TDOT contract CN263066 bid tabulation
The rockfall mitigation on u.s. 70n (s.r. 24) from near waggoner street (l.m. 9.88) to near cedar street (l.m. 10.46) in south carthage. Let by Tennessee DOT on October 2, 2026, Smith County. 4 bids received; low bid $6,542,136 by Rock Supremacy, LLC.
- Owner
- Tennessee DOT
- Letting
- 02 OCT 2026
- Pay items
- 49
- Data through
- 02 OCT 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | Rock Supremacy, LLC | $6,542,136 | Low |
| 2 | Access Limited Construction | $7,561,029 | +16% |
| 3 | T & T Earthworks, LLC | $7,827,912 | +20% |
| 4 | Guardian Fence and Construction, LLC. dba GeoSpecialities | $12,499,603 | +91% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Rock Supremacy, LLC | 2. Access Limited Construction | 3. T & T Earthworks, LLC | 4. Guardian Fence and Construction, LLC. dba GeoSpecialities |
|---|---|---|---|---|---|---|---|
| 1 | Construction stakes, lines and grades (105-01) | LS | 1 | $28,000 | $160,290 | $40,000 | $100,000 |
| 2 | Clearing and grubbing (201-01) | LS | 1 | $217,000 | $118,218 | $975,000 | $210,000 |
| 3 | Removal of structures and obstructions (202-01.50) | EACH | 4 | $8,900.00 | $31,497 | $3,500.00 | $6,800.00 |
| 4 | Road & drainage excavation (unclassified) (203-01) | CY | 6,574 | $24.00 | $92.97 | $62.00 | $19.00 |
| 5 | Scaling and trimming (203-11) | SY | 46,844 | $15.00 | $17.42 | $16.60 | $80.00 |
| 6 | Rock dowel (203-40.17) | LF | 1,345 | $149.00 | $99.16 | $94.50 | $190.00 |
| 7 | Filter sock (12 inch) (209-03.21) | LF | 3,031 | $2.00 | $7.21 | $7.50 | $3.95 |
| 8 | Sediment removal (209-05) | CY | 421 | $30.00 | $184.33 | $65.00 | $16.35 |
| 9 | Rock check dam (209-08.07) | EACH | 6 | $500.00 | $1,362.47 | $900.00 | $720.00 |
| 10 | Enhanced rock check dam (209-08.08) | EACH | 3 | $500.00 | $1,923.48 | $1,100.00 | $1,060.00 |
| 11 | Catch basin protection (type A) (209-40.30) | EACH | 4 | $150.00 | $1,122.03 | $625.00 | $600.00 |
| 12 | Bituminous material for tack coat (TC) (403-01) | TON | 3 | $1,500.00 | $1,787.24 | $1,230.00 | $915.00 |
| 13 | Acs mix(PG64-22) grading D (411-01.10) | TON | 675 | $200.00 | $296.54 | $203.50 | $145.00 |
| 14 | Scoring for rumble stripe (non-continuous) (8IN width) (411-12.03) | LM | 1.20 | $10,000 | $5,610.16 | $6,700.00 | $695.00 |
| 15 | Cold planing bituminous pavement (415-01.02) | SY | 10,186 | $5.00 | $7.61 | $5.23 | $9.35 |
| 16 | W beam GR (type 2) MASH TL-3 (705-06.01) | LF | 2,150 | $30.00 | $29.00 | $30.80 | $29.25 |
| 17 | GR terminal (energy absorbing) MASH TL-2 (705-06.30) | EACH | 3 | $4,000.00 | $3,300.00 | $3,540.00 | $4,716.00 |
| 18 | Guardrail removed (706-01) | LF | 2,276 | $1.00 | $3.25 | $1.10 | $3.96 |
| 19 | Rock anchor, type II (707-02.44) | LF | 4,520 | $123.00 | $171.82 | $170.00 | $190.00 |
| 20 | Removal of fence (chain link) (707-06.01) | LF | 576 | $10.00 | $20.84 | $15.00 | $5.70 |
| 21 | High-visibility construction fence (707-08.11) | LF | 259 | $5.00 | $4.57 | $1.92 | $2.55 |
| 22 | Rockfall drape (type II) (707-10.06) | SY | 46,500 | $77.00 | $78.02 | $81.00 | $125.50 |
| 23 | Markers (concrete R.O.W. posts) (708-02.01) | EACH | 9 | $350.00 | $1,659.00 | $1,100.00 | $400.00 |
| 24 | Machined rip-rap (class A-3) (709-05.05) | TON | 100 | $80.00 | $112.20 | $85.00 | $55.00 |
| 25 | Traffic control (712-01) | LS | 1 | $53,000 | $2,404.35 | $102,000 | $350,000 |
| 26 | Flexible drums (channelizing) (712-04.01) | EACH | 100 | $25.00 | $48.09 | $33.00 | $4.50 |
| 27 | Warning lights (type A) (712-05.01) | EACH | 6 | $20.00 | $44.88 | $30.80 | $20.75 |
| 28 | Signs (construction) (712-06) | SF | 659 | $7.00 | $10.42 | $7.15 | $8.70 |
| 29 | Temporary barricades (type III) (712-07.03) | LF | 152 | $24.00 | $32.06 | $22.00 | $17.66 |
| 30 | Modify existing overhead signs (712-09.33) | EACH | 4 | $367.00 | $1,602.90 | $1,100.00 | $4,200.00 |
| 31 | Removal & relocation of sign & support (713-15.02) | EACH | 13 | $150.00 | $160.29 | $110.00 | $812.00 |
| 32 | Remove sign, support & footing (713-15.36) | EACH | 9 | $125.00 | $80.15 | $55.00 | $1,728.00 |
| 33 | Changeable message sign unit (713-16.01) | EACH | 10 | $4,985.00 | $6,732.19 | $4,620.00 | $5,745.00 |
| 34 | Signs (W8-14) (713-16.20) | EACH | 5 | $270.00 | $480.87 | $330.00 | $285.00 |
| 35 | Signs (W3-1) (713-16.21) | EACH | 1 | $215.00 | $480.87 | $330.00 | $755.00 |
| 36 | Signs (D9-2) (713-16.22) | EACH | 1 | $165.00 | $400.73 | $275.00 | $232.00 |
| 37 | Signs (M6-1L) (713-16.23) | EACH | 1 | $65.00 | $80.15 | $55.00 | $345.00 |
| 38 | Signs (R1-1) (713-16.24) | EACH | 1 | $135.00 | $561.02 | $385.00 | $165.00 |
| 39 | Signs (R1-3P) (713-16.25) | EACH | 1 | $30.00 | $480.87 | $330.00 | $157.50 |
| 40 | Snowplowable raised pavement markers (BI-dir) (1 color) (716-01.21) | EACH | 39 | $110.00 | $76.94 | $110.00 | $144.00 |
| 41 | Removal of snowplowable reflective marker (716-01.30) | EACH | 39 | $25.00 | $19.23 | $110.00 | $36.00 |
| 42 | Plastic pavement marking (stop line) (716-02.05) | LF | 60 | $20.00 | $48.09 | $27.50 | $28.80 |
| 43 | Enhanced flatline thermo PVMT MRKNG (6IN line) (716-12.02) | LM | 2.30 | $7,500.00 | $16,029 | $8,800.00 | $10,800 |
| 44 | Mobilization (717-01) | LS | 1 | $572,000 | $437,403 | $332,000 | $483,000 |
| 45 | Remove & relocate existing traffic signal equipment (730-01.01) | EACH | 1 | $18,000 | $19,235 | $20,000 | $5,325.00 |
| 46 | Geotextile (type III)(erosion control) (740-10.03) | SY | 172 | $1.50 | $83.35 | $3.50 | $3.90 |
| 47 | Seeding (with mulch) (801-01) | UNIT | 381 | $6.00 | $77.34 | $40.00 | $57.00 |
| 48 | Water (seeding & sodding) (801-03) | MG | 39 | $1.00 | $200.36 | $135.00 | $64.00 |
| 49 | Fertilizer (supplemental application) (801-08) | TON | 5 | $900.00 | $2,564.64 | $1,700.00 | $1,222.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from TDOT's tabulation for this contract. TDOT Summary of Bids PDFs: every letting posted for February 2024 to October 2026, and nine lettings of 2018 to 2023 recovered from archived copies of the tn.gov files. Cost-plus-time bids, and bids that did not match their published total, are left out.
Every contract let that day: TDOT letting of October 2, 2026. Compiled by Mirage Metrics.