FDOT contract T5843 bid tabulation
SR 530 (US 192/VINE ST) FROM BAMBOO LN TO MAIN ST (US 441). Let by Florida DOT on January 29, 2025, Osceola, District 5. 5 bids received; low bid $26,048,427 by Hubbard Construction Company.
- Owner
- Florida DOT
- Letting
- 29 JAN 2025
- Pay items
- 183
- Data through
- 28 OCT 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | Hubbard Construction Company | $26,048,427 | Low |
| 2 | Middlesex Paving, LLC | $27,927,001 | +7.0% |
| 3 | Preferred Materials Inc. | $32,997,895 | +27% |
| 4 | Ranger Construction Industries, Inc. | $33,230,602 | +28% |
| 5 | JR. Davis Construction Co., Inc. | $33,999,401 | +31% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Hubbard Construction Company | 2. Middlesex Paving, LLC | 3. Preferred Materials Inc. | 4. Ranger Construction Industries, Inc. | 5. JR. Davis Construction Co., Inc. |
|---|---|---|---|---|---|---|---|---|
| 0005 | Mobilization (0101-1) | LS | 1 | $1,823,838 | $2,400,000 | $3,250,000 | $3,251,000 | $3,300,000 |
| 0010 | Maintenance of traffic (0102-1) | DA | 1 | $1,914,849 | $1,750,000 | $1,973,000 | $2,444,000 | $2,389,000 |
| 0015 | Commercial material for temporary driveway maintenance (0102-3) | CY | 34 | $323.86 | $800.00 | $332.00 | $958.50 | $500.00 |
| 0020 | Pedestrian or bicycle special detour (0102-4-1) | SY | 1 | $40,538 | $50,000 | $24,400 | $30,100 | $95,000 |
| 0025 | Traffic control officer (0102-14) | HR | 1,776 | $115.29 | $94.00 | $112.50 | $97.70 | $185.00 |
| 0030 | Pedestrian escort operation (0102-25100) | HR | 1,120 | $33.15 | $60.00 | $400.00 | $38.00 | $75.00 |
| 0035 | Work zone sign (0102-60) | ED | 36,949 | $0.22 | $0.25 | $0.19 | $0.25 | $0.30 |
| 0040 | Business sign (0102-61) | EACH | 46 | $27.96 | $61.00 | $25.00 | $28.75 | $30.00 |
| 0045 | Temporary barrier, F&I, low profile, concrete (0102-71-13) | LF | 451 | $51.41 | $71.00 | $43.00 | $49.45 | $50.00 |
| 0050 | Channelizing device- types I, II, VP, drum, or LCD (0102-74-1) | ED | 116,157 | $0.10 | $0.15 | $0.09 | $0.10 | $0.15 |
| 0055 | Channelizing device- pedestrian LCD (longitudinal channelizing device) (0102-74-8) | FD | 46,068 | $0.06 | $0.10 | $0.04 | $0.05 | $0.10 |
| 0060 | Arrow board / advance warning arrow panel (0102-76) | ED | 278 | $5.59 | $8.00 | $5.00 | $5.75 | $6.00 |
| 0065 | Portable changeable message sign, temporary (0102-99) | ED | 860 | $11.18 | $13.00 | $9.00 | $11.50 | $12.00 |
| 0070 | Temporary signalization and maintenance, intersection (0102-104) | ED | 6,020 | $28.10 | $29.00 | $26.00 | $25.10 | $30.00 |
| 0075 | Temporary traffic detection and maintenance, intersection (0102-107-1) | ED | 6,020 | $27.02 | $1.40 | $25.00 | $25.10 | $1.00 |
| 0080 | Type III barricade (0102-115) | ED | 692 | $0.28 | $0.40 | $0.25 | $0.30 | $0.50 |
| 0085 | Inlet protection system (0104-18) | EACH | 253 | $149.45 | $360.00 | $152.46 | $160.90 | $125.00 |
| 0090 | Litter removal (0107-1) | ACRE | 736.64 | $53.38 | $20.00 | $45.00 | $57.50 | $95.00 |
| 0095 | Mowing (0107-2) | ACRE | 736.64 | $101.41 | $45.00 | $65.00 | $109.20 | $155.00 |
| 0100 | Clearing & grubbing (0110-1-1) | ACRE | 1 | $159,489 | $220,000 | $555,650 | $550,000 | $207,000 |
| 0105 | Removal of existing concrete (0110-4-10) | SY | 9,832 | $32.60 | $62.00 | $77.69 | $57.20 | $12.00 |
