TDOT contract CN263064 bid tabulation
The construction of a concrete box bridge on old highway 64 over stokes branch (l.m. 0.11), including grading, drainage, and paving. Let by Tennessee DOT on October 2, 2026, Bedford County. 6 bids received; low bid $999,269 by Jones Bros. Contractors, LLC.
- Owner
- Tennessee DOT
- Letting
- 02 OCT 2026
- Pay items
- 50
- Data through
- 02 OCT 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | Jones Bros. Contractors, LLC | $999,269 | Low |
| 2 | Capital City Construction Services, LLC | $1,018,339 | +2.0% |
| 3 | Taggart Constructors, LLC | $1,086,375 | +9.0% |
| 4 | Adams Contracting, LLC | $1,088,450 | +9.0% |
| 5 | Jamison Construction, LLC | $1,127,955 | +13% |
| 6 | Dement Construction Group, LLC | $1,422,260 | +42% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Jones Bros. Contractors, LLC | 2. Capital City Construction Services, LLC | 3. Taggart Constructors, LLC | 4. Adams Contracting, LLC | 5. Jamison Construction, LLC | 6. Dement Construction Group, LLC |
|---|---|---|---|---|---|---|---|---|---|
| 1 | Construction stakes, lines and grades (105-01) | LS | 1 | $13,200 | $15,464 | $25,000 | $20,000 | $14,750 | $25,000 |
| 2 | Clearing and grubbing (201-01) | LS | 1 | $50,000 | $15,000 | $35,000 | $10,000 | $30,000 | $170,000 |
| 3 | Removal of asphalt pavement (202-03.01) | SY | 272 | $20.00 | $25.09 | $23.00 | $14.00 | $25.00 | $20.00 |
| 4 | Removal of structures (exist. bridge # 020A664001, sta. 15+50.84) (202-04.01) | LS | 1 | $78,000 | $159,577 | $95,000 | $80,000 | $82,000 | $90,000 |
| 5 | Road & drainage excavation (unclassified) (203-01) | CY | 814 | $40.00 | $18.66 | $95.00 | $35.00 | $42.00 | $45.00 |
| 6 | Borrow excavation (unclassified) (203-03) | CY | 119 | $70.00 | $88.09 | $75.00 | $70.00 | $66.00 | $75.00 |
| 7 | Placing and spreading topsoil (203-04) | CY | 85 | $35.00 | $80.30 | $95.00 | $25.00 | $45.00 | $35.00 |
| 8 | Water (203-06) | MG | 23 | $10.00 | $128.21 | $35.00 | $50.00 | $30.00 | $5.00 |
| 9 | Sediment removal (209-05) | CY | 17 | $30.00 | $40.15 | $23.00 | $10.00 | $50.00 | $1.00 |
| 10 | Temporary silt fence (with backing) (209-08.02) | LF | 450 | $5.90 | $2.58 | $6.25 | $5.00 | $6.00 | $6.50 |
| 11 | Temporary silt fence (without backing) (209-08.03) | LF | 340 | $3.90 | $5.88 | $4.25 | $3.00 | $5.00 | $4.95 |
| 12 | Enhanced rock check dam (209-08.08) | EACH | 8 | $700.00 | $701.03 | $1,250.00 | $850.00 | $850.00 | $1,200.00 |
| 13 | Sediment filter bag (15' X 15') (209-09.03) | EACH | 4 | $500.00 | $340.21 | $550.00 | $1,000.00 | $800.00 | $600.00 |
| 14 | Temporary in stream diversion (209-65.04) | LF | 150 | $60.00 | $235.79 | $73.00 | $125.00 | $90.00 | $80.00 |
| 15 | Mineral aggregate, type A base, grading D (303-01) | TON | 385 | $50.00 | $71.26 | $60.00 | $50.00 | $80.00 | $55.00 |
| 16 | Mineral aggregate (size 57) (303-10.01) | TON | 44 | $65.00 | $54.57 | $65.00 | $55.00 | $65.00 | $55.00 |
| 17 | Asphalt concrete mix (PG64-22) (BPMB-HM) grading B-M2 (307-01.08) | TON | 56 | $550.00 | $463.92 | $425.00 | $431.00 | $451.00 | $410.00 |
| 18 | Bituminous material for prime coat (PC) (402-01) | TON | 1.40 | $850.00 | $3,505.15 | $2,600.00 | $2,630.00 | $2,750.00 | $2,500.00 |
| 19 | Aggregate for cover material (PC) (402-02) | TON | 5 | $75.00 | $835.05 | $105.00 | $105.00 | $110.00 | $100.00 |
| 20 | Bituminous material for tack coat (TC) (403-01) | TON | 0.30 | $850.00 | $1,288.66 | $2,600.00 | $2,630.00 | $2,750.00 | $2,500.00 |
| 21 | Saw cutting asphalt pavement (407-20.05) | LF | 270 | $7.00 | $5.15 | $3.00 | $5.00 | $15.00 | $10.00 |
| 22 | Acs mix(PG64-22) grading D (411-01.10) | TON | 33 | $425.00 | $747.94 | $460.00 | $462.00 | $485.00 | $440.00 |
| 23 | Temporary shoring (621-05.02) | LS | 1 | $20,000 | $21,663 | $62,000 | $40,000 | $78,000 | $150,000 |
| 24 | Metal beam guard fence (705-01.04) | LF | 125 | $100.00 | $113.40 | $95.00 | $100.00 | $110.00 | $90.00 |
| 25 | Portable barrier rail delineator (705-04.50) | EACH | 16 | $10.00 | $10.31 | $16.00 | $21.00 | $20.00 | $13.00 |
| 26 | W beam GR (type 2) MASH TL-3 (705-06.01) | LF | 250 | $32.50 | $30.93 | $30.00 | $32.00 | $36.00 | $28.00 |
| 27 | GR terminal (energy absorbing) MASH TL-2 (705-06.30) | EACH | 4 | $3,025.00 | $2,164.95 | $2,950.00 | $3,420.00 | $3,328.00 | $2,900.00 |
| 28 | Portable impact attenuator NCHRP350 TL-3 (705-08.11) | EACH | 4 | $5,800.00 | $5,670.10 | $6,250.00 | $6,830.00 | $6,500.00 | $5,435.00 |
| 29 | High-visibility construction fence (707-08.11) | LF | 200 | $4.00 | $2.89 | $4.50 | $3.00 | $4.00 | $3.45 |
| 30 | Markers (concrete R.O.W. posts) (708-02.01) | EACH | 8 | $300.00 | $384.62 | $500.00 | $420.00 | $375.00 | $500.00 |
| 31 | Machined rip-rap (class A-3) (709-05.05) | TON | 200 | $50.00 | $35.00 | $55.00 | $63.00 | $70.00 | $55.00 |
| 32 | Traffic control (712-01) | LS | 1 | $1,300.00 | $1,855.67 | $5,000.00 | $58,000 | $30,000 | $15,000 |
| 33 | Portable barrier rail, reduced deflection (MASH TL-3) (712-02.12) | LF | 320 | $45.00 | $61.86 | $95.00 | $70.00 | $65.00 | $70.00 |
| 34 | Flexible drums (channelizing) (712-04.01) | EACH | 60 | $20.00 | $20.62 | $27.00 | $37.00 | $30.00 | $25.00 |
| 35 | Warning lights (type A) (712-05.01) | EACH | 30 | $20.00 | $20.62 | $22.00 | $42.00 | $30.00 | $20.00 |
| 36 | Signs (construction) (712-06) | SF | 124 | $6.10 | $6.29 | $7.90 | $8.00 | $9.00 | $6.85 |
| 37 | Temporary barricades (type III) (712-07.03) | LF | 20 | $14.00 | $14.43 | $23.00 | $19.00 | $20.00 | $22.00 |
| 38 | "U" section steel posts (713-11.01) | LB | 105 | $3.50 | $3.61 | $3.25 | $13.00 | $3.85 | $3.13 |
| 39 | Flat sheet aluminum signs (0.080" thick) (713-13.02) | SF | 12 | $12.00 | $12.37 | $13.50 | $14.00 | $13.50 | $12.67 |
| 40 | Removal of signs, posts and footings (713-15) | LS | 1 | $150.00 | $154.64 | $165.00 | $840.00 | $300.00 | $150.00 |
| 41 | Mobilization (717-01) | LS | 1 | $95,000 | $60,000 | $62,000 | $100,000 | $65,000 | $139,023 |
| 42 | Geotextile (type III)(erosion control) (740-10.03) | SY | 565 | $4.00 | $3.71 | $2.50 | $3.00 | $4.50 | $3.50 |
| 43 | Temporary seeding (with mulch) (801-01.07) | UNIT | 9.40 | $175.00 | $48.45 | $190.00 | $100.00 | $82.00 | $100.00 |
| 44 | Water (seeding & sodding) (801-03) | MG | 1 | $100.00 | $170.10 | $150.00 | $150.00 | $110.00 | $250.00 |
| 45 | Sodding (new sod) (803-01) | SY | 521 | $10.00 | $6.19 | $11.00 | $11.00 | $11.00 | $9.10 |
| 46 | Foundation fill material (204-08) | CY | 100 | $50.00 | $20.00 | $100.00 | $60.00 | $115.00 | $85.00 |
| 47 | Granular backfill (roadway) (303-01.01) | TON | 952.80 | $32.00 | $41.91 | $58.00 | $37.00 | $62.00 | $70.00 |
| 48 | Class A concrete (box bridges) (604-02.01) | CY | 220 | $1,600.00 | $1,551.89 | $1,400.00 | $1,700.00 | $1,600.00 | $1,800.00 |
| 49 | Steel bar reinforcement (box bridges) (604-02.02) | LB | 50,805 | $2.00 | $1.50 | $1.90 | $1.70 | $2.00 | $1.85 |
| 50 | Machined rip-rap (class B) (709-05.08) | TON | 300 | $50.00 | $40.00 | $55.00 | $60.00 | $75.00 | $50.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from TDOT's tabulation for this contract. TDOT Summary of Bids PDFs: every letting posted for February 2024 to October 2026, and nine lettings of 2018 to 2023 recovered from archived copies of the tn.gov files. Cost-plus-time bids, and bids that did not match their published total, are left out.
Every contract let that day: TDOT letting of October 2, 2026. Compiled by Mirage Metrics.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.