FDOT contract T5819 bid tabulation
SR 33 (CR 33) FROM S OF EDGEWOOD BOYS RANCH RD TO S OF WRIGH. Let by Florida DOT on July 30, 2025, Lake, District 5. 8 bids received; low bid $4,961,103 by Ranger Construction Industries, Inc..
- Owner
- Florida DOT
- Letting
- 30 JUL 2025
- Pay items
- 88
- Data through
- 28 OCT 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | Ranger Construction Industries, Inc. | $4,961,103 | Low |
| 2 | Watson Civil Construction, Inc. | $5,837,035 | +18% |
| 3 | Superior Asphalt, Inc. | $5,972,001 | +20% |
| 4 | Pigott Asphalt and Sitework LLC | $6,987,739 | +41% |
| 5 | Sema Construction, Inc. | $7,310,000 | +47% |
| 6 | Hubbard Construction Company | $7,352,437 | +48% |
| 7 | Southern Development & Construction, Inc. | $7,426,000 | +50% |
| 8 | Atlantic Civil Constructors Corp | $7,452,965 | +50% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Ranger Construction Industries, Inc. | 2. Watson Civil Construction, Inc. | 3. Superior Asphalt, Inc. | 4. Pigott Asphalt and Sitework LLC | 5. Sema Construction, Inc. | 6. Hubbard Construction Company |
|---|---|---|---|---|---|---|---|---|---|
| 0005 | Mobilization (0101-1) | LS | 1 | $488,600 | $580,000 | $606,272 | $1,099,000 | $730,000 | $735,000 |
| 0010 | Maintenance of traffic (0102-1) | DA | 1 | $501,326 | $771,000 | $534,000 | $390,000 | $750,000 | $1,536,000 |
| 0015 | Special detour- temporary pavement (0102-2200) | SY | 1 | $37,500 | $57,000 | $46,000 | $100,000 | $180,000 | $175,000 |
| 0020 | Special detour- temporary earthwork/base (0102-2300) | CY | 1 | $30,800 | $45,000 | $14,675 | $50,000 | $120,000 | $75,000 |
| 0025 | Commercial material for temporary driveway maintenance (0102-3) | CY | 59.30 | $99.20 | $160.00 | $176.00 | $100.00 | $200.00 | $146.20 |
| 0030 | Work zone sign (0102-60) | ED | 3,246 | $0.20 | $0.30 | $0.25 | $0.35 | $0.30 | $0.22 |
| 0035 | Temporary barrier, F&I, anchored (0102-71-15) | LF | 1,750 | $42.20 | $38.50 | $46.00 | $39.00 | $50.00 | $41.76 |
| 0040 | Temporary barrier, relocate, anchored (0102-71-25) | LF | 4,575 | $17.80 | $16.20 | $19.00 | $22.00 | $20.00 | $17.13 |
| 0045 | Channelizing device- types I, II, VP, drum, or LCD (0102-74-1) | ED | 16,990 | $0.10 | $0.12 | $0.10 | $0.05 | $0.10 | $0.09 |
| 0050 | Temporary raised/retroreflective pavement marker, type D (0102-78-1) | EACH | 3,428 | $4.45 | $4.35 | $4.70 | $5.00 | $5.50 | $4.00 |
| 0055 | Temporary crash cushion, redirective option (0102-89-1) | LO | 24 | $2,380.00 | $1,100.00 | $1,290.00 | $1,500.00 | $1,500.00 | $1,100.00 |
| 0060 | Type III barricade (0102-115) | ED | 2,178 | $0.40 | $0.52 | $0.35 | $1.00 | $0.40 | $0.28 |
| 0065 | Temporary raised rumble per day, includes all sets and relocations (0102-909) | DA | 130 | $31.10 | $29.00 | $33.00 | $75.00 | $30.00 | $28.00 |
| 0070 | Sediment barrier (0104-10-3) | LF | 9,539 | $2.25 | $1.20 | $1.50 | $3.00 | $1.10 | $2.37 |
| 0075 | Staked turbidity barrier- nylon reinforced PVC (0104-12) | LF | 796 | $8.50 | $6.15 | $5.70 | $25.00 | $5.00 | $9.73 |
| 0080 | Inlet protection system (0104-18) | EACH | 13 | $222.20 | $225.00 | $147.00 | $250.00 | $230.00 | $250.09 |
| 0085 | Litter removal (0107-1) | ACRE | 49.08 | $77.80 | $120.00 | $37.00 | $10.00 | $65.00 | $100.00 |
| 0090 | Mowing (0107-2) | ACRE | 54.41 | $100.00 | $150.00 | $240.00 | $100.00 | $100.00 | $150.00 |
| 0095 | Clearing & grubbing (0110-1-1) | ACRE | 1 | $104,411 | $296,000 | $166,000 | $150,000 | $513,017 | $350,000 |
| 0100 | Removal of existing concrete (0110-4-10) | SY | 189 | $15.60 | $46.00 | $70.50 | $60.00 | $38.00 | $29.85 |
| 0105 | Regular excavation (0120-1) | CY | 2,460.50 | $16.00 | $15.00 | $47.00 | $30.00 | $60.00 | $32.17 |
| 0110 | Subsoil excavation (0120-4) | CY | 138.10 | $332.50 | $69.00 | $47.00 | $100.00 | $120.00 | $81.91 |
| 0115 | Embankment (0120-6) | CY | 1,510.80 | $4.35 | $10.00 | $44.60 | $30.00 | $70.00 | $35.07 |
| 0120 | Type B stabilization (0160-4) | SY | 8,587 | $13.45 | $29.00 | $21.15 | $20.00 | $25.00 | $24.59 |
| 0125 | Optional base, base group 02 (0285-702) | SY | 254 | $58.60 | $100.00 | $35.20 | $30.00 | $25.00 | $28.01 |
| 0130 | Optional base, base group 03 (0285-703) | SY | 82 | $87.60 | $180.00 | $35.20 | $150.00 | $25.00 | $37.67 |
| 0135 | Optional base, base group 04 (0285-704) | SY | 6,002 | $29.25 | $30.00 | $39.45 | $30.00 | $32.00 | $23.78 |
| 0140 | Optional base, base group 10 (0285-710) | SY | 3,731 | $24.35 | $43.00 | $44.60 | $70.00 | $34.00 | $29.34 |
| 0145 | Milling existing asphalt pavement, 3" avg depth (0327-70-4) | SY | 13,744 | $4.00 | $4.95 | $4.75 | $5.00 | $5.00 | $8.83 |
| 0150 | Milling existing asphalt pavement, 1 1/2" avg depth (0327-70-6) | SY | 2,249 | $12.95 | $4.65 | $4.45 | $5.00 | $5.00 | $11.31 |
| 0155 | Superpave asphaltic conc, traffic E (0334-1-15) | TN | 1,796.30 | $138.70 | $181.00 | $173.25 | $190.00 | $190.00 | $250.97 |
| 0160 | Asphalt concrete friction course,traffic E, FC-12.5, PG (0337-7-88) | TN | 1,902 | $155.50 | $206.00 | $197.00 | $250.00 | $210.00 | $244.02 |
| 0165 | Miscellaneous asphalt (0339-1) | TN | 83.80 | $332.50 | $393.00 | $376.75 | $350.00 | $450.00 | $336.56 |
| 0170 | Concrete class NS, gravity index 400-011 (0400-0-11) | CY | 454.20 | $909.80 | $975.00 | $1,380.00 | $2,000.00 | $2,000.00 | $1,514.27 |
| 0175 | Inlets, curb, type P-5, <10' (0425-1351) | EACH | 7 | $8,340.00 | $8,500.00 | $14,320 | $10,000 | $9,000.00 | $7,365.56 |
| 0180 | Inlets, DT bot, type C, modify (0425-1529) | EACH | 1 | $8,050.00 | $6,100.00 | $6,455.00 | $8,500.00 | $7,500.00 | $7,102.05 |
| 0185 | Inlets, closed flume (0425-1910) | EACH | 6 | $7,570.00 | $5,500.00 | $14,085 | $10,000 | $7,700.00 | $3,716.72 |
| 0190 | Manholes, P-7, <10' (0425-2-41) | EACH | 1 | $8,120.00 | $6,500.00 | $11,500 | $8,500.00 | $6,100.00 | $5,736.49 |
| 0195 | Pipe culvert, optional material, other shape - ellip/arch, 18"SD (0430-174218) | LF | 80 | $223.50 | $211.00 | $164.50 | $300.00 | $410.00 | $215.13 |
| 0200 | Pipe culvert,optional material,round, 18"S/CD (0430-175118) | LF | 864 | $126.80 | $130.00 | $164.50 | $200.00 | $230.00 | $127.25 |
| 0205 | Pipe culvert,optional material,round, 24"S/CD (0430-175124) | LF | 49 | $210.60 | $183.00 | $176.00 | $250.00 | $480.00 | $206.98 |
| 0210 | Pipe culvert, opt material, round, 30"S/CD (0430-175130) | LF | 5 | $876.50 | $777.00 | $293.00 | $1,000.00 | $1,600.00 | $1,313.89 |
| 0215 | Straight concrete endwalls, single, 0 degrees, round (0430-518100) | EACH | 1 | $3,690.00 | $2,800.00 | $6,100.00 | $7,500.00 | $5,200.00 | $2,759.88 |
| 0220 | Straight concrete endwalls, single, 0 degrees, round (0430-524100) | EACH | 1 | $4,420.00 | $3,900.00 | $6,800.00 | $8,500.00 | $5,900.00 | $3,374.00 |
| 0225 | Straight concrete endwalls, single, 0 degrees, round (0430-530100) | EACH | 1 | $5,360.00 | $5,700.00 | $8,450.00 | $10,000 | $5,900.00 | $4,712.21 |
| 0230 | Mitered end section, optional round, 24" SD (0430-984129) | EACH | 2 | $2,880.00 | $2,300.00 | $2,350.00 | $3,900.00 | $5,200.00 | $3,475.15 |
| 0235 | Mitered end sect, optional - elliptical / arch, 18" SD (0430-984625) | EACH | 4 | $2,750.00 | $2,200.00 | $2,350.00 | $4,000.00 | $5,200.00 | $3,322.78 |
| 0240 | Pipe handrail - guiderail, aluminum (0515-1-2) | LF | 2,269 | $51.10 | $58.00 | $54.00 | $65.00 | $59.00 | $46.00 |
| 0245 | Concrete curb & gutter, type E (0520-1-7) | LF | 2,463 | $54.70 | $59.00 | $52.75 | $120.00 | $48.00 | $67.16 |
| 0255 | Concrete sidewalk and driveways, 6" thick (0522-2) | SY | 1,578 | $95.90 | $87.00 | $100.00 | $135.00 | $96.00 | $99.08 |
| 0260 | Concrete ditch pavement, non reinforced, 6" (0524-1-4) | SY | 8 | $976.50 | $172.00 | $176.00 | $500.00 | $390.00 | $130.83 |
| 0265 | Detectable warnings (0527-2) | SF | 153 | $36.65 | $42.00 | $26.75 | $40.00 | $38.00 | $32.00 |
| 0270 | Guardrail -roadway, general (0536-1-1) | LF | 2,650 | $22.80 | $22.00 | $24.65 | $25.00 | $22.00 | $22.21 |
| 0275 | Pipe rail for guardrail (0536-6) | LF | 1,556 | $22.20 | $21.00 | $23.50 | $25.00 | $21.00 | $19.99 |
| 0280 | Special guardrail post- special steel post for concrete structure mount (0536-7-2) | EACH | 9 | $362.00 | $500.00 | $557.50 | $500.00 | $500.00 | $325.95 |
| 0285 | Special guardrail post- post for shallow mount (0536-7-3) | EACH | 1 | $127.80 | $340.00 | $381.50 | $500.00 | $340.00 | $115.04 |
| 0290 | Guardrail removal (0536-73) | LF | 304 | $2.65 | $3.15 | $3.50 | $10.00 | $3.20 | $2.39 |
| 0295 | Guardrail end treatment- parallel approach terminal (0536-85-24) | EACH | 12 | $3,550.00 | $3,250.00 | $3,640.00 | $3,250.00 | $3,300.00 | $3,191.32 |
| 0300 | Performance turf, sod (0570-1-2) | SY | 7,872 | $7.25 | $7.00 | $6.90 | $5.00 | $6.00 | $5.13 |
| 0305 | Painted pavement markings, standard, white, solid, 6" (0710-11101) | GM | 6.94 | $1,880.00 | $1,850.00 | $1,985.00 | $3,000.00 | $1,700.00 | $1,691.22 |
| 0310 | Painted pavement markings, standard, yellow, solid, 6" (0710-11201) | GM | 6.94 | $1,880.00 | $1,850.00 | $1,985.00 | $3,000.00 | $1,700.00 | $1,690.73 |
| 0315 | Initial contingency amount, DO not bid (0999-25) | LS | 1 | $75,000 | $75,000 | $75,000 | $75,000 | $75,000 | $75,000 |
| 0320 | Midblock crosswalk: rectangular rapid flashing beacon, furnish & install- complete sign assembly- back back (0654-2-22) | AS | 2 | $17,000 | $13,000 | $17,950 | $15,000 | $13,700 | $11,000 |
| 0325 | Profiled thermoplastic,standard- asphalt surfaces, white, (0701-18101) | GM | 2.41 | $8,200.00 | $8,000.00 | $8,675.00 | $10,000 | $11,400 | $7,407.37 |
| 0330 | Profiled thermoplastic,standard- asphalt surfaces, yellow, solid,6" (0701-18201) | GM | 2.88 | $8,200.00 | $8,020.00 | $8,675.00 | $10,000 | $11,500 | $7,384.31 |
| 0335 | Raised pavement marker, type B (0706-1-3) | EACH | 478 | $4.45 | $4.35 | $4.70 | $5.00 | $5.50 | $4.00 |
| 0340 | Painted pavement markings, surface (0710-90) | LS | 1 | $14,400 | $13,000 | $15,235 | $35,000 | $22,900 | $12,978 |
| 0345 | Thermoplastic, standard, solid, 12" for crosswalk and roundabout (0711-11123) | LF | 448 | $3.35 | $3.30 | $3.50 | $6.00 | $5.50 | $3.00 |
| 0350 | Thermoplastic, standard, solid, 24" for stop line and crosswalk (0711-11125) | LF | 65 | $7.80 | $7.60 | $8.20 | $12.00 | $10.00 | $7.00 |
| 0355 | Thermoplastic, standard, arrow (0711-11170) | EACH | 10 | $83.30 | $81.50 | $88.00 | $150.00 | $100.00 | $75.00 |
| 0360 | Thermoplastic, standard, yellow, solid, 18" for diagonal or chevron (0711-11224) | LF | 338 | $5.00 | $4.90 | $5.30 | $10.00 | $8.00 | $4.50 |
| 0365 | Thermoplastic, preformed, white, solid, 24" for crosswalk (0711-14125) | LF | 50 | $15.55 | $15.20 | $16.50 | $20.00 | $29.00 | $14.00 |
| 0370 | Thermoplastic, standard-other surfaces, white, solid, 6" (0711-16101) | GM | 0.16 | $5,720.00 | $5,600.00 | $6,200.00 | $25,000 | $15,000 | $5,151.22 |
| 0375 | Thermoplastic, standard-other surfaces, yellow, solid, 6" (0711-16201) | GM | 0.02 | $5,870.00 | $5,750.00 | $6,200.00 | $100,000 | $15,000 | $5,280.00 |
