FDOT contract T5874 bid tabulation

SR 426 (FAIRBANKS AVE / ALOMA AVE) FROM S PARK AVE TO N ... Let by Florida DOT on January 28, 2026, Orange, District 5. 5 bids received; low bid $9,523,246 by Masci General Contractors, Inc.

Owner
Florida DOT
Letting
28 JAN 2026
Pay items
191
Data through
28 OCT 2026

Bidders

RankBidderTotal bidAgainst the low bid
1Masci General Contractors, Inc$9,523,246Low
2JR. Davis Construction Co., Inc.$10,254,120+8.0%
3Hubbard Construction Company$10,455,290+10%
4Ranger Construction Industries, Inc.$11,387,371+20%
5Atlantic Civil Constructors Corp$11,413,787+20%
FDOT contract T5874: bids by rank

Bid tabulation

LinePay itemUnitQuantity1. Masci General Contractors, Inc2. JR. Davis Construction Co., Inc.3. Hubbard Construction Company4. Ranger Construction Industries, Inc.5. Atlantic Civil Constructors Corp
0005Mobilization (0101-1)LS1$65,000$89,000$68,993$1,100,000$255,405
0010Mobilization (0101-1)LS1$800,000$935,000$790,172$50,000$1,017,468
0015Maintenance of traffic (0102-1)DA1$56,000$75,000$697,982$545,000$201,349
0020Maintenance of traffic (0102-1)DA1$288,000$205,000$220,167$44,500$600,931
0025Traffic control officer (0102-14)HR172$95.00$255.00$106.40$110.00$100.00
0030Work zone sign (0102-60)ED38,189$0.23$0.21$0.20$0.20$0.18
0035Channelizing device- types I, II, VP, drum, or LCD (0102-74-1)ED198,019$0.12$0.09$0.09$0.10$0.08
0040Channelizing device- pedestrian LCD (longitudinal channelizing device) (0102-74-8)FD2,376$0.10$0.06$0.05$0.05$0.05
0045Arrow board / advance warning arrow panel (0102-76)ED5,824$5.75$5.00$4.90$7.00$4.50
0050Portable changeable message sign, temporary (0102-99)ED2,038$12.00$10.00$9.80$11.00$9.00
0055Temporary signalization and maintenance, intersection (0102-104)ED1,870$15.23$75.00$68.65$14.50$63.50
0060Temporary traffic detection and maintenance, intersection (0102-107-1)ED1,870$15.23$1.50$1.08$14.50$1.00
0065Type III barricade (0102-115)ED4,592$0.40$0.25$0.22$0.30$0.20
0070Sediment barrier (0104-10-3)LF2,286$1.75$5.00$1.05$2.00$4.50
0075Inlet protection system (0104-18)EACH42$150.00$145.00$107.03$190.00$150.94
0080Litter removal (0107-1)ACRE46.34$35.00$35.00$26.76$98.00$298.96
0085Mowing (0107-2)ACRE1.75$325.00$30.00$26.75$629.00$743.96
0090Clearing & grubbing (0110-1-1)ACRE1$15,000$25,000$16,340$485,000$368,345
0095Clearing & grubbing (0110-1-1)ACRE1$15,000$325,000$29,956$47,000$518,357
0100Removal of existing concrete (0110-4-10)SY3,102$29.25$50.00$43.57$46.00$38.65
0105Type B stabilization (0160-4)SY288$22.29$80.00$32.68$95.00$78.71
0110Optional base, base group 09 (0285-709)SY137$41.25$125.00$70.81$210.00$165.58
0115Milling existing asphalt pavement, 3" avg depth (0327-70-4)SY10,131$3.54$2.00$5.33$10.00$5.50
0120Milling existing asphalt pavement, 1 1/2" avg depth (0327-70-6)SY53,906$2.59$3.00$4.34$9.70$6.00
0125Superpave asphaltic conc, traffic C (0334-1-13)TN1,697$157.25$245.00$287.40$232.00$235.00
0130Superpave asphaltic concrete, traffic C, PG76-22 (0334-1-53)TN22.60$289.65$325.00$326.04$484.00$300.00
0135Asphalt concrete friction course,traffic C, FC-12.5, PG (0337-7-83)TN5,295.20$179.35$215.00$241.80$251.00$200.00
