TDOT contract CN264052 bid tabulation

The miscellaneous safety improvements on u.s. 51 (s.r. 3) at the intersection of rialto/leighs chapel road (l.m. 20.97 - l.m. 21.50). Let by Tennessee DOT on August 14, 2026, Tipton County. 2 bids received; low bid $2,806,436 by Delta Contracting Company, LLC.

Owner
Tennessee DOT
Letting
14 AUG 2026
Pay items
67
Data through
02 OCT 2026

Bidders

RankBidderTotal bidAgainst the low bid
1Delta Contracting Company, LLC$2,806,436Low
2Ford Construction Company$3,223,106+15%
TDOT contract CN264052: bids by rank

Bid tabulation

LinePay itemUnitQuantity1. Delta Contracting Company, LLC2. Ford Construction Company
1Construction stakes, lines and grades (105-01)LS1$50,000$35,000
2Clearing and grubbing (201-01)LS1$40,000$35,000
3Removal of structures and obstructions (202-01)LS1$10,000$15,000
4Removal of asphalt pavement (202-03.01)SY750$8.00$40.00
5Road & drainage excavation (unclassified) (203-01)CY3,500$36.00$22.00
6Borrow excavation (unclassified) (203-03)CY2,757$10.00$33.00
7Placing and spreading topsoil (203-04)CY1,634$15.00$15.00
8Water (203-06)MG45$60.00$20.00
9Furnishing & spreading topsoil (203-07)CY965$10.00$30.00
10Backfill material (flowable fill) (204-08.01)CY12$400.00$660.00
11Sediment removal (209-05)CY168$10.00$32.00
12Temporary silt fence (without backing) (209-08.03)LF1,457$1.75$1.75
13Enhanced rock check dam (209-08.08)EACH5$1,800.00$1,200.00
14Catch basin protection (type A) (209-40.30)EACH3$1,025.00$400.00
15Mineral aggregate, type A base, grading D (303-01)TON5,096$60.00$66.00
16Mineral aggregate (size 57) (303-10.01)TON21$70.00$73.00
17Asphalt concrete mix (PG64-22) (BPMB-HM) grading B-M2 (307-01.08)TON135$281.80$281.80
18Asp. conc. mix(PG70-22) (BPMB-HM) GR. A-S (307-01.21)TON571$248.50$248.50
19Asphalt concrete mix (PG70-22) (BPMB-HM) grading A (307-02.01)TON1,270$236.65$236.65
20Asphalt concrete mix (PG70-22) (BPMB-HM) grading B-M2 (307-02.08)TON747$245.45$245.45
21Bituminous material for prime coat (PC) (402-01)TON11$1,375.00$1,375.00
22Aggregate for cover material (PC) (402-02)TON38$64.65$64.65
23Bituminous material for tack coat (TC) (403-01)TON15$1,375.00$1,375.00
24Saw cutting asphalt pavement (407-20.05)LF2,666$3.00$10.00
25Acs mix (PG64-22) grading E shoulder (411-01.07)TON127$304.65$304.65
26Acs mix(PG70-22) grading D (411-02.10)TON1,736$212.55$212.55
27Cold planing bituminous pavement (415-01.01)TON1,358$90.50$90.50
2818" concrete pipe culvert (class III) (607-03.02)LF135$100.00$130.00
2930" concrete pipe culvert (class III) (607-06.02)LF73$200.00$222.00
3015" pipe culvert (side drain) (607-39.01)LF47$50.00$130.00
3130IN endwall (cross drain) 6:1 (611-07.62)EACH2$9,000.00$8,500.00
3218IN endwall (median drain) (611-07.73)EACH2$16,900$10,000
33Junction structure, 60IN round,> 4FT-8FT depth (611-63.10)EACH1$7,000.00$4,900.00
34Junction structure, 120IN round,> 4FT-8FT depth (611-63.60)EACH1$28,000$28,000
35Concrete median pavement (701-03)CY484$450.00$1,300.00
36Concrete curb (702-01)CY51$885.00$1,250.00
37High-visibility construction fence (707-08.11)LF265$2.75$2.75
38Markers (concrete R.O.W. posts) (708-02.01)EACH7$750.00$400.00
39Machined rip-rap (class A-1) (709-05.06)TON114$68.00$68.00
40Aggregate underdrains (with pipe) (710-02)LF1,817$14.50$14.50
41Lateral underdrain (710-05)LF90$14.00$14.00
42Lateral underdrain endwall (6:1) (710-06.15)EACH18$1,100.00$1,100.00
43Traffic control (712-01)LS1$50,000$50,000
44Flexible drums (channelizing) (712-04.01)EACH404$35.00$35.00
45Warning lights (type C) (712-05.03)EACH478$10.00$10.00
46Signs (construction) (712-06)SF613$6.00$6.00
47Temporary barricades (type III) (712-07.03)LF96$15.00$15.00
48Sign post delineation enhancement (713-02.21)LF196$5.50$5.50
49"U" section steel posts (713-11.01)LB1,738$3.95$3.95
50Perforated/knockout square tube post (713-11.02)LB454$4.00$4.00
51P post slip base (713-11.21)EACH15$350.00$350.00
52U post slip base (713-11.22)EACH40$300.00$300.00
53Flat sheet aluminum signs (0.080" thick) (713-13.02)SF66$14.00$14.00
54Flat sheet aluminum signs (0.100" thick) (713-13.03)SF456$14.50$14.50
55Removal of signs, posts and footings (713-15)LS1$225.00$225.00
56Plastic pavement marking(channelization striping) (716-02.04)SY198$40.00$40.00
57Plastic pavement marking (stop line) (716-02.05)LF127$35.00$35.00
58Plastic pavement marking (turn lane arrow) (716-02.06)EACH13$300.00$300.00
59Plastic pavement marking (8" dotted line) (716-02.08)LF1,354$4.00$4.00
60Plastic pavement marking (U turn arrow) (716-02.15)EACH2$300.00$300.00
61Enhanced flatline thermo PVMT MRKNG (6IN line) (716-12.02)LM2.56$15,000$15,000
62Enhanced flatline thermo PVMT MRKNG (8IN barrier line) (716-12.03)LF2,289$4.00$4.00
63Mobilization (717-01)LS1$255,429$160,000
64Geotextile (type III)(erosion control) (740-10.03)SY270$7.50$7.00
65Temporary seeding (with mulch) (801-01.07)UNIT141$40.00$40.00
66Water (seeding & sodding) (801-03)MG171$20.00$20.00
67Sodding (new sod) (803-01)SY15,593$3.50$3.50
TDOT contract CN264052: unit prices by line

The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.

Source

Read from TDOT's tabulation for this contract. TDOT Summary of Bids PDFs: every letting posted for February 2024 to October 2026, and nine lettings of 2018 to 2023 recovered from archived copies of the tn.gov files. Cost-plus-time bids, and bids that did not match their published total, are left out.

Every contract let that day: TDOT letting of August 14, 2026. Compiled by Mirage Metrics.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy