estimate
1Kokosing Construction Company Inc$31,149,716Low-1.0%
2Allard Excavation LLC$34,982,063+12%+11%
3George J Igel & Co Inc$36,145,902+16%+15%
4Kanawha Stone Company Incorporated$36,334,852+17%+15%
5Triton Construction Inc$38,518,205+24%+22%
6Alan Stone Co Inc$40,417,626+30%+28%
ODOT contract 250128: bids by rank

Engineer's estimate: $31,509,000.

Bid tabulation

LinePay itemUnitQuantity1. Kokosing Construction Company Inc2. Allard Excavation LLC3. George J Igel & Co Inc4. Kanawha Stone Company Incorporated5. Triton Construction Inc6. Alan Stone Co Inc
1Clearing and grubbing, as per plan (201E11001)LS1$100,000$950,000$935,000$1,549,991$403,953$650,000
2Headwall removed (202E20010)EACH1$350.00$256.00$550.00$457.24$500.00$470.00
3Pavement removed (202E23000)SY28,966$5.00$10.00$6.50$5.19$5.00$10.00
4Pipe removed, 24" and under (202E35100)FT110$16.00$7.00$4.50$16.53$30.00$15.00
5Pipe removed, 24" and under, as per plan (202E35101)FT565$12.00$7.00$4.00$24.59$50.00$15.00
6Guardrail removed (202E38000)FT19,827.50$1.80$2.00$1.80$1.90$3.00$2.50
7Impact attenuator removed (202E47800)EACH1$150.00$186.00$150.00$150.00$500.00$160.00
8Catch basin removed (202E58100)EACH1$1,700.00$390.00$200.00$1,077.28$1,500.00$470.00
9Fence removed (202E75000)FT924$5.00$2.00$6.50$4.05$4.00$5.00
10Excavation (203E10000)CY931,325$6.25$8.25$9.00$8.00$10.00$12.00
11Embankment (203E20000)CY507,036$0.95$3.00$2.25$1.59$2.00$2.00
12Granular material, type C, as per plan (203E35121)CY470$116.00$109.00$110.00$111.60$120.00$120.00
13Special - settlement platform (203E65000)EACH3$1,340.00$5,961.00$6,300.00$6,783.79$1,200.00$6,100.00
14Subgrade compaction (204E10000)SY133,105$1.77$1.42$1.00$2.05$2.00$1.50
15Excavation of subgrade (204E13000)CY8,317$6.25$8.00$21.75$3.62$10.00$20.00
16Granular material, type B, as per plan (204E30011)CY8,317$85.00$91.00$100.00$119.24$120.00$70.00
17Proof rolling (204E45000)HR45$250.00$268.00$120.00$255.50$250.00$1,000.00
18Pre-blast condition survey (208E10000)LS1$34,775$8,595.00$34,755$34,755$25,000$95,000
19Blasting consultant (208E12000)LS1$5,000.00$5,500.00$5,500.00$5,500.00$10,000$60,000
20Air blast and noise control (208E13000)LS1$8,775.00$10,000$15,600$7,800.00$15,000$17,000
21Vibration control and monitoring (208E14000)LS1$8,775.00$10,000$15,600$7,800.00$30,000$15,000
22Hydrologist (208E16000)LS1$15,300$45,000$27,300$46,500$90,000$150,000
23Reshaping under guardrail (209E15000)STA132.50$85.00$64.00$280.00$89.88$80.00$150.00
24Borrow (209E70000)CY350.80$85.00$43.00$31.00$66.07$80.00$25.00
25Guardrail, type MGS (606E15050)FT20,925$16.78$16.78$16.78$16.78$16.78$20.00
26MGS guardrail, type 8 (606E15400)FT2,450$25.62$25.92$25.62$25.62$25.62$30.00
27Guardrail, barrier design, type MGS (606E15550)FT62.50$31.20$31.20$31.20$31.20$31.20$35.00
28Raising type MGS guardrail (606E17050)FT2,087.50$4.50$4.50$4.50$4.50$4.50$5.00