| 0110 | Regular excavation (0120-1) | CY | 2,293.50 | $48.89 | $53.00 | $57.29 | $58.80 | $45.00 |
| 0115 | Embankment (0120-6) | CY | 798.70 | $43.46 | $98.00 | $53.71 | $11.75 | $52.00 |
| 0120 | Type B stabilization (0160-4) | SY | 1,233 | $48.89 | $67.00 | $146.76 | $31.50 | $125.00 |
| 0125 | Optional base, base group 02 (0285-702) | SY | 63 | $195.43 | $74.95 | $103.06 | $88.60 | $100.00 |
| 0130 | Optional base, base group 09 (0285-709) | SY | 2,653 | $73.13 | $60.00 | $126.13 | $70.80 | $129.00 |
| 0135 | Milling existing asphalt pavement, 4 1/2" avg depth (0327-70-3) | SY | 161,538 | $5.98 | $8.00 | $7.55 | $9.40 | $11.80 |
| 0140 | Milling existing asphalt pavement, 2" avg depth (0327-70-5) | SY | 53,592 | $9.29 | $5.00 | $8.00 | $6.80 | $8.25 |
| 0145 | Milling existing asphalt pavement, 1 1/2" avg depth (0327-70-6) | SY | 20,641 | $10.80 | $11.00 | $4.05 | $9.85 | $8.00 |
| 0150 | Milling existing asphalt pavement, 4" avg depth (0327-70-7) | SY | 78,963 | $6.20 | $7.00 | $6.60 | $8.45 | $11.00 |
| 0155 | Superpave asphaltic conc, traffic C (0334-1-13) | TN | 39,630.20 | $124.46 | $120.00 | $180.25 | $157.00 | $185.00 |
| 0160 | Asphalt concrete friction course,traffic C, FC-12.5, PG (0337-7-83) | TN | 27,628.80 | $171.14 | $165.00 | $254.00 | $200.00 | $240.00 |
| 0165 | Inlets, curb, type 9, partial (0425-1205) | EACH | 1 | $12,709 | $9,500.00 | $6,629.47 | $8,710.00 | $9,500.00 |
| 0170 | Inlets, curb, type J-5, <10' (0425-1451) | EACH | 1 | $20,445 | $22,000 | $24,056 | $22,900 | $16,400 |
| 0175 | Inlets, curb, type J-6, <10' (0425-1461) | EACH | 1 | $2,541.77 | $24,000 | $26,573 | $25,100 | $17,000 |
| 0180 | Inlets, curb, type J-6, partial (0425-1465) | EACH | 1 | $14,919 | $11,000 | $7,836.01 | $9,720.00 | $8,500.00 |
| 0185 | Inlets, ditch bottom type C modified- back of sidewalk, partial (0425-1535) | EACH | 3 | $14,146 | $9,000.00 | $5,908.99 | $8,480.00 | $10,500 |
| 0190 | Pipe culvert,optional material,round, 18"S/CD (0430-175118) | LF | 4 | $303.91 | $1,200.00 | $445.69 | $1,180.00 | $1,600.00 |
| 0195 | Pipe culvert,optional material,round, 24"S/CD (0430-175124) | LF | 8 | $386.79 | $1,200.00 | $419.80 | $1,370.00 | $1,800.00 |
| 0200 | Pipe culvert, opt material, round, 30"S/CD (0430-175130) | LF | 4 | $552.56 | $1,500.00 | $603.87 | $1,370.00 | $2,000.00 |
| 0205 | Trench drain, standard (0436-1-1) | LF | 277 | $806.74 | $690.00 | $600.12 | $716.00 | $425.00 |
| 0210 | Pipe handrail - guiderail, aluminum (0515-1-2) | LF | 50 | $81.28 | $116.00 | $117.60 | $137.90 | $96.00 |
| 0215 | Concrete curb & gutter, type E (0520-1-7) | LF | 679 | $52.42 | $38.00 | $47.27 | $135.40 | $95.00 |
| 0220 | Concrete curb & gutter, type F (0520-1-10) | LF | 6,200 | $50.75 | $30.00 | $46.19 | $67.50 | $112.00 |
| 0225 | Concrete curb, type D (0520-2-4) | LF | 263 | $49.81 | $45.00 | $53.95 | $87.20 | $46.00 |
| 0230 | Traffic separator concrete- type I, 4' wide (0520-5-11) | LF | 573 | $130.38 | $58.00 | $46.99 | $105.90 | $130.00 |
| 0235 | Concrete traffic separator, special- variable width (0520-70) | SY | 4 | $271.63 | $240.00 | $363.49 | $3,150.00 | $1,500.00 |
| 0240 | Concrete sidewalk and driveways, 4" thick (0522-1) | SY | 5,478 | $76.06 | $79.00 | $95.09 | $100.20 | $50.00 |
| 0245 | Concrete sidewalk and driveways, 6" thick (0522-2) | SY | 5,423 | $97.79 | $93.00 | $131.41 | $152.50 | $80.00 |
| 0247 | Pavers, architectural, remove existing and reinstall (0526-1101) | SY | 47 | $271.63 | $160.00 | $141.07 | $345.00 | $225.00 |
| 0250 | Detectable warnings (0527-2) | SF | 2,117 | $48.89 | $42.00 | $29.40 | $37.45 | $55.00 |
| 0255 | Performance turf, sod (0570-1-2) | SY | 3,904 | $12.57 | $13.00 | $5.45 | $10.60 | $8.25 |
| 0260 | Performance turf, sod and shoulder treatment index (0570-1-3) | SY | 44 | $20.41 | $20.00 | $38.00 | $35.45 | $65.00 |
| 0265 | Raised pavement marker, type B (0706-1-3) | EACH | 1,295 | $4.40 | $6.00 | $4.50 | $4.60 | $5.50 |
| 0270 | Painted pavement markings, standard, white, solid, 6" (0710-11101) | GM | 22.17 | $1,397.24 | $1,200.00 | $1,500.20 | $1,460.00 | $1,550.00 |
| 0275 | Painted pavement markings, standard, white, solid for interchange and urban island, (0710-11102) | GM | 0.55 | $0.45 | $1,450.00 | $2,550.00 | $0.45 | $2,750.00 |
| 0280 | Painted pavement markings, standard, white, solid for crosswalk and roundabout, 12" (0710-11123) | LF | 6,829 | $1.65 | $1.25 | $0.80 | $1.70 | $1.00 |
| 0285 | Painted pavement markings, standard, white, solid for stop line or crosswalk, 24" (0710-11125) | LF | 1,620 | $2.59 | $2.50 | $2.50 | $2.70 | $4.50 |
| 0290 | Painted pavement markings, standard, white, skip, 10-30 or skip, 6" wide (0710-11131) | GM | 20.18 | $550.16 | $600.00 | $400.12 | $575.00 | $520.00 |
| 0295 | Painted pavement markings, standard, white, 2-4 dotted guideline/ 6-10 dotted 6" (0710-11141) | GM | 3.51 | $604.26 | $650.00 | $700.80 | $631.50 | $775.00 |
| 0300 | Painted pavement markings, standard, white, arrows (0710-11170) | EACH | 38 | $38.52 | $36.00 | $45.00 | $40.25 | $55.00 |
| 0305 | Painted pavement markings, standard, yellow, solid, 6" (0710-11201) | GM | 6.38 | $1,396.58 | $1,200.00 | $1,501.18 | $1,460.00 | $1,650.00 |
| 0310 | Painted pavement markings, standard, yellow, 2-4 dotted guideline/6-10 dotted extension, 6" (0710-11241) | GM | 0.56 | $707.63 | $225.00 | $705.04 | $739.50 | $800.00 |
| 0315 | Disputes review board, meeting- DO not bid (0999-20-1) | DA | 10 | $4,800.00 | $4,800.00 | $4,800.00 | $4,800.00 | $4,800.00 |
| 0320 | Disputes review board, hearing- DO not bid (0999-20-2) | EACH | 1 | $5,750.00 | $5,750.00 | $5,750.00 | $5,750.00 | $5,750.00 |
| 0325 | Initial contingency amount, DO not bid (0999-25) | LS | 1 | $150,000 | $150,000 | $150,000 | $150,000 | $150,000 |
| 0330 | Single column ground sign assembly, F&I ground mount, than 12 SF (0700-1111) | EACH | 92 | $544.76 | $600.00 | $500.00 | $569.00 | $540.00 |
| 0335 | Single column ground sign assembly, F&I ground mount, 20.0 SF (0700-1112) | EACH | 24 | $1,705.83 | $2,000.00 | $1,800.00 | $1,780.00 | $2,000.00 |
| 0340 | Single column ground sign assembly, F&I ground mount, 30.0 SF (0700-1113) | EACH | 4 | $2,256.10 | $2,600.00 | $2,300.00 | $2,360.00 | $2,500.00 |
| 0345 | Single column ground sign assembly, relocate (0700-1500) | EACH | 5 | $214.60 | $450.00 | $300.00 | $224.10 | $325.00 |
| 0350 | Single column ground sign assembly, remove (0700-1600) | EACH | 37 | $33.02 | $70.00 | $20.00 | $34.50 | $22.00 |
| 0355 | Multi-column ground sign assembly, F&I ground mount, 30.0 SF (0700-2113) | EACH | 1 | $5,392.63 | $6,000.00 | $6,000.00 | $5,630.00 | $6,500.00 |
| 0360 | Multi-column ground sign assembly, F&I ground mount, 50.0 SF (0700-2114) | EACH | 1 | $6,823.31 | $7,000.00 | $8,000.00 | $7,130.00 | $8,600.00 |
| 0365 | Multi-column ground sign assembly, remove (0700-2600) | EACH | 2 | $1,650.80 | $1,500.00 | $1,350.00 | $1,720.00 | $1,500.00 |
| 0370 | Sign panel, furnish & install ground mount, UP to 12 SF (0700-3101) | EACH | 154 | $247.62 | $250.00 | $175.00 | $258.60 | $190.00 |
| 0375 | Sign panel, furnish & install ground mount, 12-20 SF (0700-3102) | EACH | 2 | $324.66 | $920.00 | $575.00 | $339.00 | $615.00 |
| 0380 | Sign panel, remove, UP to 12 SF (0700-3601) | EACH | 152 | $11.01 | $38.00 | $50.00 | $11.50 | $55.00 |
| 0385 | Sign panel, remove, 12-20 SF (0700-3602) | EACH | 2 | $11.01 | $62.00 | $75.00 | $11.50 | $80.00 |
| 0390 | Tubular marker, durable, 36" white post (0704-1-1) | EACH | 5 | $247.62 | $120.00 | $225.00 | $258.60 | $245.00 |
| 0395 | Tubular marker, 36" yellow (0704-1-4) | EACH | 8 | $247.62 | $120.00 | $225.00 | $258.60 | $245.00 |
| 0400 | Object marker, type 1 (0705-10-1) | EACH | 13 | $137.57 | $60.00 | $325.00 | $143.70 | $350.00 |
| 0405 | Raised pavement marker, type B (0706-1-3) | EACH | 6,700 | $4.40 | $6.00 | $4.50 | $4.60 | $5.50 |
| 0410 | Painted pavement markings, standard, yellow, island nose (0710-11290) | SF | 800 | $4.40 | $4.00 | $3.00 | $4.60 | $5.50 |
| 0415 | Painted pavement markings, surface (0710-90) | LS | 1 | $182,670 | $135,000 | $150,000 | $119,000 | $165,000 |
| 0420 | Thermoplastic, standard, solid, 8" for interchange and urban island (0711-11102) | GM | 1.40 | $6,433.53 | $8,800.00 | $5,736.62 | $6,720.00 | $6,400.00 |
| 0425 | Thermoplastic, standard, solid, 12" for crosswalk and roundabout (0711-11123) | LF | 12,195 | $3.85 | $5.00 | $2.60 | $4.00 | $3.75 |
| 0430 | Thermoplastic, standard, solid, 18" for diagonals and chevrons (0711-11124) | LF | 1,196 | $4.95 | $6.50 | $5.35 | $5.15 | $6.25 |
| 0435 | Thermoplastic, standard, solid, 24" for stop line and crosswalk (0711-11125) | LF | 2,900 | $6.60 | $7.50 | $8.25 | $6.90 | $9.00 |
| 0440 | Thermoplastic, standard, 2-4 dotted guideline/ 6-10 gap extension, 6" (0711-11141) | GM | 3.63 | $1,451.11 | $2,250.00 | $2,604.29 | $1,520.00 | $2,800.00 |
| 0445 | Thermoplastic, standard, message or symbol (0711-11160) | EACH | 37 | $275.13 | $225.00 | $145.00 | $287.50 | $175.00 |
| 0450 | Thermoplastic, standard, arrow (0711-11170) | EACH | 386 | $82.54 | $100.00 | $65.00 | $86.20 | $78.00 |
| 0455 | Thermoplastic, standard, yellow, solid, 18" for diagonal or chevron (0711-11224) | LF | 2,588 | $4.95 | $7.00 | $5.35 | $5.15 | $6.00 |
| 0460 | Thermoplastic, standard, yellow, 2-4 dotted guide line dotted extension line, 6" (0711-11241) | GM | 0.60 | $2,451.28 | $4,000.00 | $2,617.45 | $2,560.00 | $3,100.00 |
| 0465 | Thermoplastic, preformed, white, solid, 24" for crosswalk (0711-14125) | LF | 10,341 | $15.96 | $19.00 | $13.50 | $16.65 | $16.25 |
| 0470 | Thermoplastic, preformed, white, message (0711-14160) | EACH | 72 | $357.67 | $300.00 | $205.00 | $373.50 | $240.00 |
| 0475 | Thermoplastic, preformed, white, arrow (0711-14170) | EACH | 72 | $286.14 | $275.00 | $145.00 | $299.00 | $170.00 |
| 0480 | Thermoplastic, preformed, 24" white with 4" black contrast stop line on concrete 32" (0711-14527) | LF | 16 | $46.22 | $35.00 | $15.00 | $48.30 | $36.00 |
| 0485 | Thermoplastic, preformed, 12" white with 4" black contrast crosswalk on concrete pavement, 20" (0711-14528) | LF | 4,241 | $17.61 | $16.00 | $5.00 | $18.40 | $25.00 |
| 0490 | Thermoplastic, standard-other surfaces, white, solid, 6" (0711-16101) | GM | 22.06 | $5,348.60 | $7,500.00 | $3,700.00 | $5,590.00 | $4,000.00 |
| 0495 | Thermoplastic, standard-other surfaces, white, skip, 6",10-30 or 3-9 lane drop (0711-16131) | GM | 19.35 | $1,595.45 | $2,300.00 | $1,600.50 | $1,670.00 | $1,800.00 |
| 0500 | Thermoplastic, standard-other surfaces, yellow, solid, 6" (0711-16201) | GM | 11.23 | $5,347.65 | $7,500.00 | $3,702.64 | $5,590.00 | $4,200.00 |
| 0505 | Permanent tape, white, solid, 6" for concrete bridges (0713-103101) | GM | 0.12 | $53,685 | $32,000 | $39,106 | $56,100 | $40,000 |
| 0510 | Permanent tape, white, 10-30 6" wide, for concrete surfaces (0713-103181) | GM | 0.12 | $13,421 | $17,000 | $21,138 | $14,000 | $21,000 |
| 0515 | Permanent tape, yellow, solid, for concrete bridges (0713-103201) | GM | 0.06 | $54,125 | $33,000 | $42,459 | $56,500 | $40,000 |
| 0520 | Permanent tape, black, 10-30 6" wide, for concrete surfaces (0713-103381) | GM | 0.12 | $13,421 | $17,000 | $21,138 | $14,000 | $21,000 |
| 0525 | Preformed/permanent tape, remove (0713-107) | SF | 652 | $3.14 | $8.00 | $5.00 | $3.30 | $10.00 |
| 0530 | Conduit, furnish & install, open trench (0630-2-11) | LF | 433 | $23.78 | $27.00 | $22.00 | $20.00 | $24.00 |
| 0535 | Conduit, furnish & install, directional bore (0630-2-12) | LF | 32 | $47.56 | $85.00 | $44.00 | $25.80 | $44.00 |
| 0540 | Pull & splice box, F&I, 13" X 24" cover size (0635-2-11) | EACH | 9 | $989.04 | $2,900.00 | $915.00 | $1,910.00 | $2,000.00 |
| 0545 | Lighting conductors, F&I, insulated, no.8 - 6 (0715-1-12) | LF | 1,828 | $2.16 | $4.00 | $2.00 | $3.55 | $3.50 |
| 0550 | Light pole complete, relocate (0715-68000) | EACH | 9 | $3,919.40 | $9,500.00 | $3,626.00 | $9,420.00 | $6,500.00 |
| 0555 | Itsfm subsurface documentation- project length (0611-1-1) | MI | 6.08 | $2,968.60 | $3,300.00 | $2,750.90 | $3,960.00 | $4,600.00 |
| 0560 | Itsfm location documentation- intersection (0611-2-1) | EACH | 15 | $2,229.93 | $2,200.00 | $2,063.00 | $2,660.00 | $3,100.00 |
| 0565 | Conduit, furnish & install, open trench (0630-2-11) | LF | 766 | $30.27 | $29.00 | $28.00 | $30.50 | $25.00 |
| 0570 | Conduit, furnish & install, directional bore (0630-2-12) | LF | 5,973 | $59.45 | $39.00 | $55.00 | $38.95 | $42.50 |
| 0575 | Signal cable- new or reconstructed intersection, furnish & install (0632-7-1) | PI | 14 | $8,623.54 | $14,500 | $7,978.00 | $18,600 | $15,500 |
| 0580 | Signal cable, adjust (0632-7-4) | PI | 1 | $193.49 | $1,600.00 | $179.00 | $4,440.00 | $1,700.00 |
| 0585 | Signal cable, remove- intersection (0632-7-6) | PI | 11 | $1,754.32 | $5,000.00 | $1,623.00 | $2,960.00 | $1,950.00 |
| 0590 | Fiber optic cable, F&I, underground,2-12 fibers (0633-1121) | LF | 1,022 | $4.32 | $7.00 | $4.00 | $6.00 | $6.25 |