0140Concrete class NS, gravity index 400-011 (0400-0-11)CY69.10$1,950.00$1,500.00$1,797.39$1,960.00$1,269.69
0145Inlets, curb, type 9, <10' (0425-1201)EACH1$15,361$11,000$18,519$6,270.00$13,151
0150Inlets, curb, type 9, J bot, <10' (0425-1203)EACH2$19,914$13,000$16,340$10,500$15,363
0155Inlets, curb, type P-3, partial (0425-1335)EACH1$12,430$12,000$18,845$13,000$7,693.82
0160Inlets, curb, type P-4, <10' (0425-1341)EACH1$17,740$12,000$20,697$8,500.00$14,017
0165Inlets, curb, type P-5, <10' (0425-1351)EACH13$15,238$12,000$17,429$8,140.00$10,808
0170Inlets, curb, type P-6, <10' (0425-1361)EACH3$15,690$13,000$16,340$8,940.00$12,386
0175Inlets, curb, type J-5, <10' (0425-1451)EACH7$19,735$16,000$23,965$14,100$19,434
0180Manholes, P-7, <10' (0425-2-41)EACH2$14,345$9,000.00$15,251$6,520.00$10,010
0185Manholes, P-8, <10' (0425-2-61)EACH2$15,417$9,000.00$14,706$9,940.00$9,730.95
0190Manholes, P-8, partial (0425-2-63)EACH7$12,443$8,000.00$9,041.40$8,380.00$3,557.12
0195Manhole, adjust (0425-5)EACH7$2,100.00$800.00$3,050.11$1,150.00$1,866.16
0200Pipe culvert,optional material,round, 15"S/CD (0430-175115)LF112$315.68$700.00$326.80$460.00$1,399.92
0205Pipe culvert,optional material,round, 18"S/CD (0430-175118)LF429$325.97$400.00$326.80$232.00$608.60
0210Pipe culvert,optional material,round, 24"S/CD (0430-175124)LF34$539.25$340.00$435.73$549.00$664.74
0215Trench drain, standard (0436-1-1)LF19$725.00$750.00$1,960.79$582.00$976.89
0220Pipe handrail - guiderail, aluminum (0515-1-2)LF202$65.99$68.00$64.92$74.00$56.00
0225Concrete curb & gutter, type E (0520-1-7)LF874$55.29$80.00$39.22$64.00$71.71
0230Concrete curb & gutter, type F (0520-1-10)LF4,687$55.29$106.50$38.13$75.00$67.26
0235Concrete curb, type D (0520-2-4)LF229$51.25$61.00$32.68$63.00$103.39
0240Traffic separator concrete- type I, 4' wide (0520-5-11)LF817$121.20$117.00$179.74$74.00$79.03
0245Traffic separator concrete- type I, 6' wide (0520-5-12)LF147$179.10$130.00$245.10$109.00$112.09
0250Concrete traffic separator, special- variable width (0520-70)SY144$215.39$120.00$299.56$295.00$194.47
0255Shoulder concrete barrier, curb and gutter barrier (0521-72-43)LF615$279.23$380.00$446.62$353.00$685.67
0260Concrete sidewalk and driveways, 4" thick (0522-1)SY1,584$95.12$84.00$81.70$108.00$125.18
0265Concrete sidewalk and driveways, 6" thick (0522-2)SY956$111.65$140.00$103.49$164.00$186.20
0270Pavers, architectural, (0526-1-1)SY594$459.29$175.00$179.74$160.00$159.31
0275Pavers, architectural, (0526-1-2)SY44$187.45$175.00$179.74$188.00$236.97
0280Pavers, architectural, remove existing and reinstall (0526-1101)SY70$81.20$175.00$179.74$223.00$72.00
0285Detectable warnings (0527-2)SF1,141$42.00$50.00$49.02$39.60$26.80
0290Guardrail removal (0536-73)LF404$6.00$4.50$4.35$9.00$22.83
0295Performance turf, sod (0570-1-2)SY527$5.23$7.25$4.57$18.00$43.15
0300Conduit, furnish & install, open trench (0630-2-11)LF10$43.57$24.00$82.70$25.40$76.50
0305Conduit, furnish & install, directional bore (0630-2-12)LF345$33.77$34.00$56.76$35.80$52.50
0310Pull & splice box, F&I, 13" X 24" cover size (0635-2-11)EACH6$2,450.00$1,867.00$1,302.69$1,920.00$1,205.00
0315Traffic monitoring site vehicle sensor-non-weight, furnish & install (0695-1-1)EACH12$2,500.00$2,392.00$2,289.71$2,460.00$2,118.00
0320Traffic monitoring site inductive loop assembly, & install, 2 loops (0695-6-12)EACH12$3,000.00$2,678.00$1,886.47$2,750.00$1,745.00
0325Traffic monitoring site cabinet, furnish & install, type 3, pedestal mount (0695-7132)EACH3$8,500.00$8,633.00$8,422.64$8,880.00$7,791.00
0330Traffic monitoring site cabinet, remove existing cabinet (0695-7600)EACH3$1,500.00$1,512.00$1,139.45$1,560.00$1,054.00
0335Raised pavement marker, type B (0706-1-3)EACH293$7.00$5.45$5.41$9.30$5.00
0340Painted pavement markings, standard, white, solid, 6" (0710-11101)GM1.25$4,000.00$1,947.00$4,320.84$2,560.00$4,500.00
0345Painted pavement markings, standard, white, solid for interchange and urban island, (0710-11102)GM0.03$5,000.00$2,345.33$4,324.33$2,910.00$4,000.00
0350Painted pavement markings, standard, white, solid for crosswalk and roundabout, 12" (0710-11123)LF3,320$2.75$2.00$2.16$2.30$2.00
0355Painted pavement markings, standard, white, solid for diagonal or chevron, 18" (0710-11124)LF20$3.00$2.00$2.70$3.50$2.50
0360Painted pavement markings, standard, white, solid for stop line or crosswalk, 24" (0710-11125)LF2,379$4.00$2.00$3.24$4.70$3.00
0365Painted pavement markings, standard, white, skip, 10-30 or skip, 6" wide (0710-11131)GM0.48$1,500.00$450.00$1,076.60$1,400.00$1,000.00
0370Painted pavement markings, standard, white, 2-4 dotted guideline/ 6-10 dotted 6" (0710-11141)GM0.15$1,500.00$800.00$1,081.13$1,400.00$1,000.00
0375Painted pavement markings, standard, white, message or symbol (0710-11160)EACH57$75.00$90.00$70.27$116.00$65.00
0380Painted pavement markings, standard, white, arrows (0710-11170)EACH18$55.00$56.00$48.65$58.00$45.00
0385Painted pavement markings, standard, yellow, solid, 6" (0710-11201)GM4.49$3,500.00$1,920.00$4,320.44$2,560.00$4,500.00
0390Painted pavement markings, standard, yellow, 2-4 dotted guideline/6-10 dotted extension, 6" (0710-11241)GM0.07$1,500.00$770.00$1,022.70$1,400.00$1,000.00
0395Raised crosswalk, type RC curb with plate/grate (0920-520100)LF216$347.50$170.00$469.90$434.00$497.23
0400Initial contingency amount, DO not bid (0999-25)LS1$6,500.00$6,500.00$6,500.00$6,500.00$6,500.00
0405Initial contingency amount, DO not bid (0999-25)LS1$75,000$75,000$75,000$75,000$75,000
0410Local agency initial amount (DO not bid) (0999-26)LS1$33,000$33,000$33,000$33,000$33,000
0415Single column ground sign assembly, F&I ground mount, than 12 SF (0700-1111)EACH60$910.00$900.00$1,529.72$1,030.00$1,415.00
0420Single column ground sign assembly, remove (0700-1600)EACH25$240.00$230.00$115.67$259.00$107.00
0425Sign panel, furnish & install ground mount, UP to 12 SF (0700-3101)EACH31$500.00$470.00$248.65$493.00$230.00
0430Sign panel, remove, UP to 12 SF (0700-3601)EACH35$250.00$250.00$115.67$259.00$107.00
0435Overhead static sign deep foundation removal, cantilever (0700-4612)EACH1$19,000$17,000$20,104$17,900$18,596
0440Retroreflective sign strip- furnish and install, 5' (0700-13-15)EACH2$90.00$88.00$217.30$91.00$201.00
