TDOT contract CN263065 bid tabulation
The construction of a concrete bulb-tee beam bridge on cedar grove road over hurricane creek (l.m. 0.49), including grading, drainage, and paving. Let by Tennessee DOT on October 2, 2026, Humphreys County. 6 bids received; low bid $4,286,414 by Dement Construction Group, LLC.
- Owner
- Tennessee DOT
- Letting
- 02 OCT 2026
- Pay items
- 69
- Data through
- 02 OCT 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | Dement Construction Group, LLC | $4,286,414 | Low |
| 2 | Bell & Associates Construction, LLC | $4,742,358 | +11% |
| 3 | Concrete Structures, Inc. | $4,775,597 | +11% |
| 4 | Louis-Company, LLC | $4,887,633 | +14% |
| 5 | Capital City Construction Services, LLC | $5,279,706 | +23% |
| 6 | Jones Bros. Contractors, LLC | $5,499,232 | +28% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Dement Construction Group, LLC | 2. Bell & Associates Construction, LLC | 3. Concrete Structures, Inc. | 4. Louis-Company, LLC | 5. Capital City Construction Services, LLC | 6. Jones Bros. Contractors, LLC |
|---|---|---|---|---|---|---|---|---|---|
| 1 | Construction stakes, lines and grades (105-01) | LS | 1 | $83,750 | $49,500 | $65,000 | $58,836 | $85,000 | $35,000 |
| 2 | Trainee (109-10.01) | HR | 1,100 | $0.80 | $0.80 | $0.80 | $0.80 | $0.80 | $0.80 |
| 3 | Clearing and grubbing (201-01) | LS | 1 | $100,000 | $112,000 | $41,000 | $52,978 | $28,000 | $250,000 |
| 4 | Removal of structures (concrete ditches) (202-04.02) | LS | 1 | $4,000.00 | $5,900.00 | $3,500.00 | $7,535.11 | $2,739.00 | $10,000 |
| 5 | Removal of structures (gate, sta. 63+15.68) (202-04.03) | LS | 1 | $2,500.00 | $1,700.00 | $2,300.00 | $1,883.78 | $333.33 | $5,000.00 |
| 6 | Road & drainage excavation (unclassified) (203-01) | CY | 453 | $65.00 | $85.00 | $64.00 | $41.28 | $46.06 | $65.00 |
| 7 | Borrow excavation (unclassified) (203-03) | CY | 99 | $15.00 | $90.00 | $17.00 | $47.57 | $142.49 | $65.00 |
| 8 | Placing and spreading topsoil (203-04) | CY | 123 | $50.00 | $50.00 | $46.00 | $28.72 | $57.71 | $21.00 |
| 9 | Water (203-06) | MG | 1 | $100.00 | $500.00 | $116.00 | $65.38 | $133.33 | $5.00 |
| 10 | Construction of haul road (203-50) | LS | 1 | $350,000 | $477,283 | $320,000 | $265,252 | $275,000 | $600,000 |
| 11 | Filter sock (18 inch) (209-03.22) | LF | 286 | $14.40 | $11.00 | $17.00 | $13.07 | $7.10 | $14.40 |
| 12 | Sediment removal (209-05) | CY | 66 | $40.00 | $39.50 | $46.00 | $28.54 | $34.83 | $15.00 |
| 13 | Temporary silt fence (with backing) (209-08.02) | LF | 2,378 | $4.60 | $6.00 | $6.00 | $3.92 | $5.50 | $4.60 |
| 14 | Enhanced rock check dam (209-08.08) | EACH | 1 | $1,000.00 | $1,750.00 | $2,900.00 | $1,438.21 | $680.00 | $1,800.00 |
| 15 | Sediment filter bag(15' X 10') (209-09.04) | EACH | 2 | $500.00 | $750.00 | $850.00 | $130.75 | $320.00 | $1,000.00 |
| 16 | Temporary in stream diversion (209-65.04) | LF | 450 | $50.00 | $100.00 | $80.00 | $421.35 | $326.97 | $120.00 |
| 17 | Mineral aggregate, type A base, grading D (303-01) | TON | 499 | $50.00 | $56.00 | $58.00 | $83.81 | $50.00 | $95.00 |
| 18 | Mineral aggregate (size 57) (303-10.01) | TON | 19 | $100.00 | $78.00 | $68.00 | $101.35 | $94.86 | $75.00 |
| 19 | Asphalt concrete mix (PG64-22) (BPMB-HM) grading B-M2 (307-01.08) | TON | 95 | $300.00 | $381.00 | $350.00 | $451.07 | $300.00 | $325.00 |
