FDOT contract T1813 bid tabulation
SR 45 (US 41) FROM N OF EDWARDS DR TO N MAGELLAN... Let by Florida DOT on February 25, 2026, Dist/St-Wide, Manateefed Aid No:D121031B, District 1. 4 bids received; low bid $15,369,593 by Superior Asphalt, Inc..
- Owner
- Florida DOT
- Letting
- 25 FEB 2026
- Pay items
- 212
- Data through
- 28 OCT 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | Superior Asphalt, Inc. | $15,369,593 | Low |
| 2 | Preferred Materials Inc. | $15,474,399 | +1.0% |
| 3 | Watson Civil Construction, Inc. | $16,009,128 | +4.0% |
| 4 | Ajax Paving Industries of Florida LLC | $16,390,753 | +7.0% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Superior Asphalt, Inc. | 2. Preferred Materials Inc. | 3. Watson Civil Construction, Inc. | 4. Ajax Paving Industries of Florida LLC |
|---|---|---|---|---|---|---|---|
| 0005 | Mobilization (0101-1) | LS | 1 | $735,000 | $1,249,352 | $1,500,000 | $875,248 |
| 0010 | Mobilization (0101-1) | LS | 1 | $40,000 | $32,892 | $8,000.00 | $56,697 |
| 0015 | Mobilization (0101-1) | LS | 1 | $55,000 | $291,172 | $88,000 | $66,113 |
| 0020 | Maintenance of traffic (0102-1) | DA | 1 | $772,500 | $506,947 | $559,000 | $968,902 |
| 0025 | Maintenance of traffic (0102-1) | DA | 1 | $78,250 | $12,374 | $3,000.00 | $42,575 |
| 0030 | Maintenance of traffic (0102-1) | DA | 1 | $106,000 | $52,377 | $31,000 | $242,680 |
| 0033 | Pedestrian or bicycle special detour (0102-4-1) | SY | 1 | $106,500 | $42,055 | $53,000 | $197,801 |
| 0035 | Traffic control officer (0102-14) | HR | 1,213 | $105.00 | $97.04 | $120.00 | $113.71 |
| 0040 | Work zone sign (0102-60) | ED | 33,376 | $0.25 | $0.22 | $0.30 | $0.22 |
| 0045 | Temporary barrier, F&I, low profile, concrete (0102-71-13) | LF | 25,828 | $42.00 | $39.60 | $39.00 | $30.00 |
| 0050 | Temporary barrier, F&I, anchored (0102-71-15) | LF | 1,965 | $37.00 | $34.91 | $34.00 | $36.28 |
| 0052 | Temporary barrier, relocate, low profile concrete (0102-71-23) | LF | 3,257 | $16.60 | $12.82 | $12.50 | $20.00 |
| 0053 | Temporary barrier, relocate, anchored (0102-71-25) | LF | 1,596 | $16.60 | $15.49 | $15.00 | $15.70 |
| 0055 | Channelizing device- types I, II, VP, drum, or LCD (0102-74-1) | ED | 224,850 | $0.10 | $0.11 | $0.12 | $0.08 |
| 0060 | Channelizing device- pedestrian LCD (longitudinal channelizing device) (0102-74-8) | FD | 499,528 | $0.05 | $0.05 | $0.04 | $0.03 |
| 0065 | Arrow board / advance warning arrow panel (0102-76) | ED | 1,875 | $5.50 | $5.05 | $6.00 | $4.33 |
| 0070 | Temporary crash cushion, redirective option (0102-89-1) | LO | 4 | $1,200.00 | $1,125.53 | $1,100.00 | $2,165.94 |
| 0075 | Portable changeable message sign, temporary (0102-99) | ED | 1,167 | $10.00 | $10.94 | $14.00 | $9.75 |
| 0080 | Temporary signalization and maintenance, intersection (0102-104) | ED | 375 | $44.20 | $34.54 | $62.00 | $43.32 |
| 0085 | Temporary traffic detection and maintenance, intersection (0102-107-1) | ED | 375 | $44.20 | $37.98 | $62.00 | $43.32 |
| 0090 | Type III barricade (0102-115) | ED | 1,668 | $0.50 | $0.27 | $0.35 | $0.27 |
| 0095 | Removable tape, white, solid 6" (0102-913-21) | GM | 2.70 | $12,000 | $11,430 | $11,000 | $11,371 |
| 0100 | Removable tape, white, 10'-30', 6'-10', or 2'-4' skip, 6" wide (0102-913-22) | GM | 0.07 | $3,500.00 | $3,366.92 | $2,900.00 | $3,248.92 |
| 0105 | Removable tape, yellow, solid, (0102-913-31) | GM | 1.84 | $12,000 | $11,464 | $11,000 | $11,371 |