0445Enhanced highway sign AC powered, remove - overhead mount (0700-141903)EACH1$1,900.00$1,800.00$219.46$1,940.00$203.00
0450Enhanced highway sign solar powered, F&I ground mount, W/eds, UP to 12 SF of static sign panels (0700-142131)EACH2$16,500$16,000$17,874$17,100$16,534
0455Enhanced highway sign solar powered, F&I ground mount, W/eds, 12-20 SF of static sign panels (0700-142132)EACH4$19,000$19,000$17,874$20,000$16,534
0460Enhanced highway sign solar powered, F&I ground mount, highlighted sign <12 SF (0700-142140)EACH7$16,500$16,100$10,577$17,100$9,784.00
0465Enhanced hwy sign assembly, solar powered, F&I ground mount, W/highlighted sign <12 UP to 12 SF of static panels (0700-142141)EACH1$16,500$16,590$10,957$17,100$10,135
0470Object marker, type 3 (0705-10-3)EACH5$200.00$190.00$324.32$198.00$300.00
0475Delineator, flexible tubular (0705-11-1)EACH27$350.00$350.00$235.67$363.00$218.00
0480Raised pavement marker, type B (0706-1-3)EACH1,700$6.00$5.00$5.41$9.30$5.00
0485Raised pavement marker, type F internally illuminated (0706-1110)EACH146$325.00$433.00$406.70$454.00$305.12
0490Painted pavement markings, surface (0710-90)LS1$32,200$7,700.00$46,162$18,000$39,000
0495Painted pavement markings, surface (0710-90)LS1$33,350$54,000$47,694$58,200$40,000
0500Thermoplastic, standard, solid, 8" for interchange and urban island (0711-11102)GM0.06$10,000$4,900.00$10,270$8,730.00$9,500.00
0505Thermoplastic, standard, solid, 12" for crosswalk and roundabout (0711-11123)LF4,166$3.95$3.00$3.78$5.80$3.50
0510Thermoplastic, standard, solid, 18" for diagonals and chevrons (0711-11124)LF99$6.00$5.00$5.95$8.20$5.50
0515Thermoplastic, standard, solid, 24" for stop line and crosswalk (0711-11125)LF958$9.00$6.00$8.65$10.50$8.00
0520Thermoplastic, standard, vertical deflection marking (0711-11130)EACH58$63.00$343.00$64.86$175.00$60.00
0525Thermoplastic, standard, vertical deflection advance warning marking (0711-11140)EACH44$125.00$500.00$124.32$233.00$115.00
0530Thermoplastic, standard, 2-4 dotted guideline/ 6-10 gap extension, 6" (0711-11141)GM0.28$3,000.00$2,750.00$2,693.06$5,240.00$2,500.00
0535Thermoplastic, standard, message or symbol (0711-11160)EACH24$185.00$166.00$162.16$349.00$150.00
0540Thermoplastic, standard, arrow (0711-11170)EACH40$125.00$100.00$108.11$105.00$100.00
0545Thermoplastic, standard, yellow, solid, 18" for diagonal or chevron (0711-11224)LF701$6.00$6.20$5.95$8.20$5.50
0550Thermoplastic, standard, yellow, 2-4 dotted guide line dotted extension line, 6" (0711-11241)GM0.16$3,000.00$2,600.00$2,565.82$5,240.00$2,500.00
0555Thermoplastic, preformed, white, solid, 24" for crosswalk (0711-14125)LF3,746$17.00$14.50$16.22$18.60$15.00
0560Thermoplastic, preformed, white, arrow (0711-14170)EACH16$175.00$1,032.00$162.16$932.00$150.00
0565Thermoplastic, standard-other surfaces, white, solid, 6" (0711-16101)GM4.84$5,800.00$4,500.00$5,936.07$6,060.00$5,500.00
0570Thermoplastic, standard-other surfaces, white, skip, 6",10-30 or 3-9 lane drop (0711-16131)GM3.01$1,900.00$1,900.00$1,837.82$4,660.00$1,700.00
0575Thermoplastic, standard-other surfaces, yellow, solid, 6" (0711-16201)GM4.16$5,900.00$4,600.00$5,943.04$6,060.00$5,500.00
