TxDOT contract A00020688 bid tabulation
Interchange Improvement, US 67 (AT LAKE RIDGE PKWY to .). Let by Texas DOT on March 4, 2026, Ellis, Dallas District. 9 bids received; low bid $63,703,074 by Highway 19 Construction LLC, -0.1% against the engineer's estimate of $63,765,204.
- Owner
- Texas DOT
- Letting
- 04 MAR 2026
- Pay items
- 255
- Data through
- 19 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | Highway 19 Construction LLC | $63,703,074 | Low | 0.0% |
| 2 | RPM Xconstruction, LLC | $64,759,007 | +2.0% | +2.0% |
| 3 | Harper Brothers Construction LLC | $66,338,016 | +4.0% | +4.0% |
| 4 | Webber, LLC | $67,440,046 | +6.0% | +6.0% |
| 5 | Granite Construction Company | $68,859,637 | +8.0% | +8.0% |
| 6 | Mario Sinacola & Sons Excavating, Inc. | $73,360,305 | +15% | +15% |
| 7 | Zachry Construction Corporation | $73,861,075 | +16% | +16% |
| 8 | Sema Construction, Inc. | $74,989,385 | +18% | +18% |
| 9 | Austin Bridge & Road Services, LP | $86,099,270 | +35% | +35% |
Engineer's estimate: $63,765,204.
Bid tabulation
| Line | Pay item | Unit | Quantity | Estimate | 1. Highway 19 Construction LLC | 2. RPM Xconstruction, LLC | 3. Harper Brothers Construction LLC | 4. Webber, LLC | 5. Granite Construction Company | 6. Mario Sinacola & Sons Excavating, Inc. |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Preparing row (100-7002) | STA | 125 | $10,000 | $300.00 | $9,000.00 | $4,000.00 | $27,609 | $49,400 | $15,000 |
| 2 | Removing concrete (pavement) (104-7001) | SY | 59,167 | $12.00 | $13.00 | $2.50 | $6.00 | $12.60 | $4.80 | $9.00 |
| 3 | Removing concrete (riprap) (104-7006) | SY | 2,264 | $12.50 | $15.00 | $5.00 | $10.17 | $20.20 | $4.40 | $9.00 |
| 4 | Removing concrete (pavers) (104-7010) | SY | 320 | $9.20 | $25.00 | $12.00 | $12.73 | $16.10 | $4.00 | $9.00 |
| 5 | Removing concrete (driveways) (104-7011) | SY | 2,849 | $20.00 | $9.00 | $6.93 | $18.60 | $8.00 | $9.00 | |
| 6 | Removing concrete (sidewalk, ramp or shared use path) (104-7013) | SY | 400 | $25.00 | $20.00 | $8.00 | $10.58 | $25.20 | $4.00 | $9.00 |
| 7 | Removing concrete (curb or curb & gutter) (104-7018) | LF | 245 | $12.50 | $10.00 | $1.80 | $10.90 | $18.50 | $1.00 | $9.00 |
| 8 | Removing concrete (traffic barrier) (104-7035) | LF | 6,352 | $15.00 | $10.00 | $13.70 | $10.65 | $21.60 | $15.00 | $11.00 |
| 9 | Remove (4"-8") TRT/untrt base & asphalt pavement (105-7004) | SY | 70,165 | $8.00 | $4.00 | $3.50 | $3.50 | $4.00 | $4.00 | $4.00 |
| 10 | Remove (8"-14") TRT/untrt base & asphalt pavement (105-7059) | SY | 70,504 | $10.00 | $5.00 | $5.00 | $5.50 | $8.35 | $7.00 | $9.00 |
| 11 | Excavation (roadway) (110-7001) | CY | 168,119.08 | $5.00 | $4.52 | $6.80 | $5.00 | $9.15 | $12.00 | $12.00 |
| 12 | Embankment (final)(DC)(type C1) (132-7008) | CY | 341,039.83 | $12.00 | $11.00 | $19.50 | $16.00 | $11.70 | $17.00 | $20.00 |
| 13 | Embankment (final)(DC)(type C2) (132-7010) | CY | 18,515.52 | $30.00 | $11.00 | $27.00 | $28.00 | $149.00 | $65.00 | $30.00 |
| 14 | Compost manuf topsoil (4") (161-7002) | SY | 306,274 | $1.00 | $1.00 | $1.80 | $1.23 | $1.65 | $1.70 | $2.00 |
| 15 | Block sodding (162-7002) | SY | 306,274 | $3.00 | $3.85 | $3.50 | $3.42 | $3.40 | $3.45 | $3.42 |
| 16 | Drill seed (temporary_warm) (164-7013) | SY | 153,137 | $0.12 | $0.13 | $0.01 | $0.12 | $0.10 | $0.10 | $0.12 |
| 17 | Drill seed (temporary_cool) (164-7014) | SY | 153,137 | $0.12 | $0.13 | $0.01 | $0.12 | $0.10 | $0.10 | $0.12 |
| 18 | Vegetative watering (168-7001) | TGL | 91,122.55 | $1.00 | $1.00 | $0.10 | $8.00 | $7.55 | $0.10 | $0.10 |
| 19 | Proof rolling (216-7001) | HR | 2 | $110.00 | $100.00 | $618.00 | $300.00 | $287.00 | $115.00 | $115.00 |
| 20 | Lime (com or QK)(slurry) (260-7005) | TON | 2,722 | $295.00 | $350.00 | $300.00 | $404.55 | $298.00 | $325.00 | $300.00 |
| 21 | Lime TRT (existing material)(6") (260-7006) | SY | 1,618 | $5.00 | $3.50 | $3.00 | $10.76 | $23.50 | $7.00 | $5.00 |
| 22 | Lime TRT (existing material)(10") (260-7008) | SY | 97,228 | $6.00 | $7.00 | $2.80 | $5.38 | $3.65 | $5.00 | $6.00 |
| 23 | Lime TRT (existing material)(12") (260-7009) | SY | 87,218 | $8.00 | $7.00 | $3.20 | $7.76 | $3.20 | $6.00 | $7.00 |
| 24 | SP mixes SP-B PG64-22 (344-7001) | TON | 42,611 | $110.00 | $111.00 | $112.00 | $108.10 | $108.00 | $109.09 | $108.10 |
| 25 | SP mixes SP-C sac-A PG70-22 (344-7020) | TON | 179 | $200.00 | $200.00 | $273.00 | $200.00 | $262.00 | $264.61 | $262.20 |
| 26 | Concrete pavement (CRCP) (11") (360-7005) | SY | 89,247 | $85.00 | $95.00 | $85.00 | $80.00 | $81.75 | $81.00 | $78.00 |
| 27 | Concrete pavement (CRCP) (13") (360-7007) | SY | 77,416 | $105.00 | $104.00 | $87.00 | $85.00 | $91.00 | $92.00 | $92.00 |
