TDOT contract CN262018 bid tabulation
The slide mitigation on i-24 wb near mm 137. Let by Tennessee DOT on January 9, 2026, Marion County. 4 bids received; low bid $3,482,063 by Summers-Taylor, Inc..
- Owner
- Tennessee DOT
- Letting
- 09 JAN 2026
- Pay items
- 54
- Data through
- 02 OCT 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | Summers-Taylor, Inc. | $3,482,063 | Low |
| 2 | Jones Bros. Contractors, LLC | $4,188,589 | +20% |
| 3 | Wright Brothers Civil Construction, LLC | $4,283,657 | +23% |
| 4 | Dement Construction Group, LLC | $4,794,339 | +38% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Summers-Taylor, Inc. | 2. Jones Bros. Contractors, LLC | 3. Wright Brothers Civil Construction, LLC | 4. Dement Construction Group, LLC |
|---|---|---|---|---|---|---|---|
| 1 | Construction stakes, lines and grades (105-01) | LS | 1 | $18,200 | $100,000 | $17,000 | $50,000 |
| 2 | Clearing and grubbing (201-01) | LS | 1 | $28,000 | $225,000 | $55,450 | $142,050 |
| 3 | Road & drainage excavation (unclassified) (203-01) | CY | 16,069 | $77.50 | $75.00 | $83.50 | $60.00 |
| 4 | Presplitting of rock excavation (203-01.11) | SY | 3,265 | $68.00 | $42.00 | $110.00 | $280.00 |
| 5 | Furnishing & spreading topsoil (203-07) | CY | 484 | $87.00 | $35.00 | $55.00 | $75.00 |
| 6 | Scaling and trimming (203-11) | SY | 800 | $182.00 | $55.00 | $78.50 | $120.00 |
| 7 | Construction of haul road (203-50) | LS | 1 | $21,000 | $130,000 | $30,000 | $242,000 |
| 8 | Filter sock (8 inch) (209-03.20) | LF | 1,000 | $3.60 | $6.00 | $3.40 | $5.00 |
| 9 | Sediment removal (209-05) | CY | 21 | $54.00 | $75.00 | $49.00 | $200.00 |
| 10 | Temporary silt fence (with backing) (209-08.02) | LF | 525 | $5.70 | $6.00 | $5.95 | $5.90 |
| 11 | Rock check dam (209-08.07) | EACH | 4 | $522.00 | $1,125.00 | $1,225.00 | $1,200.00 |
| 12 | Enhanced rock check dam (209-08.08) | EACH | 1 | $1,270.00 | $1,275.00 | $2,625.00 | $2,000.00 |
| 13 | Mineral aggregate, type A base, grading D (303-01) | TON | 80 | $56.50 | $100.00 | $69.00 | $100.00 |
| 14 | Bituminous material for tack coat (TC) (403-01) | TON | 6 | $1,130.00 | $950.00 | $1,050.00 | $950.00 |
| 15 | Acs mix(PG76-22) grading D (411-03.10) | TON | 900 | $227.00 | $190.00 | $218.00 | $190.00 |
| 16 | Scoring shoulders (continuous) (16IN width) (411-12.01) | LM | 0.80 | $7,170.00 | $10,000 | $4,375.00 | $2,000.00 |
| 17 | Cold planing bituminous pavement (415-01.02) | SY | 12,000 | $6.60 | $5.50 | $6.60 | $5.50 |
| 18 | Class A concrete (pad for 51" barrier wall) (604-03.07) | CY | 79 | $720.00 | $625.00 | $715.00 | $700.00 |
| 19 | Horizontal drains (610-12.02) | LF | 510 | $101.00 | $85.00 | $110.00 | $70.00 |
| 20 | Guardrail transition 27IN to 31IN (705-02.10) | EACH | 1 | $143.00 | $100.00 | $500.00 | $184.00 |
| 21 | Earth pad for type 38 GR end treatment (705-04.09) | EACH | 2 | $1,970.00 | $800.00 | $2,375.00 | $1,826.00 |
| 22 | W beam GR (type 2) MASH TL-3 (705-06.01) | LF | 289 | $37.00 | $32.50 | $29.00 | $50.78 |
| 23 | Tangent energy absorbing term MASH TL-3 (705-06.20) | EACH | 2 | $4,000.00 | $3,750.00 | $3,950.00 | $4,343.00 |
| 24 | Thrie beam bridge transition MASH TL-3 (705-06.25) | EACH | 1 | $3,100.00 | $2,750.00 | $3,600.00 | $2,497.00 |
| 25 | Michigan and modified michigan end shoe (706-10.80) | EACH | 1 | $239.00 | $250.00 | $170.00 | $305.00 |
| 26 | Rock anchor, type I (707-02.43) | LF | 504 | $111.00 | $163.00 | $111.00 | $145.00 |
| 27 | Rockfall drape (type III) (707-10.07) | SY | 4,667 | $97.50 | $120.00 | $110.00 | $165.00 |
| 28 | Machined rip-rap (class A-3) (709-05.05) | TON | 50 | $61.00 | $90.00 | $84.00 | $90.00 |
| 29 | Machined rip-rap (class B) (709-05.08) | TON | 4,627 | $40.50 | $82.00 | $71.00 | $55.00 |
| 30 | 51IN single slope concrete barrier wall (711-05.71) | LF | 800 | $183.00 | $185.00 | $169.00 | $145.00 |
| 31 | Traffic control (712-01) | LS | 1 | $87,000 | $150,000 | $350,000 | $101,800 |
| 32 | Interconnected portable barrier rail (712-02.02) | LF | 1,250 | $53.00 | $50.00 | $0.01 | $75.00 |
| 33 | Temporary work zone crash cushion (MASH TL-3) (712-02.60) | EACH | 1 | $6,000.00 | $11,000 | $5,000.00 | $7,500.00 |
| 34 | Flexible drums (channelizing) (712-04.01) | EACH | 160 | $30.00 | $25.00 | $27.75 | $32.00 |
| 35 | Barrier rail delineator (712-04.50) | EACH | 60 | $15.50 | $13.00 | $13.00 | $12.00 |
| 36 | Warning lights (type A) (712-05.01) | EACH | 160 | $10.00 | $1.00 | $1.00 | $20.00 |
| 37 | Warning lights (type C) (712-05.03) | EACH | 160 | $24.00 | $20.00 | $22.00 | $20.00 |
| 38 | Signs (construction) (712-06) | SF | 460 | $8.00 | $6.50 | $7.25 | $7.50 |
| 39 | Arrow board (type C) (712-08.03) | EACH | 1 | $895.00 | $750.00 | $830.00 | $1,100.00 |
| 40 | Queue protection truck (712-08.11) | HR | 200 | $137.00 | $130.00 | $130.00 | $150.00 |
| 41 | Removable pavement marking (8" barrier line) (712-09.02) | LF | 900 | $5.00 | $4.25 | $4.20 | $4.25 |
| 42 | Flexible delineator (yellow) (713-02.15) | EACH | 75 | $53.50 | $75.00 | $50.00 | $64.00 |
| 43 | Changeable message sign unit (713-16.01) | EACH | 2 | $3,580.00 | $3,000.00 | $3,300.00 | $4,000.00 |
| 44 | Snowplowable raised pavement markers (BI-dir)(2 color) (716-01.23) | EACH | 75 | $119.00 | $35.00 | $69.50 | $100.00 |
| 45 | Removal of snowplowable reflective marker (716-01.30) | EACH | 75 | $30.00 | $16.00 | $27.80 | $25.00 |
| 46 | Removal of pavement marking (line) (716-08.01) | LF | 5,920 | $1.50 | $1.00 | $0.90 | $1.25 |
| 47 | Enhanced flatline thermo PVMT MRKNG (6IN line) (716-12.02) | LM | 3.26 | $10,400 | $7,000.00 | $6,900.00 | $8,700.00 |
| 48 | Enhanced flatline thermo PVMT MRKNG (8IN barrier line) (716-12.03) | LF | 8,500 | $2.50 | $2.00 | $1.60 | $2.00 |
| 49 | Mobilization (717-01) | LS | 1 | $144,000 | $415,000 | $427,680 | $384,750 |
| 50 | Geotextile (type III)(erosion control) (740-10.03) | SY | 86 | $6.90 | $9.00 | $6.00 | $10.00 |
| 51 | Temporary sediment tube 18IN (740-11.03) | LF | 634 | $4.75 | $6.00 | $5.40 | $4.50 |
| 52 | Seeding (with mulch) (801-01) | UNIT | 33 | $59.50 | $85.00 | $68.00 | $65.80 |
| 53 | Water (seeding & sodding) (801-03) | MG | 5 | $239.00 | $100.00 | $113.00 | $200.00 |
| 54 | Sodding (new sod) (803-01) | SY | 2,907 | $7.50 | $6.00 | $6.40 | $6.50 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from TDOT's tabulation for this contract. TDOT Summary of Bids PDFs: every letting posted for February 2024 to October 2026, and nine lettings of 2018 to 2023 recovered from archived copies of the tn.gov files. Cost-plus-time bids, and bids that did not match their published total, are left out.
Every contract let that day: TDOT letting of January 9, 2026. Compiled by Mirage Metrics.