0580Conduit, furnish & install, open trench (0630-2-11)LF113$14.00$12.00$14.05$12.40$13.00
0585Conduit, furnish & install, directional bore (0630-2-12)LF1,254$24.72$24.00$20.54$25.20$19.00
0590Pull & splice box, F&I, 13" X 24" cover size (0635-2-11)EACH32$1,500.00$1,170.00$2,324.31$1,210.00$2,150.00
0595Lighting conductors, F&I, insulated, no.8 - 6 (0715-1-12)LF5,301$2.95$2.00$2.97$2.40$2.75
0600Luminaire, F&I- replace existing luminaire on existing pole/arm, roadway, cobra head (0715-11211)EACH5$1,500.00$1,620.00$1,445.40$1,660.00$1,337.00
0605Luminaire, remove (0715-11500)EACH5$500.00$470.00$282.16$485.00$261.00
0610Light pole complete, F&I, standard pole standard foundation, 30' mounting height, 0' arm length (0715-61100)EACH1$10,500$9,900.00$9,329.66$10,200$8,630.00
0615Light pole complete, F&I, standard pole standard foundation, 30' mounting height, 8' arm length (0715-61111)EACH7$9,800.00$10,050$9,194.53$10,300$8,505.00
0620Light pole complete, F&I, standard pole special foundation, 30' mounting height, 8' arm length (0715-62111)EACH5$18,000$15,000$16,451$15,700$15,217
0625Light pole complete, F&I, standard pole special foundation, 30' mounting height, 10' arm length (0715-62121)EACH1$20,000$15,380$14,414$15,800$13,333
0630Light pole complete, remove pole and foundation (0715-69000)EACH3$1,200.00$1,000.00$3,385.92$1,040.00$3,132.00
0635Pole cable distribution system, furnish and install, conventional (0715-500-1)EACH14$780.00$771.00$876.75$793.00$811.00
0640Itsfm subsurface documentation- project length (0611-1-1)MI1.81$4,325.00$4,400.00$4,537.89$4,540.00$4,199.89
0645Itsfm location documentation- intersection (0611-2-1)EACH7$1,500.00$1,512.00$1,815.12$1,560.00$1,679.00
0650Conduit, furnish & install, open trench (0630-2-11)LF1,812$23.99$23.00$26.49$23.70$24.50
0655Conduit, furnish & install, directional bore (0630-2-12)LF10,218$41.92$38.00$31.89$39.81$29.50
0660Conduit, furnish & install, aboveground (0630-2-14)LF260$39.22$34.00$95.40$35.60$88.25
0665Signal cable- new or reconstructed intersection, furnish & install (0632-7-1)PI8$13,630$12,000$12,125$13,100$11,216
0670Signal cable, remove- intersection (0632-7-6)PI4$3,200.00$2,268.00$1,648.64$2,330.00$1,525.00
0675Fiber optic cable, F&I, underground,2-12 fibers (0633-1121)LF1,032$4.75$4.00$4.32$4.30$4.00
0680Fiber optic cable, F&I, underground,49-96 fibers (0633-1123)LF10,962$5.65$4.00$4.65$4.50$4.30
0685Fiber optic connection, install, splice (0633-2-31)EACH128$65.90$55.00$58.38$58.00$54.00
0690Fiber optic connection hardware, F&I, splice (0633-3-11)EACH8$1,800.00$1,864.00$1,633.50$1,920.00$1,511.00
0695Fiber optic connection hardware, F&I, splice tray (0633-3-12)EACH8$97.25$87.00$64.87$90.00$60.00
0700Fiber optic connection hardware, F&I, preterminated connector assembly (0633-3-13)EACH96$59.59$53.00$58.38$56.00$54.00
0705Fiber optic connection hardware, F&I, patch panel- terminated (0633-3-16)EACH8$1,200.00$1,080.00$1,459.45$1,110.00$1,350.00
0710Fiber optic cable locator (0633-6)DA425$225.00$188.00$316.75$194.00$293.00
0715Span wire assembly, F&I, two point, diagonal (0634-4152)PI1$11,269$9,500.00$4,297.26$9,800.00$3,975.00
0720Span wire assembly, F&I, two point, box or drop box (0634-4153)PI1$14,299$12,700$10,405$13,100$9,625.00
0725Span wire assembly, remove- poles remain (0634-4600)PI2$1,300.00$1,261.00$2,632.41$1,300.00$2,435.00
0730Pull & splice box, F&I, 13" X 24" cover size (0635-2-11)EACH59$1,800.00$1,735.00$1,302.69$1,790.00$1,205.00
0735Pull & splice box, F&I, 24" X 36" cover size (0635-2-12)EACH14$3,330.00$3,100.00$3,491.87$3,280.00$3,230.00
0740Pull & splice box, F&I, 30" X 60" rectangular or 36" round size (0635-2-13)EACH9$5,875.00$5,900.00$7,091.84$6,130.00$6,560.00
0745Pull & splice box, F&I, 17" X 30" cover size (0635-2-14)EACH9$3,330.00$2,350.00$2,043.23$2,420.00$1,890.00
0750Electrical power service, F&I, underground, meter furnished by power company (0639-1121)AS6$5,100.00$5,100.00$7,207.52$5,300.00$6,667.00
0755Electrical power service, remove overhead (0639-1610)AS2$1,200.00$745.00$1,405.40$778.00$1,300.00
0760Electrical service wire, & install (0639-2-1)LF1,283$7.75$6.55$8.38$7.20$7.75
0765Electrical service disconnect, F&I, pole mount (0639-3-11)EACH5$2,400.00$2,400.00$2,648.63$2,490.00$2,450.00
0770Prestressed concrete pole, type P-II service pole (0641-2-12)EACH10$2,355.00$2,300.00$2,794.57$2,430.00$2,585.00
0775Prestressed concrete pole, complete pole removal- pedestal/service pole (0641-2-60)EACH6$890.00$750.00$329.73$778.00$305.00
0780Aluminum signals pole, (0646-1-11)EACH32$3,700.00$3,100.00$2,313.50$3,220.00$2,140.00
0785Aluminum signals pole, furnish install pedestrian detector post (0646-1-12)EACH6$3,400.00$2,800.00$2,509.17$2,960.00$2,321.00
0790Steel mast arm assembly, and install, double arm 30'-30' (0649-21-2)EACH1$74,230$68,000$78,609$71,700$72,714
0795Steel mast arm assembly, and install, single arm 50' (0649-21-6)EACH2$74,000$70,000$68,827$72,300$63,665
0800Vehicular traffic signal, furnish & install aluminum, 3 section, 1 way (0650-1-14)AS6$2,500.00$2,560.00$2,111.34$2,660.00$1,953.00
0805Vehicular traffic signal, furnish & install aluminum, 3 section, 2-4 ways (0650-1-15)AS4$5,000.00$4,900.00$3,569.70$5,050.00$3,302.00
0810Vehicular traffic signal, furnish & install aluminum, 5 section cluster, 1 way (0650-1-19)AS3$3,800.00$3,800.00$3,189.16$3,910.00$2,950.00
0815Vehicular traffic signal, remove- poles to remain (0650-1-60)AS12$700.00$535.00$274.59$551.00$254.00
0820Vehicular signal auxiliaries, repair/replace/retrofit- & install, backplate- flexible required (0650-2109)EACH12$1,040.00$964.00$602.16$992.00$557.00
0825Pedestrian signal, furnish & install LED countdown, 1 way (0653-1-11)AS39$1,200.00$1,161.00$994.59$1,190.00$920.00
0830Pedestrian signal, furnish & install LED countdown, 2 ways (0653-1-12)AS1$2,000.00$1,967.00$1,987.02$2,020.00$1,838.00
0835Pedestrian signal, remove ped signal- pole/pedestal to remain (0653-1-60)AS23$399.00$377.00$110.27$389.00$102.00
0840Midblock crosswalk: hybrid beacon assembly, & install complete assembly (0654-3-10)AS12$2,500.00$2,300.00$2,156.74$2,370.00$1,995.00
0845Vehicle detection system- furnish & install cabinet equipment (0660-4-11)EACH4$20,200$21,050$22,224$21,600$20,557