| 20 | Bituminous material for prime coat (PC) (402-01) | TON | 2 | $100.00 | $2,762.00 | $120.00 | $3,268.66 | $100.00 | $900.00 |
| 21 | Aggregate for cover material (PC) (402-02) | TON | 5 | $40.00 | $110.00 | $46.00 | $235.45 | $40.00 | $225.00 |
| 22 | Bituminous material for tack coat (TC) (403-01) | TON | 0.50 | $100.00 | $2,762.00 | $120.00 | $3,268.66 | $100.00 | $900.00 |
| 23 | Acs mix(PG64-22) grading D (411-01.10) | TON | 81 | $300.00 | $419.00 | $350.00 | $496.84 | $300.00 | $500.00 |
| 24 | Cold planing bituminous pavement (415-01.01) | TON | 15 | $300.00 | $1,325.00 | $350.00 | $130.75 | $300.00 | $1,225.00 |
| 25 | Earth pad for guard rail end treatment (705-04.10) | EACH | 3 | $800.00 | $1,979.00 | $2,300.00 | $1,045.97 | $800.00 | $800.00 |
| 26 | W beam GR (type 2) MASH TL-3 (long post) (705-06.02) | LF | 613 | $36.00 | $39.00 | $42.00 | $47.07 | $36.00 | $36.00 |
| 27 | Thrie beam bridge transition MASH TL-2 (705-06.26) | EACH | 4 | $2,000.00 | $2,210.00 | $2,300.00 | $2,614.93 | $2,000.00 | $2,000.00 |
| 28 | GR terminal (energy absorbing) MASH TL-2 (705-06.30) | EACH | 3 | $3,200.00 | $3,536.00 | $3,700.00 | $4,183.89 | $3,200.00 | $3,200.00 |
| 29 | Guardrail removed (706-01) | LF | 923 | $1.00 | $2.00 | $2.00 | $1.31 | $1.00 | $1.00 |
| 30 | High-visibility construction fence (707-08.11) | LF | 436 | $5.60 | $3.50 | $7.00 | $7.59 | $2.80 | $5.60 |
| 31 | Machined rip-rap (class A-3) (709-05.05) | TON | 100 | $80.00 | $61.00 | $75.00 | $99.13 | $72.38 | $50.00 |
| 32 | Machined rip-rap (class B) (709-05.08) | TON | 2,710 | $60.00 | $70.00 | $64.00 | $73.44 | $61.11 | $60.00 |
| 33 | Traffic control (712-01) | LS | 1 | $5,800.00 | $900.00 | $7,900.00 | $1,045.96 | $17,300 | $800.00 |
| 34 | Warning lights (type A) (712-05.01) | EACH | 4 | $25.00 | $28.00 | $29.00 | $32.69 | $25.00 | $25.00 |
| 35 | Signs (construction) (712-06) | SF | 147 | $7.00 | $8.00 | $8.00 | $9.15 | $7.00 | $7.00 |
| 36 | Temporary barricades (type III) (712-07.03) | LF | 35 | $22.00 | $24.00 | $26.00 | $28.76 | $22.00 | $22.00 |
| 37 | Painted pavement marking (4" line) (716-05.01) | LM | 0.40 | $2,000.00 | $2,210.00 | $16,000 | $2,614.90 | $2,000.00 | $2,000.00 |
| 38 | Mobilization (717-01) | LS | 1 | $391,500 | $400,000 | $230,000 | $360,862 | $393,000 | $545,000 |
| 39 | Geotextile (type III)(erosion control) (740-10.03) | SY | 331 | $7.00 | $5.00 | $8.00 | $3.27 | $3.60 | $5.00 |
| 40 | Seeding (with mulch) (801-01) | UNIT | 23 | $100.00 | $110.00 | $120.00 | $104.60 | $52.00 | $100.00 |
| 41 | Natve seed MX final stablizatn of slopes (801-01.38) | UNIT | 9 | $250.00 | $442.00 | $290.00 | $339.94 | $315.56 | $250.00 |
| 42 | Water (seeding & sodding) (801-03) | MG | 1.50 | $100.00 | $55.00 | $120.00 | $339.94 | $165.00 | $100.00 |
| 43 | Acer negundo (box elder seedlng B.R.) (802-12.01) | EACH | 15 | $40.00 | $16.00 | $46.00 | $19.61 | $17.00 | $40.00 |
| 44 | Liriodendron tulipifera (tulip poplar seedlng B.R.) (802-12.19) | EACH | 15 | $40.00 | $16.00 | $46.00 | $32.69 | $18.00 | $40.00 |
| 45 | Platanus occidentalis (sycamore seedlng B.R.) (802-12.26) | EACH | 15 | $40.00 | $16.00 | $46.00 | $32.69 | $19.00 | $40.00 |
| 46 | Ulmus americana (american elm seedlng B.R.) (802-12.44) | EACH | 15 | $40.00 | $16.00 | $46.00 | $32.69 | $18.00 | $40.00 |
| 47 | Salix nigra (black willow 3FT live stakes) (802-16.01) | EACH | 194 | $14.00 | $16.00 | $17.00 | $52.30 | $14.00 | $14.00 |
| 48 | Removal of asbestos (202-01.02) | LS | 1 | $25,000 | $29,500 | $23,000 | $45,761 | $24,632 | $12,500 |
| 49 | Removal of structures (exist. BR. no. 43-A341-0.49) (202-04.01) | LS | 1 | $200,000 | $290,000 | $430,000 | $238,930 | $543,920 | $233,000 |
| 50 | Dry excavation (bridges) (204-02.01) | CY | 288 | $30.00 | $85.00 | $31.00 | $53.96 | $63.86 | $24.00 |
| 51 | Core drilling and sampling (204-05.01) | LF | 530 | $115.00 | $127.00 | $43.00 | $220.79 | $125.00 | $133.00 |
| 52 | Granular backfill (bridges) (303-01.02) | TON | 48 | $80.00 | $65.00 | $80.00 | $110.64 | $228.53 | $65.00 |
| 53 | Epoxy coated reinforcing steel (604-02.03) | LB | 97,630 | $1.46 | $2.00 | $2.20 | $2.60 | $1.85 | $2.00 |
| 54 | Class A concrete (bridges) (604-03.01) | CY | 219 | $1,650.00 | $1,200.00 | $1,450.00 | $1,346.24 | $2,472.02 | $1,500.00 |
| 55 | Steel bar reinforcement (bridges) (604-03.02) | LB | 46,671 | $1.32 | $1.50 | $2.00 | $2.44 | $1.63 | $1.50 |
| 56 | Class DS concrete (604-03.32) | CY | 347 | $1,600.00 | $1,100.00 | $1,550.00 | $1,368.24 | $1,381.81 | $1,100.00 |
| 57 | Applied texture finish (new structures) (604-04.01) | SY | 5,236 | $12.50 | $14.00 | $15.00 | $17.00 | $10.00 | $12.50 |
| 58 | Steel piles (12 inch) (606-03.03) | LF | 511 | $110.00 | $115.00 | $120.00 | $116.22 | $149.46 | $105.00 |
| 59 | Pile tips (steel piles, 12 inch) (606-03.06) | EACH | 14 | $350.00 | $300.00 | $400.00 | $159.51 | $271.33 | $150.00 |
| 60 | Prestressed concrete bulb tee beam (6" web)(BT-54) (615-01.10) | LF | 1,238 | $350.00 | $500.00 | $480.00 | $497.65 | $687.19 | $500.00 |
| 61 | Concrete railing (620-06) | LF | 910 | $200.00 | $290.00 | $225.00 | $201.65 | $214.90 | $200.00 |
| 62 | Camera inspection - drilled shaft (underwater) (625-01.11) | EACH | 8 | $1,000.00 | $2,320.00 | $1,200.00 | $3,007.17 | $1,052.63 | $1,500.00 |
| 63 | Drilled shaft-soil (4'-6" dia.) (625-02.01) | VF | 209 | $725.00 | $362.00 | $700.00 | $346.48 | $763.16 | $1,000.00 |
| 64 | Drilled shaft-rock (4'-0"/4'-6" dia.) (625-02.13) | VF | 156 | $1,425.00 | $1,780.00 | $2,500.00 | $2,026.57 | $1,500.00 | $3,000.00 |
| 65 | Drilled shaft casing-permanent (4'-6" inside diameter) (625-02.25) | VF | 217 | $785.00 | $745.00 | $830.00 | $849.85 | $826.32 | $1,500.00 |
| 66 | Drilled shaft (SH-SCC) concrete (625-02.40) | CY | 195 | $700.00 | $693.00 | $820.00 | $922.44 | $736.84 | $700.00 |
| 67 | Drilled shaft reinforcing steel (625-02.44) | LB | 63,112 | $1.49 | $2.50 | $2.50 | $2.82 | $1.63 | $3.00 |
| 68 | 6" perforated pipe with vertical drain system (710-09.01) | LF | 116 | $75.00 | $85.00 | $45.00 | $77.42 | $53.33 | $50.00 |
| 69 | 6" pipe underdrain (710-09.02) | LF | 50 | $15.00 | $30.00 | $22.00 | $40.42 | $26.67 | $25.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from TDOT's tabulation for this contract. TDOT Summary of Bids PDFs: every letting posted for February 2024 to October 2026, and nine lettings of 2018 to 2023 recovered from archived copies of the tn.gov files. Cost-plus-time bids, and bids that did not match their published total, are left out.
Every contract let that day: TDOT letting of October 2, 2026. Compiled by Mirage Metrics.