| 1 | Clearing and grubbing, as per plan (201E11001) | LS | 1 | $320,000 |
| 2 | Headwall removed (202E20010) | EACH | 12 | $770.00 |
| 3 | Pavement removed (202E23000) | SY | 44,739 | $6.00 |
| 4 | Pipe removed, 24" and under (202E35100) | FT | 20,322 | $10.00 |
| 5 | Pipe removed, over 24" diameter (202E35200) | FT | 91 | $90.00 |
| 6 | Guardrail removed (202E38000) | FT | 17,408 | $1.90 |
| 7 | Anchor assembly removed, type A (202E42000) | EACH | 4 | $250.00 |
| 8 | Anchor assembly removed, type T (202E42040) | EACH | 9 | $125.00 |
| 9 | Anchor assembly removed (202E42206) | EACH | 1 | $150.00 |
| 10 | Anchor assembly removed (202E42206) | EACH | 1 | $150.00 |
| 11 | Mailbox removed (202E53100) | EACH | 3 | $80.00 |
| 12 | Catch basin removed (202E58100) | EACH | 19 | $1,200.00 |
| 13 | Special - pipe cleanout, 27" to 48" (202E70120) | FT | 1,818 | $6.00 |
| 14 | Special - pipe cleanout over 48" (202E70130) | FT | 245 | $19.00 |
| 15 | Fence removed (202E75000) | FT | 379 | $5.00 |
| 16 | Removal misc.: guardrail removed for storage (202E98000) | LS | 1 | $2,400.00 |
| 17 | Excavation (203E10000) | CY | 1,615,644 | $8.76 |
| 18 | Embankment (203E20000) | CY | 1,927,050 | $2.00 |
| 19 | Granular embankment, as per plan (203E35001) | CY | 17,434 | $100.00 |
| 20 | Subgrade compaction (204E10000) | SY | 167,767 | $1.80 |
| 21 | Proof rolling (204E45000) | HR | 56 | $250.00 |
| 22 | Pre-blast condition survey (208E10000) | LS | 1 | $23,565 |
| 23 | Blasting consultant (208E12000) | LS | 1 | $8,500.00 |
| 24 | Air blast and noise control (208E13000) | LS | 1 | $19,500 |
| 25 | Vibration control and monitoring (208E14000) | LS | 1 | $19,500 |
| 26 | Presplitting (208E15000) | SY | 1,556 | $30.00 |
| 27 | Hydrologist (208E16000) | LS | 1 | $85,000 |
| 28 | Guardrail, type MGS (606E15050) | FT | 33,269 | $17.06 |
| 29 | MGS guardrail, type 8 (606E15400) | FT | 250 | $27.24 |
| 30 | Guardrail, barrier design, type MGS (606E15550) | FT | 375 | $31.20 |
| 31 | Post end anchor (or concrete block end anchor) (606E17500) | EACH | 1 | $1,300.00 |
| 32 | Rounded end section (606E20050) | EACH | 1 | $60.00 |
| 33 | Anchor assembly, MGS type E, MASH 2016 (606E26150) | EACH | 25 | $2,200.00 |
| 34 | Anchor assembly, MGS type T (606E26550) | EACH | 34 | $1,000.00 |
| 35 | MGS bridge terminal assembly, type 1 (606E35002) | EACH | 8 | $1,980.00 |
| 36 | Impact attenuator, type 1 (bidirectional) (606E60012) | EACH | 6 | $7,400.00 |
| 37 | Impact attenuator, type 2 (bidirectional), 62 MPH (606E60028) | EACH | 2 | $34,770 |
| 38 | Fence, type 47 (607E15000) | FT | 386 | $47.80 |
| 39 | Gate, type 47 (607E40500) | EACH | 1 | $2,600.00 |
| 40 | Reference monument, type A (623E40500) | EACH | 50 | $480.00 |
| 41 | Special - geotextile fabric, 712.09, type A (690E12010) | SY | 30,397 | $1.50 |
| 42 | Special - mailbox support system, single (690E50100) | EACH | 3 | $300.00 |
| 43 | Riprap, type D (601E11000) | SY | 26 | $980.00 |
| 44 | Tied concrete block mat with type 1 underlayment (601E21050) | SY | 61 | $250.00 |
| 45 | Tied concrete block mat with type 2 underlayment (601E21060) | SY | 401 | $100.00 |
| 46 | Rock channel protection, type B with filter (601E32100) | CY | 135 | $140.00 |
| 47 | Rock channel protection, type C with filter (601E32200) | CY | 107 | $150.00 |
| 48 | Rock channel protection, type D with filter (601E32300) | CY | 786 | $170.00 |
| 49 | Soil analysis test (659E00100) | EACH | 12 | $25.00 |
| 50 | Topsoil (659E00300) | CY | 11,852 | $11.00 |
| 51 | Seeding and mulching (659E10000) | SY | 547,116 | $0.60 |
| 52 | Seeding and mulching, as per plan (659E10001) | SY | 92,645 | $0.55 |
| 53 | Repair seeding and mulching (659E14000) | SY | 27,358 | $0.60 |
| 54 | Inter-seeding (659E15000) | SY | 27,358 | $0.01 |
| 55 | Commercial fertilizer (659E20000) | TON | 76.31 | $250.00 |
| 56 | Lime (659E31000) | ACRE | 113.05 | $25.00 |
| 57 | Water (659E35000) | MGAL | 2,216 | $0.01 |
| 58 | Mowing (659E40000) | MSF | 137 | $1.00 |
| 59 | Ditch erosion protection (670E00700) | SY | 122,488 | $1.15 |
| 60 | Storm water pollution prevention plan (832E15000) | LS | 1 | $9,500.00 |
| 61 | Storm water pollution prevention inspections (832E15002) | LS | 1 | $50,000 |
| 62 | Storm water pollution prevention inspection software (832E15010) | LS | 1 | $43,000 |
| 63 | Erosion control (832E30000) | EACH | 1,139,504 | $1.00 |
| 64 | Seeding and erosion control with turf reinforcing mat, type 1 (836E10000) | SY | 3,939 | $5.00 |
| 65 | Seeding and erosion control with turf reinforcing mat, type 2 (836E10020) | SY | 2,134 | $4.00 |
| 66 | Seeding and erosion control with turf reinforcing mat, type 3 (836E10030) | SY | 3,675 | $4.50 |
| 67 | Concrete masonry (602E20000) | CY | 57.30 | $5,400.00 |
| 68 | 6" shallow pipe underdrains (605E11100) | FT | 31,432 | $14.00 |
| 69 | 6" unclassified pipe underdrains (605E13300) | FT | 5,820 | $20.00 |
| 70 | 6" unclassified pipe underdrains for springs (605E13402) | FT | 44 | $30.00 |
| 71 | 6" rock cut underdrains (605E13500) | FT | 16,232 | $18.00 |
| 72 | 6" base pipe underdrains (605E14000) | FT | 24,434 | $14.00 |
| 73 | Aggregate drains (605E31100) | FT | 952 | $21.00 |
| 74 | Aggregate drains for springs (605E32200) | FT | 44 | $16.00 |
| 75 | 6" conduit, type F for underdrain outlets (611E00510) | FT | 5,197 | $50.00 |
| 76 | 6" conduit, type B (611E00900) | FT | 100 | $54.00 |
| 77 | 6" conduit, type E (611E01400) | FT | 100 | $54.00 |
| 78 | 6" conduit, type E (611E01400) | FT | 19,160 | $6.00 |
| 79 | 6" conduit, type F (611E01500) | FT | 100 | $54.00 |
| 80 | 6" conduit, type F (611E01500) | FT | 3,433 | $42.00 |
| 81 | 12" conduit, type B (611E04400) | FT | 1,254 | $225.00 |
| 82 | 12" conduit, type C (611E04600) | FT | 1,152 | $163.00 |
| 83 | 12" conduit, type D (611E04900) | FT | 50 | $185.00 |
| 84 | 15" conduit, type B (611E05900) | FT | 69 | $205.00 |
| 85 | 15" conduit, type C (611E06100) | FT | 6,798 | $155.00 |
| 86 | 18" conduit, type B (611E07400) | FT | 1,658 | $260.00 |
| 87 | 18" conduit, type C (611E07600) | FT | 280 | $196.00 |
| 88 | 24" conduit, type A (611E10200) | FT | 336 | $250.00 |
| 89 | 24" conduit, type A (611E10200) | FT | 209 | $240.00 |
| 90 | 24" conduit, type B (611E10400) | FT | 402 | $255.00 |
| 91 | 30" conduit, type A, 706.02, or 36" type A, 707.02 (611E13200) | FT | 281 | $330.00 |
| 92 | 30" conduit, type B (611E13400) | FT | 17 | $475.00 |
| 93 | 36" conduit, type A (611E16200) | FT | 764 | $466.00 |
| 94 | 36" conduit, type B (611E16400) | FT | 186 | $350.00 |
| 95 | 42" conduit, type A, 707.02 (0.064) aluminized, 70 (611E19200) | FT | 452 | $380.00 |
| 96 | 48" conduit, type A, 706.02, or 54" type A, 707.02 (611E20700) | FT | 260 | $430.00 |
| 97 | 48" conduit, type C (611E21100) | FT | 256 | $470.00 |
| 98 | 54" conduit, type B (611E22400) | FT | 280 | $610.00 |
| 99 | Catch basin, no. 3A (611E98180) | EACH | 2 | $8,000.00 |
| 100 | Catch basin, no. 4 (611E98230) | EACH | 42 | $10,000 |
| 101 | Catch basin, no. 5 (611E98300) | EACH | 1 | $14,000 |
| 102 | Catch basin, no. 2-2B (611E98470) | EACH | 2 | $4,600.00 |
| 103 | Catch basin, no. 2-2C, as per plan (611E98505) | EACH | 23 | $5,100.00 |
| 104 | Catch basin, no. 2-3 (611E98510) | EACH | 1 | $5,500.00 |
| 105 | Catch basin, no. 2-5 (611E98570) | EACH | 2 | $10,500 |
| 106 | Precast reinforced concrete outlet (611E99710) | EACH | 129 | $850.00 |
| 107 | Junction chamber, as per plan (611E99731) | EACH | 2 | $56,000 |
| 108 | Cured-in-place pipe liner (42" diameter) (899E10000) | FT | 1,818 | $420.00 |
| 109 | Cured-in-place pipe liner (54" diameter) (899E10000) | FT | 245 | $550.00 |
| 110 | Partial depth pavement repair (441) (251E01010) | CY | 262 | $375.00 |
| 111 | Full depth pavement sawing (252E01500) | FT | 26,329 | $1.54 |
| 112 | Pavement planing, asphalt concrete (1.5" thickness (254E01000) | SY | 1,143 | $15.00 |
| 113 | Full depth pavement removal and rigid replacement, type 1, class QC1 (255E11000) | SY | 369 | $432.87 |
| 114 | Full depth pavement sawing (255E20000) | FT | 2,976 | $1.54 |
| 115 | Asphalt concrete base, PG64-22, (449) (301E56000) | CY | 4 | $2,000.00 |
| 116 | Asphalt concrete base, PG64-22, (449) (302E56000) | CY | 21,821 | $186.75 |
| 117 | Aggregate base (304E20000) | CY | 27,349 | $95.00 |
| 118 | Tack coat, 702.13 (407E13900) | GAL | 7,824 | $4.05 |
| 119 | Non-tracking tack coat (407E20000) | GAL | 22,061 | $4.40 |
| 120 | Stabilized crushed aggregate (411E10000) | CY | 593 | $150.00 |
| 121 | Asphalt concrete surface course, type 1, (448), PG64-22 (441E50000) | CY | 48 | $265.00 |
| 122 | Asphalt concrete intermediate course, type 1, (449), as per plan (441E70201) | CY | 40 | $675.00 |
| 123 | Asphalt concrete surface course, type 1, (449), (driveways) (441E70500) | CY | 18 | $335.00 |
| 124 | Asphalt concrete intermediate course, type 1, (449), (under guardrail) (441E70800) | CY | 909 | $320.00 |
| 125 | Asphalt concrete surface course, 12.5 MM, type A (446) (442E10000) | CY | 1,081 | $247.00 |
| 126 | Asphalt concrete intermediate course, 12.5 MM, type A (446) (442E10080) | CY | 7,549 | $207.00 |
| 127 | Asphalt concrete intermediate course, 19 MM, type A (446) (442E10100) | CY | 5,700 | $200.00 |
| 128 | Asphalt concrete surface course, 12.5 MM, type A (447) (442E10300) | CY | 8,848 | $240.00 |
| 129 | Curb, type 4-C (609E24510) | FT | 64 | $110.00 |
| 130 | 9" concrete traffic island (609E60000) | CY | 29 | $715.00 |
| 131 | Compacted aggregate (617E10100) | CY | 338 | $180.00 |
| 132 | Shoulder preparation (617E20000) | SY | 8,550 | $2.40 |
| 133 | Rumble strips, shoulder (asphalt concrete) (618E40600) | MI | 18 | $1,058.33 |
| 134 | Connection, fused pull apart (625E00450) | EACH | 76 | $220.00 |
| 135 | Connection, unfused permanent (625E00480) | EACH | 120 | $180.00 |
| 136 | Light pole, conventional: AT15B40 (625E10490) | EACH | 6 | $5,800.00 |
| 137 | Light pole, conventional: AT22B40 (625E10490) | EACH | 32 | $6,000.00 |
| 138 | Light pole foundation, 24" X 8' deep (625E14100) | EACH | 38 | $3,800.00 |
| 139 | No. 4 AWG 2400 volt distribution cable (625E23200) | FT | 2,529 | $5.00 |
| 140 | No. 10 AWG pole and bracket cable (625E23400) | FT | 7,512 | $2.50 |
| 141 | 1-1/2" duct cable with three no. 4 AWG 2400 volt cables (625E24320) | FT | 19,057 | $15.00 |
| 142 | Conduit, 3", 725.04 (625E25500) | FT | 115 | $63.00 |
| 143 | Conduit, concrete encased, 3" (625E25802) | FT | 548 | $45.00 |
| 144 | Luminaire, conventional, solid state (LED), as per plan (625E26253) | EACH | 19 | $700.00 |
| 145 | Luminaire, conventional, solid state (LED), as per plan (625E26253) | EACH | 19 | $700.00 |
| 146 | Trench, 24" deep (625E29002) | FT | 19,090 | $7.00 |
| 147 | Pull box, 725.08, 18" (625E30700) | EACH | 36 | $2,100.00 |
| 148 | Pull box, 725.08, 24" (625E30706) | EACH | 4 | $3,100.00 |
| 149 | Pull box removed (625E31510) | EACH | 6 | $495.00 |
| 150 | Ground rod (625E32000) | EACH | 38 | $425.00 |
| 151 | Power service, as per plan (625E34001) | EACH | 4 | $15,000 |
| 152 | Underground warning marking tape (625E36010) | FT | 19,090 | $1.90 |
| 153 | Special - maintain existing lighting (625E40000) | LS | 1 | $53,000 |
| 154 | Light pole removed (625E75400) | EACH | 4 | $1,200.00 |
| 155 | Light pole foundation removed (625E75500) | EACH | 4 | $630.00 |
| 156 | Luminaire removed, as per plan (625E75507) | EACH | 4 | $240.00 |
| 157 | Power service removed (625E75510) | EACH | 2 | $4,900.00 |
| 158 | Distribution cable removed (625E75550) | FT | 362 | $4.50 |
| 159 | Distribution cable removed, as per plan (625E75551) | FT | 366 | $4.50 |
| 160 | Disconnect circuit (625E75800) | EACH | 2 | $175.00 |
| 161 | Arc flash calculations and label: at CC (625E76000) | EACH | 4 | $1,100.00 |
| 162 | Delineator, post ground mounted (620E00500) | EACH | 364 | $52.00 |
| 163 | RPM (621E00100) | EACH | 608 | $38.00 |
| 164 | Raised pavement marker removed (621E54000) | EACH | 396 | $34.56 |
| 165 | Barrier reflector, type 2, BI-directional (626E00110) | EACH | 205 | $11.00 |
| 166 | Barrier reflector, type 2, one way (626E00110) | EACH | 419 | $10.00 |
| 167 | Ground mounted support, no. 2 post (630E02100) | FT | 462 | $9.00 |
| 168 | Ground mounted support, no. 3 post (630E03100) | FT | 696 | $10.50 |
| 169 | Ground mounted support, no. 4 post (630E04100) | FT | 626.60 | $14.50 |
| 170 | Ground mounted structural beam support, W6X9 (630E06500) | FT | 228.90 | $23.00 |
| 171 | Ground mounted structural beam support, W10X22 (630E07500) | FT | 92 | $45.00 |
| 172 | Ground mounted structural beam support, W10X12 (630E07600) | FT | 203.30 | $28.00 |
| 173 | Ground mounted structural beam support, W12X30 (630E08000) | FT | 540.20 | $59.00 |
| 174 | One way support, no. 3 post (630E08004) | FT | 207 | $14.00 |
| 175 | Sign post reflector (630E08600) | EACH | 49 | $28.00 |
| 176 | Breakaway structural beam connection (630E09000) | EACH | 26 | $750.00 |
| 177 | Sign, flat sheet (630E80100) | SF | 1,077.80 | $14.50 |
| 178 | Sign, ground mounted extrusheet (630E80200) | SF | 2,984 | $20.00 |
| 179 | Ground mounted structural beam support foundation (630E84500) | EACH | 46 | $1,850.00 |
| 180 | Removal of ground mounted sign and disposal (630E84900) | EACH | 89 | $15.00 |
| 181 | Removal of ground mounted major sign and disposal (630E85400) | EACH | 2 | $150.00 |
| 182 | Removal of ground mounted post support and disposal (630E86002) | EACH | 111 | $20.00 |
| 183 | Removal of ground mounted structural beam support (630E86102) | EACH | 2 | $250.00 |
| 184 | Removal of ground mounted wooden box beam support (630E86292) | EACH | 3 | $250.00 |
| 185 | Removal of overhead mounted sign and disposal (630E87400) | EACH | 1 | $400.00 |
| 186 | Removal of overhead sign support and disposal (630E89702) | EACH | 1 | $3,000.00 |
| 187 | Removal of pavement marking (642E30000) | FT | 52,309 | $0.25 |
| 188 | Edge line, 6" (644E00104) | MI | 1.50 | $5,250.00 |
| 189 | Center line (644E00300) | MI | 0.76 | $9,165.00 |
| 190 | Stop line (644E00500) | FT | 154 | $9.30 |
| 191 | Chevron marking (644E00720) | FT | 784 | $9.30 |
| 192 | Island marking (644E00900) | SF | 88 | $3.50 |
| 193 | Wrong way arrow (644E01360) | EACH | 4 | $180.00 |
| 194 | Wet reflective thermoplastic pavement marking, edge line, 6" (807E14010) | MI | 24.63 | $5,250.00 |
| 195 | Wet reflective thermoplastic pavement marking, lane line, 6" (807E14110) | MI | 10.02 | $2,493.00 |
| 196 | Wet reflective thermoplastic pavement marking, channelizing line, 12" (807E14310) | FT | 5,430 | $2.90 |
| 197 | Wet reflective thermoplastic pavement marking, dotted line, 6" (807E14410) | FT | 6,940 | $1.00 |
| 198 | Grooving for 6" recessed pavement marking, (asphalt) (850E10010) | MI | 34.65 | $1,765.00 |
| 199 | Grooving for 6" recessed pavement marking, (asphalt) (850E10110) | FT | 6,940 | $1.25 |
| 200 | Grooving for 12" recessed pavement marking, (asphalt) (850E10130) | FT | 5,430 | $1.50 |
| 201 | Conduit, 2", 725.051 (625E25408) | FT | 148 | $23.00 |
| 202 | Trench, 36" deep (625E29100) | FT | 148 | $24.00 |
| 203 | Pull box, 725.08, 18" (625E30700) | EACH | 2 | $2,300.00 |
| 204 | Ground rod (625E32000) | EACH | 1 | $425.00 |
| 205 | Power cable, 1 conductor, no. 8 AWG (632E67190) | FT | 173 | $16.00 |
| 206 | Power cable, 2 conductor, no. 4 AWG (632E69200) | FT | 173 | $19.00 |
| 207 | Power service, as per plan (632E70001) | EACH | 1 | $15,000 |
| 208 | Traffic compacted surface, type A or B (410E12000) | CY | 681 | $225.00 |
| 209 | Law enforcement officer with patrol car for assistance (614E11110) | HR | 360 | $120.00 |
| 210 | Increased barrier delineation (614E11630) | FT | 12,822 | $0.85 |
| 211 | Work zone impact attenuator, 24" wide hazards, (unidirectional) (614E12380) | EACH | 11 | $4,000.00 |
| 212 | Detour signing (614E12420) | LS | 1 | $64,000 |
| 213 | Detour signing (614E12420) | LS | 1 | $48,000 |
| 214 | Replacement sign (614E12500) | EACH | 28 | $590.00 |
| 215 | Replacement drum (614E12600) | EACH | 400 | $80.00 |
| 216 | Work zone crossover lighting system (614E12756) | EACH | 1 | $82,000 |
| 217 | Asphalt concrete for maintaining traffic (614E13000) | CY | 106 | $360.00 |
| 218 | Barrier reflector, type 1 one-way (614E13310) | EACH | 34 | $10.00 |
| 219 | Barrier reflector, type 3 one-way (614E13314) | EACH | 265 | $22.00 |
| 220 | Object marker, one way (614E13350) | EACH | 556 | $22.00 |
| 221 | Portable changeable message sign, as per plan (614E18601) | SNMT | 144 | $800.00 |
| 222 | Work zone lane line, class I, 6", 642 paint (614E20110) | MI | 18 | $930.00 |
| 223 | Work zone center line, class I, 642 paint (614E21100) | MI | 8.23 | $970.00 |
| 224 | Work zone edge line, class I, 6", 642 paint (614E22110) | MI | 108.30 | $825.00 |
| 225 | Work zone channelizing line, class I, 12", 642 paint (614E23210) | FT | 28,175 | $0.65 |
| 226 | Work zone dotted line, class I, 6", 642 paint (614E24202) | FT | 27,242 | $1.00 |
| 227 | Work zone stop line, class I, 642 paint (614E26200) | FT | 570 | $15.00 |
| 228 | Roads for maintaining traffic (615E10000) | LS | 1 | $85,000 |
| 229 | Pavement for maintaining traffic, class A (615E20000) | SY | 1,412 | $55.00 |
| 230 | Water (616E10000) | MGAL | 14,284 | $62.00 |
| 231 | Portable barrier, unanchored (622E41100) | FT | 15,341 | $21.00 |
| 232 | Portable barrier, anchored (622E41110) | FT | 300 | $100.00 |
| 233 | Unclassified excavation (503E21100) | CY | 290 | $95.00 |
| 234 | Shale excavation (503E31120) | CY | 115 | $95.00 |
| 235 | Pile driving equipment mobilization (505E11100) | LS | 1 | $20,000 |
| 236 | Steel piles HP14X73, furnished (507E00300) | FT | 1,040 | $90.00 |
| 237 | Steel piles HP14X73, driven (507E00350) | FT | 910 | $25.00 |
| 238 | Epoxy coated steel reinforcement (509E10000) | LB | 159,194 | $2.00 |
| 239 | No. 4 deformed GFRP reinforcement (509E30020) | FT | 9,267 | $3.00 |
| 240 | Semi-integral diaphragm guide (511E33500) | EACH | 2 | $4,000.00 |
| 241 | Class QC2 concrete with QC/QA, bridge deck, as per plan (511E34447) | CY | 311 | $1,300.00 |
| 242 | Class QC2 concrete with QC/QA, bridge deck (parapet) (511E34450) | CY | 96 | $900.00 |
| 243 | Class QC1 concrete with QC/QA, pier above footings (511E41012) | CY | 31 | $2,400.00 |
| 244 | Class QC1 concrete with QC/QA, abutment not including footing (511E44112) | CY | 192 | $1,300.00 |
| 245 | Class QC1 concrete with QC/QA, footing (511E46512) | CY | 277 | $1,000.00 |
| 246 | Sealing of concrete surfaces (epoxy-urethane) (512E10100) | SY | 1,080 | $27.00 |
| 247 | Sealing concrete bridge decks with HMWM resin (512E10300) | SY | 1,074 | $17.00 |
| 248 | Type 2 waterproofing (512E33000) | SY | 23 | $50.00 |
| 249 | Structural steel members, level 4 (513E10280) | LB | 522,869 | $2.50 |
| 250 | Welded stud shear connectors (513E20000) | EACH | 3,660 | $7.00 |
| 251 | Field painting structural steel, intermediate coat (514E00060) | SF | 20,600 | $10.00 |
| 252 | Field painting structural steel, finish coat (514E00066) | SF | 20,600 | $4.25 |
| 253 | Final inspection repair (514E10000) | EACH | 20 | $1.00 |
| 254 | Armorless preformed joint seal (516E10010) | FT | 68 | $80.00 |
| 255 | 1" preformed expansion joint filler (516E13600) | SF | 18 | $16.00 |
| 256 | 2" preformed expansion joint filler (516E13900) | SF | 79 | $20.00 |
| 257 | Semi-integral abutment expansion joint seal (516E14020) | FT | 112 | $75.00 |
| 258 | Elastomeric bearing with internal laminates and load plate, as per plan (516E44201) | EACH | 5 | $3,700.00 |
| 259 | Elastomeric bearing with internal laminates and load plate, as per plan (516E44401) | EACH | 10 | $4,700.00 |
| 260 | Porous backfill with geotextile fabric (518E21200) | CY | 197 | $130.00 |
| 261 | 6" perforated corrugated plastic pipe (518E40000) | FT | 195 | $20.00 |
| 262 | 6" non-perforated corrugated plastic pipe, including specials, as per plan (518E40011) | FT | 40 | $75.00 |
| 263 | Reinforced concrete approach slabs with QC/QA (T=1 (526E30010) | SY | 223 | $400.00 |
| 264 | Type C installation (526E90030) | FT | 68 | $450.00 |
| 265 | Rock channel protection, type C without filter (601E34200) | CY | 133 | $160.00 |
| 266 | Excavation (203E10000) | CY | 1,804 | $13.00 |
| 267 | Granular material, type C (203E35120) | CY | 1,804 | $140.00 |
| 268 | Unclassified excavation (503E21300) | LS | 1 | $135,000 |
| 269 | Pile driving equipment mobilization (505E11100) | LS | 1 | $40,000 |
| 270 | Steel piles HP14X73, furnished (507E00300) | FT | 1,335 | $90.00 |
| 271 | Steel piles HP14X73, driven (507E00350) | FT | 1,145 | $25.00 |
| 272 | Epoxy coated steel reinforcement (509E10000) | LB | 165,848 | $2.00 |
| 273 | No. 4 deformed GFRP reinforcement (509E30020) | FT | 7,801 | $3.00 |
| 274 | Class QC2 concrete with QC/QA, bridge deck (511E34446) | CY | 524 | $1,300.00 |
| 275 | Class QC2 concrete with QC/QA, bridge deck (parapet) (511E34450) | CY | 82 | $900.00 |
| 276 | Class QC1 concrete with QC/QA, pier above footings (511E41012) | CY | 65 | $1,900.00 |
| 277 | Class QC1 concrete with QC/QA, abutment including footing (511E43512) | CY | 174 | $1,200.00 |
| 278 | Class QC1 concrete with QC/QA, footing (511E46512) | CY | 42 | $1,000.00 |
| 279 | Sealing of concrete surfaces (epoxy-urethane) (512E10100) | SY | 1,366 | $21.93 |
| 280 | Sealing concrete bridge decks with HMWM resin (512E10300) | SY | 1,568 | $17.00 |
| 281 | Draped strand prestressed concrete bridge I-beam members, level 3, type WF66-49 (515E15120) | EACH | 12 | $125,000 |
| 282 | Intermediate diaphragms (515E20000) | EACH | 30 | $4,000.00 |
| 283 | Armorless preformed joint seal (516E10010) | FT | 98 | $80.00 |
| 284 | 1/2" preformed expansion joint filler (516E13200) | SF | 104 | $10.00 |
| 285 | 1" preformed expansion joint filler (516E13600) | SF | 104 | $16.00 |
| 286 | 2" preformed expansion joint filler (516E13900) | SF | 79 | $20.00 |
| 287 | Integral abutment expansion joint seal (516E14014) | FT | 141 | $75.00 |
| 288 | Elastomeric bearing with internal laminates and load plate, as per plan (516E44001) | EACH | 12 | $4,700.00 |
| 289 | Elastomeric bearing with internal laminates and load plate (516E44200) | EACH | 12 | $3,700.00 |
| 290 | Porous backfill with geotextile fabric (518E21200) | CY | 116 | $130.00 |
| 291 | 6" perforated corrugated plastic pipe (518E40000) | FT | 157 | $20.00 |
| 292 | 6" perforated corrugated plastic pipe, as per plan (518E40001) | FT | 340 | $20.00 |
| 293 | 6" non-perforated corrugated plastic pipe, including specials, as per plan (518E40011) | FT | 80 | $50.00 |
| 294 | Reinforced concrete approach slabs with QC/QA (T=1 (526E25010) | SY | 250 | $400.00 |
| 295 | Type C installation (526E90030) | FT | 98 | $450.00 |
| 296 | Rock channel protection, type C without filter (601E34200) | CY | 389 | $160.00 |
| 297 | Department'S share of the dispute resolution advisor (100E51200) | EACH | 115,000 | $1.00 |
| 298 | Premium for contract performance bond and for payment bond (103E05000) | LS | 1 | $300,000 |
| 299 | CPM progress schedule (108E10000) | LS | 1 | $10,000 |
| 300 | Special - departments share facilitated partnering costs (111E10100) | EACH | 12,250 | $1.00 |
| 301 | Maintaining traffic (614E11000) | LS | 1 | $1,060,000 |
| 302 | Field office, type C (619E16020) | MNTH | 54 | $2,800.00 |
| 303 | Construction layout stakes and surveying (623E10000) | LS | 1 | $540,000 |
| 304 | Mobilization (624E10000) | LS | 1 | $3,060,000 |
| 400 | Manhole, no. 3 (611E99574) | EACH | 1 | $9,600.00 |
| 401 | Anti-segregation equipment (442E00100) | CY | 16,397 | $7.25 |