| 28 | Concrete pavement (CPCD) (11") (360-7021) | SY | 9,146 | $90.00 | $103.00 | $73.00 | $85.88 | $99.50 | $80.00 | $84.00 |
| 29 | Cut & restoring pavement (400-7006) | SY | 344 | $105.75 | $250.00 | $195.00 | $188.64 | $214.00 | $175.00 | $200.00 |
| 30 | Cem stabil BKFL (400-7010) | CY | 500 | $165.75 | $180.00 | $289.00 | $212.96 | $176.00 | $100.00 | $213.00 |
| 31 | Trench excavation protection (402-7001) | LF | 4,770 | $2.80 | $10.00 | $2.40 | $5.00 | $7.05 | $20.00 | $10.00 |
| 32 | Temporary special shoring (403-7001) | SF | 41,080 | $30.00 | $55.00 | $28.00 | $31.89 | $36.25 | $30.00 | $56.00 |
| 33 | Drilled shaft (18 in) (416-7002) | LF | 376 | $225.00 | $150.00 | $139.00 | $194.62 | $124.00 | $100.00 | $100.00 |
| 34 | Drilled shaft (36 in) (416-7006) | LF | 354 | $300.00 | $250.00 | $240.00 | $316.47 | $228.00 | $210.00 | $250.00 |
| 35 | Drilled shaft (42 in) (416-7007) | LF | 2,416 | $275.00 | $265.00 | $259.00 | $271.17 | $241.00 | $240.00 | $275.00 |
| 36 | Drilled shaft (sign mounts) (24 in) (416-7028) | LF | 82 | $295.90 | $184.00 | $280.00 | $232.00 | $184.00 | $185.85 | $230.00 |
| 37 | Drilled shaft (sign mounts) (54 in) (416-7033) | LF | 55 | $690.00 | $717.00 | $841.00 | $705.00 | $717.00 | $724.25 | $685.00 |
| 38 | Drilled shaft (roadway illumination pole) (30 in) (416-7040) | LF | 408 | $479.73 | $265.00 | $322.00 | $236.25 | $265.00 | $305.00 | $275.00 |
| 39 | Drilled shaft (traffic signal pole) (30 in) (416-7043) | LF | 33 | $383.90 | $415.00 | $561.00 | $699.00 | $415.00 | $477.65 | $330.00 |
| 40 | Drilled shaft (traffic signal pole) (36 in) (416-7044) | LF | 39 | $386.61 | $487.00 | $730.00 | $767.00 | $487.00 | $560.50 | $400.00 |
| 41 | Class B concrete (flume) (420-7010) | CY | 8 | $744.00 | $1,000.00 | $666.00 | $1,150.20 | $1,050.00 | $1,200.00 | $970.00 |
| 42 | Class C concrete (abutment)(HPC) (420-7013) | CY | 238.40 | $1,269.00 | $963.00 | $1,240.00 | $1,575.03 | $1,340.00 | $1,290.00 | $1,500.00 |
| 43 | Class C concrete (cap)(HPC) (420-7023) | CY | 188.60 | $1,300.00 | $1,000.00 | $1,568.00 | $1,525.53 | $1,380.00 | $1,200.00 | $1,500.00 |
| 44 | Class C concrete (column)(HPC) (420-7039) | CY | 142.80 | $1,600.00 | $1,300.00 | $1,337.00 | $1,560.37 | $1,270.00 | $1,400.00 | $1,500.00 |
| 45 | Reinforced concrete slab (HPC) (422-7002) | SF | 55,308 | $23.00 | $19.00 | $28.00 | $34.94 | $22.00 | $26.75 | $26.00 |
| 46 | Approach slab (HPC) (422-7014) | CY | 310 | $500.00 | $750.00 | $649.00 | $1,195.35 | $577.00 | $650.00 | $652.00 |
| 47 | Retaining wall (MSE) (423-7001) | SF | 45,663 | $75.00 | $80.00 | $71.00 | $128.64 | $60.50 | $65.00 | $99.00 |
| 48 | Retaining wall (special) (423-7029) | SF | 4,586 | $110.00 | $92.00 | $157.00 | $208.00 | $41.00 | $80.00 | $120.00 |
| 49 | Prestressed concrete girder (TX34) (425-7002) | LF | 884.87 | $200.00 | $275.00 | $220.00 | $304.03 | $199.00 | $200.00 | $185.00 |
| 50 | Prestressed concrete girder (TX62) (425-7006) | LF | 6,362.93 | $227.50 | $275.00 | $272.00 | $304.24 | $253.00 | $250.00 | $215.00 |
| 51 | Riprap (concrete)(4 in) (432-7001) | CY | 600 | $550.00 | $550.00 | $610.00 | $482.52 | $543.00 | $425.00 | $645.00 |
| 52 | Riprap (concrete)(5 in) (432-7002) | CY | 7.10 | $1,000.00 | $648.00 | $654.45 | $567.00 | $800.00 | $900.00 | |
| 53 | Riprap (concrete)(CL B) (432-7005) | CY | 18.20 | $401.17 | $500.00 | $533.00 | $708.36 | $812.00 | $500.00 | $750.00 |
| 54 | Riprap (mow strip)(4 in) (432-7013) | CY | 233 | $508.00 | $550.00 | $555.00 | $744.98 | $711.00 | $625.00 | $645.00 |
| 55 | Riprap (stone common)(dry)(12 in) (432-7031) | CY | 200 | $100.50 | $150.00 | $247.00 | $179.20 | $270.00 | $205.00 | $310.00 |
| 56 | Rail (type SSTR) (450-7024) | LF | 4,240 | $69.75 | $90.00 | $75.00 | $98.19 | $81.25 | $74.00 | $80.00 |
| 57 | Rail (type SSTR)(HPC) (450-7025) | LF | 1,966.60 | $74.50 | $120.00 | $107.00 | $141.19 | $64.75 | $100.00 | $80.00 |
| 58 | Sealed expansion joint (4 in) (SEJ - M) (454-7004) | LF | 331 | $226.00 | $180.00 | $203.00 | $270.06 | $225.00 | $300.00 | $220.00 |
| 59 | Concrete box culvert (3 FT X 2 FT) (462-7001) | LF | 2,176 | $350.00 | $272.00 | $300.23 | $193.00 | $250.00 | $275.00 | |
| 60 | Concrete box culvert (5 FT X 2 FT) (462-7006) | LF | 84 | $450.00 | $478.00 | $1,317.68 | $363.00 | $300.00 | $350.00 | |
| 61 | RC pipe (CL III)(18 in) (464-7003) | LF | 4,232 | $80.00 | $64.00 | $74.20 | $76.55 | $68.25 | $75.00 | $120.00 |
| 62 | RC pipe (CL III)(24 in) (464-7005) | LF | 12,034 | $92.00 | $83.00 | $90.00 | $102.04 | $79.00 | $85.00 | $153.00 |
| 63 | RC pipe (CL III)(36 in) (464-7009) | LF | 1,254 | $200.00 | $156.00 | $150.00 | $136.76 | $121.00 | $130.00 | $245.00 |
| 64 | RC pipe (CL IV)(24 in) (464-7021) | LF | 208 | $100.00 | $95.00 | $280.80 | $720.00 | $95.00 | $260.00 | |
| 65 | RC pipe (CL IV)(36 in) (464-7024) | LF | 560 | $247.00 | $181.00 | $243.23 | $710.00 | $130.00 | $310.00 | |
| 66 | Junction box(complete)(PJB)(3FTX3FT) (465-7005) | EACH | 40 | $5,000.00 | $4,500.00 | $3,840.00 | $6,309.12 | $5,920.00 | $1.00 | $9,500.00 |
| 67 | Inlet (complete)(pcu)(3FT)(none) (465-7029) | EACH | 10 | $7,425.00 | $5,000.00 | $5,705.00 | $9,889.75 | $7,240.00 | $5,500.00 | $10,000 |
| 68 | Inlet (complete)(pcu)(3FT)(left) (465-7030) | EACH | 20 | $6,500.00 | $7,500.00 | $6,130.00 | $9,913.44 | $7,540.00 | $6,000.00 | $10,500 |
| 69 | Inlet (complete)(pcu)(3FT)(right) (465-7031) | EACH | 14 | $6,810.00 | $9,500.00 | $6,325.00 | $10,602 | $7,620.00 | $6,000.00 | $10,500 |
| 70 | Inlet (complete)(pcu)(3FT)(both) (465-7032) | EACH | 17 | $8,450.00 | $5,750.00 | $6,735.00 | $11,041 | $7,980.00 | $6,500.00 | $11,600 |
| 71 | Inlet (complete)(PSL)(FG)(3FTX3FT-3FTX3FT) (465-7126) | EACH | 2 | $5,750.00 | $5,230.00 | $7,707.36 | $6,360.00 | $4,500.00 | $7,600.00 | |
| 72 | Inlet (complete)(PSL)(FG)(3FTX5FT-3FTX5FT) (465-7130) | EACH | 8 | $7,836.36 | $6,900.00 | $5,665.00 | $9,874.15 | $5,710.00 | $5,000.00 | $8,000.00 |
| 73 | Inlet(complete)(PSL)(SFG)(4FTX4FT-4FTX4FT) (465-7147) | EACH | 1 | $7,500.00 | $5,800.00 | $8,613.86 | $5,330.00 | $6,000.00 | $9,400.00 | |
| 74 | Inlet(complete)(type MSE1) (465-7362) | EACH | 41 | $8,000.00 | $6,675.00 | $7,640.00 | $7,715.21 | $9,490.00 | $7,400.00 | $9,820.09 |
| 75 | Headwall (CH - FW - 0) (diameter= 18 in) (466-7003) | EACH | 1 | $6,450.00 | $2,500.00 | $5,720.00 | $8,089.72 | $8,990.00 | $11,000 | $10,250 |
| 76 | Headwall (CH - FW - 0) (diameter= 24 in) (466-7005) | EACH | 2 | $9,730.13 | $4,500.00 | $4,880.00 | $6,457.13 | $6,220.00 | $10,500 | $5,000.00 |
| 77 | Headwall (CH - FW - 15) (diameter= 24 in) (466-7020) | EACH | 1 | $6,872.00 | $4,500.00 | $7,410.00 | $9,489.56 | $9,810.00 | $11,000 | $11,600 |
| 78 | Headwall (CH - FW - 30) (diameter= 24 in) (466-7035) | EACH | 3 | $7,923.05 | $4,500.00 | $6,760.00 | $7,778.03 | $9,960.00 | $11,000 | $10,000 |
| 79 | Headwall (CH - FW - 45) (diameter= 36 in) (466-7054) | EACH | 1 | $7,200.00 | $8,150.00 | $11,066 | $16,520 | $12,500 | $11,300 | |
| 80 | Headwall (CH - PW - 0) (diameter= 18 in) (466-7099) | EACH | 1 | $7,800.00 | $3,500.00 | $5,595.00 | $6,620.08 | $8,890.00 | $11,000 | $9,500.00 |
| 81 | Headwall (CH - PW - S) (diameter= 24 in) (466-7116) | EACH | 2 | $7,768.81 | $4,500.00 | $7,460.00 | $8,851.13 | $13,480 | $11,500 | $8,500.00 |
| 82 | Headwall (CH - PW - S) (diameter= 36 in) (466-7120) | EACH | 3 | $9,984.73 | $7,200.00 | $16,550 | $14,412 | $17,990 | $13,500 | $19,275 |
| 83 | Wingwall (FW - 0) (HW=5 FT) (466-7147) | EACH | 1 | $15,000 | $14,720 | $13,924 | $12,930 | $14,000 | $27,000 | |
| 84 | Wingwall (PW - 1) (HW=4 FT) (466-7174) | EACH | 1 | $12,000 | $13,290 | $14,532 | $15,940 | $14,700 | $19,000 | |
| 85 | Wingwall (PW - 1) (HW=5 FT) (466-7175) | EACH | 1 | $15,000 | $22,525 | $20,916 | $19,700 | $16,700 | $33,500 | |
| 86 | Set (type I) (24 in) (4: 1) (C) (467-7006) | EACH | 1 | $2,175.00 | $950.00 | $1,635.00 | $11,027 | $11,190 | $5,500.00 | $3,000.00 |
| 87 | Set (type II) (18 in) (RCP) (4: 1) (C) (467-7306) | EACH | 1 | $950.00 | $1,295.00 | $2,312.11 | $1,420.00 | $1,600.00 | $2,750.00 | |
| 88 | Set (type II) (18 in) (RCP) (6: 1) (P) (467-7308) | EACH | 16 | $1,200.00 | $1,150.00 | $1,370.00 | $2,016.67 | $1,790.00 | $2,000.00 | $3,000.00 |
| 89 | Set (type II) (24 in) (RCP) (6: 1) (C) (467-7327) | EACH | 1 | $2,550.00 | $1,600.00 | $1,635.00 | $2,622.91 | $1,719.01 | $2,200.00 | $3,350.00 |
| 90 | Set (type II) (24 in) (RCP) (6: 1) (P) (467-7328) | EACH | 33 | $2,256.93 | $1,600.00 | $1,640.00 | $2,164.13 | $1,660.00 | $2,200.00 | $3,350.00 |
| 91 | Set (type II) (36 in) (RCP) (6: 1) (P) (467-7368) | EACH | 4 | $6,910.00 | $4,950.00 | $5,218.46 | $3,710.00 | $7,500.00 | $8,000.00 | |
| 92 | Jack bor or tun pipe(24 in)(RC)(CL IV) (476-7021) | LF | 76 | $250.00 | $860.00 | $1,610.77 | $720.00 | $900.00 | $925.00 | |
| 93 | Jack bor or tun pipe(36 in)(RC)(CL IV) (476-7023) | LF | 466 | $2,000.00 | $350.00 | $1,445.00 | $1,456.34 | $710.00 | $1,400.00 | $1,175.00 |
| 94 | Removing structure (inlet) (496-7002) | EACH | 8 | $500.00 | $1,125.00 | $584.85 | $1,080.00 | $650.00 | $1,500.00 | |
| 95 | Removing structure (set) (496-7004) | EACH | 34 | $350.00 | $500.00 | $747.00 | $397.80 | $723.00 | $384.10 | $950.00 |