| 0110 | Removable tape, yellow, 10'-30', 9', 6'-10', or 2'-4' skip (0102-913-32) | GM | 0.04 | $3,500.00 | $3,393.02 | $2,900.00 | $3,248.92 |
| 0115 | Sediment barrier (0104-10-3) | LF | 530 | $26.00 | $3.30 | $1.50 | $5.96 |
| 0120 | Soil tracking prevention device (0104-15) | EACH | 4 | $2,715.00 | $5,182.74 | $4,300.00 | $3,790.41 |
| 0125 | Inlet protection system (0104-18) | EACH | 93 | $295.00 | $181.79 | $114.00 | $189.52 |
| 0130 | Litter removal (0107-1) | ACRE | 136.05 | $55.00 | $130.85 | $104.00 | $10.83 |
| 0135 | Mowing (0107-2) | ACRE | 80.40 | $225.00 | $221.43 | $151.00 | $10.83 |
| 0140 | Clearing & grubbing (0110-1-1) | ACRE | 1 | $27,800 | $74,929 | $51,000 | $313,666 |
| 0145 | Clearing & grubbing (0110-1-1) | ACRE | 1 | $283,450 | $59,258 | $204,000 | $71,614 |
| 0150 | Removal of existing concrete (0110-4-10) | SY | 1,679 | $61.00 | $30.19 | $30.00 | $58.48 |
| 0155 | Regular excavation (0120-1) | CY | 137.20 | $300.00 | $34.94 | $45.00 | $77.97 |
| 0160 | Embankment (0120-6) | CY | 2,621.20 | $55.00 | $39.66 | $41.00 | $72.56 |
| 0165 | Type B stabilization (0160-4) | SY | 2,934 | $72.00 | $53.05 | $35.00 | $30.32 |
| 0170 | Optional base, base group 03 (0285-703) | SY | 52 | $167.00 | $76.53 | $105.00 | $292.66 |
| 0175 | Optional base, base group 09 (0285-709) | SY | 1,824 | $76.50 | $65.51 | $123.00 | $64.20 |
| 0180 | Milling existing asphalt pavement, 1" avg depth (0327-70-1) | SY | 181 | $21.00 | $50.33 | $24.00 | $19.93 |
| 0185 | Milling existing asphalt pavement, 3 1/2" avg depth (0327-70-2) | SY | 56,203 | $2.40 | $5.20 | $3.80 | $7.51 |
| 0190 | Milling existing asphalt pavement, 4 1/2" avg depth (0327-70-3) | SY | 18,730 | $2.40 | $6.14 | $4.15 | $9.55 |
| 0195 | Milling existing asphalt pavement, 3" avg depth (0327-70-4) | SY | 980 | $13.00 | $10.97 | $15.40 | $4.49 |
| 0200 | Milling existing asphalt pavement, 1 1/2" avg depth (0327-70-6) | SY | 5,711 | $8.85 | $10.98 | $10.30 | $1.73 |
| 0205 | Milling existing asphalt pavement, 4" avg depth (0327-70-7) | SY | 40,844 | $2.40 | $4.94 | $4.00 | $8.66 |
| 0210 | Superpave asphaltic conc, traffic C (0334-1-13) | TN | 13,539.70 | $140.00 | $156.03 | $172.00 | $148.90 |
| 0215 | Superpave asphaltic concrete, traffic C, PG76-22 (0334-1-53) | TN | 1,694.30 | $160.00 | $178.99 | $193.00 | $166.51 |
| 0220 | Asphalt concrete friction course,traffic C, FC-12.5, PG (0337-7-83) | TN | 10,324.90 | $157.00 | $188.48 | $193.00 | $172.69 |
| 0225 | Miscellaneous asphalt (0339-1) | TN | 8.60 | $1,475.00 | $311.06 | $1,650.00 | $679.83 |
| 0230 | Plain cement concrete 6" (0350-3-1) | SY | 1,458 | $82.00 | $108.70 | $77.00 | $81.22 |
| 0235 | Plain cement concrete 12" (0350-3-13) | SY | 52 | $175.00 | $203.37 | $135.00 | $162.45 |
| 0240 | Inlets, curb, type P-1, <10' (0425-1311) | EACH | 8 | $12,155 | $10,868 | $11,500 | $16,805 |
| 0245 | Inlets, curb, type P-6, partial (0425-1365) | EACH | 1 | $15,850 | $9,034.18 | $5,600.00 | $9,798.19 |
| 0250 | Inlets, curb type J-1, <10' (0425-1411) | EACH | 1 | $14,865 | $16,087 | $10,500 | $13,982 |
| 0255 | Inlets, curb, type J-2, <10' (0425-1421) | EACH | 2 | $13,500 | $15,876 | $16,000 | $22,441 |
| 0260 | Manholes, P-7, <10' (0425-2-41) | EACH | 3 | $8,840.00 | $9,217.57 | $5,000.00 | $10,070 |
| 0265 | Manholes, J-7, <10' (0425-2-71) | EACH | 3 | $11,271 | $12,716 | $6,500.00 | $11,273 |
| 0270 | Pipe culvert,optional material,round, 15"S/CD (0430-175115) | LF | 143 | $422.50 | $234.20 | $230.00 | $304.48 |
| 0275 | Pipe culvert,optional material,round, 18"S/CD (0430-175118) | LF | 38 | $643.00 | $347.66 | $376.00 | $423.95 |
| 0280 | Pipe culvert,optional material,round, 24"S/CD (0430-175124) | LF | 32 | $715.00 | $370.12 | $487.00 | $686.98 |
| 0285 | Pipe culvert, opt material, round, 30"S/CD (0430-175130) | LF | 32 | $775.00 | $407.36 | $496.00 | $507.09 |
| 0290 | Pipe culvert, opt material, round, 36"S/CD (0430-175136) | LF | 8 | $1,575.00 | $446.86 | $1,000.00 | $863.27 |
| 0295 | Pipe culvert,optional material,other-elip/arch, (0430-175218) | LF | 81 | $385.00 | $235.59 | $329.00 | $286.93 |
| 0300 | Concrete curb & gutter, type F (0520-1-10) | LF | 861 | $57.00 | $42.01 | $35.00 | $27.07 |
| 0305 | Concrete curb, type A (0520-2-1) | LF | 11,139 | $23.00 | $23.87 | $26.00 | $24.37 |
| 0310 | Valley gutter- concrete (0520-3) | LF | 134 | $91.00 | $65.94 | $45.00 | $29.24 |
| 0315 | Traffic separator concrete- type I, 4' wide (0520-5-11) | LF | 1,247 | $53.50 | $61.01 | $45.00 | $102.88 |
| 0320 | Concrete traffic separator, special- variable width (0520-70) | SY | 985 | $107.00 | $109.90 | $117.00 | $200.35 |
| 0325 | Concrete sidewalk and driveways, 4" thick (0522-1) | SY | 793 | $87.50 | $85.39 | $64.00 | $64.98 |
| 0330 | Concrete sidewalk and driveways, 6" thick (0522-2) | SY | 370 | $119.90 | $108.03 | $97.00 | $81.22 |
| 0335 | Detectable warnings (0527-2) | SF | 671 | $60.00 | $28.19 | $37.00 | $41.15 |
| 0340 | Guardrail -roadway, general (0536-1-1) | LF | 164 | $25.50 | $23.97 | $26.00 | $24.91 |
| 0345 | Guardrail removal (0536-73) | LF | 226 | $2.00 | $2.08 | $2.30 | $2.17 |
| 0350 | Guardrail end treatment- trailing anchorage (0536-85-20) | EACH | 1 | $2,150.00 | $2,032.20 | $2,200.00 | $2,735.59 |
| 0355 | Guardrail end treatment- parallel approach terminal (0536-85-24) | EACH | 1 | $3,600.00 | $3,387.00 | $3,700.00 | $3,519.67 |
| 0360 | Performance turf, sod (0570-1-2) | SY | 7,431 | $11.50 | $4.22 | $5.60 | $4.50 |
| 0365 | Electrical power service- contribution in aid of construction (ciac), FPL (DO not bid) (0639-8130) | LS | 1 | $3,804.72 | $3,804.72 | $3,804.72 | $3,804.72 |
| 0370 | Raised pavement marker, type B (0706-1-3) | EACH | 9,484 | $4.00 | $4.17 | $3.90 | $4.06 |
| 0375 | Painted pavement markings, standard, white, solid, 6" (0710-11101) | GM | 28.18 | $2,100.00 | $1,979.95 | $2,000.00 | $2,057.65 |
| 0380 | Painted pavement markings, standard, white, solid for interchange and urban island, (0710-11102) | GM | 2.55 | $2,800.00 | $2,630.46 | $2,700.00 | $2,744.26 |
| 0385 | Painted pavement markings, standard, white, solid for crosswalk and roundabout, 12" (0710-11123) | LF | 22,419 | $1.75 | $1.62 | $1.65 | $1.62 |
| 0390 | Painted pavement markings, standard, white, solid for diagonal or chevron, 18" (0710-11124) | LF | 2,049 | $1.85 | $1.72 | $1.75 | $1.79 |
| 0395 | Painted pavement markings, standard, white, solid for stop line or crosswalk, 24" (0710-11125) | LF | 17,955 | $2.00 | $1.88 | $1.90 | $1.95 |
| 0400 | Painted pavement markings, standard, white, skip, 10-30 or skip, 6" wide (0710-11131) | GM | 48.52 | $600.00 | $546.88 | $545.00 | $568.56 |
| 0405 | Painted pavement markings, standard, white, 2-4 dotted guideline/ 6-10 dotted 6" (0710-11141) | GM | 5.13 | $750.00 | $702.08 | $695.00 | $731.01 |
| 0410 | Painted pavement markings, standard, white, message or symbol (0710-11160) | EACH | 315 | $45.00 | $41.69 | $42.00 | $43.32 |
| 0415 | Painted pavement markings, standard, white, arrows (0710-11170) | EACH | 1,162 | $39.00 | $36.48 | $37.00 | $37.90 |
| 0420 | Painted pavement markings, standard, yellow, solid, 6" (0710-11201) | GM | 26.25 | $2,100.00 | $1,979.49 | $1,700.00 | $2,057.65 |
| 0425 | Painted pavement markings, standard, yellow, skip, 6" (0710-11231) | GM | 0.01 | $600.00 | $1,094.00 | $1,100.00 | $568.56 |
| 0430 | Painted pavement markings, standard, yellow, 2-4 dotted guideline/6-10 dotted extension, 6" (0710-11241) | GM | 2.19 | $750.00 | $701.20 | $695.00 | $731.01 |
| 0435 | Initial contingency amount, DO not bid (0999-25) | LS | 1 | $59,000 | $59,000 | $59,000 | $59,000 |
| 0440 | Initial contingency amount, DO not bid (0999-25) | LS | 1 | $45,000 | $45,000 | $45,000 | $45,000 |
| 0445 | Initial contingency amount, DO not bid (0999-25) | LS | 1 | $15,000 | $15,000 | $15,000 | $15,000 |
| 0450 | Initial contingency amount, DO not bid (0999-25) | LS | 1 | $6,000.00 | $6,000.00 | $6,000.00 | $6,000.00 |
| 0455 | Initial contingency amount, DO not bid (0999-25) | LS | 1 | $25,000 | $25,000 | $25,000 | $25,000 |
| 0460 | Prestressed concrete pole, complete pole removal- pole 30' and greater (0641-2-80) | EACH | 2 | $4,975.00 | $5,523.42 | $12,100 | $4,873.38 |
| 0465 | Single column ground sign assembly, F&I ground mount, than 12 SF (0700-1111) | EACH | 96 | $605.00 | $573.18 | $570.00 | $595.64 |
| 0470 | Single column ground sign assembly, F&I ground mount, 20.0 SF (0700-1112) | EACH | 19 | $2,000.00 | $1,875.88 | $1,900.00 | $1,949.35 |
| 0475 | Single column ground sign assembly, F&I ground mount, 30.0 SF (0700-1113) | EACH | 5 | $2,650.00 | $2,501.17 | $2,500.00 | $2,599.14 |
| 0480 | Single column ground sign assembly, relocate (0700-1500) | EACH | 2 | $165.00 | $156.33 | $155.00 | $162.45 |
| 0485 | Single column ground sign assembly, remove (0700-1600) | EACH | 51 | $72.00 | $67.74 | $68.00 | $70.39 |
| 0490 | Single column ground sign assembly, F&I cantilever mount, 12.0-20.0 SF (0700-1912) | EACH | 2 | $2,820.00 | $2,657.50 | $2,700.00 | $2,761.58 |
| 0495 | Single column ground sign assembly, F&I cantilever mount, 20.1-30.0 SF (0700-1913) | EACH | 4 | $3,100.00 | $2,918.03 | $2,900.00 | $3,032.33 |
| 0500 | Single column ground sign assembly, F&I cantilever mount, 30.1+ SF (0700-1914) | EACH | 2 | $3,500.00 | $3,282.79 | $3,300.00 | $3,411.37 |
| 0505 | Multi-column ground sign assembly, remove (0700-2600) | EACH | 1 | $1,655.00 | $1,563.23 | $1,600.00 | $1,624.46 |
| 0510 | Sign panel, furnish & install ground mount, UP to 12 SF (0700-3101) | EACH | 1 | $390.00 | $364.75 | $365.00 | $379.04 |
| 0515 | Sign panel, relocate, UP to 12 SF (0700-3501) | EACH | 29 | $40.00 | $36.48 | $37.00 | $37.90 |
| 0520 | Retroreflective sign strip- furnish and install, 5' (0700-13-15) | EACH | 46 | $121.50 | $114.64 | $114.00 | $119.13 |
| 0525 | Object marker, type 1 (0705-10-1) | EACH | 9 | $221.00 | $208.43 | $207.00 | $216.59 |
| 0530 | Delineator, flexible tubular (0705-11-1) | EACH | 27 | $121.50 | $114.64 | $114.00 | $119.13 |
| 0535 | Raised pavement marker, type B (0706-1-3) | EACH | 1,712 | $5.00 | $4.17 | $3.90 | $4.06 |
| 0540 | Painted pavement markings, durable paint, yellow, island nose (0710-12290) | SF | 105 | $5.00 | $5.21 | $4.15 | $4.33 |
| 0545 | Painted pavement markings, surface (0710-90) | LS | 1 | $55,900 | $78,793 | $49,000 | $54,805 |
| 0550 | Painted pavement markings, surface (0710-90) | LS | 1 | $4,700.00 | $8,077.74 | $4,000.00 | $4,602.64 |
| 0555 | Painted pavement markings, surface (0710-90) | LS | 1 | $6,100.00 | $7,816.16 | $5,000.00 | $5,956.36 |
| 0560 | Thermoplastic, standard, solid, 12" for crosswalk and roundabout (0711-11123) | LF | 4,020 | $3.50 | $3.49 | $3.25 | $3.39 |
| 0565 | Thermoplastic, standard, solid, 18" for diagonals and chevrons (0711-11124) | LF | 345 | $5.20 | $5.24 | $4.90 | $5.09 |
| 0570 | Thermoplastic, standard, solid, 24" for stop line and crosswalk (0711-11125) | LF | 861 | $7.00 | $6.98 | $6.50 | $6.78 |
| 0575 | Thermoplastic, standard, 2-4 dotted guideline/ 6-10 gap extension, 6" (0711-11141) | GM | 0.86 | $2,800.00 | $2,590.15 | $2,600.00 | $2,707.44 |
| 0580 | Thermoplastic, standard, message or symbol (0711-11160) | EACH | 5 | $600.00 | $571.10 | $570.00 | $593.47 |
| 0585 | Thermoplastic, standard, arrow (0711-11170) | EACH | 152 | $70.00 | $66.70 | $66.00 | $69.31 |
| 0590 | Thermoplastic, standard, yellow, 2-4 dotted guide line dotted extension line, 6" (0711-11241) | GM | 0.39 | $2,800.00 | $2,598.72 | $2,600.00 | $2,707.44 |
| 0595 | Thermoplastic, preformed, white, solid, 24" for crosswalk (0711-14125) | LF | 2,440 | $18.00 | $16.92 | $17.00 | $17.59 |
| 0600 | Thermoplastic, preformed, white, message (0711-14160) | EACH | 50 | $245.00 | $230.32 | $230.00 | $239.34 |
| 0605 | Thermoplastic, preformed, white, arrow (0711-14170) | EACH | 48 | $100.00 | $91.71 | $91.00 | $95.30 |
| 0610 | Thermoplastic, standard-open graded asphalt surfaces solid, 6" (0711-15101) | GM | 0.08 | $7,450.00 | $6,311.15 | $6,300.00 | $6,224.94 |
| 0615 | Thermoplastic, standard-open graded asphalt surfaces, skip, 6",10-30 skip or 3-9 lane (0711-15131) | GM | 0.13 | $2,000.00 | $1,732.50 | $1,750.00 | $1,828.06 |
| 0620 | Thermoplastic, standard-open graded asphalt surfaces, yellow, skip, 6" (0711-15231) | GM | 0.01 | $2,000.00 | $3,230.00 | $3,200.00 | $1,678.61 |
| 0625 | Thermoplastic, standard-other surfaces, white, solid, 6" (0711-16101) | GM | 5.05 | $5,300.00 | $4,998.38 | $5,000.00 | $5,198.28 |
| 0630 | Thermoplastic, standard-other surfaces, white, solid, 8" (0711-16102) | GM | 0.44 | $7,100.00 | $6,639.62 | $6,600.00 | $6,931.04 |
| 0635 | Thermoplastic, standard-other surfaces, white, skip, 6",10-30 or 3-9 lane drop (0711-16131) | GM | 8.48 | $1,350.00 | $1,249.26 | $1,250.00 | $1,299.57 |
| 0640 | Thermoplastic, standard-other surfaces, yellow, solid, 6" (0711-16201) | GM | 4.69 | $5,000.00 | $4,587.08 | $4,600.00 | $4,775.92 |
| 0645 | Preformed/permanent tape, remove (0713-107) | SF | 330 | $4.50 | $4.17 | $4.20 | $4.33 |
| 0650 | Conduit, furnish & install, open trench (0630-2-11) | LF | 1,038 | $15.50 | $13.27 | $14.50 | $15.16 |
| 0655 | Conduit, furnish & install, directional bore (0630-2-12) | LF | 16,281 | $22.00 | $24.27 | $26.00 | $21.66 |
| 0660 | Pull & splice box, F&I, 13" X 24" cover size (0635-2-11) | EACH | 108 | $1,380.00 | $1,550.30 | $1,675.00 | $1,353.72 |
| 0665 | Electrical power service, adjust/modify (0639-1500) | AS | 2 | $4,550.00 | $6,290.33 | $6,750.00 | $4,440.19 |
| 0670 | Electrical service wire, & install (0639-2-1) | LF | 8 | $30.00 | $28.93 | $31.00 | $29.78 |
| 0675 | Lighting conductors, F&I, insulated, no.8 - 6 (0715-1-12) | LF | 88,308 | $2.00 | $2.09 | $2.25 | $1.95 |
| 0680 | Lighting conductors, F&I, insulated, no 4 to no 2 (0715-1-13) | LF | 12,545 | $3.00 | $4.29 | $4.60 | $2.92 |
| 0685 | Lighting conductors, remove & dispose, contractor owns (0715-1-60) | LF | 51,925 | $0.15 | $0.77 | $0.85 | $0.11 |
| 0690 | Luminaire & bracket arm, relocate (0715-5-40) | EACH | 1 | $725.00 | $948.45 | $1,020.00 | $703.93 |
| 0695 | Load center, F&I, secondary voltage (0715-7-11) | EACH | 2 | $22,250 | $20,041 | $21,500 | $21,768 |
| 0700 | Load center, remove, voltage (0715-7-41) | EACH | 2 | $885.00 | $5,768.76 | $6,200.00 | $866.38 |
| 0705 | Luminaire, F&I- replace existing luminaire on existing pole/arm, roadway, cobra head (0715-11211) | EACH | 25 | $1,660.00 | $1,304.12 | $1,400.00 | $1,624.46 |
| 0710 | Light pole complete, F&I, standard pole standard foundation, 30' mounting height, 8' arm length (0715-61111) | EACH | 3 | $14,150 | $7,908.48 | $8,500.00 | $13,862 |
| 0715 | Light pole complete, F&I, standard pole standard foundation, 30' mounting height, 15' arm length (0715-61152) | EACH | 25 | $14,150 | $8,287.81 | $8,900.00 | $13,862 |
| 0720 | Light pole complete, F&I, standard pole standard foundation, 35' mounting height, 8' arm length (0715-61211) | EACH | 4 | $12,750 | $7,800.93 | $8,350.00 | $12,454 |
| 0725 | Light pole complete, F&I, standard pole standard foundation, 35' mounting height, 15' arm length (0715-61252) | EACH | 2 | $12,750 | $8,509.84 | $9,100.00 | $12,454 |
| 0730 | Light pole complete, F&I, standard pole standard foundation, 45' mounting height, 8' arm length (0715-61411) | EACH | 1 | $1,650.00 | $11,674 | $12,500 | $16,245 |
| 0735 | Light pole complete, F&I, standard pole standard foundation, 45' mounting height, 15' arm length (0715-61452) | EACH | 41 | $16,500 | $10,507 | $11,200 | $16,245 |
| 0740 | Light pole complete, F&I, utility conflict pole standard foundation, 30' mounting height, 16' arm length (0715-65166) | EACH | 9 | $14,600 | $11,235 | $12,000 | $14,295 |
| 0745 | Light pole complete, F&I, utility conflict pole standard foundation, 35' mounting height, 16' arm length (0715-65266) | EACH | 1 | $16,950 | $11,670 | $12,500 | $16,461 |
| 0750 | Light pole complete, remove pole and foundation (0715-69000) | EACH | 39 | $1,105.00 | $919.22 | $980.00 | $1,082.97 |
| 0755 | Pole cable distribution system, furnish and install, conventional (0715-500-1) | EACH | 118 | $965.00 | $705.50 | $755.00 | $947.60 |
| 0760 | Conduit, furnish & install, open trench (0630-2-11) | LF | 1,036 | $15.50 | $16.11 | $17.20 | $15.16 |
| 0765 | Conduit, furnish & install, directional bore (0630-2-12) | LF | 1,776 | $48.00 | $66.06 | $71.00 | $46.57 |
| 0770 | Signal cable- new or reconstructed intersection, furnish & install (0632-7-1) | PI | 5 | $15,000 | $21,420 | $23,000 | $14,620 |
| 0775 | Signal cable, remove- intersection (0632-7-6) | PI | 4 | $760.00 | $786.55 | $840.00 | $741.84 |
| 0780 | Fiber optic cable, F&I, underground,2-12 fibers (0633-1121) | LF | 1,804 | $6.00 | $7.26 | $7.80 | $5.85 |
| 0785 | Fiber optic connection, install, splice (0633-2-31) | EACH | 68 | $72.00 | $72.62 | $78.00 | $69.85 |
| 0790 | Fiber optic connection hardware, F&I, splice tray (0633-3-12) | EACH | 8 | $80.00 | $123.45 | $132.00 | $77.43 |
| 0795 | Fiber optic connection hardware, F&I, preterminated connector assembly (0633-3-13) | EACH | 48 | $87.00 | $79.88 | $86.00 | $85.01 |
| 0800 | Fiber optic connection hardware, F&I, preterminated patch panel (0633-3-15) | EACH | 4 | $1,900.00 | $3,093.57 | $3,300.00 | $1,841.06 |