0850Vehicle detection system- furnish & install above ground equipment (0660-4-12)EACH22$11,200$10,550$8,794.53$10,900$8,135.00
0855Vehicle detection system- remove (0660-4-60)EACH3$2,000.00$1,891.00$1,648.64$1,940.00$1,525.00
0860Traffic data detection system- video, furnish and install, cabinet equipment (0660-9-11)EACH4$28,000$27,000$22,306$28,800$20,633
0865Traffic data detection system- video, furnish and install, ground equipment (0660-9-12)EACH5$16,390$15,700$7,198.87$16,200$6,659.00
0870Signal priority and preemption system, F&I, optical, cabinet electronics (0663-1111)EACH4$12,900$11,500$9,053.99$11,300$8,375.00
0875Signal priority and preemption system, F&I, optical, detector (0663-1112)EACH12$2,800.00$2,850.00$2,572.95$2,830.00$2,380.00
0880Pedestrian detector, furnish & install, standard (0665-1-11)EACH39$400.00$400.00$292.97$408.00$271.00
0885Pedestrian detector, furnish & install, accessible (0665-1-12)EACH2$2,500.00$2,600.00$3,707.00$2,680.00$3,429.00
0890Pedestrian detector, remove- pole/pedestal to remain (0665-1-60)EACH23$159.00$126.00$165.40$130.00$153.00
0895Traffic controller assembly, F&I, NEMA W/standard lock (0670-5160)AS7$55,500$57,000$49,053$58,500$45,374
0900Traffic controller assembly, remove controller with (0670-5600)AS3$3,645.00$2,230.00$1,608.64$2,330.00$1,488.00
0905Traffic signal controller cabinet, adjust/modify (0676-1500)EACH1$4,000.00$3,530.00$2,169.71$3,630.00$2,007.00
0910ITS CCTV camera, non- pressurized, IP, high definition (0682-1173)EACH3$7,900.00$8,067.00$9,144.80$8,290.00$8,459.00
0915Managed field ethernet switch, furnish & install (0684-1-1)EACH8$5,390.00$5,585.00$4,269.16$5,740.00$3,949.00
0920Uninterruptible power supply, furnish and install, line interactive with cabinet (0685-1-13)EACH6$15,800$16,600$13,907$17,100$12,864
0925Remote power management rpmu, furnish and install (0685-2-1)EACH7$900.00$795.00$2,058.36$821.00$1,904.00
0930Single column ground sign assembly, remove (0700-1600)EACH1$159.00$127.00$447.56$130.00$414.00
0935Sign panel, furnish & install overhead mount, UP to 12 SF (0700-3201)EACH6$1,200.00$1,030.00$795.67$1,060.00$736.00
0940Sign panel, remove, UP to 12 SF (0700-3601)EACH10$225.00$220.00$164.32$227.00$152.00
0945Internally illuminated sign, furnish & install, overhead mount, 12-18 SF (0700-5-22)EACH16$8,615.00$8,650.00$7,603.19$8,920.00$7,033.00
0950Internally illuminated sign, remove (0700-5-60)EACH1$690.00$693.00$330.70$713.00$305.90
0955Enhanced highway sign AC powered, F&I ground mount, blank out sign <12 SF, UP to 12 SF of static sign panels (0700-141161)EACH1$5,020.00$5,235.00$9,117.77$5,380.00$10,135
FDOT contract T5874: unit prices by line

The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.

Source

Read from FDOT's tabulation for this contract. FDOT Tabulation of Bids PDFs from its central office lettings, January 2018 to October 2026, all pay items. On A+B contracts the cost part is kept (the total the pay items add up to). Bidders listed without a rank or total are left out.

Every contract let that day: FDOT letting of January 28, 2026. Compiled by Mirage Metrics.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy