ODOT contract 260405 bid tabulation
DEL-US 36-00.00 (MAJOR RECONSTRUCTION). Let by Ohio DOT on October 1, 2026, DEL. 3 bids received; low bid $17,654,157 by Shelly & Sands Inc, +1.7% against the engineer's estimate of $17,363,000.
- Owner
- Ohio DOT
- Letting
- 01 OCT 2026
- Pay items
- 186
- Data through
- 12 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | Shelly & Sands Inc | $17,654,157 | Low | +2.0% |
| 2 | Complete General Construction Company | $18,904,071 | +7.0% | +9.0% |
| 3 | Miller Bros Const Inc | $20,363,649 | +15% | +17% |
Engineer's estimate: $17,363,000.
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Shelly & Sands Inc | 2. Complete General Construction Company | 3. Miller Bros Const Inc |
|---|---|---|---|---|---|---|
| 1 | Clearing and grubbing (201E11000) | LS | 1 | $60,000 | $60,000 | $200,000 |
| 2 | Structure removed (202E11100) | CY | 1 | $630.00 | $1,500.00 | $664.25 |
| 3 | Headwall removed (202E20010) | EACH | 24 | $630.44 | $690.00 | $515.19 |
| 4 | Pavement removed (202E23000) | SY | 45,305 | $6.00 | $16.50 | $34.00 |
| 5 | Walk removed (202E30000) | SF | 28 | $12.00 | $11.00 | $19.90 |
| 6 | Pipe removed (202E34900) | FT | 3,081 | $25.00 | $32.00 | $29.00 |
| 7 | Pipe removed, 24" and under (202E35100) | FT | 358 | $7.00 | $45.00 | $12.65 |
| 8 | Pipe removed for reuse, over 24" diameter (202E35600) | FT | 8 | $250.00 | $105.00 | $146.55 |
| 9 | Guardrail removed (202E38000) | FT | 8,283 | $2.80 | $2.00 | $2.00 |
| 10 | Catch basin removed (202E58100) | EACH | 4 | $930.00 | $500.00 | $571.60 |
| 11 | Special - pipe cleanout, 24" and under (202E70110) | FT | 331 | $25.00 | $40.00 | $5.00 |
| 12 | Special - pipe cleanout, 27" to 48" (202E70120) | FT | 339 | $20.00 | $60.00 | $10.00 |
| 13 | Fence removed (202E75000) | FT | 3,508 | $3.75 | $3.75 | $10.00 |
| 14 | Gate removed (202E75250) | EACH | 1 | $220.00 | $220.00 | $2,500.00 |
| 15 | Removal misc.:existing block wall (202E98100) | EACH | 2 | $300.00 | $390.00 | $283.85 |
| 16 | Removal misc.:existing rock (202E98100) | EACH | 21 | $55.00 | $92.00 | $30.05 |
| 17 | Removal misc.:private sign (202E98100) | EACH | 9 | $1,000.00 | $550.00 | $130.30 |
| 18 | Removal misc.:removal of post and disposal (202E98100) | EACH | 61 | $60.00 | $80.00 | $92.60 |
| 19 | Removal misc.:existing landscape area (202E98400) | SF | 292 | $3.00 | $11.00 | $2.35 |
| 20 | Excavation (203E10000) | CY | 25,093 | $27.00 | $36.00 | $32.00 |
| 21 | Embankment (203E20000) | CY | 13,259 | $17.00 | $12.00 | $32.00 |
| 22 | Proof rolling (204E45000) | HR | 27 | $300.00 | $375.00 | $350.00 |
| 26 | Guardrail, type MGS with long posts (606E15100) | FT | 7,363 | $26.00 | $26.00 | $24.50 |
| 27 | Guardrail, type MGS, long-span (606E17360) | FT | 100 | $22.40 | $22.40 | $26.00 |
| 28 | Anchor assembly, MGS type B (606E26050) | EACH | 10 | $2,620.00 | $2,620.00 | $2,475.00 |
| 29 | Anchor assembly, MGS type E (MASH 2016) (606E26150) | EACH | 10 | $2,580.00 | $2,580.00 | $2,600.00 |
| 30 | Anchor assembly, MGS type T (606E26550) | EACH | 3 | $1,395.00 | $1,395.00 | $1,450.00 |
| 31 | MGS bridge terminal assembly, type 1 (606E35002) | EACH | 8 | $2,650.00 | $2,650.00 | $2,350.00 |
| 32 | 4" concrete walk (608E10000) | SF | 34 | $30.00 | $29.00 | $38.05 |
| 33 | Special - mailbox support (690E50000) | EACH | 56 | $200.00 | $195.00 | $200.00 |
| 34 | Tied concrete block mat with type 1 underlayment (601E21050) | SY | 260 | $160.00 | $155.00 | $217.70 |
| 35 | Rock channel protection, type C with filter (601E32200) | CY | 48 | $315.00 | $300.00 | $165.55 |
| 36 | Soil analysis test (659E00100) | EACH | 2 | $100.00 | $100.00 | $50.00 |
| 37 | Topsoil (659E00300) | CY | 9,375 | $25.00 | $35.00 | $23.20 |
| 38 | Seeding and mulching (659E10000) | SY | 69,198 | $0.68 | $0.78 | $0.61 |
| 39 | Repair seeding and mulching (659E14000) | SY | 3,460 | $0.68 | $0.78 | $0.61 |
| 40 | Inter-seeding (659E15000) | SY | 3,460 | $0.68 | $0.78 | $0.45 |
| 41 | Commercial fertilizer (659E20000) | TON | 9.34 | $750.00 | $750.00 | $500.00 |
| 42 | Lime (659E31000) | ACRE | 15 | $10.00 | $10.00 | $1.00 |
| 43 | Water (659E35000) | MGAL | 383 | $1.00 | $1.00 | $0.50 |
| 44 | Mowing (659E40000) | MSF | 0.16 | $1,500.00 | $1,500.00 | $25.00 |
| 45 | Vegetated swale erosion protection (670E00200) | SY | 15,250 | $1.85 | $1.85 | $1.53 |
| 46 | Ditch erosion protection (670E00700) | SY | 3,350 | $1.85 | $1.85 | $1.58 |
| 47 | Storm water pollution prevention plan (832E15000) | LS | 1 | $19,000 | $8,500.00 | $8,500.00 |
| 48 | Storm water pollution prevention inspections (832E15002) | LS | 1 | $28,200 | $27,000 | $31,200 |
| 49 | Storm water pollution prevention inspection software (832E15010) | LS | 1 | $18,850 | $19,000 | $18,850 |
| 50 | Erosion control (832E30000) | EACH | 679,600 | $1.00 | $1.00 | $1.00 |
| 51 | Seeding and erosion control with turf reinforcing mat, type 1 (836E10000) | SY | 712 | $5.00 | $5.00 | $1.58 |
| 52 | Concrete masonry (602E20000) | CY | 18 | $3,500.00 | $2,500.00 | $3,889.15 |
| 53 | 4" base pipe underdrains (605E06000) | FT | 53,304 | $6.00 | $9.00 | $6.50 |
| 54 | 4" conduit, type B (611E00100) | FT | 50 | $24.00 | $22.00 | $29.30 |
| 55 | 4" conduit, type E (611E00400) | FT | 50 | $24.00 | $20.00 | $20.30 |
| 56 | 4" conduit, type F (611E00406) | FT | 50 | $24.00 | $20.00 | $20.30 |
| 57 | 4" conduit, type F for underdrain outlet (611E00410) | FT | 988 | $42.00 | $25.00 | $34.25 |
| 58 | 8" conduit, type F (611E02600) | FT | 8 | $85.00 | $35.00 | $69.45 |
| 59 | 12" conduit, type B (611E04400) | FT | 145 | $98.00 | $165.00 | $118.45 |
| 60 | 12" conduit, type C (611E04600) | FT | 175 | $88.00 | $80.00 | $86.90 |
| 61 | 12" conduit, type D (611E04900) | FT | 3,045 | $60.00 | $95.00 | $58.75 |
| 62 | 15" conduit, type A (611E05700) | FT | 47 | $170.00 | $210.00 | $159.65 |
| 63 | 15" conduit, type A (611E05700) | FT | 68 | $150.00 | $190.00 | $135.35 |
| 64 | 15" conduit, type B (611E05900) | FT | 347 | $115.00 | $160.00 | $124.05 |
| 65 | 15" conduit, type D (611E06400) | FT | 559 | $73.00 | $100.00 | $66.85 |
| 66 | 18" conduit, type A (611E07200) | FT | 50 | $180.00 | $250.00 | $188.00 |
| 67 | 18" conduit, type A (611E07200) | FT | 112 | $170.00 | $240.00 | $186.10 |
| 68 | 18" conduit, type A (611E07200) | FT | 68 | $160.00 | $200.00 | $195.10 |
| 69 | 18" conduit, type A (611E07200) | FT | 21 | $200.00 | $150.00 | $130.50 |
| 70 | 18" conduit, type B (611E07400) | FT | 38 | $120.00 | $160.00 | $197.70 |
| 71 | 18" conduit, type D (611E07900) | FT | 196 | $90.00 | $120.00 | $84.60 |
| 72 | 21" conduit, type A (611E08700) | FT | 9 | $320.00 | $250.00 | $357.65 |
| 73 | 21" conduit, type D (611E09400) | FT | 107 | $95.00 | $150.00 | $110.15 |
| 74 | 24" conduit, type A (611E10200) | FT | 59 | $41.00 | $280.00 | $252.65 |
| 75 | 24" conduit, type A (611E10200) | FT | 100 | $195.00 | $230.00 | $246.85 |
| 76 | 24" conduit, type A (611E10200) | FT | 52 | $200.00 | $280.00 | $210.60 |
| 77 | 24" conduit, type A (611E10200) | FT | 59 | $185.00 | $275.00 | $256.15 |
| 78 | 24" conduit, type A (611E10200) | FT | 51 | $200.00 | $275.00 | $234.95 |
| 79 | 24" conduit, type A (611E10200) | FT | 14 | $200.00 | $300.00 | $310.45 |
| 80 | 24" conduit, type A (611E10200) | FT | 18 | $300.00 | $285.00 | $468.70 |
| 81 | 24" conduit, type B (611E10400) | FT | 8 | $150.00 | $300.00 | $382.10 |
| 82 | 30" conduit, type A, 706.02 (611E13200) | FT | 47 | $200.00 | $400.00 | $608.50 |
| 83 | 30" conduit, type A, 706.02, 707.65 (611E13200) | FT | 52 | $270.00 | $345.00 | $259.10 |
| 84 | 30" conduit, type A, 706.02, 707.65, 36" 707.01 AL (611E13200) | FT | 53 | $270.00 | $350.00 | $269.90 |
| 85 | Catch basin, no. 2-2B (611E98470) | EACH | 4 | $4,000.00 | $2,600.00 | $2,181.50 |
| 86 | Precast reinforced concrete outlet (611E99710) | EACH | 134 | $560.00 | $350.00 | $688.50 |
| 87 | Drainage structure, misc.:adjust drain tile riser (611E99900) | EACH | 1 | $800.00 | $500.00 | $301.10 |
| 88 | Partial depth pavement repair (441), as per plan (251E01001) | SY | 3,000 | $75.00 | $78.75 | $78.75 |
| 89 | Partial depth pavement repair (442) (251E01030) | CY | 56 | $592.00 | $585.00 | $585.00 |
| 90 | Pavement planing, asphalt concrete (0"-2.5" depth) (254E01000) | SY | 88,908 | $3.50 | $3.55 | $3.55 |
| 91 | Asphalt concrete base, PG64-22, (449) (301E56000) | CY | 10,568 | $185.00 | $156.00 | $156.00 |
| 92 | Aggregate base (304E20000) | CY | 15,631 | $71.00 | $80.00 | $77.00 |
| 94 | Tack coat (407E10000) | GAL | 534 | $3.50 | $4.50 | $4.50 |
| 95 | Non-tracking tack coat (407E20000) | GAL | 20,302 | $3.50 | $4.43 | $4.43 |
| 96 | Prime coat (408E10000) | GAL | 534 | $7.00 | $5.00 | $5.00 |
| 97 | Asphalt concrete surface course, type 1, (446), PG64-22 (441E10000) | CY | 6,076 | $230.00 | $214.25 | $214.25 |
| 98 | Asphalt concrete intermediate course, type 2, (446) (441E10200) | CY | 8,070 | $205.00 | $184.50 | $184.50 |
| 99 | Asphalt concrete surface course, type 1, (449), PG64-22 (441E70000) | CY | 278 | $300.00 | $229.25 | $229.25 |
| 100 | Compacted aggregate (617E10100) | CY | 248 | $150.00 | $85.00 | $85.00 |
| 101 | Water (617E25000) | MGAL | 10 | $100.00 | $100.00 | $60.45 |
| 102 | Rumble stripes, edge line (asphalt concrete) (618E41000) | MI | 14 | $492.00 | $1,795.00 | $2,495.00 |
| 103 | Rumble stripes, center line (asphalt concrete) (618E43000) | MI | 7 | $1,583.00 | $1,795.00 | $2,995.00 |
| 104 | Longitudinal joint preparation (874E21000) | MI | 7 | $4,000.00 | $9,500.00 | $9,500.00 |
| 105 | Service box adjusted to grade (638E10900) | EACH | 1 | $800.00 | $150.00 | $543.80 |
| 106 | RPM (621E00100) | EACH | 529 | $39.00 | $39.00 | $35.60 |
| 107 | Raised pavement marker removed (621E54000) | EACH | 529 | $12.00 | $15.00 | $23.45 |
| 108 | Ground mounted support, no. 2 post (630E02100) | FT | 1,066 | $15.50 | $15.50 | $12.50 |
| 109 | Ground mounted support, no. 3 post (630E03100) | FT | 157 | $17.00 | $17.00 | $13.50 |
| 110 | Sign, flat sheet (630E80100) | SF | 700.40 | $20.00 | $20.00 | $21.50 |
| 111 | Removal of ground mounted sign and disposal (630E84900) | EACH | 146 | $10.00 | $10.00 | $20.00 |
| 112 | Removal of ground mounted post support and disposal (630E86002) | EACH | 118 | $15.00 | $15.00 | $20.00 |
| 113 | Edge line, 4", type 1 (642E00100) | MI | 7.60 | $790.00 | $790.00 | $845.00 |
| 114 | Center line, type 1 (642E00300) | MI | 3.80 | $1,390.00 | $1,390.00 | $1,565.00 |
| 115 | Edge line, 6" (644E00104) | MI | 13.70 | $4,260.00 | $4,260.00 | $4,270.00 |
| 116 | Center line (644E00300) | MI | 7.30 | $4,390.00 | $4,390.00 | $3,475.00 |
| 117 | Channelizing line, 8" (644E00400) | FT | 1,502 | $2.40 | $2.40 | $1.50 |
| 118 | Stop line (644E00500) | FT | 193 | $9.00 | $9.00 | $9.40 |
| 119 | Transverse/diagonal line (644E00700) | FT | 133 | $9.00 | $9.00 | $9.15 |
| 120 | Lane arrow (644E01300) | EACH | 18 | $105.00 | $105.00 | $125.00 |
| 121 | Two way left turn arrow (644E01370) | EACH | 3 | $200.00 | $200.00 | $250.00 |
| 122 | Edge line, 6" (646E10010) | MI | 0.20 | $14,500 | $14,500 | $20,085 |
| 123 | Center line (646E10200) | MI | 0.10 | $21,500 | $21,500 | $26,850 |
| 124 | Conduit, 4", 725.04 (625E25600) | FT | 16 | $100.00 | $200.00 | $100.00 |
| 125 | ITS pull box with pad and hinged lid assembly, 32" wide, type 1 (809E01920) | EACH | 2 | $7,500.00 | $8,500.00 | $7,500.00 |
| 126 | Traffic compacted surface, type A (410E10000) | CY | 100 | $66.00 | $117.00 | $35.10 |
| 127 | Traffic compacted surface, type A or B (410E12000) | CY | 400 | $66.00 | $117.00 | $35.05 |
| 128 | Traffic compacted surface, type C (410E13000) | CY | 200 | $94.00 | $121.00 | $55.50 |
| 129 | Law enforcement officer with patrol car for assistance (614E11110) | HR | 740 | $108.00 | $125.00 | $109.30 |
| 130 | Special - work zone traffic signal (614E11300) | EACH | 2 | $49,500 | $52,500 | $49,000 |
| 131 | Increased barrier delineation (614E11630) | FT | 900 | $0.50 | $1.95 | $1.70 |
| 132 | Work zone impact attenuator, 24" wide hazards, (unidirectional) (614E12380) | EACH | 34 | $2,240.00 | $2,240.00 | $1,917.11 |
| 133 | Work zone impact attenuator, 24" wide hazards, (bidirectional) (614E12384) | EACH | 5 | $2,420.00 | $2,420.00 | $2,131.63 |
| 134 | Detour signing (614E12420) | LS | 1 | $30,000 | $75,000 | $50,680 |
| 135 | Replacement sign (614E12500) | EACH | 15 | $225.00 | $350.00 | $239.35 |
| 136 | Replacement drum (614E12600) | EACH | 15 | $50.00 | $80.00 | $55.00 |
| 137 | Work zone raised pavement marker, as per plan (614E12801) | EACH | 200 | $9.00 | $40.00 | $7.31 |
| 138 | Asphalt concrete for maintaining traffic (614E13000) | CY | 102 | $305.00 | $490.00 | $275.00 |
| 139 | Barrier reflector, type 1, (1 way) (614E13310) | EACH | 149 | $9.00 | $7.50 | $10.81 |
| 140 | Barrier reflector, type 2, (bidirectional) (614E13312) | EACH | 20 | $11.00 | $15.50 | $11.63 |
| 141 | Object marker, one way (614E13350) | EACH | 169 | $15.00 | $19.00 | $20.90 |
| 142 | Portable changeable message sign, as per plan (614E18601) | SNMT | 11 | $525.00 | $900.00 | $960.47 |
| 143 | Work zone center line, class I (614E21000) | MI | 20.86 | $995.00 | $995.00 | $1,355.00 |
| 144 | Work zone center line, class III, 642 paint (614E21550) | MI | 7.27 | $995.00 | $995.00 | $1,325.00 |
| 145 | Work zone edge line, class I, 4" (614E22000) | MI | 54.55 | $630.00 | $630.00 | $755.00 |
| 146 | Work zone edge line, class III, 4", 642 paint (614E22350) | MI | 14.54 | $630.00 | $630.00 | $1,195.00 |
| 147 | Work zone channelizing line, class I, 8" (614E23000) | FT | 450 | $0.90 | $0.90 | $0.75 |
| 148 | Work zone dotted line, class I (614E24000) | FT | 216 | $0.90 | $0.90 | $0.50 |
| 149 | Work zone stop line, class I (614E26000) | FT | 494 | $3.50 | $3.50 | $3.50 |
| 150 | Work zone stop line, class III, 642 paint (614E26610) | FT | 150 | $3.50 | $3.50 | $3.40 |
| 151 | Work zone arrow, class I (614E30000) | EACH | 24 | $75.00 | $75.00 | $75.00 |
| 152 | Business entrance sign (614E40050) | EACH | 15 | $330.00 | $400.00 | $175.00 |
| 153 | Roads for maintaining traffic (615E10000) | LS | 1 | $125,000 | $300,000 | $112,963 |
| 154 | Pavement for maintaining traffic, class B (615E25000) | SY | 4,593 | $63.00 | $46.75 | $66.00 |
| 155 | Water (616E10000) | MGAL | 80 | $50.00 | $100.00 | $73.25 |
| 156 | Portable barrier, unanchored (622E41100) | FT | 7,250 | $16.50 | $28.00 | $14.85 |
| 157 | Unclassified excavation (503E21100) | CY | 767 | $40.00 | $150.00 | $55.66 |
| 158 | Portions of structure removed, over 20 foot span, as per plan (202E11203) | LS | 1 | $120,000 | $160,000 | $350,000 |
| 159 | Approach slab removed (202E22900) | SY | 244.50 | $40.00 | $50.00 | $68.51 |
| 160 | Wearing course removed (202E23500) | SY | 999 | $17.00 | $18.00 | $9.45 |
| 161 | Epoxy coated steel reinforcement (509E10000) | LB | 69,449 | $1.50 | $2.00 | $1.48 |
| 162 | Dowel holes with nonshrink, nonmetallic grout (510E10000) | EACH | 170 | $56.00 | $22.00 | $38.67 |
| 163 | Class QC2 concrete, bridge deck (511E34444) | CY | 263 | $1,374.00 | $1,400.00 | $1,349.43 |
| 164 | Sealing of concrete surfaces (epoxy-urethane) (512E10100) | SY | 118 | $49.00 | $46.00 | $57.71 |
| 165 | Structural steel members, level UF (513E10200) | LB | 1,450 | $20.00 | $21.00 | $15.34 |
| 166 | Welded stud shear connectors (513E20000) | EACH | 3,045 | $3.70 | $3.70 | $4.80 |
| 167 | Structural steel, misc.: moment plate retrofits (513E90000) | LB | 2,790 | $22.00 | $22.00 | $18.03 |
| 168 | Surface preparation of existing structural steel (514E00050) | SF | 8,988 | $13.00 | $16.00 | $19.75 |
| 169 | Field painting of existing structural steel, prime coat (514E00056) | SF | 8,988 | $7.00 | $5.00 | $7.85 |
| 170 | Field painting structural steel, intermediate coat (514E00060) | SF | 8,988 | $4.00 | $4.50 | $4.00 |
| 171 | Field painting structural steel, finish coat (514E00066) | SF | 8,988 | $3.00 | $4.50 | $2.00 |
| 172 | Grinding fins, tears, slivers on existing structural steel (514E00504) | MNHR | 15 | $160.00 | $90.00 | $200.00 |
| 173 | Final inspection repair (514E10000) | EACH | 5 | $265.00 | $250.00 | $300.00 |
| 174 | Armorless preformed joint seal (516E10010) | FT | 88 | $101.00 | $95.00 | $47.26 |
| 175 | Railing (three steel tube bridge railing) (517E70100) | FT | 377 | $460.00 | $488.00 | $487.50 |
| 176 | Special - steel drip strip (518E22300) | FT | 346 | $17.00 | $23.00 | $26.55 |
| 177 | Reinforced concrete approach slabs (T=15") (526E25000) | SY | 245 | $525.00 | $450.00 | $508.52 |
| 178 | Type C installation (526E90030) | FT | 88 | $500.00 | $400.00 | $336.34 |
| 179 | Structure grounding system (625E33000) | EACH | 1 | $28,400 | $25,500 | $28,400 |
| 180 | Premium for contract performance bond and for payment bond (103E05000) | LS | 1 | $60,001 | $96,000 | $71,293 |
| 181 | Maintaining traffic (614E11000) | LS | 1 | $700,000 | $625,500 | $799,000 |
| 182 | Construction layout stakes and surveying (623E10000) | LS | 1 | $236,560 | $238,000 | $63,400 |
| 183 | Mobilization (624E10000) | LS | 1 | $800,000 | $950,000 | $1,018,000 |
| 200 | Granular material, type B (203E35110) | CY | 23,068 | $54.00 | $54.00 | $77.00 |
| 201 | Subgrade compaction (204E10000) | SY | 70,015 | $4.00 | $2.20 | $0.50 |
| 202 | Excavation of subgrade (204E13000) | CY | 22,656 | $30.00 | $36.00 | $57.00 |
| 203 | Geotextile fabric (204E50000) | SY | 70,015 | $1.50 | $1.65 | $2.40 |
| 204 | Asphalt concrete intermediate course, type 2, (449) (441E70300) | CY | 76 | $215.00 | $187.25 | $187.25 |
| 205 | Portable barrier, anchored (622E41110) | FT | 180 | $53.00 | $38.00 | $49.85 |
| 206 | Field office, type B (619E16010) | MNTH | 24 | $6,000.00 | $2,250.00 | $3,543.30 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from ODOT's tabulation for this contract. ODOT Official Bid Tabulation PDFs from its public DigitalPaper bid tab cabinet, January 2020 to November 2026 (the source links open after DigitalPaper starts a guest session). ODOT prints unit prices to two decimals but computes line amounts from the full price, so a few bids miss their total and are left out. Descriptions are cut at about 50 characters, as ODOT prints them.
Every contract let that day: ODOT letting of October 1, 2026. Compiled by Mirage Metrics.