| 0805 | Fiber optic connection hardware, adjust/modify splice enclosure (0633-3-51) | EACH | 4 | $1,300.00 | $1,234.53 | $1,320.00 | $1,245.42 |
| 0810 | Fiber optic cable locator (0633-6) | DA | 375 | $196.00 | $167.36 | $180.00 | $189.52 |
| 0815 | Multi-conductor cable, furnish & install, cat 6 (0633-8-11) | LF | 118 | $5.00 | $4.39 | $4.70 | $3.03 |
| 0820 | Pull & splice box, F&I, 24" X 36" cover size (0635-2-12) | EACH | 5 | $3,150.00 | $2,323.64 | $255.00 | $3,086.48 |
| 0825 | Pull & splice box, F&I, 17" X 30" cover size (0635-2-14) | EACH | 102 | $1,925.00 | $1,988.85 | $2,150.00 | $1,895.21 |
| 0830 | Electrical power service, F&I, underground, meter by contractor (0639-1122) | AS | 4 | $5,000.00 | $10,802 | $11,600 | $4,602.64 |
| 0835 | Electrical power service, remove overhead (0639-1610) | AS | 4 | $250.00 | $732.64 | $785.00 | $433.19 |
| 0840 | Electrical service wire, & install (0639-2-1) | LF | 574 | $12.00 | $11.36 | $12.20 | $11.91 |
| 0845 | Prestressed concrete pole, type P-II service pole (0641-2-12) | EACH | 4 | $2,200.00 | $2,012.13 | $2,200.00 | $2,165.95 |
| 0850 | Prestressed concrete pole, complete pole removal- pedestal/service pole (0641-2-60) | EACH | 4 | $615.00 | $1,620.26 | $1,800.00 | $601.05 |
| 0855 | Aluminum signals pole, (0646-1-11) | EACH | 30 | $2,325.00 | $2,818.34 | $3,050.00 | $2,274.25 |
| 0860 | Aluminum signals pole, remove (0646-1-60) | EACH | 19 | $275.00 | $193.37 | $207.00 | $270.74 |
| 0865 | Steel mast arm assembly, and install, single arm 30' (0649-21-1) | EACH | 1 | $66,500 | $48,560 | $52,000 | $64,978 |
| 0870 | Steel mast arm assembly, and install, single arm 40' (0649-21-3) | EACH | 1 | $68,500 | $58,168 | $62,000 | $67,144 |
| 0875 | Steel mast arm assembly, and install, single arm 50' (0649-21-6) | EACH | 1 | $79,500 | $72,121 | $77,000 | $77,974 |
| 0880 | Steel mast arm assembly, and install, single arm 60' (0649-21-10) | EACH | 2 | $79,500 | $73,562 | $79,000 | $77,974 |
| 0885 | Steel mast arm assembly, remove, deep foundation- bolt on attachment (0649-26-5) | EACH | 5 | $36,500 | $8,153.76 | $8,700.00 | $35,738 |
| 0890 | Vehicular traffic signal, furnish & install aluminum, 3 section, 1 way (0650-1-14) | AS | 40 | $1,650.00 | $2,077.40 | $2,250.00 | $1,624.46 |
| 0895 | Vehicular traffic signal, furnish & install aluminum, 4 section, 1 way (0650-1-16) | AS | 8 | $2,650.00 | $2,428.16 | $1,400.00 | $2,599.14 |
| 0900 | Vehicular traffic signal, remove- poles to remain (0650-1-60) | AS | 30 | $300.00 | $337.77 | $360.00 | $281.57 |
| 0905 | Pedestrian signal, furnish & install LED countdown, 1 way (0653-1-11) | AS | 30 | $995.00 | $936.96 | $1,000.00 | $974.68 |
| 0910 | Pedestrian signal, remove ped signal- pole/pedestal to remain (0653-1-60) | AS | 3 | $185.00 | $124.60 | $133.00 | $178.69 |
| 0915 | Loop assembly, F&I, type B (0660-2102) | AS | 10 | $1,150.00 | $1,444.58 | $1,550.00 | $1,137.12 |
| 0920 | Loop assembly, F&I, type F (0660-2106) | AS | 6 | $2,325.00 | $2,637.92 | $2,850.00 | $2,274.25 |
| 0925 | Vehicle detection system- microwave, furnish & install cabinet equipment (0660-3-11) | EACH | 4 | $13,250 | $10,333 | $11,100 | $12,996 |
| 0930 | Vehicle detection system- microwave, furnish & install, above ground equipment (0660-3-12) | EACH | 24 | $12,700 | $9,767.62 | $10,500 | $12,454 |
| 0935 | Vehicle detection system- avi, bluetooth, furnish & install, cabinet equipment (0660-6121) | EACH | 1 | $2,800.00 | $2,523.08 | $2,700.00 | $2,761.58 |
| 0940 | Vehicle detection system- avi, bluetooth, furnish & install, above ground equipment (0660-6122) | EACH | 1 | $9,400.00 | $8,756.67 | $9,400.00 | $9,205.28 |
| 0945 | Vehicle detection system- avi, bluetooth relocate, cabinet equipment (0660-6421) | EACH | 1 | $550.00 | $446.33 | $480.00 | $541.49 |
| 0950 | Signal priority and preemption system, F&I, optical, cabinet electronics (0663-1111) | EACH | 4 | $9,900.00 | $8,099.48 | $900.00 | $9,692.62 |
| 0955 | Signal priority and preemption system, F&I, optical, detector (0663-1112) | EACH | 4 | $4,500.00 | $4,021.14 | $4,300.00 | $4,494.34 |
| 0960 | Signal priority & preemption system, remove (0663-1600) | EACH | 3 | $445.00 | $289.03 | $308.00 | $433.19 |
| 0965 | Pedestrian detector, furnish & install, standard (0665-1-11) | EACH | 30 | $425.00 | $354.42 | $380.00 | $416.95 |
| 0970 | Pedestrian detector, remove- pole/pedestal to remain (0665-1-60) | EACH | 3 | $72.00 | $56.17 | $60.00 | $70.39 |
| 0975 | Traffic controller assembly, F&I, NEMA W/standard lock, 1 preemption (0670-5161) | AS | 4 | $65,000 | $58,412 | $63,000 | $63,895 |
| 0980 | Traffic controller assembly, remove controller with (0670-5600) | AS | 4 | $925.00 | $616.37 | $660.00 | $904.28 |
| 0985 | Traffic signal controller cabinet, furnish & install without controller, type/size 20" W X 32" H X 14" D (0676-1112) | EACH | 3 | $11,000 | $40,082 | $42,800 | $10,721 |
| 0990 | Traffic signal controller cabinet, remove (0676-1600) | EACH | 3 | $500.00 | $1,861.20 | $2,000.00 | $487.34 |
| 0995 | ITS cabinet- adjust/modify (0676-2500) | EACH | 2 | $1,500.00 | $4,567.02 | $4,900.00 | $1,462.02 |
| 1000 | ITS CCTV camera, pressurized, high definition (0682-1163) | EACH | 3 | $555.00 | $7,448.10 | $8,000.00 | $9,800.92 |
| 1005 | ITS CCTV camera, remove & disposal (0682-1600) | EACH | 2 | $10,000 | $360.34 | $385.00 | $541.49 |
| 1010 | Managed field ethernet switch, furnish & install (0684-1-1) | EACH | 4 | $5,900.00 | $10,238 | $11,000 | $5,793.91 |
| 1015 | Uninterruptible power supply, furnish and install, line interactive (0685-1-11) | EACH | 4 | $13,925 | $14,250 | $15,200 | $13,645 |
| 1020 | Remote power management rpmu, furnish and install (0685-2-1) | EACH | 4 | $850.00 | $1,304.32 | $1,400.00 | $839.31 |
| 1025 | Sign panel, furnish & install overhead mount, UP to 12 SF (0700-3201) | EACH | 8 | $940.00 | $943.04 | $1,050.00 | $920.53 |
| 1030 | Sign panel, remove, UP to 12 SF (0700-3601) | EACH | 3 | $165.00 | $185.75 | $200.00 | $162.45 |
| 1035 | Internally illuminated sign, furnish & install, overhead mount, 12-18 SF (0700-5-22) | EACH | 16 | $6,740.00 | $5,209.55 | $5,550.00 | $6,606.14 |
| 1040 | Internally illuminated sign, remove (0700-5-60) | EACH | 11 | $250.00 | $763.12 | $815.00 | $243.67 |
| 1045 | Enhanced highway sign AC powered, F&I overhead blank out sign <12 SF (0700-141360) | EACH | 2 | $9,945.00 | $8,967.46 | $9,600.00 | $9,746.77 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from FDOT's tabulation for this contract. FDOT Tabulation of Bids PDFs from its central office lettings, January 2018 to October 2026, all pay items. On A+B contracts the cost part is kept (the total the pay items add up to). Bidders listed without a rank or total are left out.
Every contract let that day: FDOT letting of February 25, 2026. Compiled by Mirage Metrics.