| 96 | Removing structure (wingwall) (496-7005) | EACH | 1 | $1,000.00 | $2,430.00 | $2,339.40 | $2,170.00 | $1,540.95 | $3,500.00 | |
| 97 | Removing structure (pipe) (496-7007) | LF | 4,986 | $31.75 | $10.00 | $25.00 | $16.29 | $25.60 | $20.00 | $35.00 |
| 98 | Mobilization (500-7001) | LS | 1 | $5,797,128 | $6,000,000 | $6,400,000 | $4,300,000 | $6,744,000 | $6,000,000 | $7,200,000 |
| 99 | Barricades, signs and traffic handling (502-7001) | MO | 32 | $20,000 | $5,000.00 | $15,000 | $18,000 | $38,430 | $18,000 | $40,000 |
| 100 | TMA (stationary) (505-7001) | DAY | 963 | $170.00 | $250.00 | $220.00 | $150.00 | $122.00 | $190.00 | $300.00 |
| 101 | TMA (mobile operation) (505-7003) | DAY | 30 | $300.00 | $1,000.00 | $1,040.00 | $894.32 | $808.00 | $100.00 | $1,500.00 |
| 102 | Rock filter dams (install) (type 2) (506-7002) | LF | 1,112 | $33.85 | $45.00 | $50.00 | $43.17 | $43.00 | $43.60 | $35.00 |
| 103 | Rock filter dams (remove) (506-7011) | LF | 1,112 | $18.52 | $5.00 | $17.50 | $15.17 | $5.00 | $15.30 | $5.00 |
| 104 | Construction exits (install) (type 1) (506-7020) | SY | 246 | $29.28 | $35.00 | $59.00 | $51.33 | $33.25 | $10.00 | $30.00 |
| 105 | Temporary sediment control fence (install) (506-7039) | LF | 10,516 | $3.20 | $3.00 | $4.00 | $3.52 | $3.50 | $3.55 | $3.15 |
| 106 | Temporary sediment control fence (remove) (506-7041) | LF | 10,516 | $0.96 | $1.00 | $0.90 | $0.80 | $0.80 | $0.80 | $0.10 |
| 107 | Biodegradable erosion control logs (install) (12") (506-7044) | LF | 2,920 | $4.90 | $4.00 | $7.40 | $6.50 | $4.00 | $6.55 | $3.25 |
| 108 | Biodegradable erosion control logs (remove) (506-7046) | LF | 2,920 | $1.55 | $1.00 | $1.10 | $0.93 | $1.00 | $0.95 | $0.25 |
| 109 | Constructing detours (508-7001) | SY | 23,650 | $85.00 | $75.00 | $88.00 | $73.35 | $89.25 | $90.00 | $120.00 |
| 110 | Portable concrete traffic barrier (furnish and install)(F-shape)(type 1) (512-7005) | LF | 18,316 | $30.00 | $79.00 | $49.00 | $25.22 | $19.00 | $36.75 | $20.00 |
| 111 | Portable concrete traffic barrier (furnish and install)(low prof)(type 1) (512-7009) | LF | 580 | $60.00 | $90.00 | $82.00 | $78.41 | $56.25 | $78.40 | $47.00 |
| 112 | Portable concrete traffic barrier (furnish and install)(low prof)(type 2) (512-7010) | LF | 20 | $60.00 | $110.00 | $733.00 | $332.06 | $106.00 | $141.25 | $65.00 |
| 113 | Portable concrete traffic barrier (move)(F-shape)(type 1) (512-7029) | LF | 32,085 | $7.80 | $10.00 | $3.75 | $5.01 | $5.85 | $5.40 | $5.00 |
| 114 | Portable concrete traffic barrier (remove)(F-shape)(type 1) (512-7053) | LF | 18,316 | $9.00 | $25.00 | $4.80 | $11.38 | $8.00 | $7.98 | $5.00 |
| 115 | Portable concrete traffic barrier (pinning) (512-7071) | EACH | 1,287 | $60.00 | $10.00 | $97.00 | $153.87 | $128.00 | $54.80 | $120.00 |
| 116 | Permanent CTB (single slope) (type 1) (42 ) (514-7001) | LF | 4,380 | $108.00 | $84.00 | $112.00 | $105.53 | $82.25 | $95.00 | $80.00 |
| 117 | Permanent CTB (F-shape) (type 1) (514-7013) | LF | 1,645 | $100.00 | $80.00 | $94.00 | $77.83 | $78.50 | $110.00 | $125.00 |
| 118 | Colored textured concrete (6") (527-7003) | SY | 4,032 | $100.00 | $180.00 | $192.00 | $169.09 | $87.50 | $65.00 | $150.00 |
| 119 | Concrete curb (mono) (type II) (529-7007) | LF | 34,328 | $3.25 | $10.00 | $2.50 | $1.89 | $4.05 | $7.00 | $1.00 |
| 120 | Concrete curb & gutter (type II) (529-7009) | LF | 525 | $35.00 | $27.00 | $44.02 | $36.00 | $45.00 | $48.00 | |
| 121 | Driveways (concrete) (530-7006) | SY | 4,293 | $90.00 | $96.00 | $97.00 | $90.28 | $108.00 | $90.00 | $100.00 |
| 122 | Concrete sidewalks (4") (531-7001) | SY | 260 | $95.00 | $66.00 | $62.00 | $67.39 | $103.00 | $55.00 | $80.00 |
| 123 | Curb ramps (type 1) (531-7005) | EACH | 2 | $3,900.00 | $1,500.00 | $2,391.00 | $2,897.80 | $3,610.00 | $3,400.00 | $2,900.00 |
| 124 | Curb ramps (type 21) (531-7013) | EACH | 1 | $4,750.00 | $2,100.00 | $2,543.00 | $2,998.31 | $6,440.00 | $4,200.00 | $3,400.00 |
| 125 | Curb ramps (type 22) (531-7014) | EACH | 2 | $5,200.00 | $1,800.00 | $4,189.00 | $3,397.80 | $6,170.00 | $4,500.00 | $3,500.00 |
| 126 | Mill rumble strips (concrete) (shoulder) (533-7003) | LF | 25,497 | $0.65 | $0.25 | $0.85 | $1.62 | $1.00 | $1.00 | $1.00 |
| 127 | Fill milled concr rumble strips (shoulder) (533-7007) | LF | 23,539 | $0.10 | $1.00 | $14.00 | $13.77 | $13.80 | $3.00 | $15.00 |
| 128 | Concrete median (mono nose) (536-7006) | SY | 48 | $190.00 | $180.00 | $221.00 | $197.60 | $321.00 | $200.00 | $160.00 |
| 129 | Right of way markers (538-7001) | EACH | 36 | $309.00 | $405.00 | $447.00 | $405.00 | $503.00 | $500.00 | $405.00 |
| 130 | Metal W-beam guard fence (timber post) (540-7001) | LF | 1,210 | $25.25 | $26.00 | $23.00 | $25.00 | $22.50 | $22.75 | $22.50 |
| 131 | Metal beam guard fence trans (thrie-beam) (540-7005) | EACH | 6 | $2,175.00 | $1,850.00 | $1,976.00 | $1,990.00 | $1,900.00 | $1,919.20 | $1,900.00 |
| 132 | Downstream anchor terminal section (540-7015) | EACH | 10 | $1,275.00 | $1,250.00 | $1,248.00 | $1,485.00 | $1,200.00 | $1,212.10 | $1,200.00 |
| 133 | Remove metal beam guard fence (542-7001) | LF | 430 | $3.00 | $3.00 | $2.75 | $2.75 | $2.80 | $2.75 | |
| 134 | Remove terminal anchor section (542-7002) | EACH | 1 | $250.00 | $156.00 | $275.00 | $150.00 | $151.50 | $150.00 | |
| 135 | Guardrail end treatment (install) (544-7001) | EACH | 10 | $3,100.00 | $3,500.00 | $3,068.00 | $3,169.00 | $2,950.00 | $3,012.72 | $2,950.00 |
| 136 | Crash cushion attenuator (move & reset) (545-7002) | EACH | 18 | $1,585.00 | $1,000.00 | $1,185.00 | $1,169.00 | $1,440.00 | $833.40 | $1,600.00 |
| 137 | Crash cushion attenuator (remove) (545-7004) | EACH | 6 | $910.00 | $500.00 | $790.00 | $885.00 | $646.00 | $1,250.10 | $1,600.00 |
| 138 | Crash cushion attenuator (install)(R)(N)(TL3) (545-7010) | EACH | 1 | $25,500 | $30,000 | $24,764 | $29,810 | $19,190 | $25,000 | $25,000 |
| 139 | Crash cushion attenuator (install)(S)(N)(TL3) (545-7014) | EACH | 6 | $7,850.00 | $7,500.00 | $9,270.00 | $7,570.00 | $7,610.00 | $1,380.15 | $10,000 |
| 140 | Pipe underdrains (type 6) (6") (556-7006) | LF | 4,546 | $28.00 | $15.00 | $27.00 | $65.49 | $35.00 | $24.00 | $60.00 |
| 141 | Relocate RD IL asm (trans-base) (610-7004) | EACH | 13 | $4,500.00 | $4,597.00 | $2,139.00 | $2,390.00 | $2,409.10 | $4,325.00 | |
| 142 | In RD IL (U/P) (type 1) (150W EQ) LED (610-7014) | EACH | 8 | $1,600.00 | $2,750.00 | $2,502.00 | $1,827.00 | $1,880.00 | $2,158.00 | $2,750.00 |
| 143 | In RD IL (type SA) 40T-8 (250W EQ) LED (610-7124) | EACH | 38 | $3,500.00 | $5,075.00 | $6,350.00 | $3,954.00 | $4,680.00 | $5,390.90 | $5,075.00 |
| 144 | Conduit (PVC) (schedule 40) (2") (618-7030) | LF | 18,023 | $12.00 | $15.00 | $11.45 | $12.74 | $8.95 | $10.30 | $15.00 |
| 145 | Conduit (PVC) (schedule 40) (2") (bore) (618-7031) | LF | 1,495 | $35.99 | $33.00 | $26.00 | $32.45 | $28.60 | $32.90 | $33.00 |
| 146 | Conduit (PVC) (schedule 40) (3") (618-7036) | LF | 132 | $25.39 | $17.00 | $18.20 | $32.55 | $11.40 | $13.15 | $17.00 |
| 147 | Conduit (PVC) (schedule 40) (4") (618-7040) | LF | 808 | $32.00 | $19.00 | $19.50 | $33.60 | $21.00 | $24.15 | $19.00 |
| 148 | Conduit (PVC) (schedule 40) (4") (bore) (618-7041) | LF | 375 | $57.97 | $45.00 | $36.50 | $63.00 | $39.75 | $45.70 | $45.00 |
| 149 | Conduit (PVC) (schedule 80) (2") (618-7054) | LF | 33 | $26.00 | $20.00 | $40.00 | $31.50 | $10.60 | $12.15 | $20.00 |
| 150 | Conduit (RM) (1") (618-7072) | LF | 205 | $29.36 | $35.00 | $40.00 | $44.25 | $25.00 | $28.75 | $35.00 |
| 151 | Conduit (RM) (2") (618-7078) | LF | 40 | $52.00 | $45.00 | $59.30 | $81.85 | $38.00 | $43.75 | $45.00 |
| 152 | Electrical conductor (no.12) insulated (620-7004) | LF | 935 | $2.10 | $1.75 | $1.82 | $1.60 | $1.00 | $1.15 | $1.75 |
| 153 | Electrical conductor (no.8) bare (620-7007) | LF | 20,382 | $2.11 | $2.00 | $2.00 | $2.48 | $1.70 | $1.95 | $2.00 |
| 154 | Electrical conductor (no.8) insulated (620-7008) | LF | 43,552 | $2.66 | $2.30 | $2.30 | $2.46 | $1.55 | $1.80 | $2.30 |
| 155 | Electrical conductor (no.6) bare (620-7009) | LF | 1,361 | $3.03 | $2.60 | $2.40 | $3.15 | $2.25 | $2.60 | $2.60 |
| 156 | Electrical conductor (no.4) insulated (620-7012) | LF | 169 | $3.33 | $4.50 | $3.65 | $4.20 | $3.65 | $4.20 | $4.50 |
| 157 | Tray cable (3 conductor) (12 AWG) (621-7002) | LF | 2,606 | $4.22 | $3.80 | $2.30 | $3.15 | $2.40 | $2.75 | $3.80 |
| 158 | Ground box type A (122311)W/apron (624-7002) | EACH | 37 | $2,108.78 | $1,400.00 | $1,540.00 | $1,860.00 | $895.00 | $1,030.10 | $1,400.00 |
| 159 | Ground box type C (162911)W/apron (624-7006) | EACH | 10 | $2,189.45 | $1,825.00 | $1,705.00 | $2,573.00 | $1,380.00 | $1,587.10 | $1,825.00 |
| 160 | Remove ground box (624-7013) | EACH | 5 | $500.00 | $592.00 | $435.00 | $210.00 | $241.70 | $500.00 | |
| 161 | Elc SRV type A 240/480 060(NS)SS(E)GC(O) (628-7044) | EACH | 2 | $13,000 | $12,000 | $13,650 | $10,930 | $10,780 | $12,407 | $12,000 |
| 162 | Elc SRV type D 120/240 070(NS)SS(E)PS(U) (628-7190) | EACH | 1 | $11,322 | $10,000 | $11,380 | $12,075 | $9,900.00 | $11,388 | $10,000 |
| 163 | Aluminum signs (type A) (636-7001) | SF | 119.50 | $40.00 | $36.00 | $35.50 | $35.00 | $33.50 | $33.95 | $35.25 |
