TDOT contract CN264052 bid tabulation
The miscellaneous safety improvements on u.s. 51 (s.r. 3) at the intersection of rialto/leighs chapel road (l.m. 20.97 - l.m. 21.50). Let by Tennessee DOT on August 14, 2026, Tipton County. 2 bids received; low bid $2,806,436 by Delta Contracting Company, LLC.
- Owner
- Tennessee DOT
- Letting
- 14 AUG 2026
- Pay items
- 67
- Data through
- 02 OCT 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | Delta Contracting Company, LLC | $2,806,436 | Low |
| 2 | Ford Construction Company | $3,223,106 | +15% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Delta Contracting Company, LLC | 2. Ford Construction Company |
|---|---|---|---|---|---|
| 1 | Construction stakes, lines and grades (105-01) | LS | 1 | $50,000 | $35,000 |
| 2 | Clearing and grubbing (201-01) | LS | 1 | $40,000 | $35,000 |
| 3 | Removal of structures and obstructions (202-01) | LS | 1 | $10,000 | $15,000 |
| 4 | Removal of asphalt pavement (202-03.01) | SY | 750 | $8.00 | $40.00 |
| 5 | Road & drainage excavation (unclassified) (203-01) | CY | 3,500 | $36.00 | $22.00 |
| 6 | Borrow excavation (unclassified) (203-03) | CY | 2,757 | $10.00 | $33.00 |
| 7 | Placing and spreading topsoil (203-04) | CY | 1,634 | $15.00 | $15.00 |
| 8 | Water (203-06) | MG | 45 | $60.00 | $20.00 |
| 9 | Furnishing & spreading topsoil (203-07) | CY | 965 | $10.00 | $30.00 |
| 10 | Backfill material (flowable fill) (204-08.01) | CY | 12 | $400.00 | $660.00 |
| 11 | Sediment removal (209-05) | CY | 168 | $10.00 | $32.00 |
| 12 | Temporary silt fence (without backing) (209-08.03) | LF | 1,457 | $1.75 | $1.75 |
| 13 | Enhanced rock check dam (209-08.08) | EACH | 5 | $1,800.00 | $1,200.00 |
| 14 | Catch basin protection (type A) (209-40.30) | EACH | 3 | $1,025.00 | $400.00 |
| 15 | Mineral aggregate, type A base, grading D (303-01) | TON | 5,096 | $60.00 | $66.00 |
| 16 | Mineral aggregate (size 57) (303-10.01) | TON | 21 | $70.00 | $73.00 |
| 17 | Asphalt concrete mix (PG64-22) (BPMB-HM) grading B-M2 (307-01.08) | TON | 135 | $281.80 | $281.80 |
| 18 | Asp. conc. mix(PG70-22) (BPMB-HM) GR. A-S (307-01.21) | TON | 571 | $248.50 | $248.50 |
| 19 | Asphalt concrete mix (PG70-22) (BPMB-HM) grading A (307-02.01) | TON | 1,270 | $236.65 | $236.65 |
| 20 | Asphalt concrete mix (PG70-22) (BPMB-HM) grading B-M2 (307-02.08) | TON | 747 | $245.45 | $245.45 |
| 21 | Bituminous material for prime coat (PC) (402-01) | TON | 11 | $1,375.00 | $1,375.00 |
| 22 | Aggregate for cover material (PC) (402-02) | TON | 38 | $64.65 | $64.65 |
| 23 | Bituminous material for tack coat (TC) (403-01) | TON | 15 | $1,375.00 | $1,375.00 |
| 24 | Saw cutting asphalt pavement (407-20.05) | LF | 2,666 | $3.00 | $10.00 |
| 25 | Acs mix (PG64-22) grading E shoulder (411-01.07) | TON | 127 | $304.65 | $304.65 |
| 26 | Acs mix(PG70-22) grading D (411-02.10) | TON | 1,736 | $212.55 | $212.55 |
| 27 | Cold planing bituminous pavement (415-01.01) | TON | 1,358 | $90.50 | $90.50 |
| 28 | 18" concrete pipe culvert (class III) (607-03.02) | LF | 135 | $100.00 | $130.00 |
| 29 | 30" concrete pipe culvert (class III) (607-06.02) | LF | 73 | $200.00 | $222.00 |
| 30 | 15" pipe culvert (side drain) (607-39.01) | LF | 47 | $50.00 | $130.00 |
| 31 | 30IN endwall (cross drain) 6:1 (611-07.62) | EACH | 2 | $9,000.00 | $8,500.00 |
| 32 | 18IN endwall (median drain) (611-07.73) | EACH | 2 | $16,900 | $10,000 |
| 33 | Junction structure, 60IN round,> 4FT-8FT depth (611-63.10) | EACH | 1 | $7,000.00 | $4,900.00 |
| 34 | Junction structure, 120IN round,> 4FT-8FT depth (611-63.60) | EACH | 1 | $28,000 | $28,000 |
| 35 | Concrete median pavement (701-03) | CY | 484 | $450.00 | $1,300.00 |
| 36 | Concrete curb (702-01) | CY | 51 | $885.00 | $1,250.00 |
| 37 | High-visibility construction fence (707-08.11) | LF | 265 | $2.75 | $2.75 |
| 38 | Markers (concrete R.O.W. posts) (708-02.01) | EACH | 7 | $750.00 | $400.00 |
| 39 | Machined rip-rap (class A-1) (709-05.06) | TON | 114 | $68.00 | $68.00 |
| 40 | Aggregate underdrains (with pipe) (710-02) | LF | 1,817 | $14.50 | $14.50 |
| 41 | Lateral underdrain (710-05) | LF | 90 | $14.00 | $14.00 |
| 42 | Lateral underdrain endwall (6:1) (710-06.15) | EACH | 18 | $1,100.00 | $1,100.00 |
| 43 | Traffic control (712-01) | LS | 1 | $50,000 | $50,000 |
| 44 | Flexible drums (channelizing) (712-04.01) | EACH | 404 | $35.00 | $35.00 |
| 45 | Warning lights (type C) (712-05.03) | EACH | 478 | $10.00 | $10.00 |
| 46 | Signs (construction) (712-06) | SF | 613 | $6.00 | $6.00 |
| 47 | Temporary barricades (type III) (712-07.03) | LF | 96 | $15.00 | $15.00 |
| 48 | Sign post delineation enhancement (713-02.21) | LF | 196 | $5.50 | $5.50 |
| 49 | "U" section steel posts (713-11.01) | LB | 1,738 | $3.95 | $3.95 |
| 50 | Perforated/knockout square tube post (713-11.02) | LB | 454 | $4.00 | $4.00 |
| 51 | P post slip base (713-11.21) | EACH | 15 | $350.00 | $350.00 |
| 52 | U post slip base (713-11.22) | EACH | 40 | $300.00 | $300.00 |
| 53 | Flat sheet aluminum signs (0.080" thick) (713-13.02) | SF | 66 | $14.00 | $14.00 |
| 54 | Flat sheet aluminum signs (0.100" thick) (713-13.03) | SF | 456 | $14.50 | $14.50 |
| 55 | Removal of signs, posts and footings (713-15) | LS | 1 | $225.00 | $225.00 |
| 56 | Plastic pavement marking(channelization striping) (716-02.04) | SY | 198 | $40.00 | $40.00 |
| 57 | Plastic pavement marking (stop line) (716-02.05) | LF | 127 | $35.00 | $35.00 |
| 58 | Plastic pavement marking (turn lane arrow) (716-02.06) | EACH | 13 | $300.00 | $300.00 |
| 59 | Plastic pavement marking (8" dotted line) (716-02.08) | LF | 1,354 | $4.00 | $4.00 |
| 60 | Plastic pavement marking (U turn arrow) (716-02.15) | EACH | 2 | $300.00 | $300.00 |
| 61 | Enhanced flatline thermo PVMT MRKNG (6IN line) (716-12.02) | LM | 2.56 | $15,000 | $15,000 |
| 62 | Enhanced flatline thermo PVMT MRKNG (8IN barrier line) (716-12.03) | LF | 2,289 | $4.00 | $4.00 |
| 63 | Mobilization (717-01) | LS | 1 | $255,429 | $160,000 |
| 64 | Geotextile (type III)(erosion control) (740-10.03) | SY | 270 | $7.50 | $7.00 |
| 65 | Temporary seeding (with mulch) (801-01.07) | UNIT | 141 | $40.00 | $40.00 |
| 66 | Water (seeding & sodding) (801-03) | MG | 171 | $20.00 | $20.00 |
| 67 | Sodding (new sod) (803-01) | SY | 15,593 | $3.50 | $3.50 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from TDOT's tabulation for this contract. TDOT Summary of Bids PDFs: every letting posted for February 2024 to October 2026, and nine lettings of 2018 to 2023 recovered from archived copies of the tn.gov files. Cost-plus-time bids, and bids that did not match their published total, are left out.
Every contract let that day: TDOT letting of August 14, 2026. Compiled by Mirage Metrics.
Your own bid history, read the same way