JR. Davis Construction Co., Inc.: FDOT bid record
JR. Davis Construction Co., Inc. submitted 16 bids on Florida DOT contracts in the data, from 13 JUN 2018 to 28 OCT 2026, and was the low bidder on 5 of them (31%). When it was not low, its total sat a median +16% above the low bid.
- Owner
- Florida DOT
- Low bid volume
- $151,644,290
- Latest bid
- 28 OCT 2026
- Data through
- 28 OCT 2026
By year
| Year | Bids | Low bids | Win rate |
|---|---|---|---|
| 2018 | 1 | 1 | 100% |
| 2019 | 1 | 0 | 0% |
| 2020 | 3 | 1 | 33% |
| 2021 | 1 | 0 | 0% |
| 2022 | 1 | 0 | 0% |
| 2023 | 1 | 1 | 100% |
| 2024 | 1 | 0 | 0% |
| 2025 | 4 | 2 | 50% |
| 2026 | 3 | 0 | 0% |
By district
| District | Bids | Low bids | Win rate |
|---|---|---|---|
| District 5 | 14 | 4 | 29% |
| District 1 | 2 | 1 | 50% |
Pay items where it is most often lowest
| Pay item | Code | Unit | Lines bid | Lowest on the line | Its median price | All bidders' median |
|---|---|---|---|---|---|---|
| Disputes review board, meeting- DO not bid | 0999-20-1 | DA | 10 | 10 (100%) | $3,900.00 | $3,900.00 |
| Disputes review board, hearing- DO not bid | 0999-20-2 | EACH | 10 | 10 (100%) | $5,125.00 | $4,500.00 |
| Conduit, furnish & install, open trench | 0630-2-11 | LF | 42 | 9 (21%) | $14.25 | $16.54 |
| Concrete sidewalk and driveways, 4" thick | 0522-1 | SY | 13 | 7 (54%) | $43.00 | $65.00 |
| Manholes, P-8, <10' | 0425-2-61 | EACH | 11 | 7 (64%) | $5,800.00 | $6,325.37 |
| Inlet protection system | 0104-18 | EACH | 16 | 6 (38%) | $99.88 | $150.00 |
| Pull & splice box, F&I, 13" X 24" cover size | 0635-2-11 | EACH | 42 | 5 (12%) | $1,305.00 | $1,150.00 |
| Regular excavation | 0120-1 | CY | 15 | 5 (33%) | $7.97 | $25.47 |
| Embankment | 0120-6 | CY | 15 | 5 (33%) | $13.25 | $30.04 |
| Removal of existing concrete | 0110-4-10 | SY | 14 | 5 (36%) | $13.82 | $33.96 |
| Permanent tape, white, solid, 6" for concrete bridges | 0713-103101 | GM | 9 | 5 (56%) | $36,950 | $33,000 |
| Permanent tape, yellow, solid, for concrete bridges | 0713-103201 | GM | 9 | 5 (56%) | $36,000 | $33,000 |
A line counts when the firm priced it and at least one other bidder did too; the lowest unit price on the line counts whoever won the contract. Token prices and bids over three times the low bid are left out.
Who it meets most
| Firm | Contracts in common | That firm ranked ahead |
|---|---|---|
| Masci General Contractors, Inc | 10 | 7 of 10 |
| Hubbard Construction Company | 9 | 2 of 9 |
| Ranger Construction Industries, Inc. | 8 | 3 of 8 |
| Sema Construction, Inc. | 6 | 2 of 6 |
| Watson Civil Construction, Inc. | 6 | 4 of 6 |
| Southland Construction, Inc. | 4 | 3 of 4 |
| Prince Contracting, LLC. | 3 | 2 of 3 |
| Granite Construction Company of California | 3 | 0 of 3 |
| Middlesex Corporation (the) | 3 | 0 of 3 |
| Thalle Construction Co., Inc. | 2 | 0 of 2 |
Latest bids
| Let | Contract | District | Project | Rank | Its bid | Against the low bid |
|---|---|---|---|---|---|---|
| 28 OCT 2026 | T5914 | District 5 | SR 9 (I-95) FROM VIERA BLVD TO SR 519 (FISKE BLVD) | 3 of 4 | $23,710,015 | +16% |
| 20 MAY 2026 | T5882 | District 5 | ELLIS RD FROM J RODES BLVD TO WICKHAM RD | 9 of 10 | $47,032,063 | +47% |
| 28 JAN 2026 | T5874 | District 5 | SR 426 (FAIRBANKS AVE / ALOMA AVE) FROM S PARK AVE TO N ... | 2 of 5 | $10,254,120 | +8.0% |
| 11 JUN 2025 | T5851 | District 5 | SR 500 (US 441) FROM N OF SR 50 TO SR 414 INTERCHANGE RAMPS | 1 of 5 | $35,181,705 | Low, 10% under the second |
| 28 MAY 2025 | T5854 | District 5 | SR 500 (E IRLO BRONSON MEMORIAL HWY) FROM CR 532 (NOVA RD).. | 1 of 5 | $11,154,437 | Low, 18% under the second |
| 30 APR 2025 | T5793 | District 5 | SR 9 (I-95) FROM MP 18.355 TO MP 19.552 | 3 of 7 | $65,285,773 | +8.0% |
| 29 JAN 2025 | T5843 | District 5 | SR 530 (US 192/VINE ST) FROM BAMBOO LN TO MAIN ST (US 441) | 5 of 5 | $33,999,401 | +31% |
| 24 APR 2024 | T5824 | District 5 | SR 46 (W 1ST ST) FROM E OF I-4 TO SR 15 (US 17/92) | 7 of 7 | $21,746,796 | +30% |
| 25 JAN 2023 | T5777 | District 5 | GALAXY WAY | 1 of 9 | $22,896,706 | Low, 3.0% under the second |
| 15 JUN 2022 | T5724 | District 5 | SR 400 (I-4) | 4 of 5 | $87,998,445 | +6.0% |
| 27 JAN 2021 | T5711 | District 5 | SR 519 (FISKE BLVD) | 3 of 4 | $9,616,161 | +10% |
| 29 JUL 2020 | T5699 | District 5 | SR 518 | 5 of 5 | $9,127,447 | +38% |
| 10 JUN 2020 | T1754 | District 1 | SR 25 (US 27) | 2 of 9 | $45,948,895 | +3.0% |
| 29 APR 2020 | T1751 | District 1 | SR 542 (DUNDEE RD) | 1 of 5 | $43,563,143 | Low, 10% under the second |
| 24 APR 2019 | T5642 | District 5 | SR 46 | 6 of 8 | $21,465,901 | +20% |
| 13 JUN 2018 | T5590 | District 5 | SR 9 (I-95) | 1 of 6 | $38,848,299 | Low, 1.0% under the second |
How this record was read
FDOT Tabulation of Bids PDFs from its central office lettings, January 2018 to October 2026, all pay items. On A+B contracts the cost part is kept (the total the pay items add up to). Bidders listed without a rank or total are left out.
- Every bid counted here matched its published total to within one dollar; FDOT's rank decides who was low.
- The gap to the low bid is the firm's total over the low total, minus one, on contracts it did not win, leaving out bids over three times the low bid.
- A record covers the lettings in the data, not every contract the firm ever bid. Coverage by year is on the state page.
A name split in two, or a figure that does not match the owner's tabulation? Write to mehdi@miragemetrics.com and we correct it.