| 164 | Aluminum signs (type G) (636-7002) | SF | 624 | $38.00 | $55.00 | $35.50 | $35.00 | $29.40 | $29.70 | $36.75 |
| 165 | Aluminum signs (type O) (636-7003) | SF | 338 | $35.00 | $58.00 | $35.50 | $35.00 | $38.75 | $39.05 | $50.00 |
| 166 | Install small roadside sign support and assembly type 10BWG(1)SA(P) (644-7001) | EACH | 22 | $640.00 | $605.00 | $855.00 | $750.00 | $687.00 | $693.95 | $605.00 |
| 167 | Install small roadside sign support and assembly type 10BWG(1)SA(T) (644-7004) | EACH | 55 | $840.00 | $745.00 | $967.00 | $800.00 | $697.00 | $704.05 | $745.00 |
| 168 | Install small roadside sign support and assembly type 10BWG(1)SB(P) (644-7009) | EACH | 3 | $635.00 | $855.00 | $720.00 | $694.00 | $701.00 | $635.00 | |
| 169 | Install small roadside sign support and assembly type 10BWG(1)SB(T) (644-7012) | EACH | 6 | $765.00 | $1,082.00 | $900.00 | $710.00 | $717.15 | $775.00 | |
| 170 | Install small roadside sign support and assembly type 10BWG(2)SA(P-exal) (644-7018) | EACH | 4 | $1,500.00 | $1,590.00 | $1,810.00 | $2,500.00 | $879.00 | $887.90 | $1,590.00 |
| 171 | Install small roadside sign support and assembly TYS80(1)SA(T) (644-7028) | EACH | 5 | $1,062.46 | $1,000.00 | $1,240.00 | $1,045.00 | $728.00 | $735.35 | $969.00 |
| 172 | Install small roadside sign support and assembly TYS80(1)SA(U-BM) (644-7034) | EACH | 4 | $1,250.00 | $1,285.00 | $1,468.00 | $1,187.00 | $831.00 | $839.40 | $1,285.00 |
| 173 | Install small roadside sign support and assembly TYS80(1)SB(U) (644-7042) | EACH | 1 | $1,000.00 | $1,355.00 | $895.00 | $855.00 | $863.65 | $999.00 | |
| 174 | Install small roadside sign support and assembly TYS80(2)SA(P-exal) (644-7049) | EACH | 1 | $2,550.00 | $2,605.00 | $2,995.00 | $1,220.00 | $1,227.25 | $2,445.00 | |
| 175 | In bridge MNT clearance sign assembly(type N) (644-7061) | EACH | 6 | $2,960.77 | $2,925.00 | $3,415.00 | $55.00 | $3,870.00 | $3,906.05 | $3,955.00 |
| 176 | Install LRSS (struct steel) (647-7001) | LB | 3,538 | $10.20 | $8.50 | $8.00 | $30.50 | $6.75 | $6.85 | $8.50 |
| 177 | Remove lrsa (647-7003) | EACH | 6 | $970.00 | $2,000.00 | $1,265.00 | $1,199.55 | $2,400.00 | $2,419.20 | $2,000.00 |
| 178 | Install overhead sign support(35 FT cant) (650-7038) | EACH | 2 | $47,528 | $38,300 | $21,030 | $54,465 | $61,400 | $62,010 | $38,300 |
| 179 | Install overhead sign support(40 FT cant) (650-7045) | EACH | 1 | $44,900 | $26,650 | $61,855 | $78,300 | $79,101 | $44,900 | |
| 180 | Install delineator assembly (D-SW)SZ 1(BRF)CTB (658-7012) | EACH | 12 | $29.00 | $15.00 | $25.00 | $75.00 | $20.00 | $28.30 | $15.00 |
| 181 | Install delineator assembly (D-SW)SZ 1(BRF)GF1 (658-7015) | EACH | 15 | $29.00 | $15.00 | $21.00 | $450.00 | $20.00 | $28.30 | $25.00 |
| 182 | Install delineator assembly (D-SY)SZ 1(BRF)CTB (658-7031) | EACH | 100 | $40.10 | $15.00 | $25.00 | $450.00 | $20.00 | $28.30 | $15.00 |
| 183 | Install delineator assembly (D-SY)SZ 1(BRF)GF1 (658-7034) | EACH | 18 | $22.00 | $65.00 | $20.80 | $350.00 | $20.00 | $28.30 | $25.00 |
| 184 | Install object marker assembly (OM-2Z)(WFLX)GNDLL (658-7248) | EACH | 70 | $73.25 | $65.00 | $85.30 | $75.00 | $50.00 | $76.65 | $70.00 |
| 185 | Work zone pavement marking non-removing (W)6"(broken) (662-7005) | LF | 4,557 | $0.42 | $0.22 | $0.42 | $0.45 | $0.35 | $1.00 | $1.00 |
| 186 | Work zone pavement marking non-removing (W)6"(solid) (662-7008) | LF | 35,437 | $0.42 | $0.29 | $0.35 | $0.37 | $0.30 | $0.75 | $0.75 |
| 187 | Work zone pavement marking non-removing (Y)6"(solid) (662-7038) | LF | 25,846 | $0.46 | $0.29 | $0.35 | $0.37 | $0.30 | $0.75 | $0.75 |
| 188 | Work zone pavement marking removing (W)6"(broken) (662-7065) | LF | 7,404 | $0.60 | $0.54 | $0.84 | $1.25 | $0.70 | $1.50 | $1.50 |
| 189 | Work zone pavement marking removing (W)6"(solid) (662-7068) | LF | 67,551 | $0.80 | $0.55 | $0.78 | $1.25 | $0.65 | $1.20 | $1.20 |
| 190 | Work zone pavement marking removing (W)8"(solid) (662-7072) | LF | 2,588 | $1.40 | $1.00 | $1.20 | $1.75 | $1.00 | $2.00 | $2.00 |
| 191 | Work zone pavement marking removing (W)12"(solid) (662-7075) | LF | 300 | $5.00 | $2.00 | $2.40 | $3.00 | $2.00 | $5.05 | $5.00 |
| 192 | Work zone pavement marking removing (W)24"(solid) (662-7077) | LF | 67 | $10.00 | $3.00 | $3.60 | $7.00 | $3.00 | $10.10 | $10.00 |
| 193 | Work zone pavement marking removing (Y)6"(solid) (662-7100) | LF | 58,511 | $0.80 | $0.55 | $0.66 | $1.25 | $0.55 | $1.20 | $1.20 |
| 194 | Reflectorized pavement marking type I (W)6"(DOT)(100MIL) (666-7009) | LF | 1,186 | $1.50 | $0.70 | $0.84 | $1.75 | $0.70 | $2.00 | $2.00 |