29Post end anchor (or concrete block end anchor) (606E17500)EACH18$1,280.00$1,280.00$1,280.00$1,280.00$1,280.00$1,500.00
30Anchor assembly, MGS type E, (MASH 2016) (606E26150)EACH6$2,180.00$2,180.00$2,180.00$2,180.00$2,180.00$2,500.00
31Anchor assembly, MGS type T (606E26550)EACH26$1,000.00$1,000.00$1,000.00$1,000.00$1,000.00$1,100.00
32Anchor assembly rebuilt, MGS type B (606E27846)EACH1$760.00$760.00$760.00$760.00$760.00$870.00
33Anchor assembly rebuilt, MGS type T (606E27910)EACH1$450.00$450.00$450.00$450.00$450.00$510.00
34MGS bridge terminal assembly, type 1 (606E35002)EACH3$1,980.00$1,980.00$1,980.00$1,980.00$1,980.00$2,300.00
35MGS bridge terminal assembly rebuilt, type 1 (606E35012)EACH2$1,250.00$1,250.00$1,250.00$1,250.00$1,250.00$1,400.00
36MGS bridge terminal assembly, type 2 (606E35102)EACH1$340.00$340.00$340.00$340.00$340.00$390.00
37Impact attenuator, type 1 (bidirectional) (606E60012)EACH1$7,500.00$7,500.00$7,500.00$7,500.00$7,500.00$8,600.00
38Fence, type 47 (607E15000)FT853$15.16$15.16$15.16$15.16$15.16$15.00
39Reference monument, type A (623E40500)EACH60$480.00$789.00$760.00$784.42$700.00$1,200.00
40Dumped rock fill, type A (601E25000)CY27$140.00$105.00$130.00$164.38$170.00$120.00
41Dumped rock fill, type B, as per plan (601E26001)CY3,056$11.00$104.00$115.00$128.95$140.00$65.00
42Rock channel protection, type B with filter (601E32100)CY892$140.00$115.00$120.00$135.91$125.00$75.00
43Rock channel protection, type C with filter (601E32200)CY1,382$145.00$115.00$120.00$131.28$160.00$70.00
44Water (616E10000)MGAL4,300$70.00$1.00$38.00$65.99$20.00$35.00
45Topsoil (659E00300)CY8,983$9.00$20.00$7.00$30.07$25.00$15.00
46Seeding and mulching (659E10000)SY393,050$0.60$0.48$0.65$0.75$0.60$0.60
47Seeding and mulching, as per plan (659E10001)SY39,133$0.55$1.00$0.85$1.00$0.55$1.00
48Repair seeding and mulching (659E14000)SY21,610$0.60$1.00$0.65$0.75$0.60$0.50
49Inter-seeding (659E15000)SY21,610$0.01$0.01$0.65$1.00$0.01$0.01
50Commercial fertilizer (659E20000)TON39$250.00$1,863.00$1,250.00$1,250.00$250.00$1,700.00
51Lime (659E31000)ACRE89.30$25.00$185.00$150.00$150.00$25.00$230.00
52Water (659E35000)MGAL1,167$0.01$1.00$1.00$1.00$0.01$1.00
53Mowing (659E40000)MSF3,168$1.00$1.00$10.00$10.00$12.00$1.00
54Ditch erosion protection (670E00700)SY88,117$1.15$2.00$2.50$2.50$1.15$2.00
55Storm water pollution prevention plan (832E15000)LS1$8,375.00$15,000$8,500.00$8,857.03$30,000$9,600.00
56Storm water pollution prevention inspections (832E15002)LS1$40,000$65,000$43,700$29,189$130,000$59,000
57Storm water pollution prevention inspection software (832E15010)LS1$40,000$40,000$29,300$41,216$35,000$33,000
58Erosion control (832E30000)EACH800,000$1.00$1.00$1.00$1.00$1.00$1.00
59Seeding and erosion control with turf reinforcing mat, type 1 (836E10000)SY1,073$5.00$6.00$6.00$6.00$5.00$5.00
60Rock excavation (503E31100)CY814$35.00$22.00$69.50$144.89$75.00$20.00