| 0595 | Fiber optic connection, install, splice (0633-2-31) | EACH | 36 | $59.45 | $82.00 | $55.00 | $68.40 | $80.00 |
| 0600 | Fiber optic connection, install, termination (0633-2-32) | EACH | 36 | $89.72 | $135.00 | $83.00 | $102.60 | $125.00 |
| 0605 | Fiber optic connection hardware, F&I, splice (0633-3-11) | EACH | 3 | $1,421.40 | $2,200.00 | $1,315.00 | $1,630.00 | $1,900.00 |
| 0610 | Fiber optic connection hardware, F&I, splice tray (0633-3-12) | EACH | 3 | $59.45 | $90.00 | $55.00 | $68.40 | $80.00 |
| 0615 | Fiber optic connection hardware, F&I, buffer tube fan out kit (0633-3-14) | EACH | 3 | $101.61 | $135.00 | $94.00 | $116.30 | $135.00 |
| 0620 | Fiber optic connection hardware, F&I, patch panel- terminated (0633-3-16) | EACH | 3 | $1,457.07 | $2,200.00 | $1,348.00 | $1,680.00 | $1,950.00 |
| 0625 | Fiber optic connection hardware, F&I, connector panel (0633-3-17) | EACH | 3 | $118.90 | $160.00 | $110.00 | $136.80 | $160.00 |
| 0630 | Fiber optic cable locator (0633-6) | DA | 430 | $351.30 | $320.00 | $325.00 | $403.50 | $380.00 |
| 0635 | Pull & splice box, F&I, 13" X 24" cover size (0635-2-11) | EACH | 84 | $1,031.19 | $1,900.00 | $954.00 | $1,840.00 | $2,000.00 |
| 0640 | Pull & splice box, F&I, 24" X 36" cover size (0635-2-12) | EACH | 2 | $2,354.23 | $4,500.00 | $2,178.00 | $3,160.00 | $3,800.00 |
| 0645 | Pull & splice box, F&I, 30" X 60" rectangular or 36" round size (0635-2-13) | EACH | 3 | $6,644.38 | $9,300.00 | $6,147.00 | $6,870.00 | $7,600.00 |
| 0650 | Electrical power service, F&I, underground, meter by contractor (0639-1122) | AS | 3 | $6,263.90 | $7,500.00 | $5,795.00 | $6,060.00 | $5,100.00 |
| 0655 | Electrical service wire, & install (0639-2-1) | LF | 328 | $4.32 | $11.00 | $4.00 | $7.10 | $12.50 |
| 0660 | Prestressed concrete pole, type P-II service pole (0641-2-12) | EACH | 3 | $1,694.88 | $3,500.00 | $1,568.00 | $3,150.00 | $4,300.00 |
| 0665 | Aluminum signals pole, (0646-1-11) | EACH | 89 | $3,462.17 | $3,500.00 | $3,203.00 | $4,553.00 | $2,500.00 |
| 0670 | Aluminum signals pole, remove (0646-1-60) | EACH | 9 | $944.72 | $400.00 | $874.00 | $1,480.00 | $325.00 |
| 0675 | Steel strain pole, remove pedestal or service pole- complete removal (0649-1-61) | EACH | 4 | $1,889.44 | $390.00 | $1,748.00 | $3,550.00 | $325.00 |
| 0680 | Steel strain pole, remove, shallow foundation removal, bolt on attachment (0649-1-63) | EACH | 14 | $8,710.01 | $9,500.00 | $8,058.00 | $13,500 | $5,600.00 |
| 0685 | Steel mast arm assembly, and install, single arm 30' (0649-21-1) | EACH | 1 | $55,774 | $80,000 | $51,599 | $71,400 | $62,500 |
| 0690 | Steel mast arm assembly, and install, single arm 40' (0649-21-3) | EACH | 2 | $63,347 | $88,000 | $58,605 | $78,200 | $65,800 |
| 0695 | Steel mast arm assembly, and install, single arm 50' (0649-21-6) | EACH | 2 | $72,387 | $99,000 | $66,968 | $85,700 | $75,100 |
| 0700 | Steel mast arm assembly, and install, single arm 60' (0649-21-10) | EACH | 8 | $85,067 | $117,000 | $78,699 | $103,796 | $88,900 |
| 0705 | Steel mast arm assembly, and install, double arm 60'-40' (0649-21-12) | EACH | 1 | $100,282 | $139,000 | $92,775 | $118,300 | $106,100 |
| 0710 | Steel mast arm assembly, and install, single arm 70' (0649-21-15) | EACH | 3 | $85,361 | $123,000 | $78,971 | $99,500 | $91,500 |
| 0715 | Steel mast arm assembly, and install, double arm 70'-50' (0649-21-18) | EACH | 1 | $113,698 | $156,000 | $105,187 | $128,000 | $121,100 |
| 0720 | Steel mast arm assembly, and install, double arm 70'-60' (0649-21-19) | EACH | 1 | $126,915 | $170,000 | $117,414 | $137,000 | $133,300 |
| 0725 | Steel mast arm assembly, and install, single arm 78' (0649-21-21) | EACH | 3 | $102,258 | $139,000 | $94,603 | $118,000 | $108,200 |
| 0730 | Vehicular traffic signal, furnish & install aluminum, 3 section, 1 way (0650-1-14) | AS | 73 | $1,797.56 | $2,300.00 | $1,663.00 | $2,550.00 | $1,500.00 |
| 0735 | Vehicular traffic signal, furnish & install aluminum, 4 section, 1 way (0650-1-16) | AS | 16 | $2,481.78 | $2,750.00 | $2,296.00 | $3,040.00 | $1,850.00 |
| 0740 | Vehicular traffic signal, remove- poles to remain (0650-1-60) | AS | 3 | $566.40 | $150.00 | $524.00 | $369.50 | $160.00 |
| 0745 | Vehicular traffic signal, relocate- includes removal reinstallation (0650-1-70) | AS | 9 | $1,453.83 | $1,200.00 | $1,345.00 | $1,750.00 | $845.00 |
| 0750 | Vehicular signal auxiliaries, repair/replace/retrofit- & install, backplate- black with reflect border (0650-2102) | EACH | 27 | $737.18 | $550.00 | $682.00 | $1,240.00 | $278.00 |
| 0755 | Vehicular signal auxiliaries, repair/replace/retrofit- & install, backplate- flexible required (0650-2109) | EACH | 21 | $775.02 | $900.00 | $717.00 | $1,250.00 | $490.00 |
| 0760 | Pedestrian signal, furnish & install LED countdown, 1 way (0653-1-11) | AS | 94 | $984.71 | $1,400.00 | $911.00 | $1,590.00 | $825.00 |
| 0765 | Pedestrian signal, remove ped signal- pole/pedestal to remain (0653-1-60) | AS | 17 | $148.08 | $75.00 | $137.00 | $295.70 | $160.00 |
| 0767 | Midblock crosswalk: hybrid beacon assembly, & install complete assembly (0654-3-10) | AS | 12 | $2,154.26 | $2,700.00 | $1,993.00 | $2,360.00 | $1,945.00 |
| 0770 | Vehicle detection system- furnish & install cabinet equipment (0660-4-11) | EACH | 12 | $27,083 | $32,000 | $25,056 | $28,900 | $30,800 |
| 0775 | Vehicle detection system- furnish & install above ground equipment (0660-4-12) | EACH | 57 | $9,388.82 | $12,000 | $8,686.00 | $13,774 | $10,100 |
| 0780 | Vehicle detection system- relocate above ground equipment (0660-4-42) | EACH | 4 | $1,208.46 | $2,200.00 | $1,118.00 | $4,320.00 | $2,950.00 |
| 0785 | Vehicle detection system- adjust/modify cabinet (0660-4-51) | EACH | 11 | $1,476.53 | $1,400.00 | $1,366.00 | $3,270.00 | $325.00 |
| 0790 | Vehicle detection system- remove cabinet equipment (0660-4-61) | EACH | 5 | $593.42 | $800.00 | $549.00 | $887.00 | $160.00 |
| 0795 | Vehicle detection system- remove above ground (0660-4-62) | EACH | 21 | $1,416.00 | $900.00 | $1,310.00 | $1,480.00 | $325.00 |
| 0800 | Signal priority and preemption system, furnish and install, detector (0663-1122) | EACH | 10 | $7,600.99 | $10,000 | $7,032.00 | $9,270.00 | $8,350.00 |
| 0805 | Signal priority and preemption system, furnish and install, cabinet electronics (0663-1123) | EACH | 6 | $8,357.63 | $13,000 | $7,732.00 | $10,944 | $9,600.00 |
| 0810 | Signal priority & preemption system, relocate (0663-1400) | EACH | 1 | $2,650.40 | $1,750.00 | $2,452.00 | $2,500.00 | $2,000.00 |
| 0815 | Signal priority & preemption system, adjust/modify (0663-1500) | EACH | 5 | $1,416.00 | $1,600.00 | $1,310.00 | $3,900.00 | $325.00 |
| 0820 | Pedestrian detector, furnish & install, accessible (0665-1-12) | EACH | 93 | $1,973.75 | $2,200.00 | $1,826.00 | $2,390.00 | $1,720.00 |
| 0825 | Pedestrian detector, adjust/modify on existing pole (0665-1-50) | EACH | 1 | $297.25 | $300.00 | $275.00 | $702.00 | $160.00 |
| 0830 | Pedestrian detector, remove- pole/pedestal to remain (0665-1-60) | EACH | 17 | $74.58 | $70.00 | $69.00 | $147.90 | $55.00 |
| 0835 | Traffic controller assembly, F&I, NEMA, 1 preemption (0670-5111) | AS | 3 | $46,692 | $65,000 | $43,197 | $60,400 | $53,000 |
| 0840 | ITS CCTV camera, relocate (0682-1400) | EACH | 2 | $3,916.15 | $6,000.00 | $3,623.00 | $2,500.00 | $3,850.00 |
| 0845 | Managed field ethernet switch, furnish & install (0684-1-1) | EACH | 3 | $5,083.54 | $7,500.00 | $4,703.00 | $5,850.00 | $4,350.00 |
| 0850 | Uninterruptible power supply, furnish and install, line interactive (0685-1-11) | EACH | 7 | $11,071 | $15,000 | $10,242 | $10,200 | $8,550.00 |
| 0855 | Uninterruptible power supply, furnish and install, line interactive with cabinet (0685-1-13) | EACH | 8 | $6,037.99 | $24,000 | $5,586.00 | $15,100 | $12,500 |
| 0860 | Uninterruptible power supply, remove- pole/cabinet remains (0685-1-60) | EACH | 7 | $593.42 | $550.00 | $549.00 | $1,770.00 | $160.00 |
| 0865 | Remote power management rpmu, furnish and install (0685-2-1) | EACH | 15 | $1,132.80 | $1,600.00 | $1,048.00 | $1,160.00 | $1,400.00 |
| 0870 | Traffic monitoring site vehicle sensor-non-weight, furnish & install (0695-1-1) | EACH | 24 | $2,063.47 | $2,600.00 | $1,909.00 | $3,390.00 | $2,900.00 |
| 0875 | Traffic monitoring site inductive loop assembly, & install, 2 loops (0695-6-12) | EACH | 24 | $1,290.61 | $2,400.00 | $1,194.00 | $2,220.00 | $2,400.00 |
| 0880 | Traffic monitoring site cabinet, F&I, type 3, 2 pane back, pedestal mount (0695-7162) | EACH | 3 | $6,829.22 | $3,200.00 | $6,318.00 | $12,900 | $8,900.00 |
| 0885 | Traffic monitoring site cabinet, remove existing cabinet (0695-7600) | EACH | 3 | $593.42 | $1,500.00 | $549.00 | $1,180.00 | $325.00 |
| 0890 | Sign panel, furnish & install overhead mount, UP to 12 SF (0700-3201) | EACH | 24 | $3,708.62 | $1,200.00 | $3,431.00 | $907.00 | $880.00 |
| 0895 | Sign panel, furnish & install overhead mount, 12-20 SF (0700-3202) | EACH | 4 | $1,730.55 | $1,800.00 | $1,601.00 | $1,770.00 | $1,400.00 |
| 0900 | Sign panel, relocate, UP to 12 SF (0700-3501) | EACH | 4 | $746.91 | $900.00 | $691.00 | $818.00 | $690.00 |
| 0905 | Internally illuminated sign, furnish & install, overhead mount, 12-18 SF (0700-5-22) | EACH | 22 | $7,622.61 | $9,000.00 | $7,052.00 | $10,350 | $9,800.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from FDOT's tabulation for this contract. FDOT Tabulation of Bids PDFs from its central office lettings, January 2018 to October 2026, all pay items. On A+B contracts the cost part is kept (the total the pay items add up to). Bidders listed without a rank or total are left out.
Every contract let that day: FDOT letting of January 29, 2025. Compiled by Mirage Metrics.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.