| 0380 | Conduit, furnish & install, open trench (0630-2-11) | LF | 4,822 | $15.45 | $18.00 | $16.30 | $15.00 | $16.00 | $12.75 |
| 0385 | Conduit, furnish & install, directional bore (0630-2-12) | LF | 1,106 | $27.25 | $29.00 | $28.75 | $40.00 | $39.00 | $36.75 |
| 0390 | Pull & splice box, F&I, 13" X 24" cover size (0635-2-11) | EACH | 49 | $1,400.00 | $2,210.00 | $1,475.00 | $1,500.00 | $2,200.00 | $2,318.00 |
| 0395 | Electrical power service, F&I, underground, meter by contractor (0639-1122) | AS | 2 | $7,300.00 | $6,600.00 | $7,710.00 | $5,000.00 | $4,400.00 | $6,860.00 |
| 0400 | Electrical service disconnect, F&I, pole mount (0639-3-11) | EACH | 2 | $3,470.00 | $3,200.00 | $3,660.00 | $2,500.00 | $3,300.00 | $1,224.00 |
| 0405 | Prestressed concrete pole, type P-II service pole (0641-2-12) | EACH | 2 | $3,270.00 | $2,720.00 | $3,455.00 | $2,000.00 | $3,100.00 | $2,708.00 |
| 0410 | Lighting conductors, F&I, insulated, no.8 - 6 (0715-1-12) | LF | 20,206 | $2.40 | $2.85 | $2.50 | $3.00 | $5.00 | $2.55 |
| 0415 | Lighting conductors, F&I, insulated, no 4 to no 2 (0715-1-13) | LF | 2,326 | $4.20 | $4.30 | $4.40 | $6.50 | $8.50 | $5.55 |
| 0420 | Load center, F&I, secondary voltage (0715-7-11) | EACH | 2 | $22,300 | $19,500 | $23,600 | $16,000 | $17,800 | $19,590 |
| 0425 | Light pole complete, F&I, standard pole standard foundation, 35' mounting height, 8' arm length (0715-61211) | EACH | 3 | $11,400 | $9,550.00 | $12,000 | $10,000 | $10,400 | $9,220.00 |
| 0430 | Light pole complete, F&I, standard pole standard foundation, 35' mounting height, 12' arm length (0715-61242) | EACH | 25 | $11,500 | $9,400.00 | $12,000 | $9,500.00 | $10,500 | $9,304.00 |
| 0435 | Light pole complete, F&I, standard pole standard foundation, 40' mounting height, 8' arm length (0715-61311) | EACH | 13 | $11,600 | $9,950.00 | $12,300 | $10,000 | $10,900 | $9,522.00 |
| 0440 | Light pole complete, F&I, standard pole standard foundation, 40' mounting height, 12' arm length (0715-61342) | EACH | 2 | $11,800 | $9,800.00 | $12,500 | $10,000 | $11,100 | $9,882.00 |
| 0445 | Pole cable distribution system, furnish and install, conventional (0715-500-1) | EACH | 43 | $935.00 | $833.00 | $990.00 | $750.00 | $810.00 | $852.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from FDOT's tabulation for this contract. FDOT Tabulation of Bids PDFs from its central office lettings, January 2018 to October 2026, all pay items. On A+B contracts the cost part is kept (the total the pay items add up to). Bidders listed without a rank or total are left out.
Every contract let that day: FDOT letting of July 30, 2025. Compiled by Mirage Metrics.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.