| 195 | Reflectorized pavement marking type I (W)8"(solid)(100MIL) (666-7024) | LF | 13,557 | $1.25 | $0.87 | $1.04 | $0.89 | $0.85 | $1.50 | $1.50 |
| 196 | Reflectorized pavement marking type I (W)12"(solid)(100MIL) (666-7030) | LF | 5,361 | $3.80 | $2.70 | $3.25 | $2.95 | $2.70 | $4.05 | $4.00 |
| 197 | Reflectorized pavement marking type I (W)24"(solid)(100MIL) (666-7036) | LF | 1,134 | $7.30 | $6.50 | $7.77 | $6.55 | $6.50 | $7.05 | $7.00 |
| 198 | Reflectorized pavement marking type I (W)(arrow)(100MIL) (666-7042) | EACH | 18 | $153.00 | $148.00 | $176.75 | $185.00 | $148.00 | $151.50 | $150.00 |
| 199 | Reflectorized pavement marking type I (W)(word)(100MIL) (666-7066) | EACH | 16 | $170.00 | $159.00 | $190.00 | $215.00 | $159.00 | $171.70 | $170.00 |
| 200 | Reflectorized pavement marking type I (Y)24"(solid)(100MIL) (666-7123) | LF | 2,303 | $11.00 | $6.18 | $7.30 | $6.55 | $6.20 | $6.05 | $6.00 |
| 201 | Reflectorized pavement marking type II (W) 6" (broken) (666-7172) | LF | 9,489 | $0.26 | $0.25 | $0.30 | $0.25 | $0.25 | $0.50 | $0.50 |
| 202 | Reflectorized pavement marking type II (W) 6" (DOT) (666-7173) | LF | 1,186 | $0.60 | $0.33 | $0.40 | $0.25 | $0.35 | $1.00 | $1.00 |
| 203 | Reflectorized pavement marking type II (W) 6" (solid) (666-7175) | LF | 48,619 | $0.21 | $0.20 | $0.24 | $0.20 | $0.20 | $0.30 | $0.30 |
| 204 | Reflectorized pavement marking type II (W) 8" (solid) (666-7179) | LF | 13,552 | $0.48 | $0.45 | $0.54 | $0.25 | $0.45 | $0.40 | $0.40 |
| 205 | Reflectorized pavement marking type II (W) 12" (solid) (666-7182) | LF | 5,361 | $3.05 | $1.45 | $1.75 | $0.40 | $1.45 | $2.00 | $2.00 |
| 206 | Reflectorized pavement marking type II (W) 24" (solid) (666-7184) | LF | 1,134 | $7.99 | $1.00 | $1.20 | $0.70 | $1.00 | $3.05 | $3.00 |
| 207 | Reflectorized pavement marking type II (W) (arrow) (666-7186) | EACH | 14 | $87.88 | $250.00 | $24.00 | $280.00 | $20.00 | $75.75 | $75.00 |
| 208 | Reflectorized pavement marking type II (W) (uturn arrow) (666-7189) | EACH | 3 | $90.00 | $500.00 | $84.00 | $120.00 | $70.00 | $151.50 | $150.00 |
| 209 | Reflectorized pavement marking type II (W) (word) (666-7194) | EACH | 16 | $108.75 | $20.00 | $24.00 | $320.00 | $20.00 | $101.00 | $100.00 |
| 210 | Reflectorized pavement marking type II (W) 36" (yld tri) (666-7201) | EACH | 12 | $30.00 | $50.00 | $60.00 | $60.00 | $50.00 | $40.40 | $40.00 |
| 211 | Reflectorized pavement marking type II (Y) 6" (solid) (666-7213) | LF | 48,493 | $0.22 | $0.25 | $0.30 | $0.20 | $0.25 | $0.30 | $0.30 |
| 212 | Reflectorized pavement marking type II (Y) 24" (solid) (666-7217) | LF | 2,303 | $11.00 | $2.00 | $2.40 | $0.70 | $2.00 | $3.05 | $3.00 |
| 213 | Reflectorized pavement marking type I (W)6"(broken)(100MIL) (666-7408) | LF | 9,489 | $0.80 | $0.57 | $0.68 | $0.69 | $0.55 | $1.00 | $1.00 |
| 214 | Reflectorized pavement marking type I (W)6"(solid)(100MIL) (666-7411) | LF | 48,609 | $0.75 | $0.52 | $0.63 | $0.59 | $0.50 | $0.80 | $0.80 |
| 215 | Reflectorized pavement marking type I (Y)6"(solid)(100MIL) (666-7423) | LF | 48,487 | $0.50 | $0.52 | $0.63 | $0.59 | $0.50 | $0.80 | $0.80 |
| 216 | Reflectorized pavement marker type I-C (672-7002) | EACH | 160 | $5.00 | $4.00 | $4.80 | $3.85 | $4.00 | $6.05 | $6.00 |
| 217 | Reflectorized pavement marker type II-A-A (672-7004) | EACH | 24 | $5.05 | $4.00 | $4.80 | $3.85 | $4.00 | $6.05 | $6.00 |
| 218 | Reflectorized pavement marker type II-C-R (672-7006) | EACH | 1,250 | $4.65 | $4.00 | $4.80 | $3.65 | $4.00 | $6.05 | $6.00 |
| 219 | Eliminating existing PM & markers (4") (677-7001) | LF | 2,946 | $0.30 | $0.80 | $0.96 | $0.50 | $0.80 | $1.00 | $1.00 |
| 220 | Eliminating existing PM & markers (6") (677-7002) | LF | 18,185 | $0.60 | $0.72 | $0.50 | $0.60 | $1.00 | $1.00 | |
| 221 | Eliminating existing PM & markers (8") (677-7004) | LF | 2,536 | $0.70 | $0.65 | $0.78 | $0.55 | $0.65 | $1.00 | $1.00 |
| 222 | Eliminating existing PM & markers (12") (677-7006) | LF | 165 | $1.50 | $1.75 | $2.08 | $1.50 | $1.75 | $2.55 | $2.50 |
| 223 | Pavement surface preparation for marking (6") (678-7002) | LF | 106,595 | $0.08 | $0.13 | $0.18 | $0.05 | $0.15 | $0.02 | $0.02 |
| 224 | Pavement surface preparation for marking (8") (678-7004) | LF | 13,552 | $0.16 | $0.20 | $0.24 | $0.07 | $0.20 | $0.05 | $0.05 |
| 225 | Pavement surface preparation for marking (12") (678-7006) | LF | 5,387 | $0.75 | $0.35 | $0.42 | $0.10 | $0.35 | $0.10 | $0.10 |
| 226 | Pavement surface preparation for marking (24") (678-7008) | LF | 3,437 | $0.95 | $0.45 | $0.54 | $0.20 | $0.45 | $0.50 | $0.50 |
| 227 | Pavement surface preparation for marking (arrow) (678-7009) | EACH | 18 | $28.00 | $9.00 | $10.75 | $10.00 | $9.00 | $50.50 | $50.00 |
| 228 | Pavement surface preparation for marking (word) (678-7016) | EACH | 16 | $25.22 | $9.00 | $10.75 | $10.00 | $9.00 | $50.50 | $50.00 |
| 229 | Pavement surface preparation for marking (RPM) (678-7033) | EACH | 1,434 | $1.86 | $0.48 | $0.57 | $0.25 | $0.50 | $1.00 | $1.00 |
| 230 | Install highway traffic signal (isolated) (680-7002) | EACH | 1 | $53,700 | $47,725 | $60,300 | $30,000 | $48,760 | $56,119 | $47,725 |
| 231 | Vehicle signal section (12")LED(green) (682-7001) | EACH | 7 | $515.23 | $430.00 | $490.00 | $683.00 | $385.00 | $443.10 | $430.00 |
| 232 | Vehicle signal section (12")LED(green arrow) (682-7002) | EACH | 9 | $546.78 | $430.00 | $490.00 | $683.00 | $393.00 | $452.30 | $430.00 |
| 233 | Vehicle signal section (12")LED(yel) (682-7003) | EACH | 11 | $530.24 | $430.00 | $490.00 | $683.00 | $385.00 | $443.10 | $430.00 |
| 234 | Vehicle signal section (12")LED(yel arrow) (682-7004) | EACH | 8 | $500.62 | $430.00 | $490.00 | $683.00 | $393.00 | $452.30 | $430.00 |
| 235 | Vehicle signal section (12")LED(red) (682-7005) | EACH | 11 | $531.28 | $430.00 | $490.00 | $683.00 | $385.00 | $443.10 | $430.00 |
| 236 | Vehicle signal section (12")LED(red arrow) (682-7006) | EACH | 8 | $485.43 | $430.00 | $490.00 | $683.00 | $393.00 | $452.30 | $430.00 |
| 237 | Pedestrian signal section (LED)(countdown) (682-7018) | EACH | 2 | $1,100.00 | $1,200.00 | $1,140.00 | $1,260.00 | $889.00 | $1,023.15 | $1,200.00 |
| 238 | Backplate W/ref border(3 sec)(vent)aluminum (682-7042) | EACH | 13 | $278.00 | $365.00 | $296.00 | $263.00 | $210.00 | $241.70 | $365.00 |
| 239 | Backplate W/ref border(5 sec)(vent)aluminum (682-7044) | EACH | 3 | $250.00 | $400.00 | $375.00 | $294.00 | $265.00 | $305.00 | $400.00 |
| 240 | Traffic signal CBL (type A)(14 AWG)(5 conductor) (684-7031) | LF | 538 | $3.60 | $3.25 | $2.50 | $3.15 | $3.30 | $3.80 | $3.25 |
| 241 | Traffic signal CBL (type A)(14 AWG)(7 conductor) (684-7033) | LF | 325 | $3.85 | $4.25 | $3.65 | $3.15 | $3.55 | $4.10 | $4.25 |
| 242 | Traffic signal CBL (type A)(14 AWG)(16 conductor) (684-7042) | LF | 2,246 | $5.70 | $6.25 | $7.05 | $7.35 | $4.00 | $4.60 | $6.50 |
| 243 | Traffic signal CBL (type C)(12 AWG)(2 conductor) (684-7079) | LF | 275 | $3.40 | $4.65 | $2.50 | $3.15 | $2.00 | $2.30 | $4.65 |
| 244 | Ins traffic signal PL AM(S)1 arm(32')ilsn (686-7034) | EACH | 2 | $14,000 | $14,125 | $16,500 | $17,535 | $11,270 | $12,970 | $14,125 |
| 245 | Ins traffic signal PL AM(S)1 arm(32')lum&ilsn (686-7036) | EACH | 1 | $12,523 | $16,500 | $17,750 | $19,425 | $13,550 | $15,595 | $16,500 |
| 246 | Ins traffic signal PL AM(S)1 arm(44')lum&ilsn (686-7048) | EACH | 2 | $22,300 | $19,000 | $22,750 | $22,260 | $17,150 | $19,738 | $19,000 |
| 247 | Ins traffic signal PL AM(S)1 arm(55')lum&ilsn (686-7060) | EACH | 1 | $33,450 | $42,000 | $36,410 | $43,050 | $27,680 | $31,852 | $42,000 |
| 248 | Pedestrian pole assembly (687-7001) | EACH | 2 | $5,307.91 | $2,500.00 | $2,845.00 | $5,670.00 | $3,550.00 | $4,085.80 | $2,500.00 |
| 249 | Pedestrian detect push button (APS) (688-7001) | EACH | 2 | $1,524.65 | $1,150.00 | $1,250.00 | $1,105.00 | $911.00 | $1,048.50 | $1,150.00 |
| 250 | Pedestrian detector controller unit (688-7003) | EACH | 2 | $4,085.36 | $4,100.00 | $4,210.00 | $5,250.00 | $4,160.00 | $4,782.10 | $4,100.00 |
| 251 | Full - width mowing (730-7019) | CYC | 6 | $7,500.00 | $2,000.00 | $6,956.00 | $6,500.00 | $8,290.00 | $20,000 | $5,000.00 |
| 252 | Bbu system (external battery cabinet) (6007-7001) | EACH | 1 | $8,100.00 | $8,750.00 | $9,380.00 | $9,450.00 | $9,260.00 | $10,658 | $8,750.00 |
| 253 | RVDS (presence detection only) (6008-7001) | EACH | 6 | $8,500.00 | $7,500.00 | $10,240 | $13,650 | $7,180.00 | $8,263.65 | $7,500.00 |
| 254 | RVDS (presence and advance detection) (6008-7003) | EACH | 3 | $12,500 | $9,460.00 | $10,240 | $19,950 | $10,300 | $11,855 | $9,460.00 |
| 255 | Decorative medallion W/ LED backlight (6155-7001) | EACH | 2 | $52,019 | $1,000.00 | $5,231.00 | $66,750 | $9,550.00 | $10,991 | $2,500.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from TxDOT's tabulation for this contract. TxDOT Bid Tabulations open-data export (data.texas.gov) from September 2024, read 21 November 2026, and TxDOT's legacy Tabulation of Bids pages for January 2020 to August 2024. The legacy pages are a large sample, not every contract: their file names were reused from year to year. Their district is the one TxDOT gives the county. Bids that did not match their published total are left out.
Every contract let that day: TxDOT letting of March 4, 2026. Compiled by Mirage Metrics.