TDOT contract CN262060 bid tabulation

The repair of the bridge on s.r. 60 over the tennessee river (l.m. 3.10). Let by Tennessee DOT on August 14, 2026, Meigs County. 5 bids received; low bid $6,672,928 by Mid-State Construction Company, Inc..

Owner
Tennessee DOT
Letting
14 AUG 2026
Pay items
69
Data through
02 OCT 2026

Bidders

RankBidderTotal bidAgainst the low bid
1Mid-State Construction Company, Inc.$6,672,928Low
2Jamison Construction, LLC$6,856,029+3.0%
3Louis-Company, LLC$8,582,807+29%
4Jones Bros. Contractors, LLC$9,378,577+41%
5Southern Road & Bridge, LLC$13,901,471+108%
TDOT contract CN262060: bids by rank

Bid tabulation

LinePay itemUnitQuantity1. Mid-State Construction Company, Inc.2. Jamison Construction, LLC3. Louis-Company, LLC4. Jones Bros. Contractors, LLC5. Southern Road & Bridge, LLC
1Construction stakes, lines and grades (105-01)LS1$51,300$10,000$18,423$100,000$65,000
2Clearing and grubbing (201-01)LS1$108,188$80,000$12,500$340,000$175,000
3Vegetation removal (201-05.31)LS1$9,068.38$30,000$15,840$50,000$250,000
4Removal of structures (BR. no. 61-SR060-03.10) (202-04.01)LS1$435,791$174,500$72,380$1,000,000$25,000
5Road & drainage excavation (unclassified) (203-01)CY2,926$57.45$75.00$13.62$120.00$68.00
6Dry excavation (bridges) (204-02.01)CY767$49.05$75.00$13.62$200.00$100.00
7Stream mitigation-step pool (209-03.36)EACH41$5,835.70$5,200.00$1,473.83$2,500.00$25,000
8Sediment removal (209-05)CY13$57.64$50.00$210.15$350.00$150.00
9Temporary silt fence (with backing) (209-08.02)LF2,500$5.42$6.50$5.77$4.75$10.00
10Enhanced rock check dam (209-08.08)EACH7$922.24$850.00$982.55$1,000.00$1,000.00
11Sandbags (209-09.01)BAG800$9.22$15.00$9.83$10.00$15.00
12Polyethylene sheeting (6 mil. minimum) (209-20.03)SY34$11.53$12.00$12.28$10.00$10.00
13Catch basin filter assembly(type 4) (209-40.44)EACH3$691.68$900.00$736.92$800.00$5,500.00
14Granular backfill (bridges) (303-01.02)TON114$59.04$75.00$55.27$200.00$200.00
15Mineral aggregate (size 57) (303-10.04)TON1,200$51.49$72.00$49.13$100.00$150.00
16Asphalt concrete mix (PG70-22) (BPMB-HM) grading A (307-02.01)TON45$801.20$765.00$307.05$695.00$1,250.00
17Asphalt concrete mix (PG70-22) (BPMB-HM) grading B-M2 (307-02.08)TON133$368.90$352.00$245.64$320.00$445.00
18Trackless tack coat (403-02.01)TON2$1,095.16$1,050.00$1,473.83$950.00$2,200.00
19Acs mix(PG70-22) grading D (411-02.10)TON89$391.95$375.00$276.34$340.00$500.00
20Cold planing bituminous pavement (415-01.02)SY1,350$16.14$16.00$14.74$14.00$33.00
21Bearing device (repair) (602-10.12)LS1$230,214$85,000$32,082$725,000$185,000
22Jacking steel spans (602-10.19)LS1$151,915$102,000$195,095$729,000$225,000
23Painting steel structures (new plates, abt.1) (603-01.01)LS1$3,677.43$3,300.00$10,543$3,000.00$155,000
24Pavement @ bridge ends (604-03.04)SY248$562.74$520.00$578.45$1,500.00$1,500.00
25Class D concrete (604-03.30)CY17$4,005.02$4,000.00$3,710.34$10,000$25,000
26Applied texture finish (existing structures) (604-04.02)SY10,722$17.44$18.00$35.61$16.00$28.00
27Concrete (604-10.05)SF65$535.00$425.00$576.65$300.00$950.00
28Concrete parapet repair (604-10.22)LF5$2,167.43$1,175.00$416.93$10,000$2,850.00
29Bracing (604-10.26)EACH9$1,729.20$8,000.00$2,210.74$12,000$69,500
30Bridge deck repairs (partial depth of slab) (604-10.50)SY73$286.85$475.00$597.05$900.00$4,848.00
31Concrete repairs (604-10.54)SF82$535.38$425.00$198.60$146.00$951.00
32Epoxy injection (injection) (604-10.58)GAL258$80.70$105.00$112.75$624.50$950.00
33Expansion joint repairs (modular type) (604-10.60)LF50$3,521.87$4,560.00$4,633.78$5,000.00$10,000