61Concrete masonry (602E20000)CY8.19$6,420.00$4,142.00$3,500.00$4,695.49$6,500.00$3,000.00
626" shallow pipe underdrains (605E11100)FT16,446$14.00$14.00$12.00$13.48$16.00$20.00
636" unclassified pipe underdrains (605E13300)FT11,122$22.00$14.00$11.00$15.07$18.00$20.00
646" unclassified pipe underdrains for springs (605E13402)FT1,200$30.00$30.00$15.75$19.53$30.00$20.00
656" rock cut underdrains (605E13500)FT28,000$18.00$23.00$16.00$17.71$17.00$20.00
666" base pipe underdrains (605E14000)FT13,058$9.00$13.00$9.00$11.37$12.00$15.00
67Aggregate drains for springs (605E32200)FT200$16.00$46.00$22.75$48.29$30.00$25.00
684" conduit, type F (611E00406)FT453$60.00$26.00$48.00$38.31$25.00$30.00
696" conduit, type F for underdrain outlets (611E00510)FT2,126$34.00$22.00$28.00$25.38$24.00$30.00
706" conduit, type F (611E01500)FT10$67.00$16.00$65.00$80.18$30.00$60.00
7112" conduit, type B (611E04400)FT835$190.00$102.00$220.00$101.10$160.00$100.00
7212" conduit, type C (611E04600)FT1,000$145.00$65.00$75.00$93.19$160.00$100.00
7318" conduit, type B (611E07400)FT1,391$210.00$121.00$340.00$118.26$210.00$95.00
7418" conduit, type C (611E07600)FT200$190.00$93.00$100.00$107.48$210.00$120.00
7521" conduit, type B (611E08900)FT628$270.00$137.00$270.00$134.96$240.00$130.00
76Conduit, misc.: class QC1 concrete backfill (611E97600)CY105$330.00$358.00$310.00$589.89$400.00$300.00
77Catch basin, no. 4 (611E98230)EACH18$9,930.00$5,148.00$5,500.00$7,372.75$9,500.00$5,600.00
78Catch basin, no. 8 (611E98410)EACH2$9,345.00$4,535.00$3,900.00$6,674.00$8,500.00$4,800.00
79Catch basin, no. 2-2C, as per plan (611E98505)EACH13$4,710.00$3,099.00$4,100.00$4,450.03$4,200.00$2,800.00
80Manhole, no. 3, as per plan (611E99575)EACH1$7,485.00$4,993.00$11,000$6,170.56$6,500.00$4,200.00
81Precast reinforced concrete outlet (611E99710)EACH11$950.00$448.00$364.00$475.90$450.00$650.00
82Full depth pavement sawing (252E01500)FT27,439$2.47$2.85$1.98$1.90$5.00$3.00
83Pavement planing, asphalt concrete, 1.5" (254E01000)SY837$13.50$13.50$13.50$2.41$14.00$9.00
84Pavement planing, portland cement concrete, 1.5" (254E01010)SY2,498$12.00$13.50$13.50$10.46$14.00$7.00
85Pavement planing, portland cement concrete, variab (254E01010)SY153$66.50$13.50$13.50$13.75$14.00$40.00
86Full depth pavement removal and rigid replacement, type 1, class QC1 (255E11000)SY1,997$225.00$273.00$171.25$338.00$235.00$260.00
87Full depth pavement sawing (255E20000)FT6,200$3.90$5.00$3.00$3.00$5.00$5.50
88Asphalt concrete base, PG64-22, (449) (302E56000)CY19,377$190.00$193.35$198.10$198.10$208.00$230.00
89Aggregate base (304E20000)CY21,687$95.00$92.00$102.00$120.79$105.00$100.00
90Tack coat, 702.13 (407E13900)GAL12,544$4.05$4.05$4.05$4.05$4.05$4.50
91Non-tracking tack coat (407E20000)GAL20,192$4.45$4.35$4.45$4.45$4.45$5.00
92Prime coat (408E10000)GAL2,790$5.00$5.00$5.00$5.00$5.00$5.50
93Asphalt concrete intermediate course, type 1, (449), (under guardrail) (441E70800)CY662.60$341.00$345.00$345.00$345.00$362.00$390.00
94Anti-segregation equipment (442E00100)CY16,187$7.00$7.00$7.00$7.00$8.00$8.00
95Asphalt concrete intermediate course, 12.5 MM, type A (446) (442E10080)CY6,064$205.00$208.00$212.50$212.50$225.00$240.00
96Asphalt concrete intermediate course, 19 MM, type A (446) (442E10100)CY9,607$200.00$204.00$207.50$207.50$220.00$240.00
97Asphalt concrete surface course, 12.5 MM, type A (447) (442E10300)CY11,730$235.00$241.50$242.00$242.00$255.00$280.00
98Compacted aggregate (617E10100)CY364$135.00$135.00$135.00$87.12$145.00$120.00
99Rumble strips, shoulder (asphalt concrete) (618E40600)MI23.20$880.00$635.00$1,150.00$1,320.00$635.00$1,500.00
100Connection, fused pull apart (625E00450)EACH4$226.00$140.00$115.00$140.00$140.00$180.00
101Connection, unfused pull apart (625E00460)EACH4$220.00$140.00$115.00$140.00$140.00$180.00
102Connection, unfused permanent (625E00480)EACH10$192.00$140.00$115.00$140.00$140.00$180.00
103Light pole foundation, 24" X 8' deep (625E14100)EACH3$3,960.00$3,550.00$2,900.00$3,550.00$3,550.00$4,500.00
104No. 4 AWG 2400 volt distribution cable (625E23200)FT1,605$4.60$3.50$3.80$3.50$3.50$4.50
105No. 10 AWG pole and bracket cable (625E23400)FT744$2.60$2.50$1.75$2.50$2.50$3.00
1061-1/2" duct cable with three no. 4 AWG 2400 volt cables (625E24320)FT144$39.00$33.00$12.00$33.00$33.00$40.00
107Conduit, jacked or drilled, 725.04, 3" (625E25902)FT371$142.50$52.00$50.00$52.00$52.00$65.00
108Conduit cleaned and cables removed (625E25910)FT149$6.10$1.00$1.00$1.00$1.00$1.50
109Luminaire, conventional, solid state (LED), as per plan (625E26253)EACH4$530.00$775.00$575.00$775.00$775.00$980.00
110Trench, 24" deep (625E29002)FT104$26.00$10.00$14.00$10.00$10.00$15.00
111Pull box, 725.08, 18" (625E30700)EACH4$1,820.00$1,450.00$1,150.00$1,450.00$1,450.00$1,800.00
112Ground rod (625E32000)EACH4$350.00$325.00$276.00$325.00$325.00$410.00
113Power service, as per plan (625E34001)EACH2$18,800$7,700.00$8,925.00$7,700.00$7,700.00$9,800.00
114Remove and reerect existing light pole (625E35010)EACH4$3,110.00$1,400.00$1,375.00$1,400.00$1,400.00$1,800.00
115Underground warning marking tape (625E36010)FT104$8.50$1.00$3.00$1.00$1.00$1.50
116Power service removed (625E75510)EACH2$1,650.00$500.00$650.00$500.00$500.00$630.00
117Luminaire support foundation removed (625E75522)EACH3$750.00$650.00$500.00$650.00$650.00$820.00
118Distribution cable removed, as per plan (625E75551)FT480$4.80$1.50$1.00$1.50$1.50$2.00
119Arc flash calculations and label (PS-1 at US 33 & (625E76000)EACH1$630.00$2,350.00$4,000.00$2,350.00$2,350.00$3,000.00
120Arc flash calculations and label (PS-1 at US 33 & (625E76000)EACH1$630.00$2,350.00$4,000.00$2,350.00$2,350.00$3,000.00
121Lighting, misc.: reuse and rehabilitation of exist (625E98000)EACH1$2,700.00$1,250.00$250.00$1,250.00$1,250.00$1,600.00
122Lighting, misc.: reuse and rehabilitation of exist (625E98000)EACH3$990.00$1,250.00$250.00$1,250.00$1,250.00$1,600.00
123RPM (621E00100)EACH895$36.00$36.00$35.00$36.00$36.00$36.00
124Raised pavement marker removed (621E54000)EACH485$28.00$31.00$31.00$31.00$6.00$31.00
125Barrier reflector, type 2, (1WAY) (626E00110)EACH259$10.00$10.00$10.00$10.00$10.00$10.00
126Barrier reflector, type 2, (bidirectional) (626E00110)EACH39$10.50$10.50$10.50$10.50$10.50$10.00
127Ground mounted support, no. 2 post (630E02100)FT156$8.30$8.30$8.30$8.30$8.30$9.50
128Ground mounted support, no. 3 post (630E03100)FT867$10.20$10.20$10.20$10.20$10.20$10.00
129Ground mounted support, no. 4 post, as per plan (630E04101)FT88$14.20$14.20$14.20$14.20$14.20$15.00
130Ground mounted structural beam support, S4X7.7 (630E06400)FT143.70$22.60$22.60$22.60$22.60$22.60$25.00
131Ground mounted structural beam support, W6X9 (630E06500)FT71.50$23.00$23.00$23.00$23.00$23.00$25.00
132Ground mounted structural beam support, W10X12 (630E07600)FT366.70$27.60$27.60$27.60$27.60$27.60$30.00
133Ground mounted structural beam support, W12X30 (630E08000)FT235.60$56.00$56.00$56.00$56.00$56.00$65.00
134Sign post reflector (630E08600)EACH17$21.00$21.00$21.00$21.00$21.00$25.00
135Breakaway structural beam connection (630E09000)EACH34$650.00$650.00$650.00$650.00$650.00$740.00
136Sign, flat sheet (630E80100)SF553.50$13.60$13.60$13.60$13.60$13.60$15.00
137Sign, ground mounted extrusheet (630E80200)SF1,650$19.50$19.50$19.50$19.50$19.50$20.00
138Ground mounted structural beam support foundation (630E84500)EACH42$1,480.00$1,480.00$1,480.00$1,480.00$1,480.00$1,700.00
139Removal of ground mounted sign and disposal (630E84900)EACH30$12.00$12.00$12.00$12.00$12.00$15.00
140Removal of ground mounted sign and storage (630E85000)EACH70$20.00$20.00$20.00$20.00$20.00$25.00
141Removal of ground mounted major sign and disposal (630E85400)EACH10$115.00$115.00$115.00$115.00$115.00$130.00
142Removal of ground mounted post support and storage (630E86006)EACH116$55.00$55.00$55.00$55.00$55.00$65.00
143Removal of ground mounted structural beam support (630E86102)EACH24$250.00$250.00$250.00$250.00$250.00$290.00
144Stop line (644E00500)FT111$8.50$8.50$8.50$8.50$8.50$9.50
145Transverse/diagonal line (644E00700)FT777$8.50$8.50$8.50$8.50$8.50$9.50
146Island marking (644E00900)SF904$2.50$2.50$2.50$2.50$2.50$3.00
147Lane arrow (644E01300)EACH12$105.00$105.00$105.00$105.00$105.00$120.00
148Edge line, 6", type A4 (645E00118)MI0.22$58,350$58,350$58,350$58,350$58,350$67,000
149Lane line, 6", type A4 (645E00220)MI0.12$30,225$30,225$30,225$30,225$30,225$35,000
150Removal of pavement marking (646E50100)FT3,267$4.22$4.72$4.72$4.70$5.00$5.50
151Removal of pavement marking (646E50300)MI10.58$2,003.23$5,700.00$5,700.00$5,700.00$5,700.00$6,500.00
152Wet reflective thermoplastic pavement marking, edge line, 6" (807E14010)MI24.84$5,150.00$5,150.00$5,150.00$5,150.00$5,150.00$5,900.00
153Wet reflective thermoplastic pavement marking, lane line, 6" (807E14110)MI11.82$2,390.00$2,390.00$2,390.00$2,390.00$2,390.00$2,700.00
154Wet reflective thermoplastic pavement marking, channelizing line, 12" (807E14310)FT6,553$2.75$2.75$2.75$2.75$2.75$3.00
155Wet reflective thermoplastic pavement marking, dotted line, 6" (807E14410)FT1,378$1.10$1.40$1.10$1.10$1.10$1.50
156Grooving for 6" recessed pavement marking, (asphalt) (850E10010)MI36.66$2,617.00$2,617.00$2,617.00$2,617.00$2,617.00$3,000.00
157Grooving for 6" recessed pavement marking, (asphalt) (850E10110)FT1,378$1.35$1.35$1.35$1.35$1.35$1.50
158Grooving for 12" recessed pavement marking, (asphalt) (850E10130)FT6,553$2.00$2.00$2.00$2.00$2.00$2.50
159Traffic compacted surface, type A (410E10000)CY100$216.00$151.00$116.00$117.75$200.00$140.00
160Law enforcement officer with patrol car for assistance (614E11110)HR175$120.00$112.00$100.00$93.06$70.00$110.00
161Work zone impact attenuator, 24" wide hazards, (bidirectional) (614E12384)EACH13$8,920.00$2,200.00$2,575.00$5,000.00$2,500.00$3,500.00
162Detour signing (614E12420)LS1$6,500.00$3,500.00$3,500.00$3,500.00$3,500.00$4,000.00
163Detour signing (614E12420)LS1$5,400.00$2,950.00$2,950.00$2,950.00$2,950.00$3,400.00
164Work zone marking sign (614E12460)EACH26$85.00$85.00$85.00$85.00$85.00$95.00
165Replacement drum (614E12600)EACH200$80.00$80.00$80.00$80.00$80.00$90.00
166Work zone crossover lighting system (614E12756)EACH1$40,000$48,750$72,500$48,750$48,750$62,000
167Asphalt concrete for maintaining traffic (614E13000)CY150$250.00$250.00$297.50$135.00$400.00$350.00
168Barrier reflector, type 1, (1WAY) (614E13310)EACH165$18.00$18.00$11.00$18.00$18.00$20.00
169Barrier reflector, type 1, (bidirectional) (614E13310)EACH211$20.25$20.25$14.25$20.25$20.25$25.00
170Object marker, one way (614E13350)EACH165$22.50$22.50$15.25$22.50$22.50$25.00
171Object marker, two way (614E13360)EACH211$26.50$26.50$18.75$26.50$26.50$30.00
172Portable changeable message sign, as per plan (614E18601)SNMT24$1,500.00$1,500.00$1,500.00$1,500.00$1,500.00$1,700.00
173Work zone center line, class III, 642 paint (614E21550)MI4.10$975.00$975.00$975.00$975.00$975.00$1,100.00
174Work zone edge line, class III, 6", 642 paint (614E22360)MI28.61$825.00$825.00$825.00$825.00$825.00$940.00
175Work zone channelizing line, class III, 8", 642 paint (614E23680)FT4,514$0.65$0.65$0.65$0.65$0.65$0.70
176Work zone dotted line, class III, 6", 642 paint (614E24612)FT3,134$1.00$1.00$1.00$1.00$1.00$1.00
177Work zone transverse/diagonal line, class III, 642 paint (614E25620)FT2,058$4.50$4.50$4.50$4.50$4.50$5.00
178Work zone stop line, class III, 642 paint (614E26610)FT48$14.00$14.00$14.00$14.00$14.00$15.00
179Work zone arrow, class III, 642 paint (614E30650)EACH24$160.00$160.00$160.00$160.00$160.00$180.00
180Work zone word on pavement, 96", class III, 642 paint (614E31670)EACH8$270.00$270.00$270.00$270.00$270.00$310.00
181Roads for maintaining traffic, as per plan (615E10001)LS1$10,000$32,000$80,100$17,315$150,000$120,000
182Pavement for maintaining traffic, class A (615E20000)SY2,261$51.00$83.00$65.00$86.67$85.00$65.00
183Portable barrier, unanchored (622E41100)FT9,168$21.00$33.00$21.50$27.72$75.00$22.00
184Removal of pavement marking (642E30000)FT1,004$4.22$4.72$4.72$4.70$5.00$5.50
185Removal of pavement marking (642E30020)EACH12$48.03$52.00$52.00$52.00$52.00$60.00
186Removal of pavement marking (642E30030)MI4.02$2,003.23$3,300.00$3,300.00$3,300.00$3,300.00$3,800.00
187Removal of longitudinal channelizing device (831E00500)FT369$4.00$6.00$9.00$0.52$7.00$4.50
188Steel piles, misc.: W36X262 (507E00400)FT2,323.40$380.00$307.00$340.00$315.00$400.00$570.00
189Drilled shafts, 48" diameter above bedrock, as per plan (524E94903)FT1,493.90$260.00$165.00$139.50$410.00$300.00$300.00
190Drilled shafts, 48" diameter, into bedrock, as per plan (524E94905)FT840$430.00$185.00$280.00$410.00$155.00$440.00
191Premium for contract performance bond and for payment bond (103E05000)LS1$135,900$198,703$125,000$167,190$160,000$200,000
192CPM progress schedule (108E10000)LS1$5,000.00$40,000$7,500.00$42,041$25,000$18,000
193Special - departments share facilitated partnering costs (111E10100)EACH10,000$1.00$1.00$1.00$1.00$1.00$1.00
194Maintaining traffic (614E11000)LS1$334,000$350,000$815,000$573,372$200,000$810,000
195Maintaining traffic, as per plan (614E11001)LS1$8,000.00$8,072.00$6,500.00$23,280$25,000$30,000
196Field office, type C (619E16020)MNTH43$2,800.00$2,500.00$3,320.00$6,222.28$3,000.00$2,200.00
197Construction layout stakes and surveying (623E10000)LS1$220,000$300,000$236,000$388,000$300,000$450,000
198Mobilization (624E10000)LS1$1,560,000$1,750,000$1,628,000$741,365$1,925,000$466,000
200Work zone lane line, class I, 6", 642 paint (614E20110)MI23.64$675.00$675.00$675.00$713.85$675.00$770.00
201Work zone lane line, class III, 6", 642 paint (614E20560)MI11.82$525.00$525.00$525.00$555.22$525.00$600.00
202Work zone edge line, class I, 6", 642 paint (614E22110)MI49.68$1,245.00$1,245.00$1,245.00$1,316.66$1,245.00$1,400.00
ODOT contract 250128: unit prices by line

The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.

Source

Read from ODOT's tabulation for this contract. ODOT Official Bid Tabulation PDFs from its public DigitalPaper bid tab cabinet, January 2020 to November 2026 (the source links open after DigitalPaper starts a guest session). ODOT prints unit prices to two decimals but computes line amounts from the full price, so a few bids miss their total and are left out. Descriptions are cut at about 50 characters, as ODOT prints them.

Every contract let that day: ODOT letting of February 27, 2025. Compiled by Mirage Metrics.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy