TDOT contract CN262060 bid tabulation
The repair of the bridge on s.r. 60 over the tennessee river (l.m. 3.10). Let by Tennessee DOT on August 14, 2026, Meigs County. 5 bids received; low bid $6,672,928 by Mid-State Construction Company, Inc..
- Owner
- Tennessee DOT
- Letting
- 14 AUG 2026
- Pay items
- 69
- Data through
- 02 OCT 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | Mid-State Construction Company, Inc. | $6,672,928 | Low |
| 2 | Jamison Construction, LLC | $6,856,029 | +3.0% |
| 3 | Louis-Company, LLC | $8,582,807 | +29% |
| 4 | Jones Bros. Contractors, LLC | $9,378,577 | +41% |
| 5 | Southern Road & Bridge, LLC | $13,901,471 | +108% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Mid-State Construction Company, Inc. | 2. Jamison Construction, LLC | 3. Louis-Company, LLC | 4. Jones Bros. Contractors, LLC | 5. Southern Road & Bridge, LLC |
|---|---|---|---|---|---|---|---|---|
| 1 | Construction stakes, lines and grades (105-01) | LS | 1 | $51,300 | $10,000 | $18,423 | $100,000 | $65,000 |
| 2 | Clearing and grubbing (201-01) | LS | 1 | $108,188 | $80,000 | $12,500 | $340,000 | $175,000 |
| 3 | Vegetation removal (201-05.31) | LS | 1 | $9,068.38 | $30,000 | $15,840 | $50,000 | $250,000 |
| 4 | Removal of structures (BR. no. 61-SR060-03.10) (202-04.01) | LS | 1 | $435,791 | $174,500 | $72,380 | $1,000,000 | $25,000 |
| 5 | Road & drainage excavation (unclassified) (203-01) | CY | 2,926 | $57.45 | $75.00 | $13.62 | $120.00 | $68.00 |
| 6 | Dry excavation (bridges) (204-02.01) | CY | 767 | $49.05 | $75.00 | $13.62 | $200.00 | $100.00 |
| 7 | Stream mitigation-step pool (209-03.36) | EACH | 41 | $5,835.70 | $5,200.00 | $1,473.83 | $2,500.00 | $25,000 |
| 8 | Sediment removal (209-05) | CY | 13 | $57.64 | $50.00 | $210.15 | $350.00 | $150.00 |
| 9 | Temporary silt fence (with backing) (209-08.02) | LF | 2,500 | $5.42 | $6.50 | $5.77 | $4.75 | $10.00 |
| 10 | Enhanced rock check dam (209-08.08) | EACH | 7 | $922.24 | $850.00 | $982.55 | $1,000.00 | $1,000.00 |
| 11 | Sandbags (209-09.01) | BAG | 800 | $9.22 | $15.00 | $9.83 | $10.00 | $15.00 |
| 12 | Polyethylene sheeting (6 mil. minimum) (209-20.03) | SY | 34 | $11.53 | $12.00 | $12.28 | $10.00 | $10.00 |
| 13 | Catch basin filter assembly(type 4) (209-40.44) | EACH | 3 | $691.68 | $900.00 | $736.92 | $800.00 | $5,500.00 |
| 14 | Granular backfill (bridges) (303-01.02) | TON | 114 | $59.04 | $75.00 | $55.27 | $200.00 | $200.00 |
| 15 | Mineral aggregate (size 57) (303-10.04) | TON | 1,200 | $51.49 | $72.00 | $49.13 | $100.00 | $150.00 |
| 16 | Asphalt concrete mix (PG70-22) (BPMB-HM) grading A (307-02.01) | TON | 45 | $801.20 | $765.00 | $307.05 | $695.00 | $1,250.00 |
| 17 | Asphalt concrete mix (PG70-22) (BPMB-HM) grading B-M2 (307-02.08) | TON | 133 | $368.90 | $352.00 | $245.64 | $320.00 | $445.00 |
| 18 | Trackless tack coat (403-02.01) | TON | 2 | $1,095.16 | $1,050.00 | $1,473.83 | $950.00 | $2,200.00 |
| 19 | Acs mix(PG70-22) grading D (411-02.10) | TON | 89 | $391.95 | $375.00 | $276.34 | $340.00 | $500.00 |
| 20 | Cold planing bituminous pavement (415-01.02) | SY | 1,350 | $16.14 | $16.00 | $14.74 | $14.00 | $33.00 |
| 21 | Bearing device (repair) (602-10.12) | LS | 1 | $230,214 | $85,000 | $32,082 | $725,000 | $185,000 |
| 22 | Jacking steel spans (602-10.19) | LS | 1 | $151,915 | $102,000 | $195,095 | $729,000 | $225,000 |
| 23 | Painting steel structures (new plates, abt.1) (603-01.01) | LS | 1 | $3,677.43 | $3,300.00 | $10,543 | $3,000.00 | $155,000 |
| 24 | Pavement @ bridge ends (604-03.04) | SY | 248 | $562.74 | $520.00 | $578.45 | $1,500.00 | $1,500.00 |
| 25 | Class D concrete (604-03.30) | CY | 17 | $4,005.02 | $4,000.00 | $3,710.34 | $10,000 | $25,000 |
| 26 | Applied texture finish (existing structures) (604-04.02) | SY | 10,722 | $17.44 | $18.00 | $35.61 | $16.00 | $28.00 |
| 27 | Concrete (604-10.05) | SF | 65 | $535.00 | $425.00 | $576.65 | $300.00 | $950.00 |
| 28 | Concrete parapet repair (604-10.22) | LF | 5 | $2,167.43 | $1,175.00 | $416.93 | $10,000 | $2,850.00 |
| 29 | Bracing (604-10.26) | EACH | 9 | $1,729.20 | $8,000.00 | $2,210.74 | $12,000 | $69,500 |
| 30 | Bridge deck repairs (partial depth of slab) (604-10.50) | SY | 73 | $286.85 | $475.00 | $597.05 | $900.00 | $4,848.00 |
| 31 | Concrete repairs (604-10.54) | SF | 82 | $535.38 | $425.00 | $198.60 | $146.00 | $951.00 |
| 32 | Epoxy injection (injection) (604-10.58) | GAL | 258 | $80.70 | $105.00 | $112.75 | $624.50 | $950.00 |
| 33 | Expansion joint repairs (modular type) (604-10.60) | LF | 50 | $3,521.87 | $4,560.00 | $4,633.78 | $5,000.00 | $10,000 |
| 34 | Expansion joint repairs (modular type) (604-10.61) | LF | 50 | $6,706.56 | $7,372.00 | $7,211.17 | $9,500.00 | $18,500 |
| 35 | Epoxy injection repair (complete and in place) (604-10.62) | LF | 5,160 | $74.93 | $96.00 | $90.06 | $20.25 | $188.00 |
| 36 | Composite fiber encasement (604-10.83) | SF | 49,452 | $31.24 | $42.10 | $42.97 | $24.55 | $55.00 |
| 37 | Drill & grout steel bars (604-12.15) | EACH | 24 | $5,372.46 | $4,575.00 | $2,106.99 | $20,000 | $3,850.00 |
| 38 | Type 1 thin epoxy overlay (epoxy-urethane) (617-04.01) | SY | 73 | $155.63 | $200.00 | $29.99 | $135.00 | $225.00 |
| 39 | 24" temporary drainage pipe (621-03.03) | LF | 162 | $97.99 | $110.00 | $78.93 | $100.00 | $185.00 |
| 40 | W beam GR (type 2) MASH TL-3 (705-06.01) | LF | 50 | $38.04 | $50.00 | $61.41 | $33.00 | $55.00 |
| 41 | Thrie beam bridge transition MASH TL-3 (705-06.25) | EACH | 3 | $3,458.40 | $3,300.00 | $4,360.08 | $3,000.00 | $4,500.00 |
| 42 | Guardrail removed (706-01) | LF | 50 | $1.15 | $2.50 | $2.46 | $1.00 | $95.00 |
| 43 | High-visibility construction fence (707-08.11) | LF | 470 | $5.19 | $5.00 | $10.61 | $2.00 | $4.00 |
| 44 | Machined rip-rap (class A-1) (709-05.06) | TON | 117 | $141.16 | $75.00 | $186.47 | $150.00 | $225.00 |
| 45 | Machined rip-rap (class B) (709-05.08) | TON | 409 | $103.75 | $78.00 | $186.47 | $100.00 | $225.00 |
| 46 | 6" perforated pipe with vertical drain system (710-09.01) | LF | 154 | $54.61 | $48.00 | $39.79 | $50.00 | $85.00 |
| 47 | 6" pipe underdrain (710-09.02) | LF | 40 | $29.37 | $30.00 | $39.79 | $10.00 | $65.00 |
| 48 | Traffic control (712-01) | LS | 1 | $294,898 | $460,600 | $6,140.96 | $250,000 | $650,000 |
| 49 | Portable barrier rail, reduced deflection (MASH TL-3) (712-02.12) | LF | 3,860 | $58.56 | $80.00 | $68.13 | $75.00 | $115.00 |
| 50 | Temporary work zone crash cushion (MASH TL-3) (712-02.60) | EACH | 4 | $5,187.60 | $8,500.00 | $7,983.25 | $6,500.00 | $12,500 |
| 51 | Flexible drums (channelizing) (712-04.01) | EACH | 150 | $23.06 | $42.00 | $6.14 | $20.00 | $30.00 |
| 52 | Barrier rail delineator (712-04.50) | EACH | 200 | $14.99 | $16.00 | $18.42 | $13.00 | $18.00 |
| 53 | Signs (construction) (712-06) | SF | 254 | $10.38 | $11.50 | $29.48 | $9.00 | $12.00 |
| 54 | Removable pavement marking (8" barrier line) (712-09.02) | LF | 16,400 | $3.57 | $3.75 | $3.81 | $3.10 | $5.00 |
| 55 | Removable pavement marking (stop line) (712-09.04) | LF | 48 | $23.06 | $24.00 | $24.56 | $20.00 | $25.00 |
| 56 | Removable pavement marking (6" line) (712-09.08) | LF | 4,000 | $3.46 | $3.30 | $3.68 | $3.00 | $5.00 |
| 57 | Navigational lighting (714-16.01) | LS | 1 | $70,321 | $168,000 | $146,155 | $42,860 | $305,000 |
| 58 | Snowplowable raised pavement markers (BI-dir) (1 color) (716-01.21) | EACH | 12 | $172.92 | $165.00 | $184.23 | $150.00 | $250.00 |
| 59 | Removal of snowplowable reflective marker (716-01.30) | EACH | 12 | $23.06 | $30.00 | $24.56 | $20.00 | $40.00 |
| 60 | Spray thermo PVMT MRKNG (60 mil) (6IN line) (716-13.02) | LM | 2.55 | $5,101.14 | $4,870.00 | $5,434.75 | $4,425.00 | $6,850.00 |
| 61 | Mobilization (717-01) | LS | 1 | $943,769 | $460,000 | $3,172,848 | $940,000 | $1,300,000 |
| 62 | Temporary traffic signal system (730-40.02) | LS | 1 | $99,141 | $80,000 | $73,692 | $100,000 | $250,000 |
| 63 | Geogrid reinforcement type 2 (740-07.04) | SY | 1,830 | $5.95 | $6.75 | $1.71 | $10.00 | $8.00 |
| 64 | Geotextile (type III)(erosion control) (740-10.03) | SY | 167 | $3.46 | $6.00 | $4.21 | $3.00 | $5.00 |
| 65 | Geotextile (type IV)(stabilization) (740-10.04) | SY | 415 | $5.48 | $6.50 | $2.78 | $20.00 | $7.00 |
| 66 | Temporary sediment tube 18IN (740-11.03) | LF | 455 | $4.44 | $5.50 | $4.73 | $4.00 | $7.00 |
| 67 | Temporary seeding (with mulch) (801-01.07) | UNIT | 17 | $34.58 | $110.00 | $47.90 | $40.00 | $55.00 |
| 68 | Natve seed MX final stablizatn of slopes (801-01.38) | UNIT | 15 | $80.64 | $150.00 | $85.91 | $100.00 | $165.00 |
| 69 | Water (seeding & sodding) (801-03) | MG | 4 | $92.23 | $100.00 | $98.26 | $150.00 | $200.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from TDOT's tabulation for this contract. TDOT Summary of Bids PDFs: every letting posted for February 2024 to October 2026, and nine lettings of 2018 to 2023 recovered from archived copies of the tn.gov files. Cost-plus-time bids, and bids that did not match their published total, are left out.
Every contract let that day: TDOT letting of August 14, 2026. Compiled by Mirage Metrics.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.