34Expansion joint repairs (modular type) (604-10.61)LF50$6,706.56$7,372.00$7,211.17$9,500.00$18,500
35Epoxy injection repair (complete and in place) (604-10.62)LF5,160$74.93$96.00$90.06$20.25$188.00
36Composite fiber encasement (604-10.83)SF49,452$31.24$42.10$42.97$24.55$55.00
37Drill & grout steel bars (604-12.15)EACH24$5,372.46$4,575.00$2,106.99$20,000$3,850.00
38Type 1 thin epoxy overlay (epoxy-urethane) (617-04.01)SY73$155.63$200.00$29.99$135.00$225.00
3924" temporary drainage pipe (621-03.03)LF162$97.99$110.00$78.93$100.00$185.00
40W beam GR (type 2) MASH TL-3 (705-06.01)LF50$38.04$50.00$61.41$33.00$55.00
41Thrie beam bridge transition MASH TL-3 (705-06.25)EACH3$3,458.40$3,300.00$4,360.08$3,000.00$4,500.00
42Guardrail removed (706-01)LF50$1.15$2.50$2.46$1.00$95.00
43High-visibility construction fence (707-08.11)LF470$5.19$5.00$10.61$2.00$4.00
44Machined rip-rap (class A-1) (709-05.06)TON117$141.16$75.00$186.47$150.00$225.00
45Machined rip-rap (class B) (709-05.08)TON409$103.75$78.00$186.47$100.00$225.00
466" perforated pipe with vertical drain system (710-09.01)LF154$54.61$48.00$39.79$50.00$85.00
476" pipe underdrain (710-09.02)LF40$29.37$30.00$39.79$10.00$65.00
48Traffic control (712-01)LS1$294,898$460,600$6,140.96$250,000$650,000
49Portable barrier rail, reduced deflection (MASH TL-3) (712-02.12)LF3,860$58.56$80.00$68.13$75.00$115.00
50Temporary work zone crash cushion (MASH TL-3) (712-02.60)EACH4$5,187.60$8,500.00$7,983.25$6,500.00$12,500
51Flexible drums (channelizing) (712-04.01)EACH150$23.06$42.00$6.14$20.00$30.00
52Barrier rail delineator (712-04.50)EACH200$14.99$16.00$18.42$13.00$18.00
53Signs (construction) (712-06)SF254$10.38$11.50$29.48$9.00$12.00
54Removable pavement marking (8" barrier line) (712-09.02)LF16,400$3.57$3.75$3.81$3.10$5.00
55Removable pavement marking (stop line) (712-09.04)LF48$23.06$24.00$24.56$20.00$25.00
56Removable pavement marking (6" line) (712-09.08)LF4,000$3.46$3.30$3.68$3.00$5.00
57Navigational lighting (714-16.01)LS1$70,321$168,000$146,155$42,860$305,000
58Snowplowable raised pavement markers (BI-dir) (1 color) (716-01.21)EACH12$172.92$165.00$184.23$150.00$250.00
59Removal of snowplowable reflective marker (716-01.30)EACH12$23.06$30.00$24.56$20.00$40.00
60Spray thermo PVMT MRKNG (60 mil) (6IN line) (716-13.02)LM2.55$5,101.14$4,870.00$5,434.75$4,425.00$6,850.00
61Mobilization (717-01)LS1$943,769$460,000$3,172,848$940,000$1,300,000
62Temporary traffic signal system (730-40.02)LS1$99,141$80,000$73,692$100,000$250,000
63Geogrid reinforcement type 2 (740-07.04)SY1,830$5.95$6.75$1.71$10.00$8.00
64Geotextile (type III)(erosion control) (740-10.03)SY167$3.46$6.00$4.21$3.00$5.00
65Geotextile (type IV)(stabilization) (740-10.04)SY415$5.48$6.50$2.78$20.00$7.00
66Temporary sediment tube 18IN (740-11.03)LF455$4.44$5.50$4.73$4.00$7.00
67Temporary seeding (with mulch) (801-01.07)UNIT17$34.58$110.00$47.90$40.00$55.00
68Natve seed MX final stablizatn of slopes (801-01.38)UNIT15$80.64$150.00$85.91$100.00$165.00
69Water (seeding & sodding) (801-03)MG4$92.23$100.00$98.26$150.00$200.00
TDOT contract CN262060: unit prices by line

The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.

Source

Read from TDOT's tabulation for this contract. TDOT Summary of Bids PDFs: every letting posted for February 2024 to October 2026, and nine lettings of 2018 to 2023 recovered from archived copies of the tn.gov files. Cost-plus-time bids, and bids that did not match their published total, are left out.

Every contract let that day: TDOT letting of August 14, 2026. Compiled by Mirage Metrics.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy